Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML18017A9251999-10-21021 October 1999 Application for Amend to License NPF-63,implementing Selected Improvements Described in GL 93-05 ML18017A8511999-08-26026 August 1999 Application for Amend to License NPF-63,revising TS 3/4.9.4 & Associated Bases to Allow Penetrations Which Provide Direct Access from Containment Atmosphere to Outside Atmosphere to Remain Open During Refueling Operations ML18016B0501999-08-0404 August 1999 Application for Amend to License NPF-63,revising TS to Incorporate Analytical Methodology References in TS 6.9.1.6.2 Which Are Used to Determine Core Operating Limits ML18016B0431999-08-0202 August 1999 Application for Amend to License NPF-63,revising TS 6.2.2.e to Require Either Operations Manager or off-shift Operations Superintendent to Hold SRO License ML18016B0071999-07-0909 July 1999 Application for Amend to License NPF-63,revising TS 3/4.2.2, TS 3/4.2.3 & TS 3/4.2.5,providing Clarification & Reducing Burden of Addl License Amend Processing by Implementing Guidance in GL 88-16 & NUREG-1431,Rev 1, Std TS W Plants. ML18016B0111999-07-0909 July 1999 Application for Amend to License NPF-63,relocating TS 3/4.3.3.3,TS 3/4.3.3.4,TS 3/4.3.3.9 & TS 3/4.3.3.11 to Plant Procedure PLP-114, Relocated Tech Specs & Design Basis Requirements, IAW GL 95-10 ML18016A9891999-06-15015 June 1999 Application for Amend to License NPF-63,revising TS to Incorporate performance-based 10CFR50 App J,Option B for Type a Tests (Containment Integrated Leakage Rate Tests) ML18016A9761999-06-0202 June 1999 Application for Amend to License NPF-63,revising TS 6.5, Review & Audit, TS 6.8, Procedures & Program & TS 6.10, Record Retention. ML18016A8381999-02-26026 February 1999 Application for Amend to License NPF-63,revising TS Table Notations for TS Table 3.3-4, ESFAS Instrumentation Trip Setpoints. Description of Changes & Environmental Evaluation,Encl ML18016A7681998-12-23023 December 1998 Application for Amend to License NPF-63,revising TS 5.6, Fuel Storage, by Increasing Spent Fuel Storage Capacity by Adding Rack Modules to Pools 'C' & 'D.' Non-proprietary & Proprietary Licensing Repts Encl.Proprietary Info Withheld ML18016A6031998-10-0101 October 1998 Application for Amend to License NPF-63,further Revising TS 3.0.4 to Clarify Intent Re Mode Changes as Discussed in Proposed Bases.Change to Retyped Page TS 3.9.9,encl ML18016A5921998-09-23023 September 1998 Application for Amend to License NPF-63,revising TS 3/4.6.1.3 to Be Consistent with NUREG-1431,rev 1 Std Tech Specs,W Plants, Dtd Apr 1995 & to Clarify Requirements for Locking Air Lock Door Shut ML18016A5441998-09-0101 September 1998 Application for Amend to License NPF-63,revising TS 3/4.9.11 to Require 23 Feet of Water Above Top of Fuel Rods within Irradiated Fuel Assemblies Seated in Storage Racks ML18016A5391998-08-27027 August 1998 Application for Amend to License NPF-63,revising TS Re Applicability of LCO & Surveillance Requirements,Per GL 87-09 ML18016A5031998-08-14014 August 1998 Application for Amend to License NPF-63,deleting SR 4.9.12.d.4 Which Requires Verifying That Filter Cooling Bypass Valve for Fuel Handling Bldg Emergency Exhaust Sys Is Locked in Balanced Position at Least Once Per 18 Months ML18016A3991998-04-24024 April 1998 Application for Amend to License NPF-63,revising TS 3/4.3.2, ESFAS Instrumentation, to Allow Two Hour Surveillance Interval to Facilitate Testing of 6.9 Kv Emergency Bus Undervoltage Relays ML18016A3461998-03-12012 March 1998 Application for Amend to License NPF-63,deleting TS SR 4.9.12.d.4 Which Requires Verifying That Filter Cooling Bypass Valve for Fhb EES Is Locked in Balanced Position at Least Once Per 18 Months ML18016A2561997-12-16016 December 1997 Application for Amend to License NPF-63,revising TS 4.7.1.2.1.a.2.a to Change Differential Pressure & Flow Requirements of Steam turbine-driven AFW Pump to Allow Testing of Pump at Lower Speed than Is Currently Performed ML18016A2221997-10-29029 