2017 Point Beach Nuclear Plant Initial License Examination Forms ES-301-5 Revision 0
ML17201Q527
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/23/2017
From: Jesse Seymour
Operations Branch III
To:
Point Beach
Shared Package
ML16319A342 List:
References
Download: ML17201Q527 (5)


Text

ES-301 Transient and Event Checklist Group 1 Form ES-301-5 Facility: Date of Exam:

Operating Test No.:

A P P L I C A N T E V E N T T Y P E Scenarios 1 2 4 T O T A L M I N I M U M(*) CREW POSITION CREW POSITION CREW POSITION CREW POSITION S R O A T C B O P S R O A T C B O P S R O A T C B O P S R O A T C B O P R I U RO SRO-I SRO-U SRO-I 1 RX 4 2 2 1 1 0 NOR 1, 2 2 1 1 1 I/C 1, 2 , 5 3, 4, 8 3, 5, 7 9 4 4 2 MAJ 6 6 6 3 2 2 1 TS 1, 3 2 0 2 2 RO SRO-I SRO-U SRO-I 2 RX 4 2 2 1 1 0 NOR 1 1, 2 3 1 1 1 I/C 5 3, 4, 5 4, 8 6 4 4 2 MAJ 6 6 6 3 2 2 1 TS 3, 4 2 0 2 2 RO SRO-I SRO-U SRO-I 3 RX 2 2 2 1 1 0 NOR 4 1 2 1 1 1 I/C 1 , 2, 7, 8 5, 7 3, 4, 5 9 4 4 2 MAJ 6 6 6 3 2 2 1 TS 3, 4, 5 3 0 2 2 RO SRO-I SRO-U RX 1 1 0 NOR 1 1 1 I/C 4 4 2 MAJ 2 2 1 TS 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES

-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs mu-the-controls -of-(BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO

-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position. 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis. 3. Whenever practical, both instrument and component malfunctions should be included; only those that require -hand columns.

4. For licensees that use the ATC operator primarily for monitoring plant parameters

, the chief examiner may place SRO

-I applicants in either the ATC or BOP position to best evaluate the SRO

-I in manipulating plant controls.

ES-301 Transient and Event Checklist Group 2 Form ES-301-5 Facility: Date of Exam:

Operating Test No.:

A P P L I C A N T E V E N T T Y P E Scenarios 1 3 4 T O T A L M I N I M U M(*) CREW POSITION CREW POSITION CREW POSITION CREW POSITION S R O A T C B O P S R O A T C B O P S R O A T C B O P S R O A T C B O P R I U RO SRO-I SRO-U SRO-I 4 RX 4 2 2 1 1 0 NOR 3 1 1 1 1 I/C 1, 2 , 5 1, 2, 4 3, 5, 7 9 4 4 2 MAJ 6 5 6 3 2 2 1 TS 1, 3 2 0 2 2 RO SRO-I SRO-U SRO-I 5 RX 4 3 2 1 1 0 NOR 1, 2 2 1 1 1 I/C 5 1, 2, 4 4, 8 6 4 4 2 MAJ 6 5 6 3 2 2 1 TS 1, 3, 4 3 0 2 2 R O SRO-I SRO-U SRO-I 6 RX 3 2 2 1 1 0 NOR 4 1 2 1 1 1 I/C 1 , 2, 7, 8 6, 7, 8 3, 4, 5 10 4 4 2 MAJ 6 5 6 3 2 2 1 TS 3, 4, 5 3 0 2 2 RO SRO-I SRO-U RX 1 1 0 NOR 1 1 1 I/C 4 4 2 MAJ 2 2 1 TS 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES

-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs

-the-controls -of-(BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO

-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position. 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis. 3. Whenever practical, both instrument and component malfunctions should be included; only those that require -hand columns.

4. For licensees that use the ATC operator primarily for monitoring plant parameters

, the chief examiner may place SRO

-I applicants in either the ATC or BOP position to best evaluate the SRO

-I in manipulating plant controls.

ES-301 Transient and Event Checklist Group 3 Form ES-301-5 Facility: Date of Exam:

Operating Test No.:

