MONTHYEARML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a IR 05000528/20243012024-06-17017 June 2024 NRC Examination Report 05000528/2024301; 05000529/2024301; 05000530/2024301 ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A ML24157A3392024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium ML24144A2772024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 and Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24089A1892024-03-28028 March 2024 Present Levels of Financial Protection ML24068A2522024-03-0808 March 2024 License Amendment Request to Revise Technical Specifications 3.5.1 and 3.5.2 Using Risk-Informed Process for Evaluations ML24066A0472024-03-0606 March 2024 Response to Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown and TS IR 05000528/20240122024-03-0404 March 2024 Age-Related Degradation Inspection Report 05000528/2024012, 05000529/2024012 and 05000530/2024012 IR 05000528/20230062024-02-28028 February 2024 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2 and 3 Report 05000528/2023006 and 05000529/2023006 and 05000530/2023006 ML24053A3972024-02-22022 February 2024 License Renewal - Alloy 600 Management Program Plan ML24047A3632024-02-16016 February 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX177, AMZDFX178, AMZDFX179 Vertical Concrete Cask Identification No. AMZDNE179, AMZDNE178 IR 05000528/20230042024-02-12012 February 2024 Integrated Inspection Report Report 05000528/2023004 and 05000529/2023004 and 05000530/2023004 ML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line 2024-09-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24257A1012024-09-11011 September 2024 Request for Additional Information License Renewal Commitment for AMP of Alloy 600 Components ML24143A1112024-05-20020 May 2024 Draft 2nd Round Request for RAIs Concerning LAR to Modify LCO for TS 3.5.2, LCO for TS 3.6.5, and Surveillance Requirements 3.5.1.2 and 3.5.2.2 for TS 3.5.1 and TS 3.5.2 ML24123A2002024-05-0101 May 2024 (E-Mail) Draft 2nd Round Request for Additional Information Concerning License Amendment Request to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2, LCO for TS 3.6.5, 3.5.1.2 and 3.5.2.2 for TS 3.5.1, a ML24114A2812024-04-19019 April 2024 Request for Additional Information (RAI-10150-R1) ML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23031A3392023-01-31031 January 2023 In-service Inspection Request for Information ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22272A3252022-09-29029 September 2022 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML22209A1752022-07-28028 July 2022 Inservice Inspection Request for Information ML22187A2632022-07-0606 July 2022 Notification of Inspection (NRC IR 05000528/2022004, 05000529/2022004 and 05000530/2022004) and Request for Information ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22035A3302022-02-10010 February 2022 Requests for Confirmation of Information for Exemption to Delete Diverse Auxiliary Feedwater Actuation System Based on Risk-Informed Process for Evaluations ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21245A2222021-09-0101 September 2021 Request for Information ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information ML20227A0992020-08-14014 August 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20118D1362020-04-28028 April 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20049A0992020-02-14014 February 2020 Notification of Cyber Security Inspection (NRC Inspection Report 05000528/2020401; 05000529/2020401; and 05000530/2020401) and Request for Information ML20049A0252020-02-12012 February 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for License Amendment Request Associated with Changes to Emergency Plan Staffing Requirements ML20021A3172020-01-21021 January 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for Relief Request 64, Impractical Examinations for the Third 10-Year ISI Interval ML19317D0782019-11-13013 November 2019 NRR E-mail Capture - Palo Verde 1 - Requests for Additional Information on Unit 1 21st Refueling Outage Steam Generator Tube Inspection Report ML19234A3202019-08-29029 August 2019 Redacted - Request for Additional Information for Amendment and Exemption Request to Support the Implementation of Framatome High Thermal Performance Fuel (EPID L-2018-LLA-0194; EPID L-2018-LLE-0010) ML19155A1842019-05-30030 May 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mvib Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19095A6552019-04-0404 April 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mphb Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19044A7342019-02-13013 February 2019 NRR E-mail Capture - Palo Verde1, 2, and 3 - Official Requests for Additional Information for RR 62, Third and Fourth 10-Year ISI Intervals, Proposed Alternative - Pressurizer Heat Sleeve Repairs ML19008A3612019-01-0808 January 2019 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR Associated with Response Time Testing of Pressure Transmitters ML18341A0252018-12-0303 December 2018 Notification of NRC Design Bases Assurance Inspection (Teams)(05000528/2019011, 05000529/2019011, and 05000530/2019011) and Initial