October 1997 Application for Amend to License NPF-63,revising TS 3/4.8.1, AC Sources - Operating & Associated Bases to Clarify Intent of Ts,Per NUREG-1431,Rev 1 ML18012A8101997-06-12012 June 1997 Application for Amend to License NPF-63,amending TS 6.0, Administrative Controls, TS 6.2.2.e & TS 6.2.2.f ML18012A7841997-05-16016 May 1997 Application for Amend to License NPF-63,informing That TS 4.6.2.3 a.2 Requires Verification at Least Once Per 31 Days of Cw Flow Rate of Greater than or Equal to 1425 Gpm to Each Containment Fan Cooler ML18012A6341997-04-23023 April 1997 Application for Amend to License NPF-63,incorporating Enhancements to TS Identified in Plant Review Performed IAW GL 96-01.Changes Affect Specs 4.3.2.1.1.a,4.3.2.1.4.b, 4.3.2.1.6.g,4.3.2.1.10.a,4.3.2.1.10.b & 4.7.3.b.3 ML18012A5761997-03-17017 March 1997 Application for Amend to License NPF-63,revising Tech Specs Surveillances 4.1.2.2.c,4.5.2.e,4.6.2.1.c,4.6.2.2.c,4.6.3.2, 4.7.1.2.1.b,4.7.3b & 4.7.4.b to Delete Specific Restrictions in Text of Surveillances ML18022B0021997-03-14014 March 1997 Application for Amend to License NPF-63,increasing AOT for Refueling Water Storage Tank to Twelve Hs While Performing TS Surveillance 4.4.6.2.2 ML18022B0051997-03-10010 March 1997 Application for Amend to License NPF-63,revising TS 3.5.1 to Provide Optional Method of Meeting Surveillance Requirement & to Add New Action Statement Re Boron Concentration ML18022B0011997-02-27027 February 1997 Application for Amend to License NPF-63,amending TS 3/4.4.5, Sgs, & Associated Bases,To Add Sleeve Installation as Alternative to Tube Plugging for Repairing Degraded ST Tubes.Trs encl.CEN-630-P,rev 1 Withheld ML18012A5291997-02-18018 February 1997 Application for Amend to License NPF-63,revising Tech Specs 3/4.7.1, Turbine Cycle Safety Valves. ML18012A4981997-02-0606 February 1997 Application for Amend to License NPF-63,adding New Entry 3.0.5 to 3/4.0 Applicability.New 3.0.5 Provides Specific Guidance for Returning Equipment to Svc for Sole Purpose of Performing Testing to Demonstrate Operability ML18012A4941997-01-29029 January 1997 Application for Amend to License NPF-63,requesting to Add New Entry 3.0.5 to 3/4.0 to Provide Specific Guidance for Returning Equipment to Service in Order to Demonstrate Operability ML18012A4621997-01-10010 January 1997 Application for Amend to License NPF-63,requesting Rev to TS 4.8.1.1.2.h.2 Re Test Tanks & Nonisolable Piping at Test Pressure ML18012A4491996-12-30030 December 1996 Application for Amend to License NPF-63,requesting Rev to Chemistry Data (Nickel Content) in TS 3/4.4.9 Re Pressure/ Temp Limits ML18012A4141996-10-31031 October 1996 Application for Amend to License NPF-63,revising TSs Re Ultimate Heat Sink Level & Temp ML18012A3931996-10-0808 October 1996 Application for Amend to License NPF-63,proposing to Implement Change to Bases for TSs 3/4.6.1.4 & 3/4.6.1.6 Revising Calculated Peak Pressure for MSLB Event ML18012A3701996-09-18018 September 1996 Application for Amend to License NPF-63,requesting Change in Diesel Fuel Oil Sys Pressure Testing ML18012A3031996-07-19019 July 1996 Application for Amend to License NPF-63,TS 3/4.6.2, Containment Spray Sys,Extending Surveillance Interval for Performance of Air or Smoke Flow Test Through CS Nozzles from Once Every 5 Years,To Once Every 10 Years ML18012A2511996-05-31031 May 1996 Application for Amend to License NPF-63,correcting Location Described for One of Three Triaxial Peak Accelerograph Recorders ML18012A1801996-03-20020 March 1996 Application for Amend to License NPF-63,relocating TS 3.3.3.2, Movable Incore Detectors & Associated Bases, Consistent w/NUREG-1431 & GL 95-10 ML18012A1411996-02-16016 February 1996 Application for Amend to License NPF-63,revising TS 4.3.2 Re ESFAS Instrumentation ML18011A8751995-04-0505 April 1995 Application for Amend to License NPF-63,revising Portions of Section 3/4.9, Refueling Operations to Be Consistent W/ NUREG-1431 & Relocating Applicable Sections Per