{{#Wiki_filter:
{{#Wiki_filter: February 6, 2014 
[[Issue date::February 6, 2014]]
Docket No. 05000134License No. R-61
Michael J. Curley University Compliance Officer
Worcester Polytechnic Institute
100 Institute Road
Worcester, MA  01609-2280  SUBJECT: NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE 
Dear Mr. Curley:  
On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility
in Worcester, Massachusetts.  The inspection was an examination of your licensed activities as
they relate to radiation safety and to compliance with the Commission's regulations and the
license conditions.  The inspection consisted of observations by the inspectors, interviews with WPI and contractor personnel, a review of procedures and records, and acquisition of split samples.  The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform
analysis of samples obtained by the inspectors.  ORAU provided the results of the sample
analysis in a report, "Letter Report for Analytical Results for Two Concrete and Three Soil
Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,"
dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS) Accession No. ML13309B020).  Additional information in documents provided by WPI dated August 22, August 26, October 29, and December 6, 2013, were also examined as part of the
inspection.  On January 16, 2014, the inspectors held a telephone conference call exit with you
and other members of your staff.  The enclosed report presents the results of this inspection. 
No health and safety concerns were identified.    The enclosed inspection report will be provided to the NRC Division of Waste Management and Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any request to terminate the WPI license and release the site for unrestricted use.  Please note that
this report does not release the site for unrestricted use nor does it terminate the license.
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and Communications.  The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information').  You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800.  The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday
(except Federal holidays).  UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 
M. Curley 2 
No reply to this letter is required.  Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter.    Sincerely,
Original signed by Marc S. Ferdas 
Marc S. Ferdas, Chief Decommissioning and Technical 
Support Branch
Division of Nuclear Materials Safety  Enclosure: Inspection Report No. 05000134/2013001
cc:  Commonwealth of Massachusetts
   
M. Curley 2 
No reply to this letter is required.  Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter.    Sincerely,
Original signed by Marc S. Ferdas 
Marc S. Ferdas, Chief Decommissioning and Technical 
Support Branch
Division of Nuclear Materials Safety  Enclosure: Inspection Report No. 05000134/2013001
cc:  Commonwealth of Massachusetts
DISTRIBUTION: T. Smith, FSME, DWMEP
  DOCUMENT NAME:  G:\WordDocs\Current\Insp Letter\L00-00000-61.2013001.doc  ML14037A365 SUNSI Review Complete:  MRoberts  After declaring this document AAn Official Agency Record@ it will be released to the Public.  To receive a copy of this document, indicate in the box: AC@ = Copy w/o attach/encl  AE@ = Copy w/ attach/encl  AN@ = No copy  OFFICE  DNMS/RI      N  DNMS/RI  DNMS/RI E    NAME KModes\mcr f\ MRoberts\mcr  MFerdas\msf  DATE 1/31/14 2/6/14 2/6/14    OFFICIAL RECORD COPY       


Docket No. 05000134License No. R-61 Michael University Compliance Officer Worcester Polytechnic Institute 100 Institute Road Worcester, MA 01609-2280
SUBJECT: NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE
==Dear Mr. Curley:==
On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility in Worcester, Massachusetts. The inspection was an examination of your licensed activities as they relate to radiation safety and to compliance with the Commission's regulations and the license conditions. The inspection consisted of observations by the inspectors, interviews with WPI and contractor personnel, a review of procedures and records, and acquisition of split samples. The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform analysis of samples obtained by the inspectors. ORAU provided the results of the sample analysis in a report, "Letter Report for Analytical Results for Two Concrete and Three Soil Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,"
dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS) Accession No. ML13309B020). Additional information in documents provided by WPI dated August 22, August 26, October 29, and December 6, 2013, were also examined as part of the inspection. On January 16, 2014, the inspectors held a telephone conference call exit with you and other members of your staff. The enclosed report presents the results of this inspection.
No health and safety concerns were identified. The enclosed inspection report will be provided to the NRC Division of Waste Management and Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any request to terminate the WPI license and release the site for unrestricted use. Please note that this report does not release the site for unrestricted use nor does it terminate the license.
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays). No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter.
Sincerely,Original signed by Marc S. Ferdas Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety
===Enclosure:===
Inspection Report No. 05000134/2013001
cc: Commonwealth of Massachusetts
}}
}}

Revision as of 07:35, 22 March 2018

IR 05000134-13-001, on 8/22/13 - 1/16/14, Worcester Polytechnic Institute, Worcester, Ma, Site. Cover Letter
ML14037A365
Person / Time
Site: 05000134
Issue date: 02/06/2014
From: Ferdas M S
NRC/RGN-I/DNMS/NMSB3
To: Curley M J
Worcester Polytechnic Institute
Shared Package
ML14024A421 List:
References
IR-13-001
Download: ML14037A365 (3)


See also: IR 05000134/2013001

Text

February 6, 2014

Docket No. 05000134License No. R-61

Michael J. Curley University Compliance Officer

Worcester Polytechnic Institute

100 Institute Road

Worcester, MA 01609-2280 SUBJECT: NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE

Dear Mr. Curley:

On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility

in Worcester, Massachusetts. The inspection was an examination of your licensed activities as

they relate to radiation safety and to compliance with the Commission's regulations and the

license conditions. The inspection consisted of observations by the inspectors, interviews with WPI and contractor personnel, a review of procedures and records, and acquisition of split samples. The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform

analysis of samples obtained by the inspectors. ORAU provided the results of the sample

analysis in a report, "Letter Report for Analytical Results for Two Concrete and Three Soil

Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,"

dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS) Accession No. ML13309B020). Additional information in documents provided by WPI dated August 22, August 26, October 29, and December 6, 2013, were also examined as part of the

inspection. On January 16, 2014, the inspectors held a telephone conference call exit with you

and other members of your staff. The enclosed report presents the results of this inspection.

No health and safety concerns were identified. The enclosed inspection report will be provided to the NRC Division of Waste Management and Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any request to terminate the WPI license and release the site for unrestricted use. Please note that

this report does not release the site for unrestricted use nor does it terminate the license.

Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday

(except Federal holidays). UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713

M. Curley 2

No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter. Sincerely,

Original signed by Marc S. Ferdas

Marc S. Ferdas, Chief Decommissioning and Technical

Support Branch

Division of Nuclear Materials Safety Enclosure: Inspection Report No. 05000134/2013001

cc: Commonwealth of Massachusetts

M. Curley 2

No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter. Sincerely,

Original signed by Marc S. Ferdas

Marc S. Ferdas, Chief Decommissioning and Technical

Support Branch

Division of Nuclear Materials Safety Enclosure: Inspection Report No. 05000134/2013001

cc: Commonwealth of Massachusetts

DISTRIBUTION: T. Smith, FSME, DWMEP

DOCUMENT NAME: G:\WordDocs\Current\Insp Letter\L00-00000-61.2013001.doc ML14037A365 SUNSI Review Complete: MRoberts After declaring this document AAn Official Agency Record@ it will be released to the Public. To receive a copy of this document, indicate in the box: AC@ = Copy w/o attach/encl AE@ = Copy w/ attach/encl AN@ = No copy OFFICE DNMS/RI N DNMS/RI DNMS/RI E NAME KModes\mcr f\ MRoberts\mcr MFerdas\msf DATE 1/31/14 2/6/14 2/6/14 OFFICIAL RECORD COPY