Other: GNRO-2013/00015, Overall Integrated Plan in Response to March 12,2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), GNRO-2013/00016, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), GNRO-2013/00061, Entergy'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), GNRO-2015/00005, Entergy'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Lnstrumentation (Order Number EA-12-051), GNRO-2016/00006, Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), GNRO-2016/00007, Notification of Full Compliance with NRC Order EA-12-051. Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051), ML12305A207, ML14042A297, ML15237A337, ML15308A298
|
MONTHYEARML12305A2072012-10-25025 October 2012 Initial Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2013/00016, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-26026 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other GNRO-2013/00015, Overall Integrated Plan in Response to March 12,2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-02-27027 February 2013 Overall Integrated Plan in Response to March 12,2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13207A1242013-07-30030 July 2013 Request for Additional Information, Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: RAI ML13214A0952013-08-0505 August 2013 Correction to July 30, 2013, Request for Additional Information, Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: RAI GNRO-2013/00061, Entergy'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 Entergy'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other GNRO-2013/00057, Response to Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2013-08-29029 August 2013 Response to Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) Project stage: Response to RAI ML13316B9862013-11-25025 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI ML14042A2972014-02-12012 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Grand Gulf Nuclear Station, Unit 1, TAC No.: MF0954 Project stage: Other ML14007A7182014-02-19019 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Acceptance Review GNRO-2015/00005, Entergy'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Lnstrumentation (Order Number EA-12-051)2015-02-18018 February 2015 Entergy'S Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Lnstrumentation (Order Number EA-12-051) Project stage: Other ML15237A3372015-08-27027 August 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15308A2982015-11-24024 November 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other GNRO-2016/00007, Notification of Full Compliance with NRC Order EA-12-051. Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2016-05-24024 May 2016 Notification of Full Compliance with NRC Order EA-12-051. Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) Project stage: Other GNRO-2016/00006, Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-05-24024 May 2016 Notification of Full Compliance with NRC Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2016/00036, Response to Requests for Additional Information (Rais) Regarding Final Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2016-07-29029 July 2016 Response to Requests for Additional Information (Rais) Regarding Final Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI 2013-08-05
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000416/20240112024-10-16016 October 2024 – Fire Protection Team Inspection Report 05000416/2024011 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 IR 05000416/20240122024-09-17017 September 2024 License Renewal Post Approval Phase 2 Inspection Report 05000416/2024012 ML24254A3602024-09-10010 September 2024 Pre-Submittal Slides for License Amendment Request, Criticality Safety Analysis, Technical Specification 4.3.1, Criticality and Technical Specification 5.5.14, Spent Fuel Storage Rack Neutron Absorber Monitoring Program IR 05000416/20244022024-09-0909 September 2024 Security Baseline Inspection Report 05000416/2024402 05000416/LER-2024-003, Feedwater Inlet Check Valve Incorrectly Determined Operable2024-08-26026 August 2024 Feedwater Inlet Check Valve Incorrectly Determined Operable ML24235A0832024-08-22022 August 2024 Evaluations Performed in Accordance with 10 CFR 50.54(q) for Changes to Emergency Planning Documents IR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24176A1202024-07-29029 July 2024 Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000416/20240022024-07-29029 July 2024 Integrated Inspection Report 05000416/2024002 ML24172A2502024-07-29029 July 2024 – Issuance of Amendment No. 233 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24191A2432024-07-0909 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operations IR 05000416/20240102024-06-27027 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000416/2024010 ML24156A1762024-06-24024 June 2024 Regulatory Audit Summary in Support of License Amendment Requests to Adopt TSTF-505, Revision 2 and 10 CFR 50.69 (Epids L-2023-LLA-0081 and L-2023-LLA-0080) ML24165A1512024-06-13013 June 2024 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk-Informe ML24163A2652024-06-11011 June 2024 Inservice Inspection Summary Report ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 05000416/LER-2024-002, Automatic Actuation of Reactor Protection System2024-05-28028 May 2024 Automatic Actuation of Reactor Protection System ML24130A0912024-05-0909 May 2024 Request for Information Letter License Renewal Phase 2 Inspection ML24128A1512024-05-0909 May 2024 Project Manager Assignment ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000416/20240012024-05-0202 May 2024 Integrated Inspection Report 05000416 2024001 ML24122C6112024-05-0101 May 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. ML24116A0372024-04-25025 