Summary of 930202 Meeting W/Util Re Proposed Amend Requests Currently Under Review.Amends Included,Refueling & Fuel Handling Spec Changes,Containment Penetration List Removal & Instrumentation Spec ChangesML20128H958 |
Person / Time |
---|
Site: |
Prairie Island |
---|
Issue date: |
02/10/1993 |
---|
From: |
Gamberoni M Office of Nuclear Reactor Regulation |
---|
To: |
Office of Nuclear Reactor Regulation |
---|
References |
---|
GL-91-08, GL-91-8, TAC-M83379, TAC-M83380, TAC-M84058, TAC-M84059, TAC-M84671, TAC-M84672, NUDOCS 9302170245 |
Download: ML20128H958 (6) |
|
|
---|
Category:MEETING MINUTES & NOTES--CORRESPONDENCE
MONTHYEARML20206G5151999-04-30030 April 1999 Summary of 990421 Meeting with Util Re Error Involving Recent ATWS Analyses Using GE Odyn Code.List of Attendees Encl ML20207L7711999-03-11011 March 1999 Summary of 990223 Meeting with NSP to Discuss Potential NRC Review Process for New Core & Thermal Hydraulic Computer Modeling Methods Currently Under Evaluation by NSP ML20202J2031999-01-28028 January 1999 Summary of 990107 Meeting with NSP Re Recent License Amend Request for PINGP Ts.List of Meeting Participants & NSP Meeting Presentation Slides Encl ML20196F6101998-12-0101 December 1998 Summary of 981029 Meeting with Northern States Power, Wisconsin Electric,Wisconsin Public Service & Alliant-IES in Rockville,Md Re Various Aspects of Potential Regulatory Issues Associated with Ongoing Cooperative Efforts ML20249C4711998-06-24024 June 1998 Summary of 980611 Meeting W/Wog in Rockville,Md Re Part Length CRDM Issues.List of Attendees & Matl Presented at Meeting Encl ML20217E1231997-09-25025 September 1997 Summary of 970826 Meeting W/Nsp Re Plant Revised MSLB Containment Pressure Response in Anticipation for License Amend Request to Reduce Boron Concentration in Boric Acid Storage Tanks.List of Attendees & Handouts Encl ML20140H9181997-05-0909 May 1997 Trip Rept of 970410-11 Visit to Ul to Observe full-scale Fire Endurance Test of 1 & 3 Hour Versawrap Fire Barrier Sys.List of Participants Encl ML20137W3311997-04-17017 April 1997 Summary of 970407 Meeting W/Util & Transco Products,Inc Re Versawrap,New Electrical Raceway Firewrap Sys.Attachment 1 Describes Components of Typical Veraswrap Barrier & Attachment 2 Re Transco Products,Inc Test Procedure Encl ML20149D6051993-09-15015 September 1993 Summary of 930708 Region III Annual Training Managers Conference in Glen Ellyn,Il.Purpose of Meeting to Provide Forum for Discussion on Rev 7 of Operator Licensing Examiner Stds & to Discuss Operator Licensing Issues ML20128H9581993-02-10010 February 1993 Summary of 930202 Meeting W/Util Re Proposed Amend Requests Currently Under Review.Amends Included,Refueling & Fuel Handling Spec Changes,Containment Penetration List Removal & Instrumentation Spec Changes ML20151Q8131988-08-0303 August 1988 Summary of Operating Reactors Events Meeting 88-031 on 880802.Viewgraphs & List of Attendees Encl ML20154A8991988-05-0404 May 1988 Summary of Operating Reactors Events 88-18 Meeting on 880503 Re Events Which Occurred Since 880426 Meeting.List of Attendees & Viewgraphs Encl ML20237G3891987-08-27027 August 1987 Summary of Operating Reactors Events Meeting 87-25 on 870804 Re Events That Occurred Since 870728 Meeting.List of Attendees,Viewgraphs & Summary of Reactor Scrams Encl ML20236K6701987-07-13013 July 1987 Summary of 870713 Public Hearing on Northern States Power Co Fuel Rod Consolidation Pilot Project in St Paul,Mn ML20215C8721987-06-0808 June 1987 Summary of Operating Reactors Events Meeting 87-10 on 870406 Re Events Which Occurred Since 870330 Meeting.List of Attendees,Events Discussed & Significant Elements of Events & Summary of Reactor Scrams & Significant Events Encl ML20138N9841985-12-19019 December 1985 Summary of 