|
|
Line 2: |
Line 2: |
| | number = ML13217A002 | | | number = ML13217A002 |
| | issue date = 07/26/2013 | | | issue date = 07/26/2013 |
| | title = Oconee, Units 1, 2, & 3 - Additional Information Regarding License Amendment Request to Clarify the Application of the 45-day Completion Time of Technical Specification 3.8.1 Required Action C.2.2.5 License Amendment Request No. 2012-14, Su | | | title = Additional Information Regarding License Amendment Request to Clarify the Application of the 45-day Completion Time of Technical Specification 3.8.1 Required Action C.2.2.5 License Amendment Request No. 2012-14, Supplement 2 |
| | author name = Batson S L | | | author name = Batson S L |
| | author affiliation = Duke Energy Carolinas, LLC | | | author affiliation = Duke Energy Carolinas, LLC |
Letter Sequence Supplement |
---|
|
|
MONTHYEARML12307A3772012-10-30030 October 2012 (Ons), Units 1, 2, and 3, License Amendment Request to Clarify the Application of the 45-day Completion, Time of Technical Specification 3.8.1 Required Action C.2.2.5, License Amendment Request (LAR) No. 2012-14 Project stage: Request ML12346A4042012-12-11011 December 2012 License Amendment Request Related to Keowee Hydro Units, Acceptance Review Project stage: Acceptance Review ML13149A1112013-06-17017 June 2013 Request for Additional Information Regarding Amendment Application Related to Technical Specifications for the Onsite Standby Power Sources Project stage: RAI ML13204A3852013-07-16016 July 2013 Additional Information Regarding License Amendment Request to Clarify Application of the 45-day Completion Time of Technical Specification 3.8.1 Required Action C.2.2.5 License Amendment Request No. 2012-14, Supplement 1 Project stage: Supplement ML13217A0022013-07-26026 July 2013 Additional Information Regarding License Amendment Request to Clarify the Application of the 45-day Completion Time of Technical Specification 3.8.1 Required Action C.2.2.5 License Amendment Request No. 2012-14, Supplement 2 Project stage: Supplement ML13231A0132013-08-23023 August 2013 Issuance of Amendments Regarding the Technical Specification for Keowee Hydro Units (TAC Nos. ME9880, ME9881, and ME9882) Project stage: Approval 2013-06-17
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24088A3052024-03-25025 March 2024 Fws to NRC, Agreement with Nlaa Determination for Tricolored Bat for Oconee Lr 05000270/LER-2023-001, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee2024-02-29029 February 2024 Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee 05000287/LER-2023-002, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications2024-02-29029 February 2024 Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications IR 05000269/20230062024-02-28028 February 2024 Annual Assessment Letter for Oconee Nuclear Station Units 1, 2 and 3 - (NRC Inspection Report 05000269/2023006, 05000270/2023006, and 05000287/2023006) ML24045A3042024-02-16016 February 2024 Ltr. to Lisa M. Collins Chief the Wassamasaw Tribe of Varnertown Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24030A0052024-02-16016 February 2024 Ltr. to Brian Harris, Chief, Catawba Indian Nation; Re., Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2942024-02-16016 February 2024 Ltr. to Carolyn Chavis Bolton Chief Pee Dee Indian Nation of Upper Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2962024-02-16016 February 2024 Ltr. to David Hill Principal Chief Muscogee Creek Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2992024-02-16016 February 2024 Ltr. to Eric Pratt Chief the Santee Indian Organization Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3082024-02-16016 February 2024 Ltr. to Ralph Oxendine Chief Sumter Tribe of