Category:E-Mail
MONTHYEARML24215A3672024-08-0101 August 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station - License Amendment Request to Revise Emergency Plan - EPID L-2024-LLA-0011 ML24183A2392024-07-0101 July 2024 NRR E-mail Capture - LIC-109 Acceptance - Columbia Generating Station - Relief Request for the Fourth Ten-Year Interval Inservice Testing - EPID L-2024-LLR-0039 ML24169A0402024-06-14014 June 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station (Columbia) - Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs (L-2024-LLR-007 Through 0013) ML24103A2022024-04-0909 April 2024 EN 57068 - Transco Products Inc Part 21 Initial Notification of Unverified Critical Characteristics of Darmatt KM-1 Flat Board ML24060A1022024-02-28028 February 2024 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2023 Biological Monitoring Report ML24053A0092024-02-21021 February 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs L-2024-LLR-0007 Through 00013 ML24008A0022024-01-0505 January 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation - EPID L-2023-LLA-0170 ML23278A0042023-10-0404 October 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID L-2023-LLA-0128 ML23275A0092023-09-29029 September 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Tech Specs to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID: L-2023-LLA-0128 ML23150A2502023-05-26026 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - License Amendment Request to Clean-Up Operating License and Appendix a, Technical Specifications - EPID L-2023-LLA-0062 ML23124A2412023-05-0404 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise TS to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position - EPID L-2023-LLA-0063 ML23124A0062023-05-0303 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise Tech Specs to Adopt TSTF-541, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2023-LLA-0063 ML23065A0422023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Biological Monitoring Report ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22349A2002022-12-0101 December 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Priority Pollutant Discharge Monitoring Report ML22312A0042022-11-0707 November 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Fourth 10 Year ISI RR 4ISI-11 - EPID L-2022-LLR-0071 ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22256A2002022-09-13013 September 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22241A0182022-08-26026 August 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information ML22210A0072022-07-28028 July 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22166A4122022-06-15015 June 2022 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise TS to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2022-LLA-0081 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22075A3392022-03-15015 March 2022 NRR E-mail Capture - Columbia Generating Station - Audit Questions - Regulatory Audit of License Amendment Request to Adopt 50.69 - Categorization Process - EPID L-2021-LLA-0207 ML22067A0132022-03-0707 March 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4b - EPID L-2022-LLA-0023 A002515, NRR E-mail Capture - (External Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report2022-01-12012 January 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report ML21348A1852021-12-14014 December 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors - EPID L-2021-LLA-0207 ML21335A0182021-11-30030 November 2021 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Requested Licensing Action - License Amendment Request to Change TS 3.4.11 Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21162A3062021-06-11011 June 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement - EPID L-2021-LLA-0084 ML21137A0012021-05-14014 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21109A2762021-04-0808 April 2021 Email Request for Information for Columbia Generating Station'S PIR Inspection_Redacted ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML21036A2932021-02-0404 February 2021 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2020 Biological Monitoring Report ML20357B1502020-12-22022 December 2020 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request - Adoption of TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Rev. 2 - EPID L-2020-LLA-0259 ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20314A0452020-11-0606 November 2020 NMFS to Energy Northwest, Entrainment Study Results for Columbia Generating Station ML20297A3032020-10-22022 October 2020 NRR E-mail Capture - LIC-109 Acceptance Review of License Amendment Request for Columbia - Application to Revise Tech Specs to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements - EPID L-2020-LLA-0212 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20265A3242020-09-20020 September 2020 Email 9-20-2020 - Req_ Kick-Off Call Columbia Generating Station RFI Provided for Roll-Back EP Program Inspection (Week of Nov 2 2020) ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20136A0112020-05-14014 May 2020 NRR E-mail Capture - Acceptance Columbia Relief Request ISI Reactor Pressure Vessel Feedwater Nozzles, 4ISI-09 ML20112F4572020-04-21021 April 2020 NRR E-mail Capture - Official Release of NRC RAIs for Columbia Covid Exigent Due Friday April 24, 2020 ML20090F5532020-03-30030 March 2020 NRR E-mail Capture - Accepted: Columbia Relief Request, EPID: L-2020-LLR-0035 2024-08-01
[Table view] |
Text
Craver, Patti From: Logan, Dennis Sent: Thursday, January 05, 2012 8:10 AM To: Grange, Briana; Doyle, Daniel; Krieg, Rebekah
Subject:
RE: Columbia NMFS consultation
- Dan, Briana is correct that our ESA and NEPA work often continues on separate schedules. You will see in final SEISs sometimes that the section 7 consultations are continuing at the time the FSEIS is being published. We have a contention on this procedure at Indian Point, but this is how NRC has been doing things. After the FSEIS is published, responsibility for the section 7 consultations shifts from the EPM's branch to RERB, so don't worry about being tied to this.
