2012/03/28 NRR E-mail Capture - H.B. Robinson Steam Electric Plant, Unit No. 2 - Acceptance Review for Request for Technical Specifications Change Regarding Corrections to Table 3.3.1-1 Note 1 (TAC No. ME8225)
ML12091A063
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 03/28/2012
From: Billoch-Colon A T
Division of Operating Reactor Licensing
To: Hightower R E
Progress Energy Co
References
TAC ME8225
Download: ML12091A063 (3)


Text

1NRR-PMDAPEm ResourceFrom:Billoch, AraceliSent:Wednesday, March 28, 2012 9:04 AMTo:Hightower, RichardSubject:H.B. Robinson Steam Electric Plant, Unit No. 2 - Acceptance Review for Request for Technical Specifications Change Regarding Corrections to Table 3.3.1-1 Note 1 (TAC No. ME8225)Attachments:image001.gifDear Mr. Hightower, By letter dated March 16, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12083A292), Carolina Power and Light Company, submitted a license amendment request for H.B. Robinson Steam Electric Plant, Unit No. 2. The proposed change would make corrections in Technical Specification Table 3.3.1-1 for Overtemperature Delta Temperature (OTT) consistent with NUREG-1431, "Standard Technical Specification Westinghouse Plants," Revision 3.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me at (301) 415-3302.

Araceli T. Billoch Colón Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Tel. 301-415-3302

Hearing Identifier: NRR_PMDA Email Number: 309 Mail Envelope Properties (Araceli.Billoch@nrc.gov20120328090300)

Subject:

H.B. Robinson Steam Electric Plant, Unit No. 2 - Acceptance Review for Request for Technical Specifications Change Regarding Corrections to Table 3.3.1-1 Note 1 (TAC No. ME8225) Sent Date: 3/28/2012 9:03:37 AM Received Date: 3/28/2012 9:03:00 AM From: Billoch, Araceli Created By: Araceli.Billoch@nrc.gov Recipients: "Hightower, Richard" <richard.hightower@pgnmail.com> Tracking Status: None

Post Office: Files Size Date & Time MESSAGE 2172 3/28/2012 9:03:00 AM image001.gif 1332

Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date: Recipients Received: