 Start dateSiteTitle
IR 05000220/201800314 November 2018Nine Mile PointIntegrated Inspection Report 05000220/2018003 and 05000410/2018003 and NRC Office of Investigations Report 1-2018-002
IR 05000220/201800413 February 2019Nine Mile PointIntegrated Inspection Report 05000220/2018004 and 05000410/2018004
IR 05000220/202100210 August 2021Nine Mile Point
07201036
Integrated Inspection Report 05000220/2021002 and 05000410/2021002 and Independent Spent Fuel Storage Installation Report 07201036/2021002
IR 05000220/202100419 May 2022Nine Mile PointReissued Integrated Inspection Report 05000220/2021004 and 05000410/2021004
IR 05000220/20220028 August 2022Nine Mile Point
07201036
Integrated Inspection Report 05000220/2022002 and 05000410/2022002 and Independent Spent Fuel Storage Installation Report 07201036/2022001
IR 05000226/200302523 April 1985Browns Ferry
05000226
Insp Rept 50-259/85-15,50-260/85-15 & 50-296/85-15 on 850226-0325.Violations Noted:Failure to Have All Three Trains of Standby Gas Treatment Operable & to Adhere to Tech Spec 6.3.A.6
IR 05000237/199801426 June 1998DresdenInsp Repts 50-237/98-14 & 50-249/98-14 on 980403-0527.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support
IR 05000237/200400230 April 2004DresdenIR 05000237-04-002 & 05000249-04-002, on 01/01/2004 - 03/31/2004, Exelon Generation Company, Dresden Nuclear Power Station, Units 2 and 3, Personnel Performance Related to Non-routine Evolutions and Events; Post-Maintenance Test and Other A
IR 05000237/20040125 November 2004DresdenIR 05000237-04-012(DRP); on 10/04/2004-10/08/2004, for Dresden Nuclear Power Station, Unit 2; Supplemental Inspection 95001 - Unplanned Reactor Scrams White Performance Indicator
IR 05000237/200401327 January 2005DresdenIR 05000237-04-013, 05000249-04-013, on 10/01/2004 - 12/31/2004; Exelon Generation Company, Dresden Units 2 & 3; Equipment Alignment, Operability Evaluations, Outage Activities, Surveillance Testing, Problem Identification and Resolution
IR 05000237/20050143 February 2006DresdenIR 05000237-05-014; IR 05000249-05-014 on 07/01/2005 - 01/04/2006 for Exelon Generation Company, Dresden Nuclear Power Station, Units 2 and 3; Event Followup
IR 05000237/201300231 July 2013DresdenEA-13-079; Final Significance Determination of a White Finding with Assessment Followup and Notice of Violation; NRC Inspection Report No. 05000237/2013002, 05000249/2013002; Dresden Nuclear Power Station, Units 2 and 3
IR 05000237/2013007Dresden
IR 05000237/201300931 July 2013DresdenEA-13-079; Final Significance Determination of a White Finding With Assessment Followup And Notice Of Violation; NRC Inspection Report No. 05000237/2013002, 05000249/2013002; Dresden Nuclear Power Station, Units 2 and 3
IR 05000237/201301022 January 2014DresdenIR 05000237-13-010, 05000249-13-010; 12/16/2013 - 12/20/2013; Dresden Nuclear Power Station, Units 2 & 3; Supplemental Inspection - Inspection Procedure (IP) 95001
IR 05000237/202200410 February 2023DresdenIntegrated Inspection Report 05000237/2022004, 05000249/2022004 and 07200037/2022002
IR 05000245/19850264 April 1986MillstoneInsp Repts 50-245/85-26 & 50-336/85-32 on 851029-1230.No Violation Noted.Major Areas Inspected:Plant Operations, Equipment Alignment & Readiness,Radiation Protection, Physical Security & Fire Protection
IR 05000245/198701821 September 1987MillstoneSafety Insp Rept 50-245/87-18 on 870731-0807.No Violations or Deviations Noted.Major Areas Inspected:Test Witnessing, Preliminary Results Evaluation of Containment Integrated Leak Rate Test & Tours of Facility
IR 05000245/19870278 December 1987MillstoneInsp Repts 50-245/87-27 & 50-336/87-23 on 870926-1026.No Violation Noted.Major Areas Inspected:Physical Security, Plant Operations,Surveillance & Maint Activities,Fuel Receipt & IE Bulletin 87-00l Followup
IR 05000245/198801617 March 1989MillstoneExam Rept 50-245/88-16OL on 881107-10.Exam Results:All Reactor Operator Candidates Passed Exams.Six Senior Reactor Operator (SRO) Candidates Passed Written Exam & Operating Test.One SRO Candidate Failed Written Exam
IR 05000245/19880992 October 1989MillstoneSALP Repts 50-245/88-99 & 50-336/88-99 for 880101-890615
IR 05000254/198600924 June 1986Quad CitiesInsp Repts 50-254/86-09 & 50-265/86-08 on 860413-0607.No Violation Noted.Major Areas Inspected:Previous Insp Findings,Operations,Radiological Controls,Emergency Preparedness & Security
IR 05000254/198701325 August 1987Quad CitiesInsp Repts 50-254/87-13 & 50-265/87-13 on 870607-0801. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Training,Bulletins, Generic Ltrs,Radiation Control,Outages & Licensee Meetings
IR 05000254/198701915 October 1987Quad CitiesInsp Repts 50-254/87-19 & 50-265/87-19 on 870802-1003. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Training,Radiation Control,Outages & Administrative Controls Affecting Quality