Also, we know from experience that Domingue and Graves work on their own schedule and rarely return our calls, so nothing new there.
Dennis From: Balsam, Briana Sent: Thursday, January 05, 2012 7:50 AM To: Doyle, Daniel; Krieg, Rebekah Cc: Logan, Dennis
Subject:
RE: Columbia NMFS consultation
- Dan, I don't know what the next steps should be, but whether we continue consultation with NMFS or do not continue consultation, this shouldn't affect the FSEIS schedule or publication date. There are no statutory requirements to complete consultation under the ESA prior to completing the NEPA process. In a number of cases, we have had consultation draw out much longer than the NEPA process. For instance, Salem's consultation is still ongoing, yet we issued the renewed license for this plant in June 2011.
Briana From: Doyle, Daniel Sent: Wednesday, January 04, 2012 7:57 PM To: Krieg, Rebekah Cc: Balsam, Briana; Logan, Dennis
Subject:
RE: Columbia NMFS consultation
- Becky, Try this link:
http://adamswebsearch2.nrc.qov/webSearch2/main.isp?AccessionNumber='ML11335A127' Dan From: Krieg, Rebekah [1]
Sent: Wednesday, January 04, 2012 7:51 PM 1
To: Doyle, Daniel; Logan, Dennis Cc: Balsam, Briana
Subject:
RE: Columbia NMFS consultation I'm not able to access the letter in ADAMS. Do you think it might not have cleared the ADAMS "waiting period"?
From: Doyle, Daniel [mailto: Daniel.Doyle@nrc.gov]
Sent: Wednesday, January 04, 2012 3:21 PM To: Logan, Dennis; Krieg, Rebekah Cc: Balsam, Briana
Subject:
RE: Columbia NMFS consultation Dennis and Becky, The NRC response letter to NMFS was signed out on 12/20/11 (ML11335A127). Several days before it was sent, I called and left messages with Ritchie Graves and Rich Domingue giving them a heads up that our letter was coming. I haven't heard back from them.
What happens now? Do you want to call or email them again or should I? Do we need a response from them?
My main reason for asking is to determine the impact on publication of the final SEIS.
Dan From: Balsam, Briana Sent: Wednesday, November 30, 2011 11:26 AM To: Doyle, Daniel Cc: Logan, Dennis; Krieg, Rebekah
Subject:
RE: Columbia NMFS consultation Okay, thanks, Dan. It's not essential that you put that in the summary. It would just be nice to people to point back to that in the future in the event that we need to!
From: Doyle, Daniel Sent: Wednesday, November 30, 2011 11:22 AM To: Balsam, Briana Cc: Logan, Dennis; Krieg, Rebekah
Subject:
RE: Columbia NMFS consultation
- Briana, I called back and left him a voicemail asking him to confirm that NMFS does not intend to provide the NRC with EFH conservation recommendations.
He will be out until Monday, 12/5 so I will follow up with him then. I'll let you know when I hear back from him.
Dan From: Balsam, Briana Sent: Wednesday, November 30, 2011 11:10 AM To: Doyle, Daniel; Logan, Dennis; Krieg, Rebekah Cc: Wrona, David; Imboden, Andy
Subject:
RE: Columbia NMFS consultation 2
- Dan, Did Richie Graves mention anything about EFH Conservation Recommendations? I am assuming he did not since he said that NMFS does not plan to send us another letter.
You might want to rephrase the last sentence:
"NMFS does not intend to send another letter addressing the essential fish habitat assessment or provide the NRC with EFH Conservation Recommendations."
This addition will help clarify that our responsibility to respond to NMFS within a particular timeline per the EFH regulations does not apply in this case because NMFS did not send us specific conservation recommendations.