Commission Final Policy Statement ML18011A8721995-03-30030 March 1995 Application for Amend to License NPF-63,revising EDG SR Contained in Section 4.8.1.1.2 to Be Consistent w/NUREG-1431 New Std TS for Westinghouse Plants & Eliminating Need for Duplicate EDG Testing Being Performed ML18011A8501995-03-20020 March 1995 Application for Amend to License NPF-63 to Relocate Cycle Specific Overpower & Overtemperature Delta T Trip Setpoint Parameters to COLR ML18011A8111995-03-0303 March 1995 Application for Amend to License NPF-63,eliminating Response Time Testing for Selected Pressure & Differential Pressure Sensors ML18022A9471995-02-0606 February 1995 Application for Amend to License NPF-63,revising TSs Re Relocation of Shutdown Margin Vs Boron Concentration ML18011A7691995-01-19019 January 1995 Application for Amend to License NPF-63,revising TS SR 4.0.3 & Associated Bases to Provide for Delay in Which to Perform Surveillance Discovered Not Performed within Specified Frequency ML18011A7411994-12-19019 December 1994 Application for Amend to License NPF-63,requesting one-time Schedular Rev to TS Re Containment Leak Rate Testing ML18011A7151994-12-0606 December 1994 Application for Amend to License NPF-63 to TS Re Revised TS Page Concerning Relocation of Selected TS in Accordance w/NUREG-1431 ML18011A7051994-12-0606 December 1994 Application for Amend to License NPF-63,revising TS to Relocate Certain TS Requirements in Accordance w/NUREG-1431, Std Ts,Westinghouse Plants. ML18011A6881994-11-23023 November 1994 Application for Amend to License NPF-63 to TS Re Changes to ECCS Evaluation Model ML18011A6141994-10-24024 October 1994 Application for Amend to License NPF-63,relocating Selected TS Per NUREG-1431 ML18011A5841994-09-12012 September 1994 Application for Amend to License NPF-63,revising TS3/4.8.1, AC Sources & Associated Bases 1999-08-04
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML18017A9251999-10-21021 October 1999 Application for Amend to License NPF-63,implementing Selected Improvements Described in GL 93-05 ML18017A8511999-08-26026 August 1999 Application for Amend to License NPF-63,revising TS 3/4.9.4 & Associated Bases to Allow Penetrations Which Provide Direct Access from Containment Atmosphere to Outside Atmosphere to Remain Open During Refueling Operations ML18016B0501999-08-0404 August 1999 Application for Amend to License NPF-63,revising TS to Incorporate Analytical Methodology References in TS 6.9.1.6.2 Which Are Used to Determine Core Operating Limits ML18016B0431999-08-0202 August 1999 Application for Amend to License NPF-63,revising TS 6.2.2.e to Require Either Operations Manager or off-shift Operations Superintendent to Hold SRO License ML18016B0111999-07-0909 July 1999 Application for Amend to License NPF-63,relocating TS 3/4.3.3.3,TS 3/4.3.3.4,TS 3/4.3.3.9 & TS 3/4.3.3.11 to Plant Procedure PLP-114, Relocated Tech Specs & Design Basis Requirements, IAW GL 95-10 ML18016B0071999-07-0909 July 1999 Application for Amend to License NPF-63,revising TS 3/4.2.2, TS 3/4.2.3 & TS 3/4.2.5,providing Clarification & Reducing Burden of Addl License Amend Processing by Implementing Guidance in GL 88-16 & NUREG-1431,Rev 1, Std TS W Plants. ML18016A9891999-06-15015 June 1999 Application for Amend to License NPF-63,revising TS to Incorporate performance-based 10CFR50 App J,Option B for Type a Tests (Containment Integrated Leakage Rate Tests) ML18016A9761999-06-0202 June 1999 Application for Amend to License NPF-63,revising TS 6.5, Review & Audit, TS 6.8, Procedures & Program & TS 6.10, Record Retention. ML18016A8381999-02-26026 February 1999 Application for Amend to License NPF-63,revising TS Table Notations for TS Table 3.3-4, ESFAS Instrumentation Trip Setpoints. Description of Changes & Environmental Evaluation,Encl ML18016A7681998-12-23023 December 1998 Application for Amend to License NPF-63,revising TS 5.6, Fuel Storage, by Increasing Spent Fuel Storage Capacity by Adding Rack Modules to Pools 'C' & 'D.' Non-proprietary & Proprietary Licensing Repts Encl.Proprietary Info Withheld ML18016A6031998-10-0101 October 1998 Application for Amend to License NPF-63,further Revising TS 3.0.4 to Clarify Intent Re Mode Changes as Discussed in Proposed Bases.Change to Retyped Page TS 3.9.9,encl ML18016A5921998-09-23023 September 1998 Application for Amend to License NPF-63,revising TS 3/4.6.1.3 to Be Consistent with NUREG-1431,rev 1 Std Tech Specs,W Plants, Dtd Apr 1995 & to Clarify Requirements for Locking Air Lock Door Shut ML18016A5441998-09-0101 September 1998 Application for Amend to License NPF-63,revising TS 3/4.9.11 to Require 23 Feet of Water Above Top of Fuel Rods within Irradiated Fuel Assemblies Seated in Storage Racks ML18016A5391998-08-27027 August 1998 Application for Amend to License NPF-63,revising TS Re Applicability of LCO & Surveillance Requirements,Per GL 87-09 ML18016A5031998-08-14014 August 1998 Application for Amend to License NPF-63,deleting SR 4.9.12.d.4 Which Requires Verifying That Filter Cooling Bypass Valve for Fuel Handling Bldg Emergency Exhaust Sys Is Locked in Balanced Position at Least Once Per 18 Months ML18016A3991998-04-24024 April 1998 Application for Amend to License NPF-63,revising TS 3/4.3.2, ESFAS Instrumentation, to Allow Two Hour Surveillance Interval to Facilitate Testing of 6.9 Kv Emergency Bus Undervoltage Relays ML18016A3461998-03-12012 March 1998 Application for Amend to License NPF-63,deleting TS SR 4.9.12.d.4 Which Requires Verifying That Filter Cooling Bypass Valve for Fhb EES Is Locked in Balanced Position at Least Once Per 18 Months ML18016A2561997-12-16016 December 1997 Application for Amend to License NPF-63,revising TS 4.7.1.2.1.a.2.a to Change Differential Pressure & Flow Requirements of Steam turbine-driven AFW Pump to Allow Testing of Pump at Lower Speed than Is Currently Performed ML18016A2221997-10-29029 October 1997 Application for Amend to License NPF-63,revising TS 3/4.8.1, AC Sources - Operating & Associated Bases to Clarify Intent of Ts,Per NUREG-1431,Rev 1 ML18012A8101997-06-12012 June 1997 Application for Amend to License NPF-63,amending TS 6.0, Administrative Controls, TS 6.2.2.e & TS 6.2.2.f ML18012A7841997-05-16016 May 1997 Application for Amend to License NPF-63,informing That TS 4.6.2.3 a.2 Requires Verification at Least Once Per 31 Days of Cw Flow Rate of Greater than or Equal to 1425 Gpm to Each Containment Fan Cooler ML18012A6341997-04-23023 April 1997 Application for Amend to License NPF-63,incorporating Enhancements to TS Identified in Plant Review Performed IAW GL 96-01.Changes Affect Specs 4.3.2.1.1.a,4.3.2.1.4.b, 4.3.2.1.6.g,4.3.2.1.10.a,4.3.2.1.10.b & 4.7.3.b.3 ML18012A5761997-03-17017 March 1997 Application for Amend to License NPF-63,revising Tech Specs Surveillances 4.1.2.2.c,4.5.2.e,4.6.2.1.c,4.6.2.2.c,4.6.3.2, 4.7.1.2.1.b,4.7.3b & 4.7.4.b to Delete Specific Restrictions in Text of Surveillances ML18022B0021997-03-14014 March 1997 Application for Amend to License NPF-63,increasing AOT for Refueling Water Storage Tank to Twelve Hs While Performing TS Surveillance 4.4.6.2.2 ML18022B0051997-03-10010 March 1997 Application for Amend to License NPF-63,revising TS 3.5.1 to Provide Optional Method of Meeting Surveillance Requirement & to Add New Action Statement Re Boron Concentration ML18022B0011997-02-27027 February 1997 Application for Amend to License NPF-63,amending TS 3/4.4.5, Sgs, & Associated Bases,To Add Sleeve Installation as Alternative to Tube Plugging for Repairing Degraded ST Tubes.Trs encl.CEN-630-P,rev 1 Withheld ML18012A5291997-02-18018 February 1997 Application for Amend to License NPF-63,revising Tech Specs 3/4.7.1, Turbine Cycle Safety Valves. ML18012A4981997-02-0606 February 1997 Application for Amend to License NPF-63,adding New Entry 3.0.5 to 3/4.0 Applicability.New 3.0.5 Provides Specific Guidance for Returning Equipment to Svc for Sole Purpose of Performing Testing to Demonstrate Operability ML18012A4941997-01-29029 January 1997 Application for Amend to