ML18101A191: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:CORRECTED COPY OPERATING DATA REPORT Docket No: Date: Completed by: Mike Morroni Telephone:
{{#Wiki_filter:CORRECTED COPY       ~
Operating Status 1. Unit Name Salem No. 2 Notes 2. Reporting Period May 1994 3. Licensed Thermal Power (MWt) 3411 4. Nameplate Rating (Gross MWe) 1170 5. Design Electrical Rating (Net MWe) 1115 6. Maximum Dependable Capacity (Gross MWe)
OPERATING DATA REPORT   ~
* 1149 7. Maximum Dependable Capacity (Net MWe) 1106 8. If Changes Occur in Capacity Ratings (items 3 through 7) Report, Gi:ve Reason NA 9. Power Level to Which Restricted, if any (Net MWe) 10. Reasons for Restrictions., if any 11. Hours in Reporting Period 12. No. of Hrs. Rx. was Critical 13. Reactor Reserve Shutdown Hrs. 14. Hours Generator on-Line 15. Unit Reserve Shutdown Hours 16. Gross Thermal Energy Generated (MWH} -Gross Elec. Energy Generated (MWH) 18. Net Elec. Energy Gen. (MWH) 19. Unit Service Factor 20. Unit Availability Factor 21. Unit Capacity Factor (using MDC Net) 22. Unit Capacity Factor (using DER Net) 23. Unit Forced Outage Rate N/A. This Month Year to Date 744 3623 744 3546.0 0 0 744 3462.3 0 0 2335672.8
Docket No:   50-311 Date:         06/10/94 Completed by:     Mike Morroni                         Telephone:   339-2122 Operating Status
*10070244.8 743330 3254460 711102 3098446 100 95.6 100 95.6 86.4 77.3 85.7 76.7 0 4.4 50-311 06/10/94 339-2122 since Last NIA Cumulative 110736 72825.6 0 70351. 8 0 *172533164.2 73800978 70225723 63.5 63.5 57.3 56.9 21.9 24. Shutdowns scheduled over next 6 months (type, date and duration of each) Refueling outage scheduled to start October 15. 1994 and last
: 1. Unit Name                           Salem No. 2     Notes
* 60 days. 25. If shutdown at end of Report Period, Estimated Date of Startup: NA 8-1-7.R2 ,r 9408260297 940818 PDR ADOCK 05000311 R PDR}}
: 2. Reporting Period               May         1994
: 3. Licensed Thermal Power (MWt)               3411
: 4. Nameplate Rating (Gross MWe)               1170
: 5. Design Electrical Rating (Net MWe)         1115
: 6. Maximum Dependable Capacity (Gross MWe)
* 1149
: 7. Maximum Dependable Capacity (Net MWe) 1106
: 8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Gi:ve Reason     NA
: 9. Power Level to Which Restricted, if any (Net MWe)             NIA
: 10. Reasons for Restrictions., if any           N/A.
This Month    Year to Date    Cumulative
: 11. Hours in Reporting Period               744            3623        110736
: 12. No. of Hrs. Rx. was Critical           744            3546.0      72825.6
: 13. Reactor Reserve Shutdown Hrs.             0              0            0
: 14. Hours Generator on-Line                 744            3462.3      70351. 8
: 15. Unit Reserve Shutdown Hours               0              0            0
: 16. Gross Thermal Energy Generated (MWH}         -             2335672.8    *10070244.8    *172533164.2 Gross Elec. Energy Generated (MWH)                       743330        3254460      73800978
: 18. Net Elec. Energy Gen. (MWH)         711102        3098446      70225723
: 19. Unit Service Factor                     100          95.6            63.5
: 20. Unit Availability Factor               100          95.6            63.5
: 21. Unit Capacity Factor (using MDC Net)                   86.4          77.3          57.3
: 22. Unit Capacity Factor (using DER Net)                   85.7          76.7          56.9
: 23. Unit Forced Outage Rate                   0             4.4         21.9
: 24. Shutdowns scheduled over next 6 months (type, date and duration of each)
Refueling outage scheduled to start October 15. 1994 and last
* 60 days.
: 25. If shutdown at end of Report Period, Estimated Date of Startup:
NA 8-1-7.R2
,r       -------------~
9408260297 940818 PDR ADOCK 05000311 R               PDR}}

Latest revision as of 10:22, 21 October 2019

Corrected Monthly Operating Rept for May 1994 for Salem Generating Station Unit 2,correcting Gross Thermal Energy Value
ML18101A191
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/31/1994
From: Morroni M
Public Service Enterprise Group
To:
Shared Package
ML18101A190 List:
References
NUDOCS 9408260297
Download: ML18101A191 (1)


Text

CORRECTED COPY ~

OPERATING DATA REPORT ~

Docket No: 50-311 Date: 06/10/94 Completed by: Mike Morroni Telephone: 339-2122 Operating Status

1. Unit Name Salem No. 2 Notes
2. Reporting Period May 1994
3. Licensed Thermal Power (MWt) 3411
4. Nameplate Rating (Gross MWe) 1170
5. Design Electrical Rating (Net MWe) 1115
6. Maximum Dependable Capacity (Gross MWe)
  • 1149
7. Maximum Dependable Capacity (Net MWe) 1106
8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Gi:ve Reason NA
9. Power Level to Which Restricted, if any (Net MWe) NIA
10. Reasons for Restrictions., if any N/A.

This Month Year to Date Cumulative

11. Hours in Reporting Period 744 3623 110736
12. No. of Hrs. Rx. was Critical 744 3546.0 72825.6
13. Reactor Reserve Shutdown Hrs. 0 0 0
14. Hours Generator on-Line 744 3462.3 70351. 8
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated (MWH} - 2335672.8 *10070244.8 *172533164.2 Gross Elec. Energy Generated (MWH) 743330 3254460 73800978
18. Net Elec. Energy Gen. (MWH) 711102 3098446 70225723
19. Unit Service Factor 100 95.6 63.5
20. Unit Availability Factor 100 95.6 63.5
21. Unit Capacity Factor (using MDC Net) 86.4 77.3 57.3
22. Unit Capacity Factor (using DER Net) 85.7 76.7 56.9
23. Unit Forced Outage Rate 0 4.4 21.9
24. Shutdowns scheduled over next 6 months (type, date and duration of each)

Refueling outage scheduled to start October 15. 1994 and last

  • 60 days.
25. If shutdown at end of Report Period, Estimated Date of Startup:

NA 8-1-7.R2

,r -------------~

9408260297 940818 PDR ADOCK 05000311 R PDR