851122 Meeting W/Licensees & Westinghouse to Present Status of Program for Developing New Upper Plenum Injection Evaluation Model.Nonproprietary Viewgraphs,List of Attendees & Agenda Encl ML20137Y6641985-11-25025 November 1985 Summary of 851106 Meeting W/Util & B&W Re Reliability of Auxiliary Feedwater Sys.List of Attendees Encl ML20237B0671985-11-25025 November 1985 Summary of 851106 Meeting W/Util Re Reliability of Auxiliary Feedwater Sys.List of Attendees & Licensee Viewgraphs Encl ML20209G2111985-08-23023 August 1985 Trip Rept of 850715 Site Visit to Participate in INPO Training Accreditation Site Team Activities.Weaknesses Included Lack of Accreditation for Mgt Training & Evaluation Criterion ML20133F7531985-07-31031 July 1985 Summary of 850626 Meeting W/Util & Westinghouse Re Upcoming Changes to Reactor Internals & Impact on Tech Specs.Licensee Plans to Change from Exxon Fuel to Westinghouse Fuel.Agenda & Attendance List Encl ML20133E0661985-07-25025 July 1985 Summary of 850628 Meeting W/Utils & Westinghouse Re Status of Development of New Upper Plenum Injection Evaluation Model.List of Attendees & Agenda Encl ML20126L2331981-05-0101 May 1981 Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation ML20062H3561979-12-12012 December 1979 Summary of 791126 Meeting W/Westinghouse & Util Re Base Metal Cracking in Reactor Vessel Nozzles Under Stainless Steel Cladding ML20062F5591978-12-12012 December 1978 Summary of 781026 Meeting to Discuss Tech Specs for Secondary Water Chem,Reactor Coolant Activity & Secondary Coolant Activity ML20196H3981978-07-0505 July 1978 Summary of 780622 Meeting W/Westinghouse Owners Group to Discuss Results of Phase a of three-phase Plan & Current Schedule for Resolution of Asymmetric LOCA Loads Isssue.List of Attendees Encl ML20127H6361977-11-0101 November 1977 Summary of 771020 Meeting W/Util & Nuclear Associates International Re Discussions on Proposed Submittal of Topical Rept,Documenting Core Analysis Sys Used at Plant. List of Attendees & Presentation Slides Encl ML20245C3211977-07-11011 July 1977 Summary of 770525 Meeting W/Westinghouse & Util Group Members Re Efforts to Prevent Reactor Vessel Overpressurization.W/O Encls ML20128F4251977-03-10010 March 1977 Summary of 770301 Meeting W/Util Re Proposed QA Program for Plants.Attendance List & Agenda Encl ML20196H3251976-06-29029 June 1976 Summary of 760525 Meeting W/Util & Westinghouse Re Proposed Approach to Solution of Reactor Vessel Lateral Loading Question.List of Attendees,Agenda & Viewgraphs Encl ML20126C1851976-03-24024 March 1976 Summary of 760318 Meeting W/Util Re App I Requirements.List of Attendees & Agenda Encl 1999-04-30
[Table view] Category:MEETING SUMMARIES-INTERNAL (NON-TRANSCRIPT)
MONTHYEARML20206G5151999-04-30030 April 1999 Summary of 990421 Meeting with Util Re Error Involving Recent ATWS Analyses Using GE Odyn Code.List of Attendees Encl ML20207L7711999-03-11011 March 1999 Summary of 990223 Meeting with NSP to Discuss Potential NRC Review Process for New Core & Thermal Hydraulic Computer Modeling Methods Currently Under Evaluation by NSP ML20202J2031999-01-28028 January 1999 Summary of 990107 Meeting with NSP Re Recent License Amend Request for PINGP Ts.List of Meeting Participants & NSP Meeting Presentation Slides Encl ML20196F6101998-12-0101 December 1998 Summary of 981029 Meeting with Northern States Power, Wisconsin Electric,Wisconsin Public Service & Alliant-IES in Rockville,Md Re Various Aspects of Potential Regulatory Issues Associated with Ongoing Cooperative Efforts ML20249C4711998-06-24024 June 1998 Summary of 980611 Meeting W/Wog in Rockville,Md Re Part Length CRDM Issues.List of Attendees & Matl Presented at Meeting Encl ML20217E1231997-09-25025 September 1997 Summary of 970826 Meeting W/Nsp Re