License NPF-63,requesting to Add New Entry 3.0.5 to 3/4.0 to Provide Specific Guidance for Returning Equipment to Service in Order to Demonstrate Operability ML18012A4621997-01-10010 January 1997 Application for Amend to License NPF-63,requesting Rev to TS 4.8.1.1.2.h.2 Re Test Tanks & Nonisolable Piping at Test Pressure ML18012A4491996-12-30030 December 1996 Application for Amend to License NPF-63,requesting Rev to Chemistry Data (Nickel Content) in TS 3/4.4.9 Re Pressure/ Temp Limits ML18012A4141996-10-31031 October 1996 Application for Amend to License NPF-63,revising TSs Re Ultimate Heat Sink Level & Temp ML18012A3931996-10-0808 October 1996 Application for Amend to License NPF-63,proposing to Implement Change to Bases for TSs 3/4.6.1.4 & 3/4.6.1.6 Revising Calculated Peak Pressure for MSLB Event ML18012A3701996-09-18018 September 1996 Application for Amend to License NPF-63,requesting Change in Diesel Fuel Oil Sys Pressure Testing ML18012A3031996-07-19019 July 1996 Application for Amend to License NPF-63,TS 3/4.6.2, Containment Spray Sys,Extending Surveillance Interval for Performance of Air or Smoke Flow Test Through CS Nozzles from Once Every 5 Years,To Once Every 10 Years ML18012A2511996-05-31031 May 1996 Application for Amend to License NPF-63,correcting Location Described for One of Three Triaxial Peak Accelerograph Recorders ML18012A1801996-03-20020 March 1996 Application for Amend to License NPF-63,relocating TS 3.3.3.2, Movable Incore Detectors & Associated Bases, Consistent w/NUREG-1431 & GL 95-10 ML18012A1411996-02-16016 February 1996 Application for Amend to License NPF-63,revising TS 4.3.2 Re ESFAS Instrumentation ML18011A8751995-04-0505 April 1995 Application for Amend to License NPF-63,revising Portions of Section 3/4.9, Refueling Operations to Be Consistent W/ NUREG-1431 & Relocating Applicable Sections Per Commission Final Policy Statement ML18011A8721995-03-30030 March 1995 Application for Amend to License NPF-63,revising EDG SR Contained in Section 4.8.1.1.2 to Be Consistent w/NUREG-1431 New Std TS for Westinghouse Plants & Eliminating Need for Duplicate EDG Testing Being Performed ML18011A8501995-03-20020 March 1995 Application for Amend to License NPF-63 to Relocate Cycle Specific Overpower & Overtemperature Delta T Trip Setpoint Parameters to COLR ML18011A8111995-03-0303 March 1995 Application for Amend to License NPF-63,eliminating Response Time Testing for Selected Pressure & Differential Pressure Sensors ML18022A9471995-02-0606 February 1995 Application for Amend to License NPF-63,revising TSs Re Relocation of Shutdown Margin Vs Boron Concentration ML18011A7691995-01-19019 January 1995 Application for Amend to License NPF-63,revising TS SR 4.0.3 & Associated Bases to Provide for Delay in Which to Perform Surveillance Discovered Not Performed within Specified Frequency ML18011A7411994-12-19019 December 1994 Application for Amend to License NPF-63,requesting one-time Schedular Rev to TS Re Containment Leak Rate Testing ML18011A7151994-12-0606 December 1994 Application for Amend to License NPF-63 to TS Re Revised TS Page Concerning Relocation of Selected TS in Accordance w/NUREG-1431 ML18011A7051994-12-0606 December 1994 Application for Amend to License NPF-63,revising TS to Relocate Certain TS Requirements in Accordance w/NUREG-1431, Std Ts,Westinghouse Plants. ML18011A6881994-11-23023 November 1994 Application for Amend to License NPF-63 to TS Re Changes to ECCS Evaluation Model ML18011A6141994-10-24024 October 1994 Application for Amend to License NPF-63,relocating Selected TS Per NUREG-1431 ML18011A5841994-09-12012 September 1994 Application for Amend to License NPF-63,revising TS3/4.8.1, AC Sources & Associated Bases 1999-08-04
[Table view] |
Text
P RIORITY 1 t (ACCELERATED RIDS PROCESSI'EGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)ACCESSION NBR:9503230062 DOC.DATE: 95/03/20 NOTARIZED:
YES FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina AUTH.NAME AUTHOR AFFILIATION ROBINSON,W.R.
