UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 5, 2013 Vice President, Operations Entergy Operations, Inc.

Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150

SUBJECT:

GRAND GULF NUCLEAR STATION, UNIT 1 - CORRECTION TO JULY 30,2013, LETTER RELATED TO REQUEST FOR ADDITIONAL INFORMATION REGARDING OVERALL INTEGRATED PLAN FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER EA-12-051) (TAC NO. MF0955)

Dear Sir or Madam:

By letter dated July 30, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13207A124), the U.S. Nuclear Regulatory Commission (NRC) issued a request for additional information related to the Overall Integrated Plan in response to the March 12, 2012, NRC Order modifying licenses with regard to requirements for Reliable Spent Fuel Pool (SFP) Instrumentation for the Grand Gulf Nuclear Station, Unit 1.

Due to an administrative error, page 1 of the July 30,2013, letter was addressed incorrectly.

We have enclosed a replacement page 1.

We regret any inconvenience caused by this error. If you have any questions, please contact me at 301-415-1445 or via e-mail at alan.wang@nrc.gov.

Sincerely,

~LJy Alan Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosure:

As stated cc w/encl: Distribution via Listserv

ENCLOSURE CORRECTED PAGE 1 OF REQUEST FOR ADDITIONAL INFORMATION LETTER DATED JULY 30,2013 (ADAMS ACCESSION NO. ML13207A124)

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 July 30, 2013 Vice President, Operations Entergy Operations, Inc.

Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150

SUBJECT:

GRAND GULF NUCLEAR STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING OVERALL INTEGRATED PLAN FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER EA-12-051) (TAC NO. MF0955)

Dear Sir or Madam:

By letter dated February 26, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13064A417), Entergy Operations, Inc. (Entergy, the licensee),

submitted an Overall Integrated Plan (OIP) in response to the March 12,2012, U.S. Nuclear Regulatory Commission (NRC, Commission) Order modifying licenses with regard to requirements for Reliable Spent Fuel Pool (SFP) Instrumentation for the Grand Gulf Nuclear Station, Unit 1 (GGNS). The NRC staff has endorsed Nuclear Energy Institute (NEI) 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,'" Revision 1, August 2012 (ADAMS Accession No. ML12240A307), with exceptions, as documented in Interim Staff Guidance (ISG)

JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29,2012 (ADAMS Accession No. ML12221A339).

The NRC staff has reviewed your February 26,2013, response and determined that additional information is needed to complete its technical review. Enclosed is the NRC staff's request for additional information (RAI). The NRC staff requests that the responses be made within 30 days of receipt of this request or provide the date this information will be submitted in the 30-day response.

August 5, 2013 Vice President, Operations Entergy Operations, Inc.

Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150

SUBJECT:

GRAND GULF NUCLEAR STATION, UNIT 1 - CORRECTION TO JULY 30,2013, LETTER RELATED TO REQUEST FOR ADDITIONAL INFORMATION REGARDING OVERALL INTEGRATED PLAN FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER EA-12-051) (TAC NO. MF0955)

Dear Sir or Madam:

By letter dated July 30, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13207A124), the U.S. Nuclear Regulatory Commission (NRC) issued a request for additional information related to the Overall Integrated Plan in response to the March 12, 2012, NRC Order modifying licenses with regard to requirements for Reliable Spent Fuel Pool (SFP) Instrumentation for the Grand Gulf Nuclear Station, Unit 1.

Due to an administrative error, page 1 of the July 30, 2013, letter was addressed incorrectly.

We have enclosed a replacement page 1.

We regret any inconvenience caused by this error. If you have any questions, please contact me at 301-415-1445 or via e-mail at alan.wang@nrc.gov.

Sincerely, IRA!

Alan Wang, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosure:

As stated cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC LPLIV r/f RidsAcrsAcnw_MailCTR Resource RidsNrrDeEicb Resource RidsNrrDssSbpb Resource RidsNrrDoriDpr Resource RidsNrrDorlLpl4 Resource RidsNrrl-AJBurkhardt Resource RidsNrrPMGrandGulf Resource RidsRgn4MailCenter Resource ADAMS Accession No. ML13214A095 NRRlDORLlLPL4/BC NRRlDORLlLPL4/PM JBurkhardt DORLlLPL4/PM NRRlDORLlLPL4/LA MMarkley 8/2/13 8/5/13 OFFICIAL AGENCY RECORD