Request for Information ML18271A0392018-10-0202 October 2018 Non Proprietary - Supplemental Information Needed for Acceptance of Requested License Amendments and Exemptions Implementation of Framatome High Thermal Performance Fuel (Epids L-2018-LLA-0194 and L-2018-LLE-0010) ML18221A5102018-08-23023 August 2018 Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001) ML18229A3132018-08-17017 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 - Second Se ML18227A8672018-08-15015 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 ML18124A0112018-05-0303 May 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001) ML18099A0072018-04-0606 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) ML18094B1122018-04-0404 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001) ML18066A7032018-03-0707 March 2018 Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for Information ML17248A0162017-08-31031 August 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAI for RRs PRR-03, PRR-04 and PRR-05, Pump Testing ML17107A0052017-04-14014 April 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Ngf LAR and Exemption RAIs (CAC Nos. MF8076 to MF8081) ML17082A4462017-03-28028 March 2017 PVNGS Units 1, 2, and 3 Transition to CE 16x16 Ngf - Draft RAIs Rev 3 2024-09-11
[Table view] |
See also: IR 05000528/2011005
Text
September 8, 2011
Randall K. Edington, Executive Vice President, Nuclear/CNO Arizona Public Service Company P.O. Box 52034, Mail Stop 7602 Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000528/2011005, 05000529/2011005, AND 05000530/2011005) AND REQUEST FOR INFORMATION
Dear Mr. Edington:
The purpose of this letter is to notify you that on December 5, 2011, the U.S. Nuclear Regulatory Commission (NRC), Region IV staff will begin the onsite portion of the Gas
Accumulation Management in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Temporary Instruction at your Palo Verde Nuclear Generating Station. This inspection will be performed in accordance with NRC Temporary Instruction (TI) 2515/177.
Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection. The documents have been divided into two groups.
- The first group lists information necessary for our initial inspection scoping and in-office preparation activities. This information should be separated by information request number,
especially if provided electronically (e.g., folder with the information request number). This information should be available to the inspector no later than November 21, 2011. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. By December 1, 2011, the inspector will communicate the initial selected samples.
- The second group of documents requested is needed to support our onsite inspection activities. This set of documents should be available to the inspector on December 5, 2011. It is also requested that corrective action documents and responses to questions developed during the inspection be provided to the inspector as the documents are generated.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Del Elkinton
of your licensing organization. If there are any questions about this inspection or the material requested, please contact either Abin Fairbanks, at (817) 860-8158 or by email at Abin.Fairbanks@nrc.gov, or Dustin Reinert, at (817) 860-8244 or by email at Dustin.Reinert@nrc.gov. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125
Arizona Public Service Company
- 2 - This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,
a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety
Docket Nos.: 50-528, 50-529, 50-530 Licenses: NPF-41, NPF-51, NPF-74
Enclosure: INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT
REQUEST CC: Distribution via ListServ for Palo Verde
Arizona Public Service Company
- 3 -
R\Reactors\PV\2011\Palo Verde TI-177 RFI.docx ML11251A212 ADAMS: No Yes SUNSI Review Complete Reviewer Initials:
Publicly Available Non-Sensitive
Non-publicly Available Sensitive DRS/RI DRS/RI DRS/Branch Chief
AFairbanks DReinert TFarnholtz /RA/ /RA/ /RA/ 09/07/2011 09/08/2011 09/08/2011 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST
- 1 - Enclosure
Inspection Report
: 05000528/2011005, 05000529/2011005, AND 05000530/2011005
Inspection Dates
- December 5 - 9, 2011 Inspection Procedure
- TI 2515/177, "Management of Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems" Inspectors: Abin Fairbanks Dustin Reinert Reactor Inspector Reactor Inspector (817) 860-8158 (817) 860-8244 Abin.Fairbanks@nrc.gov Dustin.Reinert@nrc.gov
I. Information Requested by November 21, 2011
The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com or compact disc, preferred), in care of Abin Fairbanks, or Dustin
Reinert, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspectors will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection weeks. Also, we request that you categorize the documents in your response with the numbered list below. Please provide requested documentation electronically if possible. If
requested documents are large and only hard copy formats are available, please inform the inspectors, and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspectors as soon as possible.
