| Request for Additional Information cc: See next page | | Request for Additional Information cc: See next page |
|
| |
|
| ML062430342 NRR-088 OFFICE LPL2-2 LPL2-2/PM LPL2-2/LA SBPB/BC LPL2-2/BC NAME JPaige DPickett RSola JSegala JDixon-Herrity DATE 9/11/06 9/11/06 9/8/06 9/12/06 9/12/06 | | ML062430342 NRR-088 OFFICE LPL2-2 LPL2-2/PM LPL2-2/LA SBPB/BC LPL2-2/BC NAME JPaige DPickett RSola JSegala JDixon-Herrity DATE 9/11/06 9/11/06 9/8/06 9/12/06 9/12/06 Mr. K. W. Singer Tennessee Valley Authority WATTS BAR NUCLEAR PLANT cc: |
| | |
| Mr. K. W. Singer Tennessee Valley Authority WATTS BAR NUCLEAR PLANT cc: | |
| Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Glenn W. Morris, Manager Nuclear Operations Corporate Nuclear Licensing Tennessee Valley Authority and Industry Affairs 6A Lookout Place Tennessee Valley Authority 1101 Market Street 4X Blue Ridge Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, Vice President Nuclear Engineering & Technical Services Mr. Paul L. Pace, Manager Tennessee Valley Authority Licensing and Industry Affairs 6A Lookout Place Watts Bar Nuclear Plant 1101 Market Street Tennessee Valley Authority Chattanooga, TN 37402-2801 P.O. Box 2000 Spring City, TN 37381 Mr. Robert J. Beecken, Vice President Nuclear Support Mr. Jay Laughlin, Plant Manager Tennessee Valley Authority Watts Bar Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, TN 37381 Mr. Michael D. Skaggs Senior Resident Inspector Site Vice President Watts Bar Nuclear Plant Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road P.O. Box 2000 Spring City, TN 37381 Spring City, TN 37381 County Executive General Counsel 375 Church Street Tennessee Valley Authority Suite 215 ET 11A Dayton, TN 37321 400 West Summit Hill Drive Knoxville, TN 37902 County Mayor P. O. Box 156 Mr. John C. Fornicola, Manager Decatur, TN 37322 Nuclear Assurance and Licensing Tennessee Valley Authority Mr. Lawrence E. Nanney, Director 6A Lookout Place Division of Radiological Health 1101 Market Street Dept. of Environment & Conservation Chattanooga, TN 37402-2801 Third Floor, L and C Annex 401 Church Street Ms. Ann P. Harris Nashville, TN 37243-1532 341 Swing Loop Road Rockwood, Tennessee 37854 | | Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Glenn W. Morris, Manager Nuclear Operations Corporate Nuclear Licensing Tennessee Valley Authority and Industry Affairs 6A Lookout Place Tennessee Valley Authority 1101 Market Street 4X Blue Ridge Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, Vice President Nuclear Engineering & Technical Services Mr. Paul L. Pace, Manager Tennessee Valley Authority Licensing and Industry Affairs 6A Lookout Place Watts Bar Nuclear Plant 1101 Market Street Tennessee Valley Authority Chattanooga, TN 37402-2801 P.O. Box 2000 Spring City, TN 37381 Mr. Robert J. Beecken, Vice President Nuclear Support Mr. Jay Laughlin, Plant Manager Tennessee Valley Authority Watts Bar Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, TN 37381 Mr. Michael D. Skaggs Senior Resident Inspector Site Vice President Watts Bar Nuclear Plant Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road P.O. Box 2000 Spring City, TN 37381 Spring City, TN 37381 County Executive General Counsel 375 Church Street Tennessee Valley Authority Suite 215 ET 11A Dayton, TN 37321 400 West Summit Hill Drive Knoxville, TN 37902 County Mayor P. O. Box 156 Mr. John C. Fornicola, Manager Decatur, TN 37322 Nuclear Assurance and Licensing Tennessee Valley Authority Mr. Lawrence E. Nanney, Director 6A Lookout Place Division of Radiological Health 1101 Market Street Dept. of Environment & Conservation Chattanooga, TN 37402-2801 Third Floor, L and C Annex 401 Church Street Ms. Ann P. Harris Nashville, TN 37243-1532 341 Swing Loop Road Rockwood, Tennessee 37854 |
|
| |
|
Letter Sequence RAI |
---|
|
|
MONTHYEARML0613101782006-05-0808 May 2006 Technical Specification Change TS-06-09, Revision of Ultimate Heat Sink Temperature. Project stage: Other ML0613805382006-05-0909 May 2006 Cancelled - Notice of Meeting with Tennessee Valley Authority to Proposed License Amendment of May 8, 2006, to Increase the Technical Specification Limit of the Ultimate Heat Sink for the Watts Bar Nuclear Plant, Unit 1 Project stage: Meeting ML0612900342006-05-0909 May 2006 Notice of Meeting with Tennessee Valley Authority to Proposed License Amendment of May 8, 2006, to Increase the Technical Specification Limit of the Ultimate Heat Sink for the Watts Bar Nuclear Plant, Unit 1 Project stage: Meeting ML0615300272006-07-0303 July 2006 Letter Priority Change for TS Change TS-06-09 - Revision of Ultimate Heat Sink Project stage: Other ML0624303422006-09-12012 September 2006 Request for Additional Information for Watts Bar Unit 1 TS Change Request for Ultimate Heat Sink Temperature Project stage: RAI ML0634904042006-12-14014 December 2006 Request for Additional Information Regarding Watts Bar Nuclear Plant- Unit 1 Licensing Amendment for Increasing the Maximum Ultimate Heat Sink Temperature to 88 Degrees Fahrenheit Project stage: RAI ML0701003812006-12-29029 December 2006 Technical Specification (TS) Change WBN-TS-06-09 Request for Additional Information Regarding Technical Specification Change Request for Ultimate Heat Sink Temperature Project stage: Request ML0635404042006-12-29029 December 2006 Request for Additional Information Regarding Technical Specification Change Request for Ultimate Heat Sink Temperature Project stage: RAI ML0706400842007-02-16016 February 2007 Technical Specification Change WBN-TS-06-09 Second Request for Additional Information Regarding Technical Specification Change Request for Ultimate Heat Sink Temperature Project stage: Request ML0714304692007-06-0707 June 2007 Request for Additional Information Regarding Technical Specification Change Request for Ultimate Heat Sink Temperature (Tac No. MD1460) Project stage: RAI ML0720401152007-07-20020 July 2007 Withdrawal of WBN TS-06-09 Technical Specification Change Request for Ultimate Heat Sink (UHS) Temperature Project stage: Withdrawal ML0720504032007-07-26026 July 2007 Withdrawal of an Amendment Request Regarding Ultimate Heat Sink Project stage: Withdrawal 2006-07-03
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 ML18270A2362018-09-26026 September 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 RAIs - Modify TS 3.8.9 Completion Time for Inoperable 120V AC Vital Buses (L-2018-LLA-0050) 2024-09-10
[Table view] |
Text
September 12, 2006 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING TECHNICAL SPECIFICATION CHANGE REQUEST FOR ULTIMATE HEAT SINK TEMPERATURE (TAC NO. MD1460)
Dear Mr. Singer:
By letter dated May 8, 2006, the Tennessee Valley Authority (TVA, the licensee) submitted a proposed license amendment (WBN-TS-06-09) that would revise Technical Specification 3.7.9.1, Ultimate Heat Sink Temperature, that would increase the maximum essential raw cooling water temperature limit from 85 degrees Fahrenheit (EF) to 88 EF in accordance with Title 10 Code of Federal Regulations (10 CFR) 50.90.
In order for the staff to complete its review of the information provided by the licensee, we request that TVA provide responses to the enclosed request for additional information (RAI).
Based on discussions with your staff, we understand that you plan to respond to the enclosed RAI within 60 days of receipt of this letter. If you have any questions about this material, please contact me at (301) 415-1364.
Sincerely,
/RA/
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390
Enclosure:
Request for Additional Information cc: See next page
ML062430342 NRR-088 OFFICE LPL2-2 LPL2-2/PM LPL2-2/LA SBPB/BC LPL2-2/BC NAME JPaige DPickett RSola JSegala JDixon-Herrity DATE 9/11/06 9/11/06 9/8/06 9/12/06 9/12/06 Mr. K. W. Singer Tennessee Valley Authority WATTS BAR NUCLEAR PLANT cc:
Mr. Ashok S. Bhatnagar, Senior Vice President Mr. Glenn W. Morris, Manager Nuclear Operations Corporate Nuclear Licensing Tennessee Valley Authority and Industry Affairs 6A Lookout Place Tennessee Valley Authority 1101 Market Street 4X Blue Ridge Chattanooga, TN 37402-2801 1101 Market Street Chattanooga, TN 37402-2801 Mr. Larry S. Bryant, Vice President Nuclear Engineering & Technical Services Mr. Paul L. Pace, Manager Tennessee Valley Authority Licensing and Industry Affairs 6A Lookout Place Watts Bar Nuclear Plant 1101 Market Street Tennessee Valley Authority Chattanooga, TN 37402-2801 P.O. Box 2000 Spring City, TN 37381 Mr. Robert J. Beecken, Vice President Nuclear Support Mr. Jay Laughlin, Plant Manager Tennessee Valley Authority Watts Bar Nuclear Plant 6A Lookout Place Tennessee Valley Authority 1101 Market Street P.O. Box 2000 Chattanooga, TN 37402-2801 Spring City, TN 37381 Mr. Michael D. Skaggs Senior Resident Inspector Site Vice President Watts Bar Nuclear Plant Watts Bar Nuclear Plant U.S. Nuclear Regulatory Commission Tennessee Valley Authority 1260 Nuclear Plant Road P.O. Box 2000 Spring City, TN 37381 Spring City, TN 37381 County Executive General Counsel 375 Church Street Tennessee Valley Authority Suite 215 ET 11A Dayton, TN 37321 400 West Summit Hill Drive Knoxville, TN 37902 County Mayor P. O. Box 156 Mr. John C. Fornicola, Manager Decatur, TN 37322 Nuclear Assurance and Licensing Tennessee Valley Authority Mr. Lawrence E. Nanney, Director 6A Lookout Place Division of Radiological Health 1101 Market Street Dept. of Environment & Conservation Chattanooga, TN 37402-2801 Third Floor, L and C Annex 401 Church Street Ms. Ann P. Harris Nashville, TN 37243-1532 341 Swing Loop Road Rockwood, Tennessee 37854
REQUEST FOR ADDITIONAL INFORMATION WATTS BAR NUCLEAR PLANT, UNIT 1 TECHNICAL SPECIFICATION CHANGE REQUEST FOR ULTIMATE HEAT SINK TEMPERATURE DOCKET NO. 50-390
- 1. In Page 5, Tennessee Valley Authority (TVA) states:
The conclusion of the review is that there is sufficient justification to increase the UHS
[ultimate heat sink] upper temperature allowable limit from 85 EF to 88 EF. Operational procedure guidelines will be enhanced, as required, in order to implement this limit.
