Line 3: |
Line 3: |
| | issue date = 07/27/2010 | | | issue date = 07/27/2010 |
| | title = Emergency Diesel Generator Fuel Oil - Alternate Sampling Procedure of Storage Tanks | | | title = Emergency Diesel Generator Fuel Oil - Alternate Sampling Procedure of Storage Tanks |
| | author name = Broaddus D A | | | author name = Broaddus D |
| | author affiliation = NRC/NRR/DORL/LPLII-2 | | | author affiliation = NRC/NRR/DORL/LPLII-2 |
| | addressee name = Krich R M | | | addressee name = Krich R |
| | addressee affiliation = Tennessee Valley Authority | | | addressee affiliation = Tennessee Valley Authority |
| | docket = 05000327, 05000328 | | | docket = 05000327, 05000328 |
|
---|
Category:Letter
MONTHYEARML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions ML24247A2212024-08-29029 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-21-160, NEI 03-08 Needed Guidance: PWR Lower Radial Support Clevis Insert X-750 Bolt Inspection Requirements, September 1, 2021 ML24247A1802024-08-28028 August 2024 Application to Revise the Fuel Handling Accident Analysis, to Delete Technical Specification 3.9.4, Containment Penetrations, and to Modify Technical Specification 3.3.6, Containment Ventilation Isolation Instrumentation for Sequoyah Nuclea IR 05000327/20240052024-08-26026 August 2024 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2024005 and 05000328/2024005 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), IR 05000327/20240022024-07-31031 July 2024 Integrated Inspection Report 05000327/2024002 and 05000328/2024002 ML24211A0572024-07-29029 July 2024 Submittal of Emergency Plan Implementing Procedure Revision ML24211A0542024-07-29029 July 2024 Operator License Examination Report ML24211A0412024-07-26026 July 2024 Unit 1 Cycle 26 Refueling Outage - 90-Day Inservice Inspection Summary Report ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24191A4652024-07-0909 July 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24177A0282024-06-25025 June 2024 Emergency Plan Implementing Procedure Revisions ML24176A0222024-06-24024 June 2024 Retraction of Interim Report of a Deviation or Failure to Comply – Transducer Model 8005N ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24145A0852024-05-30030 May 2024 1B-B Diesel Generator Failure - Final Significance Determination Letter ML24145A1052024-05-29029 May 2024 301 Exam Approval Letter ML24134A1762024-05-13013 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24128A0352024-05-0707 May 2024 Providing Supplemental Information to Apparent Violation ML24120A0582024-04-26026 April 2024 10 CFR 50.46 Annual Report for Sequoyah Nuclear Plant Units 1 and 2 ML24116A2612024-04-25025 April 2024 Interim Report of a Deviation or Failure to Comply - Transducer Model 8005N ML24114A0482024-04-23023 April 2024 Annual Radioactive Effluent Release Report for 2023 Monitoring Period CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24144A2362024-04-20020 April 2024 Discharge Monitoring Report (Dmr), March 2024 ML24089A0882024-04-18018 April 2024 – Exemption from Select Requirements of 10 CFR Part 73; Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000327/20240012024-04-17017 April 2024 Integrated Inspection Report 05000327/2024001 and 05000328/2024001 ML24109A0272024-04-16016 April 2024 Cycle 27 Core Operating Limits Report Revision 0 CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) ML24106A0502024-04-12012 April 2024 Discharge Monitoring Report (Dmr), February 2024 ML24100A0162024-04-11011 April 2024 Request for Regulatory Conference (Tennessee Valley Authority - Sequoyah Nuclear Plant) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 2024-09-08
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 JUly 27, 2010 Mr. Rodney M. Krich Vice President, Nuclear Licensing Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
SEOUOYAH NUCLEAR PLANT, UNITS 1 AND 2 -EMERGENCY DIESEL GENERATOR FUEL OIL -ALTERNATE SAMPLING PROCEDURE OF STORAGE TANKS (TAC NOS. ME3439 AND ME3440)
Dear Mr. Krich:
By letter dated February 24, 2010, as supplemented by letter dated May 13, 2010, Tennessee Valley Authority (TVA or the licensee) submitted a request to use an alternative sampling procedure for the emergency diesel generator (EDG) fuel oil storage tanks for Sequoyah Nuclear Plant (SON), Units 1 and 2. The requirement to sample the diesel fuel oil storage tanks comes from Technical Specification (TS) Surveillance Requirement 4.8.1.1.2.c, which states that, "At a frequency in accordance with the Diesel Fuel Oil Testing Program, verify fuel oil properties of new and stored fuel oil are tested in accordance with, and maintained within the limits specified in the Diesel Fuel Oil Testing Program." TS Section 6.16, "Diesel Fuel Oil Testing Program," requires that sampling and testing of new and stored fuel be performed in accordance with applicable American Society for Testing Materials (ASTM) standards.