Carolina Power&Light.Co.RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)DOCKET 05000400 P R
SUBJECT:
Application for amend to license NPF-63 to relocate cycle specific Overpower&Overtemperature Delta T trip setpoint parameters to COLR.DISTRIBUTION CODE: AOOID COPIES RECEIVED:LTRj ENCL j SIZE: I 0 TITLE: OR Submittal:
General Distribution NOTES:Application for permit renewal filed.+l'7 0 o5ooo4oo RECIPIENT ID CODE/NAME PD2-1 LA LE,N COPIES LTTR ENCL 1 1 1 1 RECIPIENT ID CODE/NAME PD2-1 PD COPIES LTTR ENCL 1 1 INTERNAL: ACRS NRR/DRCH/HICB NRR/DSSA/SRXB OGC/HDS2 6 6~FAIRE CENTE~1 1 1 NRR/DSSA/SPLB 1 1 NUDOCS-ABSTRACT 1 0 1 1 1 1 1 1 EXTERNAL: NOAC 1 1 NRC PDR 1 1 D C'N NOTE TO ALL"RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM P!-37 (EXT.504-2083)TO ELIMIiVATE YOUR iVAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 17 ENCL 16 4 F P Carolina Power&Light Company PO Box 165 New Hill NC 27562 gg 20 l995 Letter Number: HO-950506 William R.Robinson Vice President Harris Nuclear Plant SERIAL: HNP-95-031 10 CFR 50.90 United States Nuclear Regulatory Commission ATTENTION:
Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO.50-400/LICENSE NO.NPF-63 REQUEST FOR LICENSE AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SETPOINT RELOCATION TO THE COLR Gentlemen:
In accordance with the Code of Federal Regulations, Title 10, Parts 50.90 and 2.101, Carolina Power 6 Light Company (CPGL)hereby requests a revision to the Technical Specifications (TS)for the Shearon Harris Nuclear Power Plant (SHNPP).This change proposes a revision to Technical Specification 2.2.1, Reactor Trip System Instrumentation Setpoints, to relocate cycle specific Overpower and Overtemperature Delta T trip setpoint parameters to the Core Operating Limits Report (COLR).Enclosure 1 provides a detailed description of the proposed changes and the basis for the changes.Enclosure 2 details, in accordance with 10 CFR 50.91(a), the basis for the Company's determination that the proposed changes do not involve a significant hazards consideration. provides an environmental evaluation which demonstrates that the proposed amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Therefore,.
pursuant to 10 CFR 51.22(b), no environmental assessment needs to be prepared in connection with the issuance of the amendment. provides page change instructions for incorporating the proposed revisions. provides the proposed Technical Specification pages.In accordance with 10 CFR 50.91(b), CPSL is providing the State of North Carolina with a copy of the proposed license amendment.
CP&L requests approval of the proposed amendment by September 1, 1995 to support preparations for Cycle No.7 operation.
In order to allow time for procedure c 9503230062 950320 PDR ADOCK 05000400 PDR State Road1134 New Hill NC Tel 919362-2502 Fax 919362-2095 1 l Document Control Desk HNP-95-031
/Page 2 revision and orderly incorporation into copies of the Technical Specifications, CP&L requests that the proposed amendment, once approved by the NRC, be issued such that implementation will occur within 60 days of issuance of the amendment.
Please refer any questions regarding this submittal to Mr.D.C.McCarthy at (919)362-2100.Sincerely, W.R.Robinson SDG/sdc
Enclosures:
1.Basis for Change Request 2.10 CFR 50.92 Evaluation 3.Environmental Considerations 4.Page Change Instructions 5.Technical Specification Pages W.R.Robinson, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and belief;and the sources of his information are officers, employees, contractors, and agents of Carolina Power 6 Light Company.My commission expires: Cu/~I(0 l;.s P~Notary (Seal)c: Mr.Dayne H.Brown Mr.S.D.Ebneter Mr.S.A.Elrod Mr.N.B.Le t f J ENCLOSURE TO SERIAL: HNP-95-031 ENCLOSURE 1 SHEARON HARRIS NUCLEAR POWER PLANT NRC DOCKET NO.50-400/LICENSE NO.NPF-63 REQUEST FOR LICENSE AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SETPOINT REVISION AND RELOCATION TO THE COLR BASIS FOR CHANGE RE UEST~Back round The Shearon Harris Nuclear Power Plant (SHNPP)Technical Specifications (TS)provide standards and restrictions on minimum equipment operability and on operation of the facility.The TS ensure that the plant is operated within its design basis and safety analyses.A number of specifications address limits associated with reactor physics parameters that generally change with each reload core, requiring the processing of changes to TS to update these limits each fuel cycle.NRC Generic Letter 88-16, dated October 4, 1988, was issued to encourage licensees to prepare changes to TS related to cycle-specific parameters.
These TS changes would relocate cycle-specific parameter limits from the TS to the Core Operating Limits Report (COLR).The Generic Letter states that if these limits are developed using an NRC-approved methodology, the license amendment process is an unnecessary burden on the licensee and the NRC.An alternative to including the values of these cycle-specific parameters in individual specifications was provided.This alternative consisted of three separate actions to modify the plant's TS: (1)the addition of the definition of a named formal report that includes the values of cycle-specific parameter limits that have been established using an NRC-approved methodology and consistent with all applicable limits of the safety analysis, (2)the addition of an administrative reporting requirement to submit the formal report on cycle-specific parameter limits to the Commission for information, and (3)the modification of individudl TS to note that cycle-specific parameters shall be maintained within the limits provided in the defined formal report.Amendment 15 to the SHNPP Operating License established a COLR, including the requisite reporting requirements, for many SHNPP cycle-specific TS limits.The purpose of this request is to allow the relocation of additional cycle-specific parameters to the SHNPP COLR.Pro osed Chan e This change proposes a revision to Technical Specification 2.2.1, Reactor Trip System Instrumentation Setpoints, to relocate cycle specific Overpower and Overtemperature Delta T trip setpoint parameters to the Core Operating Limits Report.Basis Technical Specification 2.2.1, Reactor Trip System Instrumentation Setpoints, specifies trip setpoints for a number of functions related to the reactor core's design and operation.
