IA-85-160, Trip Rept of Site Visit During Wk of 831031 Re Physical Arrangement & Installation of Electrical,Instrumentation & Control Equipment.Compliance W/Nrc Design Criteria Confirmed | 13 April 1984 | Trip Rept of Site Visit During Wk of 831031 Re Physical Arrangement & Installation of Electrical,Instrumentation & Control Equipment.Compliance W/Nrc Design Criteria Confirmed | Safe Shutdown |
IA-86-778, Trip Rept of 860514-15 Site Visit Re Seismic Design Issues Concerning Cable Trays,Conduit Qualification,Hvac Concerns, CRD Return Lines,Ie Bulletins 79-14 & 79-02 & Nonessential Piping.Request for Addl Info Re Vermont Yankee Encl | 31 July 1986 | Trip Rept of 860514-15 Site Visit Re Seismic Design Issues Concerning Cable Trays,Conduit Qualification,Hvac Concerns, CRD Return Lines,Ie Bulletins 79-14 & 79-02 & Nonessential Piping.Request for Addl Info Re Vermont Yankee Encl | Earthquake Backfit |
IA-86-855, Summary of 860909 Meeting W/Utils Re Improving Lines of Communication Between NRC & Licensees,Including Sholly Process,Interpretation of 10CFR50.59,Tech Spec Improvement Program & Discretionary Enforcement.Related Info Encl | 18 November 1986 | Summary of 860909 Meeting W/Utils Re Improving Lines of Communication Between NRC & Licensees,Including Sholly Process,Interpretation of 10CFR50.59,Tech Spec Improvement Program & Discretionary Enforcement.Related Info Encl | Backfit |
IR 05000259/1989010 | 29 June 1989 | Summary of 890606 Meeting W/Util in Rockville,Md Re Handling of Clay Pipe Issue & Condition Adverse to Quality Program, Per Findings in Insp Repts 50-259/89-10,50-260/89-10 & 50-296/89-10.List of Attendees & Presentation Slides Encl | Condition Adverse to Quality Operability Determination |
IR 05000259/1997004 | 6 February 1998 | Summary of 980126 Meeting W/Tennessee Valley Authority Re Resolution of Unresolved Issue 50-290/97-04-01 Identified in Insp Rept 50-259/97-04.List of Attendees Encl | |
ML17276A176 | 2 November 1981 | Forwards Minutes from Mechanical Engineering Branch 810929-30 & 1001 Meetings in Woodbury,Ny & 811016 Preservice Insp Meeting in Washington,Dc.Agenda Items from Both Meetings & Subsequent Resolution Encl | |
ML18038B351 | 6 June 1995 | Trip Rept of 950514-16 Visit to Browns Ferry Nuclear Power Stations Re Blast Evaluation & Subsequent Vehicle Barrier Location | |
ML18139B967 | 13 July 1982 | Trip Rept of 820512-14 Visit to Facilities Re Radiological Effluent Tech Specs | Offsite Dose Calculation Manual Process Control Program Backfit |
ML20054F286 | 27 May 1982 | Summary of 820506 Meeting W/Util & Sargent & Lundy in Bethesda,Md Re Program for Seismic Qualification of Equipment | |
ML20054J030 | 17 June 1982 | Summary of 820430 Meeting W/Utils & Bechtel in Bethesda,Md Re Alternate Shutdown Panel & Related Fire Protection | |
ML20055F094 | 10 July 1990 | Summary of 900620 Meeting W/Util Re Proposed License Amends, Including Removal of Snubber Requirements from Tech Specs for Relocation Into Inservice Insp Program & Util Responses to Generic Ltrs 88-01 & 87-09 | |
ML20055G861 | 18 July 1990 | Summary of 900712 Meeting W/Util Re Reload Design Methods. List of Attendees Encl | |
ML20056C525 | 18 June 1993 | Summary of 930513 Meeting W/Util Re Changes to Security & Response Plans.Meeting Agenda & List of Attendees Encl | |
ML20056D834 | 26 May 1993 | Summary of Operator Reactors Event Meeting 93-18 on 930519 | Loop seal |
ML20056D980 | 30 July 1993 | Summary of 930720 Meeting W/Util in Rockville,Md to Discuss Plans & Schedule to Implement Improved STS at Plant.Meeting Attendees Listed in Encl 1 | Backfit |