Cheraw Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3022024-02-16016 February 2024 Ltr. to Joe Bunch United Keetoowah Band of Cherokee Indians in Ok Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3072024-02-16016 February 2024 Ltr. to Pete Parr Chief Pee Dee Indian Tribe Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3032024-02-16016 February 2024 Ltr. to John Creel Chief Edisto Natchez-Kusso Tribe of Sc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3012024-02-16016 February 2024 Ltr. to Harold Hatcher Chief the Waccamaw Indian People Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2952024-02-16016 February 2024 Ltr. to Chuck Hoskin, Jr, Principal Chief Cherokee Nation Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A2972024-02-16016 February 2024 Ltr. to Dexter Sharp Chief Piedmont American Indian Assoc Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3052024-02-16016 February 2024 Ltr. to Louis Chavis Chief Beaver Creek Indians Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24045A3062024-02-16016 February 2024 Ltr. to Michell Hicks, Principal Chief Eastern Band of Cherokee Re Oconee Nuclear Station Units 1,2, and 3 Section 106 ML24019A1442024-02-13013 February 2024 Letter to Reid Nelson, Executive Director, Achp; Re Oconee Nuclear Station Units 1, 2, and 3 Section 106 ML24011A1532024-02-13013 February 2024 Letter to Tracy Watson EPA-Oconee Nuclear Sta, Unites 1, 2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants ML24030A5212024-02-13013 February 2024 Letter to Elizabeth Johnson, Director, SHPO; Re Oconee Nuclear Stations Units 1, 2, and 3 Section 106 ML24011A1482024-02-13013 February 2024 Letter to Steven M. Snider-Oconee Nuclear Sta, Unites 1,2 & 3 Notice of Avail of the Draft Site-Specific Supp. 2, 2nd Renewal to the Generic EIS for Lic. Renew of Nuclear Plants IR 05000269/20230042024-02-13013 February 2024 Integrated Inspection Report 05000269/2023004, 05000270/2023004, and 05000287/2023004; and Inspection Report 07200040/2023001 ML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staff’S Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds 2024-08-26
[Table view] |
Text
DU.KE Scott L. Batson ENERGY. Vice President Oconee Nuclear Station Duke Energy ONOIVP 1 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.3274 f 864.873.4208 Scott.Batson@duke-energy.com 10 CFR 50.90 July 26, 2013 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, and 50-287 Additional Information Regarding License Amendment Request to Clarify the Application of the 45-day Completion Time of Technical Specification
3.8.1 Required
Action C.2.2.5 License Amendment Request (LAR) No. 2012-14, Supplement 2 On October 30, 2012, Duke Energy Carolinas, LLC (Duke Energy) submitted a License Amendment Request (LAR) requesting the Nuclear Regulatory Commission (NRC) approve a Technical Specification (TS) change to allow the 45-day Completion Time of TS 3.8.1 Required Action C.2.2.5 to be applied cumulatively over a 3-year time period for each Keowee Hydro Unit (KHU). By letter dated June 17, 2013, the NRC requested Duke Energy to submit additional information associated with the LAR. Duke Energy responded to this request by letter dated July 16, 2013. During conference calls with NRC staff on July 9 and July 11, Duke Energy agreed to provide additional information to address the risk significance of dual KHU outages.The enclosure provides the requested information.
This license amendment is needed to allow work associated with the Protected Service Water (PSW) System tie-in to the KHU emergency power to proceed on schedule.
This work is scheduled to begin on September 3, 2013;therefore, approval no later than August 15, 2013, is requested.
