ML102350156

From kanterella
Revision as of 07:54, 9 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Response to NRC Regulatory Issue Summary 2010-08, Preparation & Scheduling of Operator Licensing Examinations
ML102350156
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 08/18/2010
From: Draxton M S
Calvert Cliffs, Constellation Energy Nuclear Group, EDF Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RIS-10-008
Download: ML102350156 (4)


See also: RIS 2010-08

Text

h Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 CENG a joint venture of Constellation

ý6 eD Energy, CALVERT CLIFFS NUCLEAR POWER PLANT August 18, 2010 U. S. Nuclear Regulatory

Commission

Washington, DC 20555/--ATTENTION:

SUBJECT: Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Response to NRC Regulatory

Issue Summary 2010-08, Preparation

and Scheduling

of Operator Licensing

Examinations (a) NRC Regulatory

Issue Summary 2010-08, Preparation

and Scheduling

of Operator Licensing

Examinations, dated June 28, 2010 REFERENCE:

The purpose of this letter is to forward Calvert Cliffs Nuclear Power Plant's response to Reference (a).Reference (a) was issued to inform addressees

of the Nuclear Regulatory

Commission (NRC) staff s need for updated information

on projected

site-specific

operator licensing

examination

schedules.

and estimated numbers of applicants

planning to take operator licensing

examinations

and the NRC's generic fundamentals

examinations.

The attached NRC Form 536 contains the proposed schedules

of examinations

intended for preparation

and the estimated

number of applicants

to be tested in site examinations

in calendar years 2012 through 2015 and generic fundamentals

examinations

in calendar years 2012 through 2013.kIL4 ~

4 Document Control Desk August 18, 2010 Page 2 Should you have questions

regarding

this matter, please contact Mr. Douglas E. Lauver at (410) 495-5219 or Mr. Mark S. Draxton at (410) 495-5214.Very truly yours, ark S. Draxton M ager -- Training MSD/RDW/bjd

Attachment:

(1) Response to Regulatory

Issue Summary 2010-08, NRC Form 536 cc: D. V. Pickett, NRC Resident Inspector, NRC M. L. Dapas, NRC S. Gray, DNR

ATTACHMENT

(1)RESPONSE TO REGULATORY

ISSUE SUMMARY 2010-08, NRC FORM 536 Calvert Cliffs Nuclear Power Plant, Inc.August 18, 2010

NRC FORM 536 U.S. NUCLEAR REGULATORY

COMMISSION

APPROVED BY OMB: NO. 3150-0131

EXPIRES: 10/31/2011

(10-20080)

Estimated

burden per response to comply with this voluntary

information

collection

request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information

collection

is used to plan budgets and resources

for operator examinations.

Send comments regarding

burden estimate to the Records and FOIA/Privacy

Services Branch (T-5 F53), U.S. Nuclear Regulatory

Commission, Washington, DC OPERATOR LICENSING

20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the EXAMINATION

DATA Desk Officer, Office of Information

and Regulatory

Affairs, NEOB-10202, (3150-0131), Office of Management

and Budget, Washington, DC 20503. If a means used to impose an information

collection

does not display a currently

valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information

I collection.

FACILITY NRC REGION Calvert Cliffs Nuclear Power Plant, LLC Unit Nos. 1 & 2, Docket Nos. 50-317 & 50-318 1 A. PROPOSED EXAMINATION

PREPARATION

SCHEDULE PROPOSED NUMBER CY 2012 CY 2013 CY 2014 CY 2015 ESTIMATED

NUMBER OF LICENSEE-PREPARED

1 0 1 0 EXAMINATIONS

ESTIMATED

NUMBER OF NRC-PREPARED

0 0 0 0 EXAMINATIONS

B. INITIAL OPERATOR LICENSE EXAMINATIONS

PROPOSED NUMBER CY 2012 CY 2013 CY 2014 CY 2015 NUMBER OF REACTOR 5 0 5 0 OPERATORS NUMBER OF SENIOR REACTOR OPERATORS-

5 0 5 0 INSTANT NUMBER OF SENIOR REACTOR OPERATORS-

5 0 5 0 UPGRADE NUMBER OF SENIOR REACTOR OPERATORS

-0 0 0 0 LIMITED PROPOSED DATES PRIMARY DATE August 13, 2012 August 11,2014 ALTERNATE

DATE August 20, 2012 August 18, 2014 C. PROPOSED GENERIC FUNDAMENTALS

EXAMINATION (GFE) SCHEDULE PROPOSED CY 2012 CY 2013 NUMBER MARCH JUNE SEPTEMBER

DECEMBER MARCH JUNE SEPTEMBER

DECEMBER ESTIMATED NUMBER OF 0 0 0 100 0 CANDIDATES-tl '-IV ..-.: --UUO1 trill i cu T