IR 05000298/2002003 | 31 October 2002 | IR 05000298-02-003, on 07/07-10/05/02; Cooper Nuclear Station. Integrated Resident/Regional Report; Permanent Plant Modifications, Access Authorization, Identification & Resolution of Problems | Safe Shutdown Grab sample Fire Barrier Contraband Temporary Modification Condition Adverse to Quality Significance Determination Process Operability Determination Maintenance Rule Program Continuous fire watch Fire Protection Program Power change Downpower Siren |
ML021700168 | 25 October 2002 | Boiling Water Reactor Vessel and Internals Project (BWRVIP) Project Implementation | |
ML022730516 | 11 October 2002 | Y020020211 - Reply to M. Mulligan Dated 10/11/02 (3) e-mails to V Dricks-Safety Concern & Corruption: Cooper & Missouri River, NRC and Cooper Ethical & Safety Concern, and Cooper Nuclear Station | Ultimate heat sink |
ML022760528 | 10 October 2002 | Letter and Safety Evaluation, Quality Assurance Plan. Review of Cooper Nuclear Station Quality Assurance Program Plan Changes | |
ML022840212 | 10 October 2002 | OI 4-2001-043, Nebraska Public Power District, Closure of Investigation | |
ML022890339 | 8 October 2002 | Proposed Technical Specification Amendment - Personnel Title Revisions and Reference Correction to Technical Specification Section 5.0, Administrative Controls for Cooper Nuclear Station | |
ML023050200 | 21 October 2002 | Attachment 18, Cooper Nuclear Station, Draft RAI on Supplemental Information Submitted by Nebraska Public Power District, Collapsed Load Method Used for Stress Analysis of Main Steam Line Piping | |
ML023090066 | 4 November 2002 | Meeting with Nebraska Public Power District Development and Submission of Revision 2 of Cooper Nuclear Station Strategic Improvement Plan | |
ML023090207 | 5 November 2002 | Summary of Category 1 Meeting with Nebraska Power, Cooper -Ultimate Heat Sink Amendment Request | Ultimate heat sink |
ML023090550 | 4 November 2002 | Generic Fundamentals Examination - Copy of PWR & BWR GFEs & Answer Keys Available on NRCs Website 60 Days Following Exam | Generic Fundamentals Examination |
ML023100131 | 13 November 2002 | Memo Draft Documents for June 26, 2002 Through October 28, 2002 | |
ML023290202 | 20 November 2002 | Summary of Meeting with Cooper Nuclear Station. Refers to Meeting Conducted on on 11/18/2002 to Discuss Development & Submission of Revision 2 of Cooper Nuclear Station Strategic Improvement Plan | |
ML023300547 | 26 November 2002 | Notification of NRC Initial Operator Licensing Examination (Examination Report 50-298/03-301) | |
ML023310442 | 27 November 2002 | Forthcoming Meeting with Nebraska Public Power District (Nppd), Cooper Licensee'S BWRVIP Briefing | |
ML023400185 | 3 December 2002 | NRC Plans to Administer Generic Fundamentals Section of Written Operator Licensing Examination on 02/05/2003 | Generic Fundamentals Examination |
ML023400623 | 6 December 2002 | Meeting Notice Revision 2 of Strategic Improvement Plan | |
ML023510123 | 16 December 2002 | Init EXAM-08/2002 - Final Written Exam Outlines | Shutdown Margin |
ML023540251 | 20 December 2002 | Withholding Information from Public Disclosure, TAC No. MB6816 | |
ML030290523 | 13 December 2002 | Briefing Slides for Presentation Status of the CNS BWRVIP Program from 12/13/2002 Meeting with Nebraska Public Power District | EVT-1 |
NLS2002093, Additional Information Related to License Condition 2.C.(6) Seismic Evaluation | 19 December 2002 | Additional Information Related to License Condition 2.C.(6) Seismic Evaluation | |
NLS2002104, License Amendment Request, Adopt Integrated Reactor Vessel Material Surveillance Program | 31 December 2002 | License Amendment Request, Adopt Integrated Reactor Vessel Material Surveillance Program | Unanalyzed Condition Anticipated operational occurrence Hydrostatic Abnormal operational transient |
NLS2002111, Inservice Testing Program Relief Request RP-06, RP-07 | 14 November 2002 | Inservice Testing Program Relief Request RP-06, RP-07 | Incorporated by reference |