Plant Revised MSLB Containment Pressure Response in Anticipation for License Amend Request to Reduce Boron Concentration in Boric Acid Storage Tanks.List of Attendees & Handouts Encl ML20137W3311997-04-17017 April 1997 Summary of 970407 Meeting W/Util & Transco Products,Inc Re Versawrap,New Electrical Raceway Firewrap Sys.Attachment 1 Describes Components of Typical Veraswrap Barrier & Attachment 2 Re Transco Products,Inc Test Procedure Encl ML20149D6051993-09-15015 September 1993 Summary of 930708 Region III Annual Training Managers Conference in Glen Ellyn,Il.Purpose of Meeting to Provide Forum for Discussion on Rev 7 of Operator Licensing Examiner Stds & to Discuss Operator Licensing Issues ML20128H9581993-02-10010 February 1993 Summary of 930202 Meeting W/Util Re Proposed Amend Requests Currently Under Review.Amends Included,Refueling & Fuel Handling Spec Changes,Containment Penetration List Removal & Instrumentation Spec Changes ML20151Q8131988-08-0303 August 1988 Summary of Operating Reactors Events Meeting 88-031 on 880802.Viewgraphs & List of Attendees Encl ML20154A8991988-05-0404 May 1988 Summary of Operating Reactors Events 88-18 Meeting on 880503 Re Events Which Occurred Since 880426 Meeting.List of Attendees & Viewgraphs Encl ML20237G3891987-08-27027 August 1987 Summary of Operating Reactors Events Meeting 87-25 on 870804 Re Events That Occurred Since 870728 Meeting.List of Attendees,Viewgraphs & Summary of Reactor Scrams Encl ML20215C8721987-06-0808 June 1987 Summary of Operating Reactors Events Meeting 87-10 on 870406 Re Events Which Occurred Since 870330 Meeting.List of Attendees,Events Discussed & Significant Elements of Events & Summary of Reactor Scrams & Significant Events Encl ML20138N9841985-12-19019 December 1985 Summary of 851122 Meeting W/Licensees & Westinghouse to Present Status of Program for Developing New Upper Plenum Injection Evaluation Model.Nonproprietary Viewgraphs,List of Attendees & Agenda Encl ML20137Y6641985-11-25025 November 1985 Summary of 851106 Meeting W/Util & B&W Re Reliability of Auxiliary Feedwater Sys.List of Attendees Encl ML20237B0671985-11-25025 November 1985 Summary of 851106 Meeting W/Util Re Reliability of Auxiliary Feedwater Sys.List of Attendees & Licensee Viewgraphs Encl ML20133F7531985-07-31031 July 1985 Summary of 850626 Meeting W/Util & Westinghouse Re Upcoming Changes to Reactor Internals & Impact on Tech Specs.Licensee Plans to Change from Exxon Fuel to Westinghouse Fuel.Agenda & Attendance List Encl ML20133E0661985-07-25025 July 1985 Summary of 850628 Meeting W/Utils & Westinghouse Re Status of Development of New Upper Plenum Injection Evaluation Model.List of Attendees & Agenda Encl ML20126L2331981-05-0101 May 1981 Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation ML20062H3561979-12-12012 December 1979 Summary of 791126 Meeting W/Westinghouse & Util Re Base Metal Cracking in Reactor Vessel Nozzles Under Stainless Steel Cladding ML20062F5591978-12-12012 December 1978 Summary of 781026 Meeting to Discuss Tech Specs for Secondary Water Chem,Reactor Coolant Activity & Secondary Coolant Activity ML20196H3981978-07-0505 July 1978 Summary of 780622 Meeting W/Westinghouse Owners Group to Discuss Results of Phase a of three-phase Plan & Current Schedule for Resolution of Asymmetric LOCA Loads Isssue.List of Attendees Encl ML20127H6361977-11-0101 November 1977 Summary of 771020 Meeting W/Util & Nuclear Associates International Re Discussions on Proposed Submittal of Topical Rept,Documenting Core Analysis Sys Used at Plant. List of Attendees & Presentation Slides Encl ML20245C3211977-07-11011 July 1977 Summary of 770525 Meeting W/Westinghouse & Util Group Members Re Efforts to Prevent Reactor Vessel Overpressurization.W/O Encls ML20128F4251977-03-10010 March 1977 Summary of 770301 Meeting W/Util Re Proposed QA Program for Plants.Attendance List & Agenda Encl ML20196H3251976-06-29029 June 1976 Summary of 760525 Meeting W/Util & Westinghouse Re Proposed Approach to Solution of Reactor Vessel Lateral Loading Question.List of Attendees,Agenda & Viewgraphs Encl ML20126C1851976-03-24024 March 1976 Summary of 760318 Meeting W/Util Re App I Requirements.List of Attendees & Agenda Encl 1999-04-30
[Table view] |
Text
_ - _ _ _ - - _ _-__
/'gma '
o UNITED STATES 8 g g NUCLEAR REGULATORY COMMISSION r,, f .t W ASHINGT ON, D. C. 20555 February 10, 1993 k....+ /
Docket No. 50-282 and 50-306 LICENSEE: Northern States Power Company FACILITY: Prairie Island Nuclear Generating Plant
SUBJECT:
DISCUSSION OF PROPOSED AMENDMENT REQUESTS MEETING
SUMMARY
A meeting was held on February 2, 1993 between the FD.C staff and Northern States Power licensing staff to discuss a number of proposed amendment requests currently under review. These amendments included; 1. Refueling and fuel Handling Specification Changes, 2. Containment Penetration List Removal, and 3. Instrumentation Specification Changes. The results of the discussions and the follow-up actions for each proposed amendment are presented below.
- 1. Refueling and Fuel Handling Specification Changes (TAC NOS. M84058 and M84059)
This amendment request incorporates Technical Specifications (TS) for containment closure requirements during refueling conditions. These include the Standard Technical Specifications and additional TS that take credit for the Auxiliary Building Special Ventilation System (ABSVS) and the Shield Building Ventilation System (SBVS). The primary focus of the discussions involved the technical details of the Auxiliary and Shield Building Ventilation Systems.
The action for this TAC is with the Containment Systems and Severe Accident Branch to determine if the additional TS on the ABSVS and SBVS are acceptable.
- 2. Removal of Component Lists from Technical Specifications (TAC NOS. M83379 and MS3380)
This amendment request is in response to Generic Letter 91-08, which allows the removal of component lists from TS. In the amendment request a TS section was included which listed the types of containment penetrations and valves that would not require type B and C testing. It was agreed during the meeting, that this section could lead to confusion since the list was not specific. However, since the licensee wanted to retain this information, a discussion of these exemptions in the current table will be addressed in the bases.
The action for this TAC is with NSP to resubmit these TS and bases pages as discussed.
- 3. Instrumentation Specification Changes (TAC NOS. M84671 and M84672) ,
9302170245 930210 PDR ADOCK 05000282 e cdIh [T PDR i P
h' 4 TB ev. #a""
y ) iW " ~
[ fo o
February in, 1993 This amendment request incorporates changes to the surveillance test intervals and allowed outage times for the engineered safety features and reactor protection system instrumentation consistent with the TS associated with WCAP-10271. This meeting was the initial discussion between the staff and Prairie Island regarding this amendment request. The Instrumentation and Controls technical reviewer had a number of questions regarding the ditferences between the generic TS presented in the NRC Safety Evaluation and the TS which were requested in the Prairie Island submittal. Discussions on this package continued during a conference call on February 4,1993.
The actions for this TAC are with NSP and the NRC. The licensee will prepare a revised submittal that will incorporate the corrections and changes discussed during the meeting and conference call. The NRC staff will continue their review of the remaining TS sections and the bases pages.