ML20056E973 | 9 August 1993 | Summary of 930728 Meeting W/Util in Rockville,Md to Discuss Proposed Mods to Reactor Vessel Water Level Instrumentation, Per NRC Bulletin 93-03.List of Attendees Encl | Reactor Vessel Water Level Probabilistic Risk Assessment |
ML20056F922 | 26 August 1993 | Summary of 930803 Meeting W/Util in Rockville,Md Re Proposed Cost Beneficial Security Program Revs at Browns Ferry Nuclear Plant.List of Attendees & Meeting Handouts Encl | Fitness for Duty |
ML20057D076 | 27 September 1993 | Summary of 930903 Meeting W/Util in Rockville,Md Re Ways Util Might Improve Quality & Completeness of Plant Licensing Submittals.List of Meeting Attendees & List of Specific Licensing Submittals Discussed During Meeting Encl | |
ML20058G944 | 7 December 1993 | Summary of 931110 Meeting W/Tva in Rockville,Md Re TVA Plans to Improve Quality of Licensing Submittals for Bfn.List of Attendees & Handouts Encl | |
ML20058M449 | 8 August 1990 | Summary of 900727 Meeting W/Util on Site Re Plant Tour. Restart Status & Condition of Unit 2 Primary Focus of Site Tour.List of Attendees Encl | |
ML20059C742 | 2 March 1993 | Summary of 392nd ACRS Meeting on 921209-11 in Bethesda,Md Re SBO Rule,Ts Improvement Program,Advanced BWR Design,River Bend Nuclear Plant Reliability Monitoring Program & Generic Issue 120,online Testability of Protection Sys | High Radiation Area Probabilistic Risk Assessment Flow Induced Vibration |
ML20079R092 | 18 June 1979 | Agenda for 790618 Meeting W/Nrc to Discuss Facility Const & Licensing.Related Info Encl | |
ML20079R105 | 14 September 1979 | Agenda for 790918-20 Caseload Forecast Panel Site Visit. Related Info Encl | |
ML20079R110 | 25 July 1980 | Agenda for 800729 Caseload Forecast Panel Site Visit. Related Info Encl | Coatings |
ML20079R129 | 24 August 1981 | Agenda for 810825 Meeting W/Nrc Caseload Forecast Panel to Conduct Plant Tour.Related Info Encl | |
ML20084K275 | 27 January 1971 | Trip Rept of 710120 Visit to Plant Re Plans for Replacement of Dome Concrete & Review of Specs for Work.Concrete Removal Operation Satisfactory | |
ML20098D112 | 5 April 1982 | Summary of 820405 Special Meeting of WPPSS Executive Board in Richland,Wa Re Status of Projects,Selection of Cost Effectiveness Study Consultant,Bpa Draft Power Load Forecast & Units 4 & 5 Termination Program | Hydrostatic |
ML20098D137 | 23 April 1982 | Summary of 820423,28 & 29 Regular Meetings of WPPSS Board of Directors in Richland,Wa Re Units 4 & 5 Termination Program, Claim Vouchers & BPA Finance Proposal.Notice of Adjournment for 820423 Meeting Encl | |
ML20098D199 | 23 April 1982 | Summary of 820423 Special Meeting of WPPSS Executive Board in Richland,Wa Re Financial Problems W/Continued Const of Facilities.Notices of Adjournment Encl | |
ML20117M362 | 11 January 1984 | Agenda for Util 840111 Performance Overview | Reactor Vessel Water Level High Radiation Area Non-Destructive Examination Fire Barrier Weld Overlay Hydrostatic Nondestructive Examination Scram Discharge Volume Process Control Program Systematic Assessment of Licensee Performance Control of Heavy Loads Fire Protection Program Fire Watch Overexposure |
ML20125A420 | 11 September 1978 | Summary of 780824 NRC Meeting Held W/Ge,Tva,Nsp, & B & P Representatives to Discuss Swelling in Four GE High Density Spent Fuel Storage Racks in Monticello Spent Fuel Pool. (Encl to 7809210158) | Hydrostatic |
ML20125C562 | 1 May 1978 | Summary of 780309-10 Meeting W/Mark I Owners Group in Bethesda,Md Re Changes in Long Term Program as Reflected in Rev 3 to Mark I Owners Group Program Action Plan | |