NLS2002122, 10CFR50.59(d)(2) Summary Report | 17 October 2002 | 10CFR50.59(d)(2) Summary Report | Safe Shutdown Stroke time Internal Flooding Fire impairment Nondestructive Examination Temporary Modification Qualified Offsite Circuit Systematic Assessment of Licensee Performance Offsite Circuit Hourly Fire Watch Unidentified leakage Overspeed trip |
NLS2002123, Reply, IR 05000298-02-007, Dated 09/20/02, Cooper Nuclear Station | 18 October 2002 | Reply, IR 05000298-02-007, Dated 09/20/02, Cooper Nuclear Station | Condition Adverse to Quality Power change |
NLS2002125, Clarification of Amendment No.194 Safety Evaluation Cooper Nuclear Station | 7 October 2002 | Clarification of Amendment No.194 Safety Evaluation Cooper Nuclear Station | |
NLS2002126, September 2002 Monthly Operating Report for Cooper Nuclear Station | 10 October 2002 | September 2002 Monthly Operating Report for Cooper Nuclear Station | |
NLS2002128, Revision to Service List | 7 October 2002 | Revision to Service List | |
NLS2002129, License Amendment Request to Revise TS-Safety Limit Minimum Critical Power Ratio, Cooper Nuclear Station | 15 November 2002 | License Amendment Request to Revise TS-Safety Limit Minimum Critical Power Ratio, Cooper Nuclear Station | Reactor Vessel Water Level Safety Limit Minimum Critical Power Ratio Anticipated operational occurrence Abnormal operational transient Fuel cladding |
NLS2002133, Clarification of Safety Evaluation, Quality Assurance Program | 6 November 2002 | Clarification of Safety Evaluation, Quality Assurance Program | |
NLS2002135, Design Basis Accident Radiological Assessment Calculation Methodology Additional Information | 25 November 2002 | Design Basis Accident Radiological Assessment Calculation Methodology Additional Information | Safe Shutdown Earthquake Operating Basis Earthquake Seismically rugged |
NLS2002136, Response to Draft Request for Additional Information on the Supplemental Information Submitted by Nebraska Public Power District for Cooper Nuclear Station License Condition, 2.6 (6) | 25 November 2002 | Response to Draft Request for Additional Information on the Supplemental Information Submitted by Nebraska Public Power District for Cooper Nuclear Station License Condition, 2.6 (6) | |
NLS2002137, Regulatory Information Summary (RIS) 2002-15, NRC Approval of Commercial Data Encryption Systems for the Electronic Transmission of Safeguards Information. | 6 November 2002 | Regulatory Information Summary (RIS) 2002-15, NRC Approval of Commercial Data Encryption Systems for the Electronic Transmission of Safeguards Information. | |
NLS2002138, October 2002 Monthly Operating Report for Cooper Nuclear Station | 15 November 2002 | October 2002 Monthly Operating Report for Cooper Nuclear Station | |
NLS2002141, the Strategic Improvement Plan, Revision 2, Appendix A-3, Action Plan 5.4.1.4 | 25 November 2002 | the Strategic Improvement Plan, Revision 2, Appendix A-3, Action Plan 5.4.1.4 | Temporary Modification Maintenance Rule Program Scaffolding Power change |
NLS2002142, Reporting of Changes and Errors in ECCS Evaluation Models | 20 December 2002 | Reporting of Changes and Errors in ECCS Evaluation Models | |
NLS2002143, November 2002 Monthly Operating Report for Cooper | 12 December 2002 | November 2002 Monthly Operating Report for Cooper | |
NLS2002144, Notification to the NRC of the New Vice President-Nuclear at Cooper | 10 December 2002 | Notification to the NRC of the New Vice President-Nuclear at Cooper | |
NLS2002145, Revised May Through October 2002 Monthly Report for Cooper Nuclear Station | 20 December 2002 | Revised May Through October 2002 Monthly Report for Cooper Nuclear Station | |
NLS2009057, Nedc 87-131B, Revision 8, Cooper Nuclear Station, 250 Vdc Division II Load and Voltage Study. | 20 November 2002 | Nedc 87-131B, Revision 8, Cooper Nuclear Station, 250 Vdc Division II Load and Voltage Study. | Safe Shutdown Stroke time |
TAC:MB5191 | 25 October 2002 | ||
TAC:MB6271 | 10 October 2002 | ||
TAC:MB6816 | 20 December 2002 |