1. List of corrective action program documents (with a short description) associated with GL 2008-01, voids in piping, and pressure transients for the previous three years.
2. List of changes (with a short description and tracking number) to the final safety analysis report (FSAR), technical specifications, technical specification bases, and technical requirements manual associated with the resolution of GL 2008-01.
3. List of calculations associated with GL 2008-01, including calculations that have been changed or created in response to GL 2008-01 (with a short description of the calculation and the change).
4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the affected system locations (e.g., identify the source, conditions, and expected void locations). Also, include a short description of how each gas intrusion mechanism has been addressed (e.g., plant hardware modification, procedure change).
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST
- 2 - Enclosure 5. List of the suction piping sections identified as susceptible to gas accumulation (the list should identify the corresponding system).
6. List of the discharge piping sections identified as susceptible to gas accumulation (the list should identify the corresponding system).
7. Copies of isometric drawings of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System (hard-copies are preferred).
8. Copies of piping and instrumentation diagrams (P&IDs) of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System (hard-copies are preferred). Please highlight any components that were part of hardware modifications installed as part of the resolution of GL 2008-01 and all high point vents that are monitored during void surveillances.
9. Copies of program documents and procedures developed to implement the resolution of GL 2008-01.
10. List of actions that were completed in response to GL 2008-01.
11. Copies of the modification packages for hardware modifications as part of the resolution of GL 2008-01.
12. Design basis documents of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.
13. Design basis documents of keep-full systems of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.
14. System walkdown reports associated with the resolution of GL 2008-01.
15. If applicable, provide a list of inaccessible locations where plant walkdowns of the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System have not been completed. Include an explanation of why each area is considered inaccessible.
16. Copies of surveillance procedures associated with the resolution of GL 2008-01 (i.e., procedures used for detecting and determining void volumes) and the results of the last two surveillances for the Emergency Core Cooling System, Decay Heat Removal System, and Containment Spray System.
17. Copies of procedures used for filling and venting.
18. Copies of trends of periodic venting results.
19. Copies of the engineering evaluations performed for all identified voids.
INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION TEMPORARY INSPECTION DOCUMENT REQUEST
- 3 - Enclosure
20. Basis for the void acceptance criteria (e.g., calculation). If applicable, provide the justification for any deviation from the void acceptance criteria established by the Office
of Nuclear Reactor Regulation (NRR).
21. Copies of the methodologies used for predicting void behavior and impact on system operability.
22. Copies of any void transport analyses.
23. Copies of vortexing calculations associated with systems under the scope of GL 2008-
01. 24. Copies of self-assessments associated with the implementation of the GL 2008-01 program. 25. Copies of any training materials for gas-related concerns.
26. Copies of training modules and attendance records that ensure personnel are aware of gas-related concerns.
II. Information Requested by December 5, 2011
27. Copies of the selected corrective action program documents.
28. Copies of the selected licensing and design basis document changes.
29. Copies of the selected calculations.
30. Copies of corrective action program implementing procedures.
31. Electronic copies of the current technical specifications, technical specification bases, updated final safety analysis report, and technical requirements manual.
Inspector Contact Information:
Abin Fairbanks Dustin Reinert Reactor Inspector Reactor Inspector (817) 860-8158 (817) 860-8244 Abin.Fairbanks@nrc.gov Dustin.Reinert@nrc.gov
Mailing Address: Mailing Address:
U.S. NRC Region IV U.S. NRC Region IV Attn: Abin Fairbanks Attn: Dustin Reinert
612 E. Lamar Blvd., Suite 400 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125 Arlington, TX 76011-4125