ML20125C571 | 9 September 1976 | Summary of 760812 Meeting W/Mark I Owners Group,Ge,Epri & Techncial Consultants Re Listed Long Term Program Tasks | |
ML20125C572 | 9 September 1976 | Summary of 760819 Meeting W/Mark I Owners Group,(Ge) in Bethesda,Md Re Discussions on Mark I Containment Ltp.List of Attendees Encl | |
ML20125D034 | 2 December 1992 | Summary of 921015 Meeting W/Util in Rockville,Md Re Util Plans for Conducting Expanded IPE for Plant.List of Attendees & Meeting Handouts Encl | |
ML20125D658 | 18 August 1976 | Summary of 760717-08 Meeting W/Representatives of Mark I Owners Group in Bethesda,Md Re Discussions on Reassessed Content of Mark I Containment LTP & Recently Submitted Responses to Questions on STP Final Rept | |
ML20126D813 | 1 May 1973 | Trip Rept of 730424-25 Site Visit to Obtain First Hand Knowledge of Site & Environs & to Discuss Possible Problem Areas.Attendance List Encl | |
ML20126G058 | 12 March 1981 | Summary of Caseload Forecast Panel 810303-05 Meeting & Site Visit W/Utils & S&W in St Francisville,La Re Scheduling of Const & Observing Const Activities in Progress.Attendance List,Meeting Agenda,Handouts & Visual Aids Encl | |
ML20126K429 | 30 December 1992 | Summary of 921201 Meeting W/Util in Rockville,Md Re Discussions on Proposed Upgrade of Refueling Floor & RB Radiation Monitoring Equipment,Including Proposed Revs to Plants TS Submitted in Ltr | |
ML20126K443 | 30 December 1992 | Summary of 921216 Meeting W/Util in Rockville,Md Re Discussions on Design & Operation of Plant Hardened Wetwell Vent.List of Attendees & Meeting Agenda Encl | Containment Hardened Vent |
ML20126L233 | 1 May 1981 | Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation | |
ML20127A468 | 1 March 1978 | Summary of 771129 Meeting W/Mark I Owners Group & GE in San Franciso,Ca Re Listed Topics,Including Results & Bases for long-term Program Decision Point 3.List of Attendees & Viewgraphs Encl | |
ML20127A700 | 5 June 1985 | Summary of 850506 Meeting W/Utils & Bechtel Corp in Bethesda,Md Re Respiratory Protection for Subatmospheric Containments.Agenda & List of Attendees Encl | |
ML20127B510 | 13 April 1984 | Trip Rept of Site Visit During Wk of 831031 Re Physical Arrangement & Installation of Electrical,Instrumentation & Control Equipment.Compliance W/Nrc Design Criteria Confirmed | Safe Shutdown |
ML20127D157 | 13 June 1985 | Summary of 850530 Operating Reactor Events Meeting to Brief Ofc Director,Div Directors & Representatives on Events Since 850515 Meeting.List of Attendees,Viewgraphs & Status of Assignments Encl | Shutdown Margin |
ML20127J028 | 13 June 1985 | Summary of 850514-15 Meetings & Site Visit W/Util in North Carolina Re Audit of Spds.List of Attendees & Viewgraphs Encl | Post Accident Monitoring |
ML20127N902 | 24 June 1985 | Summary of Operating Reactors Events Meeting 85-10 on 850612.Only 3 of 17 Items Scheduled for Completion by 850531 Remain Incomplete.List of Attendees,Summary of Events Discussed & Status of Previous Assignments Encl | Scram Discharge Volume |
ML20127P488 | 10 May 1985 | Summary of 850411 Meeting W/Util & S&W in Bethesda,Md to Review Issues Associated W/Containment as Result of Tech Spec Review | |
ML20128A906 | 13 May 1985 | Summary of 850507 Operating Reactors Events Meeting.List of Attendees,Events Discussed & Assignments Encl | |
ML20128C251 | 5 November 1973 | Summary of 731101 Meeting W/Util,Bechtel,Ssi,Southern Svcs, USGS & Dept of Army,Chief of Engineers in Bethesda,Md Re Geology & Subsurface Exploration of Plant Site.List of Attendees & Review Status as of 730531 Encl |