| | number = ML063380211 | | | number = ML063380211 |
| | issue date = 12/07/2006 | | | issue date = 12/07/2006 |
| | title = Susquehanna Steam Electric Station, Units 1 and 2 - Closeout of Nuclear Regulatory Commission (NRC) Bulletin 2005-02, Emergency Preparedness and Response Actions for Security-Based Events (TAC Nos. MC7882 and MC7883) | | | title = Closeout of Nuclear Regulatory Commission (NRC) Bulletin 2005-02, Emergency Preparedness and Response Actions for Security-Based Events (TAC Nos. MC7882 and MC7883) |
| | author name = Guzman R V | | | author name = Guzman R |
| | author affiliation = NRC/NRR/ADRO/DORL/LPLI-1 | | | author affiliation = NRC/NRR/ADRO/DORL/LPLI-1 |
| | addressee name = McKinney B T | | | addressee name = Mckinney B |
| | addressee affiliation = PPL Susquehanna, LLC | | | addressee affiliation = PPL Susquehanna, LLC |
| | docket = 05000387, 05000388 | | | docket = 05000387, 05000388 |
Letter Sequence Other |
---|
|
|
MONTHYEARML0633802112006-12-0707 December 2006 Closeout of Nuclear Regulatory Commission (NRC) Bulletin 2005-02, Emergency Preparedness and Response Actions for Security-Based Events Project stage: Other 2006-12-07
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23345A0682023-11-28028 November 2023 Technical Specification Bases, Manual PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) IR 05000387/20230032023-11-0303 November 2023 Integrated Inspection Report 05000387/2023003 and 05000388/2023003 PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML23291A1132023-10-12012 October 2023 Submittal of Revision 71 to Updated Final Safety Analysis Report and Revision 25 to Fire Protection Review Report ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information IR 05000387/20233012023-09-20020 September 2023 Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000387/20230052023-08-31031 August 2023 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval IR 05000387/20230022023-08-0101 August 2023 Integrated Inspection Report 05000387/2023002 and 05000388/2023002 ML23195A1852023-07-27027 July 2023 Correction to Technical Specifications Page 3.3-73 in Amendment No. 265 PLA-8076, Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076)2023-07-20020 July 2023 Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076) ML23201A0152023-07-20020 July 2023 Operator Licensing Examination Approval ML23200A1012023-07-19019 July 2023 Notification of Conduct of a Fire Protection Team Inspection ML23193A0062023-07-12012 July 2023 Requalification Program Inspection PLA-8078, Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-80782023-07-0505 July 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-8078 ML23163A1012023-06-12012 June 2023 10 CFR 50.46 Annual Report (Pla 8065) PLA-8054, Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence2023-06-0808 June 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence IR 05000387/20234012023-06-0707 June 2023 Security Baseline Inspection Report 05000387/2023401 and 05000388/2023401 PLA-8073, Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval2023-06-0101 June 2023 Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval PLA-8064, Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064)2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064) ML23132A3212023-05-17017 May 2023 Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 285 and 269 Related to Order Approving Transfer of Licenses PLA-8067, Notification of Completion of Emergence from Bankruptcy (PLA-8067)2023-05-17017 May 2023 Notification of Completion of Emergence from Bankruptcy (PLA-8067) IR 05000387/20230012023-05-12012 May 2023 Integrated Inspection Report 05000387/2023001 and 05000388/2023001 PLA-8066, Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-80662023-05-0808 May 2023 Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-8066 PLA-8053, Radiation Exposure Information and Reporting System2023-04-27027 April 2023 Radiation Exposure Information and Reporting System PLA-8058, Annual Radiological Environmental Operating Report (PLA-8058)2023-04-26026 April 2023 Annual Radiological Environmental Operating Report (PLA-8058) PLA-8041, Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041)2023-04-25025 April 2023 Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041) PLA-8047, 2022 Annual Environmental Operating Report (Nonradiological), PLA-80472023-04-19019 April 2023 2022 Annual Environmental Operating Report (Nonradiological), PLA-8047 PLA-8062, Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-80622023-04-11011 April 2023 Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-8062 PLA-8061, Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-80612023-04-10010 April 2023 Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-8061 ML23090A2302023-03-31031 March 2023 NRC Decommissioning Funding Status Report PLA-8049 PLA-8060, Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060)2023-03-30030 March 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060) ML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 PLA-8057, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-80572023-03-15015 March 2023 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-8057 ML23065A1962023-03-0202 March 2023 EN 56387 Paragon - Part 21 Report Re Defect Identified in Automatic Transfer Switch Pn: NLI-ATS480A400X1 IR 05000387/20220062023-03-0101 March 2023 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2022006 and 05000388/2022006) PLA-8052, (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums2023-02-13013 February 2023 (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums IR 05000387/20220042023-02-0808 February 2023 Integrated Inspection Report 05000387/2022004 and 05000388/2022004 ML23010A0882023-01-15015 January 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Control Rod Technical Specifications 2024-02-07
