ML13234A385: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:----a joint venture of------__.
{{#Wiki_filter:CENG~
Constellation Energy' ..* Calvert Cliffs Nuclear Power Plant -., .... -'7-C-'.II, "'.-0-_
a joint venture of------__.
License Amendment Request" , ., . ' ,... ...: Pre-Application Meeting with NRC August 19, I ntrod CENG Representatives  
Constellation                       ..* ~ eDF Energy'                               ~,.
-Elliott Flick Gen'l Manager, Fleet Engineering  
Calvert Cliffs Nuclear Power Plant
-Dave Dellario Manager, Engineering Services -Jim McQuighan Project Manager, NFPA 805 -Paul Darby Principal Engineer, NFPA 805 -Pat Furio Principal Engineer, Licensing  
            ~
-Jeff Stone Supervisor, PRA -Jim Landale Principal Engineer, PRA -Bret Colby Supervisor, Engineering  
                ----
-Ch ris Dobry Principal Engineer, Engineering Project NFPA Consultants  
              - ~.,....~-                                             NFPA80S
-Mark Crompton EPM, NFPA 805 Project Manager CENG.. a )CIn 1-nure 01.______ -c-:  
          ~:~
-=.wE "'" -2 Overview of CCN PP Current Fire Protection Licensing Basis NFPA 805 Transition Project Overview Compliance with NFPA 805 Probabilistic Risk Assessment Implementation Overview Summary /;...;7CENGI a joont ventum o f--___, -"!-'eor:-.r 3 Overview of Two PWRs, each rated @ 2737 MWth Combustion Engineering NSSS Commercial operations began in 1975/1977 Renewed Operating License issued -expires in 2034/2036  
          -C-'.II,               _~
-'7CENGI -8)oint VEWTlure 011-_ ____
                                            '7
.."<'"" -..... ...... -:*t -..f" eOF-.,. ..." 4 Current Fire Protection Licensing Fire Protection Program License Condition 10 CFR 50.48(a) and (b) Draft General Design Criterion 3 10 CFR 50, Appendix R Branch Technical Position APCSB 9.5-1, Appendix Current exemptions  
          "'-:'-~-
.. CENGI -,,)00 1 II8I'I1U19
            "'.                         --:
"'..:..---'*k -'.Iii---.' -f"'eDf.. -" 5
            ~- " ---..>
---NFPA 805 Transition Project License Amendment Request (LAR) committed submittal date -September 30, 2013 Using the Nuclear Energy Institute (NEI) LAR template Web portal will be established to support NRC review CENGI a joini venliml 0 1 ____ _ -,'\:.:" -..*..eDF.;.' --..&.w " 6 NFPA 805 Transi , tion Project Fire Protection Program Transition  
_ ...............                License Amendment Request
-License Condition being revised -Technical Specifications being revised -Reviewed existing exemptions  
    ~<).~
-Three exemptions will be credited post-NFPA 805 transition
,... .,
_ 19".:-" CENGI . -..... -".s-: .'.B ' ---7 Compliance with NFPA NFPA 805 Chapter 3 Compliance  
    ...:
-Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0036 Review documented in B-1 Table (Attachment A of LAR) Results of review -3 Code compliance  
          .        .--
-7 sections are addressed via Attachment L of -96 Sections/sub-sections -43 Comply with clarifications/EEEEs/required -16 Comply by previous NRC I " . .-CENG..
                          ,      '
a joInI venture 01'____--, " -c""': . -.,y <1-.J ..*..eDf -8 Compliance with NFPA Non-Power Operations  
Pre-Application Meeting with NRC Staff August 19, 2013
-Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0040 -Fire modeling not used to eliminate or reduce pinch points -Recovery actions are not credited -Results of review
 
Introd uctions
* CENG Representatives
  - Elliott Flick                       Gen'l Manager, Fleet Engineering
  - Dave Dellario                       Manager, Engineering Services
  - Jim McQuighan                       Project Manager, NFPA 805
  - Paul Darby                         Principal Engineer, NFPA 805
  - Pat Furio                           Principal Engineer, Licensing
  - Jeff Stone                         Supervisor, PRA
  - Jim Landale                         Principal Engineer, PRA
  - Bret Colby                         Supervisor, Engineering
  - Ch ris Dobry                       Principal Engineer, Engineering
* Project NFPA Consultants
  - Mark Crompton                         EPM, NFPA 805 Project Manager
                      ~    --
                -~ f~~"':: -
CENG..
a )CIn1-nure 01._ _ _ _ __  ~-:-l-
                ~-  -c-: --- - ~
                                                =.wE "'"
                        -
I)~: ~::.      - --                        ':.*~ eDF 2
 