Provide/describe the specific operational procedure guidelines, as required, in order to implement this proposed limit of 88 EF.
- 2. In Page 13, TVA states that the increased UHS temperature is justified, in part, by margins in the essential raw cooling water (ERCW) flow rates that were established for each of the affected components during the pre-operational testing program. Provide detailed discussion to explain how the existing flow margins have been demonstrated to still be valid; how much of the existing margin will be used in the revised UHS analysis and how much margin will remain; how much of the remaining margin is needed to account for tube plugging, system fouling, pump degradation, measurement uncertainty, etc.; and how technical specification surveillance requirements will ensure that the required flow margins are maintained over time for all of the affected components.
- 3. General Design Criteria (GDC) 44, Cooling Water, requires that a system to transfer heat from structures, systems, and components important to safety, to an ultimate heat sink shall be provided. The system safety function shall be to transfer the combined heat load of these structures, systems, and components under normal, operating and accident conditions.
Also, Standard Review Plan (SRP) 9.1.3, Spent Fuel Pool Cooling And Cleanup System, specifies that continuous fuel cooling be provided during normal, abnormal, and accident conditions.
With regard to TVAs evaluation of the effects on the spent fuel pool (SFP) cooling system resulting from the proposed increase in the UHS temperature, provide detailed/complete discussions of:
- the SFP cooling licensing basis (e.g., maximum heat load, temperature, time to boil, etc.) along with how the existing licensing basis will continue to be satisfied at the increased UHS temperature limit; and
- how the above cited GDC requirement and SRP criteria will continue to be satisfied at the increased UHS temperature limit. Of particular interest is the Enclosure
proposed action to terminate SFP cooling for up to 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, and to what extent is this consistent with the plant licensing basis.
- 4. TVA determined that the emergency diesel generator (EDG) jacket water heat exchangers were marginal at the higher UHS temperature and in order to resolve this problem, the heat exchanger cleaning frequency and timing will be changed to annually (instead of during each refueling outage) during the spring (prior to experiencing the hotter summer temperatures). Provide a detailed discussion to explain how the adequacy of this approach will be validated to assure acceptable EDG performance during those periods when the UHS temperature may be as high as 88 EF and heat exchanger fouling is at maximum.
- 5. The following notes in Table 2 of the submittal attachment (Page 26) credit higher current cooling water flow rates: 2, 3, 5, 6, 7, 9 and 11. Provide a detailed discussion to explain why the current flow rates constitute the most limiting condition consistent with licensing basis assumptions.
- 6. Note 7 in Table 2 of the submittal attachment (Page 26) indicates that actual heat loads were used as a basis to reduce the amount of heat that is required to be rejected.
Provide a detailed discussion to explain why this is a valid approach consistent with the plant licensing basis with respect to the worst case conditions that must be assumed.
- 7. Note 9 in Table 2 of the the submittal attachment (Page 26 & 27) indicates that increased ERCW flow rates are credited, whereas the discussion on Page 21 indicates that increased flow rates were not credited for the EDG jacket water heat exchanger.
Please provide clarification for the above discrepancy. Also, provide a detailed discussion to explain how the engineering judgement was validated.
- 8. TVA indicated that the Tennessee River system is capable of providing water beyond the 30 days (up to one year without any rainfall) as stated in the Updated Final Safety Analysis Report (Page 28). Provide a detailed discussion to explain why this capability is not able to maintain the UHS below the current 85 EF temperature limit.
- 9. TVA indicated that since ERCW flow margins above the existing flow requirements were utilized in validating acceptable performance at the higher ERCW temperature, specific evaluations will be performed prior to unit operation above 85 EF. The performance of these specific evaluations will validate any margin based inputs utilized in the original analyses that determined acceptable performance could be achieved at the higher ERCW temperature. As indicated in the above item 2, validation of the available flow margins that are being credited is requested in support of the staffs review of the proposed change. Furthermore, provide additional discussion detailing specifically how these evaluations will be performed to assure conservative results consistent with licensing basis assumptions.