[Table view] |
Text
December 7, 2006Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - CLOSEOUTOF NUCLEAR REGULATORY COMMISSION (NRC) BULLETIN 2005-02, "EMERGENCY PREPAREDNESS AND RESPONSE ACTIONS FOR SECURITY-BASED EVENTS" (TAC NOS. MC7882 AND MC7883)
Dear Mr. McKinney:
On July 18, 2005, the NRC issued Bulletin (BL) 2005-02, "Emergency Preparedness andResponse Actions for Security-Based Events," (Agencywide Documents Access and Management System (ADAMS) Accession No. ML051740058), to all holders of operating licenses for nuclear power reactors except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel.BL 2005-02 notified licensees of the NRC staff's need for information associated withemergency preparedness for security-based events at nuclear power plants. The purpose of BL 2005-02 was for the NRC staff to obtain information regarding changes licensees have made or plan to make concerning security-based emergency preparedness program capabilities and to evaluate how consistently such changes have been implemented. Licensees were requested to respond to questions and provide information in the following areas: A. Security-based Emergency Classification Levels and Emergency Action Levels; B. NRC Notifications; C. Onsite Protective Measures; D. Emergency Response Organization Augmentation; and E. Drill and Exercise Program.The Nuclear Energy Institute (NEI) developed a white paper, entitled "Enhancements toEmergency Preparedness Programs for Hostile Action," dated May 2005 (revised November 18, 2005) (ADAMS Accession No. ML053290326), to clarify various options available to licensees to implement the enhancements discussed in BL 2005-02. NEI requested endorsement of these options in a letter dated November 22, 2005 (ADAMS Accession No. ML053290352). The NRC staff issued Regulatory Issue Summary 2006-12, "Endorsement of Nuclear Energy Institute Guidance, Enhancements to Emergency Preparedness Programs for Hostile Action," on July 19, 2006, endorsing this white paper, with clarifications.By letter dated August 15, 2005 (ADAMS Accession No. ML052405513), you responded to BL2005-02. In your responses, you indicated that you either had already or would in the future incorporate enhancements consistent with the information provided in either BL 2005-02 or the B. McKinney-2-NEI white paper. With the exception of Drill and Exercise Program enhancements, allenhancements, for all licensees were scheduled to be adopted no later than February 16, 2006.
The majority of licensees indicated that they would adopt the Drill and Exercise Program enhancements contingent on NRC and Department of Homeland Security endorsement of a new evaluated exercise program. Based on the above, your response to BL 2005-02 is considered acceptable and no further action is requested of you at this time.If you have any questions regarding this matter, please contact me at 301-415-1030.Sincerely,/RA/Richard V. Guzman, Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388 cc: See next page B. McKinney-3-NEI white paper. With the exception of Drill and Exercise Program enhancements, allenhancements, for all licensees were scheduled to be adopted no later than February 16, 2006.
The majority of licensees indicated that they would adopt the Drill and Exercise Program enhancements contingent on NRC and Department of Homeland Security endorsement of a new evaluated exercise program. Based on the above, your response to BL 2005-02 is considered acceptable and no further action is requested of you at this time.If you have any questions regarding this matter, please contact me at 301-415-1030.Sincerely,/RA/Richard V. Guzman, Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388 cc: See next pageDISTRIBUTION
- PUBLICLPLI-1 R/F RidsNrrDorlLplI-1 RidsRgn1MailCenterRidsNrrPMRGuzmanRidsOgcRp RidsAcrsAcnwMailCenterRidsNrrDorlDprJRobinson, NRR RidsNrrDprPgcb ACCESSION NO: ML063380211 *SE input OFFICELPLI-1/PMLPLI-1/LADPR/PGCB/BCNRR/LPLI-1/BCNAMERGuzmanSLittleCJackson*RLaufer DATE12/7/0612/7/0610/31/200612/7/06OFFICIAL RECORD COPY Susquehanna Steam Electric Station, Units 1 and 2 cc:
Robert A. SacconeVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Terry L. HarpsterGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Walter E. MorrisseySupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Steven M. CookManager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission
475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803