Issue date | Title | Topic | |
---|---|---|---|
CNL-14-218, Application to Modify Technical Specification 3.8.1 Regarding Diesel Generator Steady State Frequency (WBN-TS-13-08) | 6 April 2015 | Application to Modify Technical Specification 3.8.1 Regarding Diesel Generator Steady State Frequency (WBN-TS-13-08) | Safe Shutdown Boric Acid Stroke time Anticipated operational occurrence Offsite Circuit |
CNL-15-001, Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03) | 31 March 2015 | Application to Revise Technical Specification 4.2.1, Fuel Assemblies, (WBN-TS-15-03) | Boric Acid Shutdown Margin Offsite Dose Calculation Manual Anticipated operational occurrence Tritium |
CNL-15-088, Application to Revise Technical Specifications for Component Cooling Water Snd Essential Raw Cooling Water to Support Dual Unit Operation (TS-WBN-15-13) | 17 June 2015 | Application to Revise Technical Specifications for Component Cooling Water Snd Essential Raw Cooling Water to Support Dual Unit Operation (TS-WBN-15-13) | Safe Shutdown Ultimate heat sink Offsite Circuit |
CNL-15-133, Response to Request for Additional Information Related to Technical Specification 3.8.1 Regarding Diesel Generator Steady State Frequency (WBN-TS-13-08) | 15 July 2015 | Response to Request for Additional Information Related to Technical Specification 3.8.1 Regarding Diesel Generator Steady State Frequency (WBN-TS-13-08) | Boric Acid Stroke time |
CNL-17-044, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 3.7.12, Auxiliary Building Gas Treatment System (Abgts), for Watts Bar Nuclear Plant, Units 1 and 2 | 5 May 2017 | Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification 3.7.12, Auxiliary Building Gas Treatment System (Abgts), for Watts Bar Nuclear Plant, Units 1 and 2 | Safe Shutdown Unanalyzed Condition |
CNL-17-123, Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (WBN-TS-16-025) | 29 September 2017 | Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (WBN-TS-16-025) | Boric Acid Shutdown Margin Anticipated operational occurrence Fuel cladding |
CNL-17-128, Application to Modify the Watts Bar Nuclear Plant Unit 2 Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Fluid Oil Pressure (391-WBN-TS-17-23) | 11 October 2017 | Application to Modify the Watts Bar Nuclear Plant Unit 2 Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Fluid Oil Pressure (391-WBN-TS-17-23) | Anticipated operational occurrence Fuel cladding |
CNL-17-149, Revised Additional Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (WBN-TS-16-025) | 27 December 2017 | Revised Additional Supplement to Application to Revise Technical Specifications to Adopt TSTF-547, Revision 1, Clarification of Rod Position Requirements (WBN-TS-16-025) | Shutdown Margin |
CNL-19-097, Non-Voluntary License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values (TS-19-22) | 23 October 2019 | Non-Voluntary License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values (TS-19-22) | |
CNL-19-105, Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) | 10 October 2019 | Supplemental Response to Second-Round NRC Request for Additional Information Regarding Application to Revise Technical Specifications Regarding DC Electrical Systems TSTF-500, Revision 2 (WBN-TS-18-09) | |
CNL-20-004, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.5, LOP DG Start Instrumentation, (WBN-TS-20-01) | 17 January 2020 | Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.5, LOP DG Start Instrumentation, (WBN-TS-20-01) | Open Phase Condition |
CNL-20-008, Application to Modify Watts Bar Nuclear Plant (WBN) Unit 2 Technical Specification 5.9.6, Reactor Coolant System Pressure and Temperature Limits Report, (WBN-TS-19-28) | 27 July 2020 | Application to Modify Watts Bar Nuclear Plant (WBN) Unit 2 Technical Specification 5.9.6, Reactor Coolant System Pressure and Temperature Limits Report, (WBN-TS-19-28) | Unanalyzed Condition Anticipated operational occurrence Hydrostatic Pressure and Temperature Limits Report Surveillance Frequency Control Program |
CNL-20-016, Application to Modify Watts Bar Nuclear Plant Unit 1 Technical Specifications 3.3.3, Post Accident Monitoring Instrumentation, (WBN-TS-19-23) | 22 June 2020 | Application to Modify Watts Bar Nuclear Plant Unit 1 Technical Specifications 3.3.3, Post Accident Monitoring Instrumentation, (WBN-TS-19-23) | Reactor Vessel Water Level Anticipated operational occurrence Post Accident Monitoring |
CNL-22-008, and Watts Bar Nuclear Plant - Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (BFN-TS-541, SQN-TS-21-09, and WBN-TS-22-002) | 13 June 2022 | and Watts Bar Nuclear Plant - Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (BFN-TS-541, SQN-TS-21-09, and WBN-TS-22-002) | Time of Discovery Incorporated by reference Missed surveillance |
CNL-23-002, Application to Revise Watts Bar Nuclear Plant Units 1 and 2 Technical Specifications to Change the Number of Tritium Producing Burnable Absorber Rods (WBN-TS-21-02) and Proposed Revision to Reactor Vessel Surveillance Capsule Removal Sche | 20 March 2023 | Application to Revise Watts Bar Nuclear Plant Units 1 and 2 Technical Specifications to Change the Number of Tritium Producing Burnable Absorber Rods (WBN-TS-21-02) and Proposed Revision to Reactor Vessel Surveillance Capsule Removal Schedu | |
CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) | 28 June 2023 | Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) | Safe Shutdown Hydrostatic Surveillance Frequency Control Program Offsite Circuit |
CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) | 2 August 2023 | Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) | Coatings Surveillance Frequency Control Program Fuel cladding |
CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) | 18 December 2023 | Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) | Safe Shutdown Anticipated operational occurrence |
CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23- | 20 September 2023 | Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 | Coatings Surveillance Frequency Control Program Fuel cladding |
ML023520628 | 13 December 2002 | Proposed License Amendment Request Change No.WBN-TS-02-16 - Steam Generator Tube Repair Sleeve | Nondestructive Examination Earthquake |
ML031420192 | 14 May 2003 | Technical Specifications Change No.TS-03-10 - Reactor Coolant System Flow Measurement Using Elbow Tap Methodology | Anticipated operational occurrence Fuel cladding |
ML032450157 | 21 August 2003 | Technical Specification (TS) Change No. TS-02-13 - Robust Fuel Assembly (RFA)-2 Upgrade - Revised Page | |
ML033220382 | 13 November 2003 | Technical Specification Pages for Watts Bar, Unit 1, Issuance of Amendment No. 49, Modifying TSs 5.1, 5.2.2, 5.3, 5.7.2.4, 5.7.2.7, 5.9.4, and 5.11 | High Radiation Area Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program |
ML033320395 | 21 November 2003 | License Amendment (WBN-TS-03-12) Monitoring of Control or Shutdown Rod Position by an Alternate Means | Shutdown Margin |
ML033380974 | 3 December 2003 | Correction Page for Amendment No. 49 Regarding Technical Specification Section 5.0, Administrative Controls | High Radiation Area |
ML040050393 | 5 January 2004 | Corrected Pages for Amendment No. 49 Regarding Technical Specification Section 5.0, Administrative Controls. | |
ML041040261 | 5 April 2004 | to Engineering Report Watts Bar Nuclear Plant, Unit 1, Ultimate Heat Sink - 88oF Maximum Operating Temperature Evaluation. | Safe Shutdown Boric Acid Ultimate heat sink Anticipated operational occurrence Time to boil Safe Shutdown Earthquake Enforcement Discretion Pressure Boundary Leakage GOTHIC |
ML042640210 | 15 September 2004 | Technical Specifications Change 04-09 - Mode Change Limitations Using the Consolidated Line Item Improvement Process | Boric Acid Shutdown Margin Grab sample Post Accident Monitoring Incorporated by reference Missed surveillance Offsite Circuit |
ML050980208 | 21 March 2005 | Tech Spec Pages for Amendment No. 57, Elimination of Monthly Report Requirement on Operating & Occupational Reports (TS-04-15) | Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program |
ML052650061 | 20 September 2005 | T.S. for License Amendment, Regarding Alternative Means for Monitoring Control or Shutdown Rod Position | |
ML061650267 | 12 June 2006 | Technical Specifications (TS) Change WBN-TS-05-10 - Application for Technical Specification Improvement Regarding Steam Generator Tube Integrity - Request for Additional Information | |
ML071210604 | 25 April 2007 | (WBN) Unit 1 - Technical Specification Change 07-01, Revision of Number of Tritium Producing Burnable Absorber Rods (TPBARS) in the Reactor Core | |
ML083170861 | 12 November 2008 | License Amendment Request TS-08-11 to Revise Reactor Coolant System Leakage Detection Systems - Exigent Change Request | Grab sample Fuel cladding Pressure Boundary Leakage |
ML090090044 | 31 December 2008 | Revised Technical Specifications Change WBN-TS-08-04 - Revision to the Maximum Number of TPBARS That Can Be Irradiated in the Reactor Core Per Cycle | |
ML091320562 | 30 April 2009 | Application for Technical Specification Change to Correct Minor Error in Amendment 70 | |
ML092950340 | 20 October 2009 | License Amendment Request for Adoption of TSTF-511, Revision 0, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 - Browns Ferry TS Change 469; Sequoyah Change 09-04; and Watts Change 09-19 | Safe Shutdown |
ML100550367 | 2 February 2010 | Developmental Revision B - Technical Specifications Table of Contents | Shutdown Margin High Radiation Area Ultimate heat sink Offsite Dose Calculation Manual Post Accident Monitoring Pressure and Temperature Limits Report Process Control Program |
ML100550401 | 2 February 2010 | Developmental Revision B - Technical Specifications 1.0 - Use and Application | Time of Discovery Shutdown Margin Hydrostatic Pressure Boundary Leakage |
ML100550441 | 2 February 2010 | Developmental Revision B - Technical Specifications 2.0 - Safety Limits | |
ML100550447 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.0 - Limiting Condition for Operation (LCO) Applicability | Time of Discovery |
ML100550449 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.1 - Reactivity Control Systems | Shutdown Margin |
ML100550450 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.2 - Power Distribution Limits | |
ML100550451 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.3 - Instrumentation | Reactor Vessel Water Level Post Accident Monitoring |
ML100550453 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.4 - Reactor Coolant System | Grab sample Hydrostatic Pressure Boundary Leakage Power change |
ML100550456 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.5 - Emergency Core Cooling Systems | |
ML100550458 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.6 - Containment Systems | High Radiation Area |
ML100550461 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.7 - Plant Systems | Ultimate heat sink |
ML100550462 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.8 - Electrical Power Systems | Offsite Circuit |
ML100550464 | 2 February 2010 | Developmental Revision B - Technical Specifications 3.9 - Refueling Operations | |
ML100550471 | 2 February 2010 | Developmental Revision B - Technical Specifications 4.0 - Design Features |