A P P L I C A N T E V E N T T Y P E Scenarios 1 3 4 T O T A L M I N I M U M(*) CREW POSITION CREW POSITION CREW POSITION CREW POSITION S R O A T C B O P S R O A T C B O P S R O A T C B O P S R O A T C B O P R I U RO SRO-I SRO-U SRO-I 7 RX 4 3 2 3 1 1 0 NOR 1 1 1 1 1 I/C 1, 2 , 5 6, 7, 8 3, 4, 5 9 4 4 2 MAJ 6 5 6 3 2 2 1 TS 1, 3 3, 4, 5 5 0 2 2 RO SRO-I SRO-U SRO-I 8 RX 4 3 2 1 1 0 NOR 1, 2 2 1 1 1 I/C 5 1, 2, 4 4, 8 6 4 4 2 MAJ 6 5 6 3 2 2 1 TS 1, 3, 4 3 0 2 2 RO SRO-I SRO-U RO 1 RX 2 1 1 1 0 NOR 4 3 2 1 1 1 I/C 1 , 2, 7, 8 1, 2, 4 3, 5, 7 10 4 4 2 MAJ 6 5 6 3 2 2 1 TS 0 0 2 2 RO SRO-I SRO-U RX 1 1 0 NOR 1 1 1 I/C 4 4 2 MAJ 2 2 1 TS 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES

-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs mu-the-controls -of-(BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO

-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position. 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis. 3. Whenever practical, both instrument and component malfunctions should be included; only those that require -hand columns.

4. For licensees that use the ATC operator primarily for monitoring plant parameters

, the chief examiner may place SRO

-I applicants in either the ATC or BOP position to best evaluate the SRO

-I in manipulating plant controls.

ES-301 Transient and Event Checklist Group 4 Form ES-301-5 Facility: Date of Exam:

Operating Test No.:

A P P L I C A N T E V E N T T Y P E Scenarios 2 3 T O T A L M I N I M U M(*) CREW POSITION CREW POSITION CREW POSITION CREW POSITION S R O A T C B O P S R O A T C B O P S R O A T C B O P S R O A T C B O P R I U RO SRO-I SRO-U SRO-U 1 RX 2 1 1 1 0 NOR 1 3 2 1 1 1 I/C 3, 4, 5 1, 2, 4 6 4 4 2 MAJ 6 5 2 2 2 1 TS 3, 4 2 0 2 2 RO SRO-I SRO-U SRO-I 9 RX 3 1 1 1 0 NOR 2 1 1 1 1 I/C 5, 7 1, 2, 4 5 4 4 2 MAJ 6 5 2 2 2 1 TS 1, 3, 4 3 0 2 2 RO SRO-I SRO-U RO 2 RX 2 3 2 1 1 0 NOR 1 1 1 1 1 I/C 3, 4, 8 6, 7, 8 6 4 4 2 MAJ 6 5 2 2 2 1 TS 0 0 2 2 RO SRO-I SRO-U RX 1 1 0 NOR 1 1 1 I/C 4 4 2 MAJ 2 2 1 TS 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES

-D-1 event numbers for each event type; -the-contro ls -of-(BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SRO

-I additiona lly serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position. 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis. 3. Whenever practical, both instrument and component malfunctions should be included; only those that require -hand columns.

4. For licensees that use the ATC operator primarily for monitoring plant parameters

, the chief examiner may place SRO

-I applicants in either the ATC or BOP position to best evaluate the SRO

-I in manipulating plant controls.

ES-301 Transient and Event Checklist Group 5 Form ES-301-5 Facility: Date of Exam:

Operating Test No.:

A P P L I C A N T E V E N T T Y P E Scenarios 2 4 T O T A L M I N I M U M(*) CREW POSITION CREW POSITION CREW POSITION CREW POSITION S R O A T C B O P S R O A T C B O P S R O A T C B O P S R O A T C B O P R I U RO SRO-I SRO-U SRO-U 2 RX 2 1 1 1 0 NOR 1 1 1 1 1 I/C 3, 4, 5 3 4 4 2 MA J 6 1 2 2 1 TS 3, 4 2 0 2 2 RO SRO-I SRO-U SRO-U 3 RX 2 1 1 1 0 NOR 1 1 1 1 1 I/C 3, 4, 5 3 4 4 2 MAJ 6 1 2 2 1 TS 3, 4, 5 3 0 2 2 RO SRO-I SRO-U RO 3 RX 2 1 1 1 0 NOR 1, 2 2 1 1 1 I/C 5, 7 4, 8 4 4 4 2 MAJ 6 6 2 2 2 1 TS 0 0 2 2 RO SRO-I SRO-U RO 4 RX 2 1 1 1 0 NOR 1, 2 2 1 1 1 I/C 3, 4, 8 3, 5, 7 6 4 4 2 MAJ 6 6 2 2 2 1 TS 0 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES

-D-1 event numbers for each event type; at-the-controls -of-(BOP) positions. Instant SROs (SRO-I) must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an SR O-I additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position. 2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a one-for-one basis. 3. Whenever practical, both instrument and component malfunctions should be included; only those that require -hand columns.

4. For licensees that use the ATC operator primarily for monitoring plant parameters

, the chief examiner may place SRO

-I applicants in either the ATC or BOP position to best evaluate the SRO

-I in manipulating plant controls.