Agenda Overview of CCN PP
* Current Fire Protection Licensing Basis
* NFPA 805 Transition Project Overview
* Compliance with NFPA 805
* Probabilistic Risk Assessment Development/Results
* Implementation Overview Summary
                  /;...;7-
                <~-
CENG..                            I a joont ventum o f - -_ _ _,
                                                              ~-"- k
            ~;J ~~ -~ --:~~~-        - .r
                                      -              "!-'eor:
01' 3
 
Overview of CCNPP
* Two PWRs, each rated @ 2737 MWth
* Combustion Engineering NSSS Commercial operations began in 1975/1977
* Renewed Operating License issued - expires in 2034/2036
              -'7-
          - --~--
          ...:>-~
CENG.
8)oint VEWTlure 011- _ _ _ __
I
                                                                  ...... -:*t
              <'"" .- . . .."-~-
J~.- "                   -.,.
                                      -                    ...
                                                          ~f " eOF
                                                        ..
4
 
Current Fire Protection Licensing Basis
* Fire Protection Program License Condition
* 10 CFR 50.48(a) and (b)
* Draft General Design Criterion 3 10 CFR 50, Appendix R
* Branch Technical Position APCSB 9.5-1, Appendix A
* Current exemptions
                  .. ~7~        CENG..                                     I
              - --~-                                             ..:..---'*k Iii ~~- - -.' ----
                            '. ,,)001II8I'I1U19 "'- - - - - - ,
            ~
                                    ~                ..f"' eDf
                                    ~                -"                   5
 
NFPA 805 Transition Project Overview
* License Amendment Request (LAR) committed submittal date - September 30, 2013
* Using the Nuclear Energy Institute (NEI) LAR template
* Web portal will be established to support NRC review
            --~~-
                    ~~7---        CENG_
a joini venliml 01_ _ __ _ -,
I
                                                                ~~ - k
            '\:.:" ~: --""- ,,~
                  ~-
              .;.'   - '    ~. -      -
                                        &.w            ..*..eDF
                                                        ~~
                  "   --- .
                          -
6
 
NFPA 805 Transi,t ion Project Overview
* Fire Protection Program Transition
  - License Condition being revised
  - Technical Specifications being revised
  - Reviewed existing exemptions
      - Three exemptions will be credited post-NFPA 805 transition
              .
            ~.
                -
_ 19".:-"
                  ,~-
              ,~~-..
s-:
                      '
                        ._.~!z,;;.
                            -
CENG_
B
                                          ---
lOinI\llllltura af- ~
                                          - ".~eDf
                                                          ~'"
                                                              ..... -".*
I
                                                                        .'. 7
 
Compliance with NFPA 80S NFPA 805 Chapter 3 Compliance
- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0036 Review documented in B-1 Table (Attachment A of LAR)
Results of review
  - 3 Code compliance modifications
  - 7 sections are addressed via Attachment L of LAR.
  - 96 Sections/sub-sections comply
  - 43 Comply with clarifications/EEEEs/required actions
  - 16 Comply by previous NRC approval
                . ~-,-        -  CENG..                            I ".
            ,-::.-'~---
              "    -c""': -.~--~-.
a joInI venture 01'_ _ _ _--,   ~~-k 1 ~'- ~      .           ~              <1-.
                        -        J       - .,y          ..*.. eDf 8
 
