|
|
Line 2: |
Line 2: |
| | number = ML062440422 | | | number = ML062440422 |
| | issue date = 08/31/2006 | | | issue date = 08/31/2006 |
| | title = Perry Status of Confirmatory Action Letter Inspections | | | title = Status of Confirmatory Action Letter Inspections |
| | author name = Duncan E R | | | author name = Duncan E |
| | author affiliation = NRC/RGN-III/DRP/RPB6 | | | author affiliation = NRC/RGN-III/DRP/RPB6 |
| | addressee name = Pearce L W | | | addressee name = Pearce L |
| | addressee affiliation = FirstEnergy Nuclear Operating Co | | | addressee affiliation = FirstEnergy Nuclear Operating Co |
| | docket = 05000440 | | | docket = 05000440 |
Revision as of 13:31, 13 July 2019
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARL-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 L-24-168, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-155, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 L-24-140, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification ML24088A1922024-03-28028 March 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 2024-09-09
[Table view] |
Text
August 31, 2006Mr. L. William PearceVice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road, A290 Perry, OH 44081
SUBJECT:
STATUS OF CONFIRMATORY ACTION LETTER INSPECTIONS
Dear Mr. Pearce:
I am writing this letter to update you on the status of augmented NRC inspection activities at thePerry Nuclear Power Plant. As you are aware, in the third quarter of 2004, Perry Nuclear Power Plant entered the Multiple/Repetitive Degraded Cornerstone column of the NRC's ActionMatrix. In accordance with Inspection Manual Chapter 0305, "Operating Reactor Assessment Program," the NRC conducted an IP 95003 supplemental inspection at Perry. The results ofthe IP 95003 inspection were provided to you by our July 8, 2005, Inspection Report
05000440/2005003.In your August 8 and 17, 2006, responses to our inspection report, FirstEnergy NuclearOperating Company (FENOC) committed to make sustained improvements to address the issues identified in the IP 95003 inspection report. Your letters specifically addressed the following four areas: 1) IP 95002 Issues, 2) Emergency Preparedness, 3) Human Performance; and 4) Corrective Action Program Implementation. To monitor FENOC's progress in implementing corrective actions and to assess theeffectiveness of the corrective actions, the NRC developed and implemented an inspectionplan to review the implementation and effectiveness of your corrective actions. To date we have completed the implementation inspections for all four areas. In addition, we have completed the Emergency Preparedness area effectiveness review and have partially completed the IP 95002 Issues effectiveness review. The effectiveness reviews in the Human Performance and Corrective Action Program areas, and completion of the effectiveness review for the IP 95002 Issues area, are scheduled for later this year.Each of the remaining effectiveness reviews are major team inspections involving numbers ofNRC inspectors and management. In addition, each inspection involves numerous individualsfrom your staff to gather information and respond to questions posed by the inspection team.
Because of the large resource investment by the NRC and FENOC, and our desire to completethe inspection in a timely manner, the timing between completion of FENOC corrective actions and on-site NRC inspection activities is critical. Our inspection plan currently has the HumanPerformance and Corrective Action Program effectiveness reviews scheduled for on-site activities from October 23 through November 11, and November 6 through 17, 2006, L. Pearce respectively. To ensure the most effective use of both NRC and FENOC resources, pleaseconfirm that these dates are still appropriate. Further, please provide me with a date afterwhich the remaining effectiveness review in the IP 95002 Issues area would be appropriate.
Because scheduling of corrective action implementation and effectiveness reviews can be influenced by many factors, I would appreciate written notification for each of the three areas of interest when your activities are complete and your organization is ready to support our inspections. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter willbe available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the PublicElectronic Reading Room).Sincerely,/RA/Eric R. Duncan, ChiefBranch 6 Division of Reactor ProjectsDocket No. 50-440License No. NPF-58 cc:G. Leidich, President and Chief Nuclear Officer - FENOC J. Hagan, Senior Vice President of Operations and Chief Operating Officer - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight Director, Site Operations Director, Regulatory Affairs Manager, Fleet Licensing Manager, Site Regulatory Compliance D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health L. Pearce respectively. To ensure the most effective use of both NRC and FENOC resources, pleaseconfirm that these dates are still appropriate. Further, please provide me with a date afterwhich the remaining effectiveness review in the IP 95002 Issues area would be appropriate.
Because scheduling of corrective action implementation and effectiveness reviews can be influenced by many factors, I would appreciate written notification for each of the three areas of interest when your activities are complete and your organization is ready to support our inspections. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter willbe available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the PublicElectronic Reading Room).Sincerely,Eric R. Duncan, ChiefBranch 6 Division of Reactor ProjectsDocket No. 50-440License No. NPF-58 cc:G. Leidich, President and Chief Nuclear Officer - FENOC J. Hagan, Senior Vice President of Operations and Chief Operating Officer - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight Director, Site Operations Director, Regulatory Affairs Manager, Fleet Licensing Manager, Site Regulatory Compliance D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of HealthDOCUMENT NAME:E:\Filenet\ML062440422.wpd X G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIINAMEGWright:dtpEDuncanDATE08/31/200608/31/2006OFFICIAL RECORD COPY L. Pearce-3-ADAMS Distribution
- DXC1 TEB SJC4 RidsNrrDirsIrib
GEG KGO RJP DRPIII DRSIII PLB1 TXN