MONTHYEARIR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 IR 05000320/20220042023-02-16016 February 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2022004 and 05000320/2022401 IR 05000289/20220022023-02-13013 February 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 NRC Inspection Report Nos. 05000289/2022002 and 005000289/2022402 IR 05000289/20220012022-08-26026 August 2022 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report Nos. 05000289/2022001 and 07200077/2022001 ML22228A0142022-08-17017 August 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report IR 05000289/20224012022-04-12012 April 2022 NRC Security Decommissioning Inspection Report No. 05000289/2022401 IR 05000289/20210022022-01-31031 January 2022 NRC Inspection Report 05000289/2021002 and 07200077/2021001 IR 05000320/20210042022-01-27027 January 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021004 IR 05000289/20210012021-06-28028 June 2021 NRC Inspection Report No. 05000289/2021001, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20214012021-06-28028 June 2021 Security Decommissioning Inspection Report 05000289/2021401 IR 05000320/20210032021-06-22022 June 2021 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021003 IR 05000289/20200052021-02-0101 February 2021 NRC Inspection Report No. 05000289/2020005, Exelon Generation Co., LLC, Three Mile Island Nuclear Station Unit 1 IR 05000320/20200022020-10-19019 October 2020 Gpu Nuclear, Inc., Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report 05000320/2020002 IR 05000289/20204012020-09-0101 September 2020 Unit 1 - Security Baseline Inspection Report 05000289/2020401 IR 05000289/20200032020-07-20020 July 2020 NRC Inspection Report No. 05000289/2020003, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20200012020-04-30030 April 2020 NRC Inspection Report 05000289/2020001 IR 05000289/20190102020-02-0404 February 2020 NRC Inspection Report No. 05000289/2019010, Exelon Generation Co., LLC, Three Mile Island Unit 1, Middletown, PA IR 05000289/20190032019-11-0606 November 2019 Integrated Inspection Report 05000289/2019003 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20193012019-08-15015 August 2019 Initial Operator Licensing Examination Report 05000289/2019301 IR 05000289/20190022019-08-0909 August 2019 Integrated Inspection Report 05000289/2019002 IR 05000320/20190012019-06-10010 June 2019 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2019001 IR 05000289/20195012019-06-0303 June 2019 Emergency Preparedness Biennial Exercise Inspection Report 05000289/2019501 IR 05000289/20194102019-03-18018 March 2019 Baseline Security Inspection Report 05000289/2019410 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180042019-01-31031 January 2019 Integrated Inspection Report 5000289/2018004 IR 05000289/20182012018-12-13013 December 2018 NRC Inspection Report 05000289/2018201 IR 05000289/20180032018-11-0808 November 2018 Integrated Inspection Report 5000289/2018003 IR 05000289/20184102018-09-18018 September 2018 Baseline Security Inspection Report 05000289/2018410 (Letter Only) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20180022018-08-0202 August 2018 Integrated Inspection Report 5000289/2018002 IR 05000320/20180112018-05-23023 May 2018 NRC Inspection Report 05000320/2018011 IR 05000289/20180102018-05-0202 May 2018 Design Bases Assurance Inspection (Teams) Report 05000289/2018010 IR 05000289/20180012018-05-0202 May 2018 Integrated Inspection Report 5000289/2018001 and Exercise of Enforcement Discretion IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170042018-01-25025 January 2018 Integrated Inspection Report 05000289-2017004 IR 05000289/20174052017-11-29029 November 2017 Problem Identification and Resolution Cyber Security Inspection Report 05000289/2017405 (Cover Letter) IR 05000289/20170032017-10-25025 October 2017 Integrated Inspection Report 5000289/2017003 IR 05000289/20174032017-09-25025 September 2017 Baseline Security Inspection Report 05000289/2017403 (Cover Letter) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20170102017-08-25025 August 2017 Susquehanna Steam Electric Station, Units 1 and 2 - Problem Identification and Resolution Cyber Security Inspection Report 05000387/2017405 and 05000388/2017405 (Cover Letter) IR 05000289/20173012017-08-23023 August 2017 Initial Operator Licensing Examination Report 05000289/2017301 IR 05000289/20170022017-08-0808 August 2017 Integrated Inspection Report 05000289/2017002 IR 05000320/20170092017-07-17017 July 2017 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2017009 IR 05000289/20170082017-07-11011 July 2017 NRC Investigation Report No. 1-2016-008 and Three Mile Island, Unit 1 - Inspection Report 05000289/2017008 IR 05000289/20174042017-06-20020 June 2017 Material Control and Accounting Program Inspection Report 05000289/2017404 (Letter Only) 2024-01-29
[Table view] Category:Letter