Compliance with NFPA 805
* Non-Power Operations
  - Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0040
  - Fire modeling not used to eliminate or reduce pinch points
  - Recovery actions are not credited
  - Results of review
* All success paths identified
* All success paths identified
* Pinch points identified
* Pinch points identified
* Component list associated with maintaining Key Safety Functions
* Component list associated with maintaining Key Safety Functions
* Recommendations to manage Fire Risk CENGI -ajan t ventuteo!_ ---..' ....eDf -9
* Recommendations to manage Fire Risk ci:~'
--Compliance with NFPA Radioactive Release -Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ -Plant evaluated on a room by room -Credit engineering controls and CENG offsite calculation for gaseous and liquid effluents  
CENGw                                I
-Reviewed Pre-Fire Plan and training materials to clarify monitoring and control requirements Minor Pre-Fire Plan/procedure changes and training program revisions in progress.
                                        -
CENGIa join t ven t ure o f _ _. :-c:-* -., --EI-wY 4' -..;;.. -10 Compliance with Nuclear Safety Capability Assessment Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 08-0054 -Safe and Stable defined as Hot Standby -Common Enclosure review (Protection)  
                "';.'~-
-Common Power Supply review (Coordination)
                ~.            -
Fire Area review -Multiple Spurious Operations review -Effects of suppression activities Results of
                  ~ - -.~ - -.;,.. ajant ventuteo! _ ~          '~-'
* k
              ;~-   .                -             ..' ....eDf
                                                      .-~
9
 
Compliance with NFPA 805
* Radioactive Release
  - Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 09-0056
  - Plant evaluated on a room by room basis
  - Credit engineering controls and CENG offsite dose calculation for gaseous and liquid effluents
  - Reviewed Pre-Fire Plan and training materials to clarify monitoring and control requirements
* Minor Pre-Fire Plan/procedure changes and training program revisions in progress.
4#9:"'::'
                  -~.,-              CENG.                        ..; . ~-wI
              *i~"':~'*
              ' _.
j~.-'
                            --
:-c:- * -., -~~
                                ~ - -
a joint venture of _ ~
                                            -EI-wY         ~'''eDF
                          --                               4' 10
 
Compliance with NFPA-80S
* Nuclear Safety Capability Assessment Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 08-0054
    - Safe and Stable defined as Hot Standby
    - Common Enclosure review (Protection)
    - Common Power Supply review (Coordination)
Fire Area review
    - Multiple Spurious Operations review
    - Effects of suppression activities review Results of review
* 21 Fire Areas to be transitioned deterministically
* 21 Fire Areas to be transitioned deterministically
* 46 Fire Areas to be transitioned using Fire Risk Evaluations
* 46 Fire Areas to be transitioned using Fire Risk Evaluations
* All VFDRs addressed I '* CENG.. a joht _01,--___ ('-., *Cn
* All VFDRs addressed
* Enefn r 11 Compliance with NFPA Recovery Actions Feasibility Assessment  
                    ;.;-.
-Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0030 -Primary Control Station (Other than main Control Room)
                        ..,~~
* Alternate Shutdown Panels 1(2)C43 -Recovery actions listed in LAR Attachment G -There was over 85% reduction in operator recovery actions --,;J#Z7-, _ CENG.
CENG..                    I '*
a pot venture 011-___---, .:;; -, , -__ 1 2
                  ~~-
__ Compliance with NFPA
                    ~        --~-
* Monitoring Program -Following FAQ 10-0059, Revision 5 guidance NSCA and Fire PRA components  
a joht _01,- -___     ~~ - -.t
-If any new functions, will be added to Maintenance Rule Program Non-Power Operation components, radioactive release systems, Fire Protection program components  
('-., *Cn
-To be included in normal system and program health monitoring Fire Protection systems and features -Low Safety Significant  
* j~-:- _    r            Enefn     ~~eDF 11
-normal system/program health monitoring  
 
-High Safety Significant  
Compliance with NFPA 805 Recovery Actions Feasibility Assessment
-NFPA 805 specific monitoring program that uses the Maintenance Rule program software CENG* a janl..,lUf1l at____<. ----.r. ....':.-. eoF 5 13 PRA Internal Events PRA -Fire PRA built on a quality Internal Events model -Full Internal Events peer review to RG 1.200, Revision 2 in 2010 Fire PRA -Fire PRA followed guidance in NUREG/CR 6850 as supplemented by -Full peer review to RG 1.200, Revision 2 in January -Total of 41 Facts & Observations
- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0030
- Primary Control Station (Other than main Control Room)
* Alternate Shutdown Panels 1(2)C43
- Recovery actions listed in LAR Attachment G
- There was over 85% reduction in operator recovery actions
            ,
:;;
                    ;J#Z7-
                  -~-,~-
                    ~:
1-~-  -__
                            ,
                          -,
_
                                ~
CENG.
a pot venture 011- _ _ _---,
                                      ~
                                      ~
                                                      -'~
                                                      ~~
eDF
                                                              ~-" , .
                                                                  --,
12
 
Compliance with NFPA 805
* Monitoring Program
    - Following FAQ 10-0059, Revision 5 guidance NSCA and Fire PRA components
    - If any new functions, will be added to Maintenance Rule Program Non-Power Operation components, radioactive release systems, Fire Protection program components
    - To be included in normal system and program health monitoring Fire Protection systems and features
    - Low Safety Significant - normal system/program health monitoring
    - High Safety Significant - NFPA 805 specific monitoring program that uses the Maintenance Rule program software CENG*                             ~-~- f
                    ,,~7 __
                  --~-              a janl..,lUf1l at_ _ _ _        ~
                <.   ~ - --~ - .:~-
5 ~:- - ~                -- .r.         ....':.-. eoF 13
 
PRA Development/Results
* Internal Events PRA
  - Fire PRA built on a quality Internal Events model
  - Full Internal Events peer review to RG 1.200, Revision 2 in 2010
* Fire PRA
  - Fire PRA followed guidance in NUREG/CR 6850 as supplemented by FAQs.
  - Full peer review to RG 1.200, Revision 2 in January 2012
  - Total of 41 Facts & Observations (F&Os)
* 17 Findings
* 17 Findings
* 23 Suggestions
* 23 Suggestions
* 1 Best  
* 1 Best Practice
-All F&Os subsequently
  - All F&Os subsequently dispositioned
* No un-reviewed methods used --, -
* No un-reviewed methods used
__________, ,..,. -"'-'-..---'->. ...*4 eDF-...-J' 14 PRA Overall Plant Risk Post-NFPA 805 Transition  
      - -        - -~..:-
-Sufficient margin to account for non-quantified hazards Unit 1 .JL Unit 2 Comments CoF LERF CoF LERF Fire PRA quantification with NFPA 3.2E-OS 3.0E-06 3.6E-OS 4.2E-06 80S modifications credited.
                  '- .::~ ~~. ---'- >.
Internal Events PRA quantification 1.3E-OS 1.3E-06 1.0E-OS with NFPA 80S modifications credited.
CENG~
IPEEE for COF. Estimate for LERF 1.7E-06 1.SE-OS 2.0E-06 based on 13% of Tornad oes/H igh IPEEE for CoF. Estimate for 4.4E-06 S.7E-07 4.4E-06 S.7E-07based on 13% of CoF. Plant-Level Total 6.2E-OS 6.6E-06 6.SE-OS 8.1E-06 Overall risk meets Reg. Guide 1.174 guidance for total plant risk of CDF < 1E-4 / year and LERF < 1E-S / year. _....
8~1~~ofl __________,
CENGwr't_. 1. 1I)oont wrdUre 01'-----,
                                                                      ,
--
                                                            ,..,. -"'-.t
-----.,. ..'" 15
                                                                          -
---PRA
J~---::'" -
* Risk improvement from NFPA 805 modifications Total delta risk for B.65E-6/ryr 6.39E-7/ryr B.B7E-6/ryr plant fire I nternal Events risk 1.74E-6/ryr 2.10E-B/ryr 2.26E-6/ryr 4.60E-B/ryr improvement from modifications Plant delta risk with 6.91E-6/ryr 6.1BE-7/ryr 6.61E-6/ryr B.62E-7/ryr plant modifications  
                                          ~        ...*4eDF
-Total risk increases  
                                          -...-     J' 14
<lE-S for CDF and <lE-6 for LERF -Delta risk meets criteria for RG 1.174 and NFPA 805 application --
 
CENG. a IC*l1 ..",ture 01-----, ....... -".*
PRA Development/Results
.. -..* eOF--..r ......1"-'+*-" ':"-' 1 6 Implementation Modifications Planned -15 Fire PRA related modifications  
* Overall Plant Risk Post-NFPA 805 Transition
-3 NFPA Code compliance modifications Process/Procedure Changes -Fire Brigade response -Design change process -Training -Operations alarm procedures, Fire Fighting Strategy Manual, hot work, lower mode (refueling outage), AOPs/recovery actions, etc.
  - Sufficient margin to account for non-quantified hazards Unit 1         .JL             Unit 2 Comments CoF         LERF             CoF               LERF Fire PRA quantification with NFPA 3.2E-OS     3.0E-06         3.6E-OS           4.2E-06 80S modifications credited.
CENGI ::--....... --.... -c;---.;..; -".,1 " 17 RCP Loss of Seal Cooling alarm and local 13 kV trip of RCPs Electrical modifications: (hot short, grounds, -Reactor vessel head and Pressurizer -Main Steam Isolation Valve -Steam Generator blowdown control -Normal sump motor operated -Hydrogen purge -Component cooling water heat exchanger flow control -Pressurizer Power Operated Relief Auxiliary Feedwater steam admission -Reactor Coolant Pump breaker 4kV breaker -Cable Spreading Room Cable replacement and lighting transformer protection CENGI -WI'"' _.eo " L  
Internal Events PRA quantification 1.3E-OS     1.3E-06         1.0E-OS           1.3E~06 with NFPA 80S modifications credited.
..:.-' 18 Complete LAR to be submitted on or before September 30, 2013 No un-reviewed methods or deviations from approved Fire PRA methods Modifications will be required and are being Transition Schedule -Assumes 2 year NRC review -Consistent with other submittals  
IPEEE for COF. Estimate for LERF 1.7E-06         1.SE-OS           2.0E-06 based on 13% of CoF.
-Implement procedure/process changes 6 months after SER -Completion of modifications for both units following SER approval-April 2018 CENG-, .-
Tornad oes/H igh                                                                       IPEEE for CoF. Estimate for LERF 4.4E-06     S.7E-07         4.4E-06           S.7E-07 Winds                                                                                  based on 13% of CoF.
8 jcont 1IeI1tuJ8 01'-------, --...*:-eoF -... .6.--19}}
Plant-Level Total             6.2E-OS     6.6E-06         6.SE-OS           8.1E-06 Overall risk meets Reg. Guide 1.174 guidance for total plant risk of CDF < 1E-4 / year and LERF < 1E-S / year.
CENG..                                            1
                    .
_.... ~;.I*7~~
                          ~-                        1I)oont wrdUre 01'- - - - - ,
                                                                                              ~  wr't _.
                    .~"    .:?~. -- -"'~
                    "i ~ -     - -- -                      -
                                                            -.,.           ..
                                                                          "*~eOF
                                                                              '"                                           15
 
PRA Development/Results
* Risk improvement from NFPA 805 modifications Total delta risk for       B.65E-6/ryr 6.39E-7/ryr                           B.B7E-6/ryr      9.0BE-7/ryr plant fire scenarios Internal Events risk       1.74E-6/ryr 2.10E-B/ryr                           2.26E-6/ryr       4.60E-B/ryr improvement from modifications Plant delta risk with     6.91E-6/ryr 6.1BE-7/ryr                           6.61E-6/ryr       B.62E-7/ryr plant modifications
    - Total risk increases <lE-S for CDF and <lE-6 for LERF
    - Delta risk meets criteria for RG 1.174 and NFPA 805 application
                      ~
                            ~~
                      - - ~"""-----
                      ,~"..~~.~ -.-.-~;. ..
1"-'+*-" ':"-'
                              ---
CENG.
a IC*l1 ..",ture
                                                  --..r
                                                  -
01- - - - -,
                                                                  ..* ... eOF
                                                                  ~ ...
                                                                                  ....... -".*
I 16
 
Implementation Overview
* Modifications Planned
  - 15 Fire PRA related modifications
  - 3 NFPA Code compliance modifications
* Process/Procedure Changes
  - Fire Brigade response
  - Design change process
  - Training
  - Operations alarm procedures, Fire Fighting Strategy Manual, hot work, lower mode (refueling outage),
AOPs/recovery actions, etc.
            ,::- - ~
                ....
1
_r~'
                      -~- -
                        .
                            .......
                          -c;- - - -~'
                                    .
 
                                      - - .-.
CENG..
                                                    .;..;
I
                                                          -" " 17
 
Modifications
* RCP Loss of Seal Cooling alarm and local 13 kV trip of RCPs Electrical modifications: (hot short, grounds, etc)
  - Reactor vessel head and Pressurizer vents
  - Main Steam Isolation Valve control
  - Steam Generator blowdown control valves
  - Normal sump motor operated valves
  - Hydrogen purge valves
  - Component cooling water heat exchanger flow control valve
  - Pressurizer Power Operated Relief Valves Auxiliary Feedwater steam admission valves
  - Reactor Coolant Pump breaker control 4kV breaker control
  - Cable Spreading Room dampers
* Cable replacement and lighting transformer protection
                  -       .-~..:-    CENG.        ..,. WI'"'
                                                              "
I
_.eo L
                ~";'~ ..:.- ~; ------~
j~.'   '                                      18
 
Summary
* Complete LAR to be submitted on or before September 30, 2013
* No un-reviewed methods or deviations from approved Fire PRA methods
* Modifications will be required and are being planned
* Transition Schedule
  - Assumes 2 year NRC review
      - Consistent with other submittals
  - Implement procedure/process changes 6 months after SER
  - Completion of modifications for both units following SER approval- April 2018
                      .;,1;
                      -z~
                    --\.~- ~
CENG.                        .      -,
                                                                      ~-"- .
              .-
                  -'  .&#xa2;;~ ---:-~'. 8 jcont 1IeI1tuJ8 01'-------,
              'i~:--- '      --          -
                                            - . . .-        ...*:-eoF
                                                              .6.
19}}

Revision as of 15:27, 4 November 2019

08/19/2013 Calvert Cliffs Nuclear Power Plant NFPA 805 License Amendment Request Pre-Application Meeting with NRC Staff
ML13234A385
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 08/19/2013
From:
Calvert Cliffs, Constellation Energy Nuclear Group, EDF Group
To:
Office of Nuclear Reactor Regulation
Morgan N
References
Download: ML13234A385 (19)


Text

CENG~

a joint venture of------__.

Constellation ..* ~ eDF Energy' ~,.

Calvert Cliffs Nuclear Power Plant

~


- ~.,....~- NFPA80S

~:~

-C-'.II, _~

'7

"'-:'-~-

"'. --:

~- " ---..>

_ ............... License Amendment Request

~<).~

,... .,

...:

. .--

, '

Pre-Application Meeting with NRC Staff August 19, 2013

Introd uctions

  • CENG Representatives

- Elliott Flick Gen'l Manager, Fleet Engineering

- Dave Dellario Manager, Engineering Services

- Jim McQuighan Project Manager, NFPA 805

- Paul Darby Principal Engineer, NFPA 805

- Pat Furio Principal Engineer, Licensing

- Jeff Stone Supervisor, PRA

- Jim Landale Principal Engineer, PRA

- Bret Colby Supervisor, Engineering

- Ch ris Dobry Principal Engineer, Engineering

  • Project NFPA Consultants

- Mark Crompton EPM, NFPA 805 Project Manager

~ --

-~ f~~"':: -

CENG..

a )CIn1-nure 01._ _ _ _ __ ~-:-l-

~- -c-: --- - ~

=.wE "'"

-

I)~: ~::. - -- ':.*~ eDF 2

Agenda Overview of CCN PP

  • Current Fire Protection Licensing Basis
  • Implementation Overview Summary

/;...;7-

<~-

CENG.. I a joont ventum o f - -_ _ _,

~-"- k

~;J ~~ -~ --:~~~- - .r

- "!-'eor:

01' 3

Overview of CCNPP

  • Two PWRs, each rated @ 2737 MWth
  • Combustion Engineering NSSS Commercial operations began in 1975/1977
  • Renewed Operating License issued - expires in 2034/2036

-'7-

- --~--

...:>-~

CENG.

8)oint VEWTlure 011- _ _ _ __

I

...... -:*t

<'"" .- . . .."-~-

J~.- " -.,.

- ...

~f " eOF

..

4

Current Fire Protection Licensing Basis

  • Branch Technical Position APCSB 9.5-1, Appendix A
  • Current exemptions

.. ~7~ CENG.. I

- --~- ..:..---'*k Iii ~~- - -.' ----

'. ,,)001II8I'I1U19 "'- - - - - - ,

~

~ ..f"' eDf

~ -" 5

NFPA 805 Transition Project Overview

  • License Amendment Request (LAR) committed submittal date - September 30, 2013
  • Using the Nuclear Energy Institute (NEI) LAR template
  • Web portal will be established to support NRC review

--~~-

~~7--- CENG_

a joini venliml 01_ _ __ _ -,

I

~~ - k

'\:.:" ~: --""- ,,~

~-

.;.' - ' ~. - -

&.w ..*..eDF

~~

" --- .

-

6

NFPA 805 Transi,t ion Project Overview

- License Condition being revised

- Technical Specifications being revised

- Reviewed existing exemptions

- Three exemptions will be credited post-NFPA 805 transition

.

~.