The trip setpoints have been selected to ensure that the Page El-l ENCLOSURE TO SERIAL: HNP-95-031 core and Reactor Coolant System are prevented from exceeding their Safety Limits during normal operation and during design basis anticipated operational occurrences.
This TS change deals with two trip functions containing cycle specific parameters, the Overtemperature Delta T (OTQT)and the Overpower Delta T (OPAT).These functions are defined by equations in Footnotes (1)and (3), respectively, of Specification 2.2.1.The Overtemperature Delta T trip provides coze protection to prevent DNB for various combinations of pressure, power, coolant temperature, and axial power distribution.
The trip function ensures that the core is always below the core Safety Limit specified in TS 2.1.1, Reactor Limits-Reactor Core.The Overpower Delta T trip provides assurance of fuel integrity (e.g., no fuel pellet melting and less than 1%cladding strain)in overpower conditions, limits the required range for Overtemperature Delta T trip, and provides a backup to the High Neutron Flux trip.It does so by ensuring that the allowable heat generation rate (kW/ft)is not exceeded.As stated previously, this change proposes to relocate the specific values for cycle specific OTAT and OPAT parameters to the COLR.They include OTAT gains KKKOTAT function f,(AI), and OPAT gains K, and K,.II Before each operating cycle, the TS values of the z'eactor trip setpoint parameters are reviewed in conjunction with core design changes to ensure that they remain valid and bounding for the next operating cycle.This ensures that the protection provided against departure from nucleate boiling and centerline fuel melt is maintained.
This parameter verification is performed in accordance with the NRC approved methodology"Statistical Setpoint/Transient Methodology for Westinghouse Type Reactors," Siemens Power Corporation (EMF-92-081A), as listed in TS 6.9.1.6.2.1.
If a value(s)is not bounded, then a revised value is selected, verified in accordance with the approved methodology and then incorporated into the TS via the TS amendment process.Revisions to the TS to update one or more of the above values have occurred for operating cycles 2, 3 and 6.As described in Generic Letter 88-16, relocation of the cycle-specific limits to the COLR eliminates the unnecessary administrative burden of processing change requests to the TS that would incorporate those limits that could be revised using NRC approved methodologies.
With the OTdT and OPAT trip setpoint parameter values in the COLR, the TS remain in control of the implementation of the parameters and of the methodology used to verify the limits.The parameters would remain within the structure of the TS without requiring cycle-specific amendments to review and approve cycle-specific changes.Therefore, relocation of the Overpower and Overtemperature Delta T trip setpoint parameters to the COLR will have no adverse effects on the establishment or implementation of the Reactor Trip System Instrumentation Setpoints.
Conclusions Relocation of cycle dependent parameters from the TS to the COLR has no impact upon plant operation or safety.No safety-related equipment, safety function, or plant operation will be altered as a result of this proposed change.Since the applicable FSAR limits, i.e., the accident analysis basis, will be Page El-2 ENCLOSURE TO SERIAL: HNP-95-031 maintained, and since the Technical Specifications will continue to require both OTBT and OPBT trip functions, as well as the establishment of their limits by NRC-approved methodologies, this proposed change is administrative in nature.Page El-3 ENCLOSURE TO SERIAL: HNP-95-031 ENCLOSURE 2 SHEARON HARRIS NUCLEAR POWER PLANT NRC DOCKET NO.50-400/LICENSE NO.NPF-63 REQUEST FOR LICENSE AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SETPOINT RELOCATION TO THE COLR 10 CFR 50.92 EVALUATION The Commission has provided standards in 10 CFR 50.92(c)for determining whether a significant hazards consideration exists.A proposed amendment to an operating license for a facility involves no significant hazards consideration if operation of the facility in accordance with the proposed amendment would not: (1)involve a significant increase in the probability or consequences of an accident previously evaluated, (2)create the possibility of a new or different kind of accident from any accident previously evaluated, or (3)involve a significant reduction in a margin of safety.Carolina Power&Light Company has reviewed this proposed license amendment request and determined that its adoption would not involve a significant hazards determinat'ion.
The bases for this determination are as follows: Pro osed Chan e This change proposes a revision to Technical Specification 2.2.1, Reactor Trip System Instrumentation Setpoints, to relocate cycle specific Overpower and Overtemperature Delta T trip setpoint parameters to the Core Operating Limits Report (COLR).Basis This change does not involve a significant hazards consideration for the following rea'sons: The proposed amendment does not involve a significant increase in the probability or consequences of an accident previously evaluated.