Briana From: Doyle, Daniel Sent: Wednesday, November 30, 2011 9:28 AM To: Logan, Dennis; Krieg, Rebekah Cc: Balsam, Briana; Wrona, David; Imboden, Andy
Subject:
RE: Columbia NMFS consultation I am submitting a record of conversation into ADAMS. Here is the current text... let me know if you have any comments or revisions:
Daniel Doyle contacted Ritchie Graves regardingthe NRC's consultation with the National Marine Fisheries Service (NMFS) for the Columbia Generating Station License Renewal EnvironmentalReview. Mr. Doyle asked about the status of NMFS's response to the NRC letter dated August 23, 2011 (ADAMS Accession Number MLII 165A023). He noted that the NRC had already received a letter from NMFS dated October 24, 2011 (ADAMS Accession Number MLI 1307A393), but that the letter only addressed the NRC's biological assessment but did not address the NRC's essential fish habitatassessment.
Ritchie Graves acknowledged that the NMFS letter dated October 24, 2011, failed to addressthe NRC's essential fish habitat assessment. He stated that NMFS believes that the concerns expressed in the October 24, 2011, letter about the biologicalassessment are identical to the concerns for the essential fish habitat assessment. He also stated that the resolution of the concerns about the biologicalassessment would likely resolve NMFS concerns about the essentialfish habitat. NMFS does not intend to send anotherletter addressingthe essential fish habitatassessment.
Dan From: Logan, Dennis Sent: Tuesday, November 29, 2011 8:27 AM To: Doyle, Daniel; Krieg, Rebekah Cc: Balsam, Briana; Wrona, David; Imboden, Andy; Subin, Lloyd
Subject:
RE: Columbia NMFS consultation
- Dan, By the way, I don't know ifyou noticed, but the title of ML11307A393, is wrong and misleading:
"Comment (44) of William W.Stelle, on Behalf of National Marine Fisheries Service, Opposing Proposed License Renewal for Energy Northwest's Columbia Generating Station."
Perhaps someone with owner's rights can change it.
Regarding a response, although I talked to Rich Domingue, he obviously did not talk to Richie Graves. We have had to send other regional NMFS offices letters clarifying NRC's responsibilities, and we will use one of those as a basis of our reply here.
3
I .. .
Dennis From: Doyle, Daniel Sent: Monday, November 28, 2011 5:00 PM To: Logan, Dennis; Krieg, Rebekah Cc: Balsam, Briana; Wrona, David; Imboden, Andy; Subin, Lloyd
Subject:
RE: Columbia NMFS consultation Dennis and Becky, I still have not seen anything from NMFS about the Columbia EFH assessment. We received a letter from NMFS dated 10/24/11 stating that they do not concur with the conclusion in the BA but that was regarding the ESA Section 7 consultation. They didn't mention the EFH assessment.
I called Rich Domingue today at 503-231-6858 but got his voicemail and did not leave a message. As stated in the letter, he is the POC for the ESA consultation. I also called Ritchie Graves at 503-231-6891 and talked to him for a few minutes. He said he would look into it and get back to me. I'll let you know if I hear anything.
Date Description ADAMS #
8/23/2011 NRC letter to NMFS re: BA and EFH assessment ML11165A023 10/24/2011 NMFS letter to NRC re: non-concurrence on BA ML11307A393 Please let me know if you think we need to do anything else about the EFH consultation right now.
Also, please let me know how you plan to respond to the NMFS letter about the BA.
- Thanks, Dan From: Doyle, Daniel Sent: Tuesday, November 01, 2011 11:11 AM To: Logan, Dennis; 'Krieg, Rebekah'; Subin, Lloyd Cc: Wrona, David
Subject:
Columbia NMFS consultation Dennis, Becky, and Lloyd, I just received the attached letter from NMFS today about Columbia. They do not concur with the determination in the BA:
Therefore, NMFS does not concur with your determination that the proposed action is not likely to adversely affect Upper Columbia River spring Chinook salmon and steelhead and is not likely to modify or destroy designated criticalhabitat.
I will follow up with you to determine our next steps.
- Thanks, Dan Doyle Project Manager Division of License Renewal U.S. Nuclear Regulatory Commission daniel.doyle*bnrc..ov 4
(301) 415-3748 5