-

_ 19".:-"

,~-

,~~-..

s-:

'

._.~!z,;;.

-

CENG_

B

---

lOinI\llllltura af- ~

- ".~eDf

~'"

..... -".*

I

.'. 7

Compliance with NFPA 80S NFPA 805 Chapter 3 Compliance

- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0036 Review documented in B-1 Table (Attachment A of LAR)

Results of review

- 3 Code compliance modifications

- 7 sections are addressed via Attachment L of LAR.

- 96 Sections/sub-sections comply

- 43 Comply with clarifications/EEEEs/required actions

- 16 Comply by previous NRC approval

. ~-,- - CENG.. I ".

,-::.-'~---

" -c""': -.~--~-.

a joInI venture 01'_ _ _ _--, ~~-k 1 ~'- ~ . ~ <1-.

- J - .,y ..*.. eDf 8

Compliance with NFPA 805

  • Non-Power Operations

- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0040

- Fire modeling not used to eliminate or reduce pinch points

- Recovery actions are not credited

- Results of review

  • All success paths identified
  • Pinch points identified
  • Component list associated with maintaining Key Safety Functions
  • Recommendations to manage Fire Risk ci:~'

CENGw I

-

"';.'~-

~. -

~ - -.~ - -.;,.. ajant ventuteo! _ ~ '~-'

  • k
~- . - ..' ....eDf

.-~

9

Compliance with NFPA 805

  • Radioactive Release

- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 09-0056

- Plant evaluated on a room by room basis

- Credit engineering controls and CENG offsite dose calculation for gaseous and liquid effluents

- Reviewed Pre-Fire Plan and training materials to clarify monitoring and control requirements

  • Minor Pre-Fire Plan/procedure changes and training program revisions in progress.

4#9:"'::'

-~.,- CENG. ..; . ~-wI

  • i~"':~'*

' _.

j~.-'

--

-c:- * -., -~~

~ - -

a joint venture of _ ~

-EI-wY ~eDF

-- 4' 10

Compliance with NFPA-80S

  • Nuclear Safety Capability Assessment Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 08-0054

- Safe and Stable defined as Hot Standby

- Common Enclosure review (Protection)

- Common Power Supply review (Coordination)

Fire Area review

- Multiple Spurious Operations review

- Effects of suppression activities review Results of review

  • 21 Fire Areas to be transitioned deterministically
  • 46 Fire Areas to be transitioned using Fire Risk Evaluations
  • All VFDRs addressed
.;-.

..,~~

CENG.. I '*

~~-

~ --~-

a joht _01,- -___ ~~ - -.t

('-., *Cn

  • j~-:- _ r Enefn ~~eDF 11

Compliance with NFPA 805 Recovery Actions Feasibility Assessment

- Review performed using NEI 04-02, Revision 2 guidance as supplemented by FAQ 07-0030

- Primary Control Station (Other than main Control Room)

  • Alternate Shutdown Panels 1(2)C43

- Recovery actions listed in LAR Attachment G

- There was over 85% reduction in operator recovery actions

,

J#Z7-

-~-,~-

~:

1-~- -__

,

-,

_

~

CENG.

a pot venture 011- _ _ _---,

~

~

-'~

~~

eDF

~-" , .

--,

12

Compliance with NFPA 805

  • Monitoring Program

- Following FAQ 10-0059, Revision 5 guidance NSCA and Fire PRA components

- If any new functions, will be added to Maintenance Rule Program Non-Power Operation components, radioactive release systems, Fire Protection program components

- To be included in normal system and program health monitoring Fire Protection systems and features

- Low Safety Significant - normal system/program health monitoring

- High Safety Significant - NFPA 805 specific monitoring program that uses the Maintenance Rule program software CENG* ~-~- f

,,~7 __

--~- a janl..,lUf1l at_ _ _ _ ~

<. ~ - --~ - .:~-

5 ~:- - ~ -- .r. ....':.-. eoF 13

PRA Development/Results

  • Internal Events PRA

- Fire PRA built on a quality Internal Events model

- Full Internal Events peer review to RG 1.200, Revision 2 in 2010

- Fire PRA followed guidance in NUREG/CR 6850 as supplemented by FAQs.

- Full peer review to RG 1.200, Revision 2 in January 2012

- Total of 41 Facts & Observations (F&Os)

  • 17 Findings
  • 23 Suggestions
  • 1 Best Practice

- All F&Os subsequently dispositioned

  • No un-reviewed methods used

- - - -~..:-

'- .::~ ~~. ---'- >.