Historically, TVA has performed a manual "all-levels" sample in accordance with Section 8 of ASTM D4057-1988, "Standard Practice for Manual Sampling of Petroleum and Petroleum Products." However, Section 8.1 of ASTM D4057-1988 specifies that alternate sampling methods may be used with agreement of the parties involved.
TVA determined that U. S. Nuclear Regulatory Commission (NRC) staff approval of the alternative sampling methods was necessary to satisfy the criteria of ASTM D4057-1988; there is no change to the TSs or its bases. The "all-levels" sample from ASTM D4057-1988 draws a sample that is representative of the entire tank, by opening an empty specialized container near the bottom of the fuel oil storage tanks and drawing the container upward to the top of the tank as it fills. Instead of this process, TVA proposed to take samples from the fuel oil transfer pump discharge lines of each fuel oil storage tank. The transfer pumps take suction near the bottom of their respective tanks through a 4-inch diameter line. There is a 1-inch diameter line and valve off each discharge line that will be used as the sample point. To obtain a fuel oil sample, TVA proposed that the fuel oil transfer pump for the tank to be sampled will be placed in the recirculation mode for a period of time necessary to ensure a one-volume recirculation of the contents, based on the volume of diesel fuel in the tank. After the tank has been recirculated for the appropriate time, TVA proposed that the sample line will be flushed and a sample obtained.
The fuel oil sample will be analyzed in accordance with existing TS requirements.
R. Krich -2 To show that the new sampling procedure would provide results that were representative of the fuel oil contained in the tanks and equivalent to the existing procedure, the licensee collected samples using the existing "all-levels" method, and the new proposed method, from Fuel Oil Storage Tanks 1 and 2 for a period of 3 months. The sampies were then tested with the same procedures and the results were provided in the enclosure of TVA letter dated February 24, 2010. The NRC staff reviewed the proposed sampling process and the test results comparison provided in the enclosure of TVA letter dated February 24, 2010. Based on the comparison of the sampling methods and test results, the NRC staff finds that the proposed sampling method provides an equivalent sample of the fuel oil storage tank contents as the "all-levels" sampling method in ASTM 04057-1988.
Based on the NRC staff review of the TVA request, the NRC staff finds the alternative sampling technique for SON, Units 1 and 2 EDG fuel oil storage tanks acceptable.
Pursuant to ASTM 04057-1988, Section 8.1, TVA is authorized to obtain samples from the fuel oil transfer pump discharge lines of each EDG storage tank by the described process in lieu of specific methods described in applicable ASTM standards.
If you have any questions regarding this matter, please contact Siva P. Lingam at 301-415-1564.
Douglas A. Broaddus.
Chief Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-327 and 50-328 cc: Distribution via Listserv R. Krich -2 To show that the new sampling procedure would provide results that were representative of the fuel oil contained in the tanks and equivalent to the existing procedure, the licensee collected samples using the existing "all-levels" method, and the new proposed method, from Fuel Oil Storage Tanks 1 and 2 for a period of 3 months. The samples were then tested with the same procedures and the results were provided in the enclosure of TVA letter dated February 24, 2010. The NRC staff reviewed the proposed sampling process and the test results comparison provided in the enclosure of TVA letter dated February 24, 2010. Based on the comparison of the sampling methods and test results, the NRC staff finds that the proposed sampling method provides an equivalent sample of the fuel oil storage tank contents as the "all-levels" sampling method in ASTM D4057-1988.
Based on the NRC staff review of the TVA request, the NRC staff finds the alternative sampling technique for SON, Units 1 and 2 EDG fuel oil storage tanks acceptable.
Pursuant to ASTM D4057-1988, Section 8.1, TVA is authorized to obtain samples from the fuel oil transfer pump discharge lines of each EDG storage tank by the described process in lieu of specific methods described in applicable ASTM standards.
If you have any questions regarding this matter, please contact Siva P. Lingam at 301-415-1564.
Sincerely, IRA BMozafari forI Douglas A. Broaddus, Chief Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-327 and 50-328 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 RlF RidsNrrDorlLpl2-2 RidsNrrPMSequoyah RidsNrrLACSola RidsOgcMailCenter RidsNrrDorlDpr RidsAcrsAcnw_MailCTR RidsNrrDciCsgb RidsRgn2MailCenter A. Johnson, NRR RidsN rrLABClayton . db 0: M L101680207 transmltte ae ADAMS Accession N* )y memo d t d OFFICE LPL2-2/PM LPL2-2/LA N RRlDCI/CSGB/BC NAME SLingam CSoia by RTaylor (BClayton)
DATE 7/26/10 7/27/10 06/16/10*
LPL2-2/BC DBroaddus by (BMozafari) 7/27/10 OFFICIAL RECORD COpy