There are no new commitments being made as a result of this letter.If there are any additional questions, please contact Boyd Shingleton, ONS Regulatory Affairs, at (864) 873-4716.www.duke-energy.com Nuclear Regulatory Commission License Amendment Request No. 2012-14, Supplement 2 July 26, 2013 Page 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on July 26, 2013.Sincerely, Scott L. Batson Vice President Oconee Nuclear Station Enclosure Response to NRC Request for Additional Information Regulatory Commission License Amendment Request No. 2012-14, Supplement 2 July 26, 2013 Page 3 cc w/
Enclosure:
Mr. Victor McCree, Regional Administrator U. S. Nuclear Regulatory Commission
-Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. John Boska, Senior Project Manager (by electronic mail only)Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop O-8G9A Rockville, MD 20852 Mr. Ed Crowe Senior Resident Inspector Oconee Nuclear Site Ms. Susan E. Jenkins, Manager Radioactive
& Infectious Waste Management Division of Waste Management South Carolina Department of Health and Environmental Control 2600 Bull St.Columbia, SC 29201 ENCLOSURE Duke Energy Response to NRC Request for Additional Information (RAI)
EncIpsure
-Duke Energy Response to NRC RAI License Amendment Request No. 2012-14, Supplement 2 July 26, 2013 Page 1 Background Information NRC requested Duke Energy to respond to 8 RAI questions by letter dated June 17, 2013. During phone calls to discuss Duke Energy responses to the RAI questions on July 9 and 11, 2013, NRC continued to express concern that allowing the 45-day Completion Time of Technical Specification (TS) Required Action C.2.2.5 to be applied cumulatively over a three year period versus one time over a three year period will result in an additional number of extended dual Keowee Hydro Unit (KHU) outages. Duke Energy's response to RAI 8, which was intended to address this concern, proposed to restrict the cumulative time allowed in dual KHU outages by adding a second Completion Time to TS 3.8.1 Required Action H.2 that restricts the time allowed in Condition H over a three year period to 240 cumulative hours when in the 45 day Completion Time of RA C.2.2.5. This is equivalent to the maximum time that could be incurred during one continuous 45-day outage for each KHU with two 60-hour dual KHU outages (one to isolate a KHU for maintenance and one to restore a KHU from maintenance).
Limiting the dual KHU outage time in this manner precludes increasing the duration of dual KHU outage time over what is currently allowed.The NRC Staff acknowledged that the proposed change limits the time in a dual KHU outage but indicated that NRC would like to get an understanding of the risk significance of these dual KHU outages and asked Duke Energy to calculate the Incremental Conditional Core Damage Probability (ICCDP) and Incremental Conditional Large Early Release Probability (ICLERP)incurred due to 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br /> of dual KHU outage time over a three year period. Duke Energy agreed to perform this calculation using a method identified as acceptable by NRC Staff.Summary of PRA results The risk evaluation was conducted for the dual KHU outage configuration using the following assumptions: " Maintenance unavailability values for all plant systems were set to zero for all plant systems except for Keowee.* The tornado initiating event frequency was set to zero and the weather-related Loss of Offsite Power (LOOP) initiating frequency was reduced to reflect risk management actions that preclude entering a dual KHU outage when the potential for severe weather exists during the outage period. This assumption is based on administrative controls and risk management plans that require review of the weather forecast prior to the beginning of the dual KHU outage and do not allow the outage to begin if any weather conditions are predicted that could adversely affect the availability of offsite power from the switchyard." Operator actions in the Probabilistic Risk Assessment (PRA) model to align backup power from transformer CT5 following a LOOP event were removed from the model. These actions are not required during the Keowee outages because the Standby Buses will be energized from a Lee Combustion Turbine (LCT) using a dedicated transmission line as required by TS 3.8.1 Condition H.* Seismic events were neglected from the analysis.
-Encl9sure
-Evaluation of Proposed Change License Amendment Request No. 2012-14, Supplement 2 July 26, 2013 Page 2 The analysis results determined that a total dual KHU unit outage time of 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br /> (10 days)corresponds to an ICCDP of approximately 6E-08. Approximately half of this risk contribution was due to LOOP initiating events and half from fire-related events. When this unavailability is averaged over a 3 year period, the equivalent ICCDP is 2E-08 which represents an insignificant impact on average annual plant risk.The ICLERP value was not specifically computed.
However, it was concluded that the ICLERP impact is also insignificant given that the Large Early Release Frequency (LERF) is a subset of the Core Damage Frequency (CDF) and that the ICCDP value is very low.