IR 05000254/198703324 February 1988Quad CitiesInsp Repts 50-254/87-33 & 50-265/87-33 on 871206-880206. Violations & Deviations Noted.Major Areas Inspected: Operations,Maint & Surveillance,Ler Review,Routine Repts & Administrative Controls Affecting Radiation Control
IR 05000254/19880011 December 1988Quad CitiesSALP Repts 50-254/88-01 & 50-265/88-01 for Apr 1987 - Sept 1988
IR 05000254/198800412 April 1988Quad CitiesInsp Repts 50-254/88-04 & 50-265/88-04 on 880207-0402. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Temporary Instructions & Administrative Controls Affecting Quality
IR 05000254/199601226 November 1996Quad CitiesInsp Repts 50-254/96-12 & 50-265/96-12 on 960823-0923. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support
IR 05000254/19980092 July 1998Quad CitiesInsp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
IR 05000254/19980112 July 1998Quad CitiesInsp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures
IR 05000254/199830313 April 1998Quad CitiesExam Repts 50-254/98-303OL & 50-265/98-303OL on 980316-20. Exam Results:All Three Applicants Passed All Portions of Respective Exams
IR 05000254/19990017 October 1999Quad CitiesInsp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity
IR 05000254/199900614 May 1999Quad CitiesInsp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support
IR 05000254/200200530 July 2002Quad CitiesIR 05000254-02-005, IR 05000265-02-005, Exelon Nuclear, on 04/01-06/30/2002, Quad Cities Nuclear Power Station, Units 1 & 2, non-routine Evolutions, Operability Evaluations, Event follow-up, and Other
IR 05000254/200400520 July 2004Quad CitiesIR 05000254-04-005, IR 05000265-04-005 on 04/01/2004-06/30/2004 for Quad Cities Nuclear Power Station, Units 1 & 2; Event Followup
IR 05000254/200400929 October 2004Quad CitiesIR 05000254-04-009; 05000265-04-009; on 07/01/2004 - 09/30/2004; Quad Cities Nuclear Power Station, Units 1 & 2; Problem Identification and Resolution, Event Followup; Other Activities
IR 05000254/200500329 July 2005Quad CitiesIR 05000254-05-003, IR 05000265-05-003 on 04/01/2005-06/30/2005 for Quad Cities Nuclear Power Station, Units 1 & 2; Operability Evaluations, Identification and Resolution of Problems, and Event Followup
IR 05000254/20080021 May 2008Quad CitiesIR 05000254-08-002 & 05000265-08-002, on 01/01/2008 to 03/31/2008, Quad Cities Nuclear Power Station, Units 1 and 2
IR 05000254/200800410 November 2008Quad CitiesIR 05000254-08-004, 05000265-08-004; on 07/01/2008 - 09/30/2008; Quad Cities Nuclear Power Station, Units 1 & 2; Flooding, Maintenance Risk Assessment, and Emergent Work Control
IR 05000254/201600128 April 2016Quad CitiesNRC Integrated Inspection Report 05000254/2016001; 05000265/2016001, January 1, 2016 Through March 31, 2016
IR 05000254/202201317 November 2022Quad CitiesBiennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013
IR 05000254/202301020 December 2023Quad CitiesComprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010
IR 05000259/19850193 April 1985Browns FerryEnforcement Conference Meeting Repts 50-259/85-19, 50-260/85-19 & 50-296/85-19 on 850314.Areas Reviewed:Reactor Startup W/Inoperable Water Level Instruments,Failure to Perform post-maint Testing & Certain Security Violations
IR 05000259/198604018 February 1987Browns FerryInsp Repts 50-259/86-40,50-260/86-40 & 50-296/86-40 on 861101-1231.Violations Noted:Failure to Correct Condition Adverse to Quality,Per 10CFR50,App B
IR 05000259/198702631 July 1987Browns FerryInsp Repts 50-259/87-26,50-260/87-26 & 50-296/87-26 on 870601-30.Violations Noted.Major Areas Inspected:Maint Observation,Environ Qualification of Electrical Equipment, Employee Concerns Program & Operator Training
IR 05000259/19890063 May 1989Browns FerryInsp Repts 50-259/89-06,50-260/89-06 & 50-296/89-06 on 890130-0203 & 0214-0310.Violations & Deviations Noted.Major Areas Inspected:Adequacy of Testing,Calibr,Maint & Configuration Control of safety-related Instrumentation
IR 05000259/20030025 May 2003Browns FerryIR 05000259-03-002, IR 05000260-03-002, IR 05000296-03-002, on 12/29/2002 - 04/05/2003, Tennessee Valley Authority; Browns Ferry, Units 1, 2 and 3; Event Follow-up
IR 05000259/200500715 August 2005Browns FerryIR 05000259-05-007, on 04/17/2005 - 07/16/2005, Tennessee Valley Authority
IR 05000259/200600228 April 2006Browns FerryIR 05000259-06-002, 05000260-06-002, 05000296-06-002; 01/01/2006 - 03/31/2006; Browns Ferry Nuclear Plant, Units 1, 2, and 3; Maintenance Risk Assessments, Emergent Work Evaluation, and Event Follow Up
IR 05000259/20060095 March 2007Browns FerryIR 05000259-06-009, Brown Ferry, Unit 1 Recovery - NRC Integrated Inspection Report