The proposed change of relocating Overtemperature Delta T (OTAT)and the Overpower Delta T (OPAT)trip setpoint parameters to the COLR has no influence or impact to the probability or consequences of an accident.The revised TS will continue to implement the Reactor Trip System Instrumentation OTQT and OPAT setpoint limits through reference to the parameters in the COLR.In addition, the COLR is subject to the existing controls of TS 6.9.1.6, including the establishment of the parameter values using an NRC approved methodology.
Given that this change administratively relocates the selected trip setpoint parameter values to another TS-controlled document, there would be no increase in the probability or consequences of an accident previously evaluated.
The proposed amendment does not create the possibility of a new or different kind of accident from any accident previously evaluated.
Page E2-1 ENCLOSURE TO SERIAL: HNP-95-031 No safety-related equipment, safety function, or plant operation will be altered as a result of this proposed change.The limits are simply being relocated to another TS-controlled document.The TS will continue to require operation within the required limits as established per NRC approved methodologies.
Therefore, the proposed changes do not create the possibility of a new or different kind of accident from any accident previously evaluated.
The proposed amendment does not involve a significant reduction in the margin of safety.Relocation of the Reactor Trip System Instrumentation OTDT and OPAT setpoint limits to the TS-controlled COLR has no effect on the trip system setpoints currently in force in TS 2.2.1.Future revisions to the trip setpoint parameters are governed by TS 6.9.1.6.TS 6.9.1.6 lists each TS that references values in the COLR and the NRC approved methodologies utilized in developing those values.Since this change is only an administrative relocation of the selected trip setpoint parameter values to another TS controlled document, the proposed changes do not involve a significant reduction in a margin of safety.Page E2-2 ENCLOSURE TO SERIAL: HNP-95-031 ENCLOSURE 3 SHEARON HARRIS NUCLEAR POWER PLANT NRC DOCKET NO.50-400/LICENSE NO.NPF-63 REQUEST FOR LICENSE AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SETPOINT RELOCATION TO THE COLR ENVIRONMENTAL CONSIDERATIONS 10 CFR 51.22(c)(9) provides criterion for and identification of licensing and regulatory actions eligible for categorical exclusion from performing an environmental assessment.
A proposed amendment to an operating license for a facility requires no environmental assessment if operation of the facility in accordance with the proposed amendment would not: (1)involve a significant hazards consideration; (2)result in a significant change in the types or significant increase in the amounts of any effluents that may be released offsite;(3)result in a significant increase in individual or cumulative occupational radiation exposure.Carolina Power 6 Light Company has reviewed this request and determined that the proposed amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Purs'uant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of the amendment.
The basis for this determination follows: Pro osed Chan e This change proposes a revision to Technical Specification 2.2.1, Reactor Trip System Instrumentation Setpoints, to relocate cycle specific Overpower and Overtemperature Delta T trip setpoint parameters to the Core Operating Limits Report (COLR).Basis The change meets the eligibility criteria for categorical exclusion set forth in.10 CFR 51.22(c)(9) for the following reasons: As demonstrated in Enclosure 2, the proposed amendment does not involve a significant hazards consideration.
The proposed amendment does not result in a significant change in the types or significant increase in the amounts of any effluents that may be released offsite.The proposed change relocates numerical values for cycle-specific Reactor Trip System Instrumentation OTAT and OPAT setpoint limit parameters from the Technical Specifications to the existing COLR.The proposed amendment does not introduce any new equipment nor does it require any existing equipment or systems to perform a different type of function than they are currently designed to perform.Plant transient and accident response remains bounded by the FSAR accident analysis.As such, the change can not affect the types or amounts of any effluents that may be released offsite.Page E3-1 ENCLOSURE TO SERIAL: HNP-95-031 The proposed amendment does not result in a significant increase in individual or cumulative occupational radiation exposure.The proposed change relocates numerical values for cycle-specific Reactor Trip System Instrumentation OTAT and OPBT setpoint limit parameters from the Technical Specifications to the existing COLR.No additional surveillances or testing results from the amendment.
Therefore, the amendment has no affect on either individual or cumulative occupational radiation exposure.Page E3-2 ENCLOSURE 4 SHEARON HARRIS NUCLEAR POWER PLANT NRC DOCKET NO.50-400/LICENSE NO.NPF-63 REQUEST FOR LICENSE AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SETPOINT RELOCATION TO THE COLR PAGE CHANGE INSTRUCTIONS Removed Pa e 2-7 2-8 2-9 Inserted Pa e 2-7 2-8 2-8a 2-9 6-24 6-24a 6-24b 6-24 6-24a 6-24b