MONTHYEARML24038A0222024-02-0505 February 2024 Achp Letter on Section 106 Programmatic Agreement Participation IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 ML23342A1242024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23325A1092024-01-0505 January 2024 Review of the Management Plan for Three Mile Island Station, Unit No. 2, Debris Material ML23354A2062023-12-20020 December 2023 (TMI-2), Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23354A2112023-12-20020 December 2023 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 ML23243A9082023-08-29029 August 2023 Shpo Letter to TMI-2 Regarding Section 106 Activities IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 ML23216A1742023-08-14014 August 2023 Consultation Letter to David Morrison for TMI-2 ML23216A1772023-08-14014 August 2023 Consultation Letter to Rebecca Countess for TMI-2 ML23216A1752023-08-14014 August 2023 Consultation Letter to Joanna Cain for TMI-2 ML23216A1732023-08-14014 August 2023 Consultation Letter to Christine Turner for TMI-2 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 ML23216A1782023-08-14014 August 2023 Consultation Letter to Steve Letavic for TMI-2 ML23221A1402023-08-0808 August 2023 (TMI-2), Response to Requests for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23200A1882023-07-31031 July 2023 TMI-2 Correction Letter Amendment 67 ML23209A7632023-07-28028 July 2023 Letter from PA Shpo to TMI-2 Solutions on Cultural and Historic Impacts of Decommissioning ML23192A8272023-07-10010 July 2023 TMI-2 Solutions, LLC - Response to Shpo Request for Additional Information for Er Project 2021PR03278.006, TMI-2 Decommissioning Project ML23167A4642023-07-0505 July 2023 Letter - TMI-2- Exemption 10 CFR Part 20 Append G Issuance ML23167A0312023-06-28028 June 2023 Acceptance Review and Schedule for the Request for Exemption from a Requirement from 10 CFR 20, Appendix G, Section Iii.E, EPID L-2023-LLE-0016 ML23171B0222023-06-19019 June 2023 (TMI-2) - Notification Pursuant to 10 CFR 72.140(d) Regarding Application of Previously Approved TMI-2 Quality Assurance Program to Independent Spent Fuel Storage Installation Activities ML23137A2822023-05-17017 May 2023 (TMI-2), Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML23138A0662023-05-17017 May 2023 TMI-2 NHPA Section 106 Shpo Letter to NRC 5-17-23 ML23026A3132023-05-0202 May 2023 Issuance of Exemption from 10 CFR 70.24 (EPID-L-2023-LLE-0003) ML23122A1842023-05-0101 May 2023 Shpo_Er_Summary_Letter ML23121A2492023-05-0101 May 2023 License Amendment Request, Historic and Cultural Resources Review, Response to Request for Additional Information ML23117A0012023-04-26026 April 2023 Commitment Revision Summary Report ML23027A0832023-04-24024 April 2023 Environmental Assessment/Finding of No Significant Impact - Request for Exemption from 10 CFR 70.24 ML23108A0802023-04-18018 April 2023 Annual Radiological Effluent Release Report ML23108A0822023-04-18018 April 2023 Annual Radiological Environmental Operating Report IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 ML23102A0382023-04-10010 April 2023 Occupational Radiation Exposure Annual Report ML23108A2002023-04-10010 April 2023 CFR 20.2206(b) Personnel Radiation Exposure Report for 2022 ML23094A2582023-04-0606 April 2023 Letter to Sidney Hill, Chief, Onondaga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0572023-04-0606 April 2023 Letter to Joanna Cain, President, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2362023-04-0606 April 2023 Letter to Carissa Speck, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2542023-04-0606 April 2023 Ltr J Bendremer Thpo Stockbridge-Munsee Community Band of Mohican Indians Re Initiation of Consultation Under Section 106 of the NHPA for Proposed License Amendment Request for TMI 2 ML23086C0652023-04-0606 April 2023 Ltr Larry Heady, Thpo, De. Tribe of Indian; Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI Nuclear Station, Unit 2 ML23093A0562023-04-0606 April 2023 Letter to Steve Minnick, Site Decommissioning Director, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2602023-04-0606 April 2023 Letter to William Tarrant, Seneca-Cayuga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23094A2392023-04-0606 April 2023 Letter to Courtney Gerzetich, Thpo, Onedia Nation of Wisconsin, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0592023-04-0606 April 2023 Letter to Rebecca Countess, Chair, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 2024-02-05
[Table view] |
Text
{{#Wiki_filter:ber 25, 2017
SUBJECT:
THREE MILE ISLAND STATION, UNIT 1 - INTEGRATED INSPECTION REPORT 5000289/2017003
Dear Mr. Hanson:
On September 30, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Three Mile Island, Unit 1 (TMI). On October 17, 2017, the NRC inspectors discussed the results of this inspection with Mr. Ed Callan, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented a licensee identified violation which was determined to be of very low safety significance in this report. Because of the very low safety significance and because it has been entered into your corrective action program, the NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Three Mile Island.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www/nrc.gov/reading-rm/adams.html the NRCs Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Silas R. Kennedy, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-289 License No. DPR-50
Enclosure:
Inspection Report 05000289/2017003 w/Attachment: Supplementary Information
REGION I==
Docket No: 50-289 License No: DPR-50 Report No: 05000289/2017003 Licensee: Exelon Generation Company Facility: Three Mile Island Station, Unit 1 Location: Middletown, PA 17057 Dates: July 01 through September 30, 2017 Inspectors: Z. Hollcraft, Senior Resident Inspector C. Roettgen, Senior Resident Inspector (Acting)
B. Lin, Resident Inspector E. Burket, Reactor Inspector M. Modes, Senior Reactor Inspector R. Rolph, Health Physicist S. Obadina, Project Engineer Approved by: S. Kennedy, Chief Reactor Projects Branch 6 Division of Reactor Projects Enclosure
SUMMARY
IR 05000289/2017003, 06/01/2017-09/30/2017; Three Mile Island, Unit 1, Licensee-Identified
Violation.
This report covered a three-month period of inspection by resident inspectors and announced inspections performed by regional inspectors. The significance of most findings is indicated by their color (i.e., greater than Green, or Green, White, Yellow, Red) and determined using Inspection Manual chapter (IMC) 0609, Significance Determination Process, dated April 29, 2015. Cross-cutting aspects are determined using IMC 0310, Aspects Within Cross-Cutting Areas, dated August 1, 2016. All violations of Nuclear Regulatory Commission (NRC)requirements are dispositioned in accordance with the NRCs Enforcement Policy, dated November 1, 2016. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision
NRC-Identified and Self-Revealing Findings
No findings were identified.
Other Findings
A violation of very low safety significance that was identified by Exelon was reviewed by the inspectors. Corrective actions taken or planned by Exelon have been entered into Exelons corrective action program. This violation and corrective action tracking number are listed in Section 4OA7 of this report.
REPORT DETAILS
Summary of Plant Status
Unit 1 began the inspection period at 100 percent power. On September 18, 2017, operators shutdown the plant for a planned refueling outage. The unit remained shutdown for the remainder of the inspection period.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
Main article: IP 71111.01
.1 External Flooding
a. Inspection Scope
On September 19, 2017, the inspectors performed an inspection of the external flood protection measures for Three Mile Island (TMI). The inspectors reviewed technical specifications; procedures; design documents; and the Updated Final Safety Analysis Report (UFSAR), Chapter 2.4.2.4, which depicted the design flood levels and protection areas containing safety-related equipment, to identify areas that may be affected by internal flooding. The inspectors conducted a general site walkdown of all external areas of the plant, including the turbine building, auxiliary building, and berm to ensure that Exelon erected flood protection measures in accordance with design specifications.
The inspectors also reviewed operating procedures for mitigating external flooding during severe weather to determine if Exelon planned or established adequate measures to protect against external flooding events. Documents reviewed for each section of this inspection report are listed in the Attachment.
b. Findings
No findings were identified.
==1R04 Equipment Alignment
.1 Partial System Walkdowns
Main article: IP 71111.04Q ==
a. Inspection Scope
The inspectors performed partial walkdowns of the following systems:
- Spent fuel cooling system during fuel receipt on August 14, 2017
- Intermediate cooling system on August 15, 2017
- Fuel handling building essential service fan ventilation system on August 28, 2017
- A train of the decay heat system on September 19, 2017 The inspectors selected these systems based on their risk-significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the UFSAR, technical specifications, work orders, issue reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted system performance of their intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies. The inspectors also reviewed whether Exelon staff had properly identified equipment issues and entered them into the corrective action program for resolution with the appropriate significance characterization.
b. Findings
No findings were identified.
==1R05 Fire Protection
.1 Resident Inspector Quarterly Walkdowns
Main article: IP 71111.05Q