CENG~

8~1~~ofl __________,

,

,..,. -"'-.t

-

J~---::'" -

~ ...*4eDF

-...- J' 14

PRA Development/Results

  • Overall Plant Risk Post-NFPA 805 Transition

- Sufficient margin to account for non-quantified hazards Unit 1 .JL Unit 2 Comments CoF LERF CoF LERF Fire PRA quantification with NFPA 3.2E-OS 3.0E-06 3.6E-OS 4.2E-06 80S modifications credited.

Internal Events PRA quantification 1.3E-OS 1.3E-06 1.0E-OS 1.3E~06 with NFPA 80S modifications credited.

IPEEE for COF. Estimate for LERF 1.7E-06 1.SE-OS 2.0E-06 based on 13% of CoF.

Tornad oes/H igh IPEEE for CoF. Estimate for LERF 4.4E-06 S.7E-07 4.4E-06 S.7E-07 Winds based on 13% of CoF.

Plant-Level Total 6.2E-OS 6.6E-06 6.SE-OS 8.1E-06 Overall risk meets Reg. Guide 1.174 guidance for total plant risk of CDF < 1E-4 / year and LERF < 1E-S / year.

CENG.. 1

.

_.... ~;.I*7~~

~- 1I)oont wrdUre 01'- - - - - ,

~ wr't _.

.~" .:?~. -- -"'~

"i ~ - - -- - -

-.,. ..

"*~eOF

'" 15

PRA Development/Results

  • Risk improvement from NFPA 805 modifications Total delta risk for B.65E-6/ryr 6.39E-7/ryr B.B7E-6/ryr 9.0BE-7/ryr plant fire scenarios Internal Events risk 1.74E-6/ryr 2.10E-B/ryr 2.26E-6/ryr 4.60E-B/ryr improvement from modifications Plant delta risk with 6.91E-6/ryr 6.1BE-7/ryr 6.61E-6/ryr B.62E-7/ryr plant modifications

- Total risk increases <lE-S for CDF and <lE-6 for LERF

- Delta risk meets criteria for RG 1.174 and NFPA 805 application

~

~~

- - ~"""-----

,~"..~~.~ -.-.-~;. ..

1"-'+*-" ':"-'

---

CENG.

a IC*l1 ..",ture

--..r

-

01- - - - -,

..* ... eOF

~ ...

....... -".*

I 16

Implementation Overview

  • Modifications Planned

- 15 Fire PRA related modifications

- 3 NFPA Code compliance modifications

  • Process/Procedure Changes

- Fire Brigade response

- Design change process

- Training

- Operations alarm procedures, Fire Fighting Strategy Manual, hot work, lower mode (refueling outage),

AOPs/recovery actions, etc.

,::- - ~

....

1

_r~'

-~- -

.

.......

-c;- - - -~'

.

- - .-.

CENG..

.;..;

I

-" " 17

Modifications

  • RCP Loss of Seal Cooling alarm and local 13 kV trip of RCPs Electrical modifications: (hot short, grounds, etc)

- Reactor vessel head and Pressurizer vents

- Main Steam Isolation Valve control

- Steam Generator blowdown control valves

- Normal sump motor operated valves

- Hydrogen purge valves

- Component cooling water heat exchanger flow control valve

- Pressurizer Power Operated Relief Valves Auxiliary Feedwater steam admission valves

- Reactor Coolant Pump breaker control 4kV breaker control

- Cable Spreading Room dampers

  • Cable replacement and lighting transformer protection

- .-~..:- CENG. ..,. WI'"'

"

I

_.eo L

~";'~ ..:.- ~; ------~

j~.' ' 18

Summary

  • Complete LAR to be submitted on or before September 30, 2013
  • No un-reviewed methods or deviations from approved Fire PRA methods
  • Modifications will be required and are being planned
  • Transition Schedule

- Assumes 2 year NRC review

- Consistent with other submittals

- Implement procedure/process changes 6 months after SER

- Completion of modifications for both units following SER approval- April 2018

.;,1;

-z~

--\.~- ~

CENG. . -,

~-"- .

.-

-' .¢;~ ---:-~'. 8 jcont 1IeI1tuJ8 01'-------,

'i~:--- ' -- -

- . . .- ...*:-eoF

.6.

19