The meeting resulted in a signification exchange of information and was beneficial to the NRC staff and the licensee. Future meetings to discuss License Amendment Requests will be scheduled as required. A list of attendees is provided in the enclosure. If you have any questions regarding the meeting or meeting summary, please contact me at 504-3024.
Original signed by Marsha Gamberoni, Project Manager Project Directorate 111-1 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page OFFICE LA:PDIII-1 PM:PDIll-1 1 PD:PDIlld.
NAME MShuttle6hrth/ MGamberonb LMarsh DATE R _ //fy93 02/iO/93 f./ /o/93
f j3 February 10, 1993 This amendment request incorporates changes to the surveillance test intervals and allowed outage times-for the engineered safety features and reactor protection system instrumentation consistent with-the TS associated with WCAP-10271. This meeting was the initial discussion between the staff and Prairie Island regarding this amendment request. The Instrumentation and Controls technical reviewer had a number of questions regarding the differences between the generic TS presented in the NRC Safety Evaluation and the TS which were requested in the Prairie Island submittal. Discussions on this package continued during a conference call on February 4,1993, lhe actions for this TAC are with NSP and the NRC. The licensee will prepare a revised submittal that will incorporate the corrections and changes discussed during the meeting and conference call. The NRC staff will continue their review of the remaining TS sections and the bases pages.
The meeting resulted in a signification exchange of information and was beneficial to the NRC staff and the licensee. Future meetings to discuss License Amendment Requests will be scheduled as required. A list of attendees is provided in the enclosure. If you have any questions regarding the meeting or meeting summary, please contact me at 504-3024.
I Cou hc~ A '
Marsha Gamberoni, Project Manager Project Directorate 111-1 Division of Reactor Projects - III/IV/V Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page
A i
i Northern States Power Company- Prairie Island Nuclear Generating Plant J. E. Silberg, Esquire Shaw, Pittman, Potts and Trowbridge 2300 N Street, N. W.
Washington DC 20037 Mr. E. L. Watzl, Site General Manager Prairie Island Nuclear Generating Plant Northern States Power Company Route 2 Welch, Minnesota 55089 Lisa R. Tiegel Assistant Attorney General Environmental Protection Division Suite 200 520 Lafayette Road St. Paul, Minnesota 55155 U.S. Nuclear Regulatory Commission Resident Inspector Office 1719 Wakonade Drive
, East Welch, Minnesota 55089 Regional Administrator. Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Mr. Jeff Cole, Auditor / Treasurer Goodhue County Courthouse Red Wing, Minnesota 55066 Kris Sanda, Commissioner Director of Public Service 121 Seventh Place East Suite 200 St. Paul, Minnesota .55101-2145 Mr. T. M. Parker, Manager Nuclear Support Services Northern States Power Company 414 Nicollet Mall Minneapolis, Minnesota 55401 I
1
l 4
MEETING ATTENDANCE SHEET DISCUSSION OF LICENSE AMENDMENT REQUESTS February 2, 1993 Hama Discussions Attendtd Affiliation '
- l. M. Gamberoni 1,2,3 NRC/NRR/DRPW/PDIII-l
- 2. J. Pulsipher 1,2 NRC/NRR/DSSA/SCSB
- 3. H. Garg 3 NRC/NRR/DRCH/HICB
~
- 4. C. Moon 1 NRC/NRR/ DORS /0TSB
- 5. M. Wohl 3 NRC/NRR/ DORS /0TSB
- 6. G. Eckholt 1,2,3 NSP
- 7. C. Mundt 3 NSP
- 8. T. Baker 3* Westinghouse
-,-_--K--- - - - - - - - , - , - -- - - - - - - - _ - - - - . - )
g-DISTRIBUTION-FOR MEETING
SUMMARY
OF 2/2/93 Docket File-NRC & Local PDRs PDIII-1 Reading File T. Murley F. Miraglia J. Partlow
.- J. Roe J. Zwolinski L. Marsh : .;
M. Shuttleworth M.-Gamberoni OGC E. Jordan MNBB 3701 J. Pulsifer M. Garg C. Moon M. Wohl ACRS (10)
W. Shafer, RIII l
.