April 2024 Report of Technical Specification Bases Changes ML24113A0952024-04-22022 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24113A0972024-04-22022 April 2024 Annual Report of Individual Monitoring - NRC Form 5 for 2023 Per 1 0 CFR 20.2206 ML24107B0402024-04-16016 April 2024 Notification by Entergy Operations, Inc., of Proposed Economic Performance Incentive and Reliance on Post-Event Improvements in Plant Procedures And/Or Methods of Operation in FERC ML24107A8872024-04-16016 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24100A0692024-04-0909 April 2024 Report of Changes or Errors to 10 CFR 50.46 Analysis ML24094A0992024-04-0303 April 2024 (GGNS) Core Operating Limits Report (COLR) Cycle 25, Revision O ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24087A1962024-03-27027 March 2024 High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close IR 05000416/20220042024-03-19019 March 2024 – Amended Integrated Inspection Report 05000416/2022004 and Exercise of Enforcement Discretion ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24058A3512024-02-28028 February 2024 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 IR 05000416/20233012024-02-26026 February 2024 NRC Examination Report 05000416-2023301 ML24043A1892024-02-12012 February 2024 Spent Fuel Storage Radioactive Effluent Release Report for 2023 ML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24043A0732024-01-29029 January 2024 2024-01 Post Examination Comments IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 IR 05000416/20234012024-01-18018 January 2024 Cyber Security Inspection Report 05000416/2023401 (Public) ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 IR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 2024-09-09
[Table view] |
Text
- C:OPEntergy GNRO-2012/0129 October 25,2012 u.s.Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Entergy Operations, Inc.P.O.Box 756 Port Gibson, MS 39150 Michael Perito Vice President, Operations Grand Gulf Nuclear Station Tel.(601)437-6409
SUBJECT:
REFERENCE:
Initial Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
Grand Gulf Nuclear Station, Unit No.1 Docket No.50-416 License No.NPF-29 1.NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies forDesign-Basis External Events (GNRI-2012/00058) 2.NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012 (ML 12229A174) 3.Nuclear Energy Institute (NEI)Letter to NRC, Industry Initiative on Procurement of Equipment for the Diverse and Flexible Coping Strategy (FLEX), dated February 24, 2012 4.NEI 12-06, Diverse and Flexible Coping Strategies (FLEX)Implementation Guide, Revision 0, dated August 2012
Dear Sir or Madam:
On March 12,2012, the Nuclear Regulatory Commission
("NRC" or"Commission")
issued an order (Reference 1)to Grand Gulf Nuclear Station (GGNS).Reference 1 was immediately effective and directs GGNS to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event.Specific requirements are outlined in Attachment 2 of Reference 1.Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance.The final interim staff gUidance (Reference 2)was issued August 30, 2012.The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition Co2, of Reference 1 within 60 days following issuance GNRO-2012/0129 Page 2 of 3 of Reference 2.This report confirms GGNS has received Reference 2 and is in the process of evaluating the guidance for the purpose of establishing mitigation strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event as described in Attachment 2 of Reference 1.Major activities completed during this reporting period:*Additional portable equipment was ordered prior to the issuance of Reference 2, as described in an NEI letter to the NRC (Reference 3).*A site-specific evaluation is in progress to establish the coping capabilities as defined in NEI 12-06 (Reference 4).*Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.Planned activities for the next six months:*Development and submittal of the overall integrated plan.Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
- None at this time.Project milestones schedule through completion of installation and testing:*A project milestones schedule will be provided with the overall integrated plan.*Implementation of the order will be completed for GGNS Unit NO.1 prior to startup from Refueling Outage (RFO)Spring 2016.This letter contains no new regulatory commitments.
If you have any questions regarding this report, please contact Jeffery A.Seiter at437-6299.I declare under penalty of perjury that the foregoing is true and correct;executed on October 25,2012.MP/jas cc: (see next page)
GNRO-2012/0129 Page 3 of 3cc:Mr.Elmo E.Collins, Jr.Regional Administrator, Region IV U.S.Nuclear Regulatory Commission 1600 East Lamar Boulevard Arlington, TX 76011-4511 u.S.Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation One White Flint North 11555 Rockville Pike Rockville, MO 20852 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 u.S.Nuclear Regulatory Commission ATTN: Mr.A.Wang, NRRlDORL Mail Stop OWFN/8 G 14 11555 Rockville Pike Rockville, MO 20852-2378 u.S.Nuclear Regulatory Commission ATTN: Robert J.Fretz Jr.OWFN, Mailstop#4A15A 11555 Rockville Pike Rockville, MO 20852-2378 u.S.Nuclear Regulatory Commission ATTN: Robert L.Oennig OWFN, Mailstop#10E1 11555 Rockville Pike Rockville, MO 20852-2378 u.S.Nuclear Regulatory Commission Attn: Ms.Jessica A.Kratchman OWFN, Mailstop#902 11555 Rockville Pike Rockville, MD 20852-2378 u.S.Nuclear Regulatory Commission Attn: Mr.Eric E.Bowman OWFN, Mailstop#12020 11555 Rockville Pike Rockville, MO 20852-2378 u.S.Nuclear Regulatory Commission Attn: Ms.Eileen M.Mckenna TWFN, Mailstop#1005 11555 Rockville Pike Rockville, MO 20852-2378