ML17033B575: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:North Anna Power Station Updated Final Safety Analysis Report Chapter 14 Intentionally Blank
{{#Wiki_filter:North Anna Power Station Updated Final Safety Analysis Report Chapter 14


Intentionally Blank Revision 52-09/29/2016 NAPS UFSAR 14-iChapter 14: Initial Tests and OperationTable of ContentsSectionTitle Page14INITIAL TESTS AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.0-114.0.1Administration of the Preoperational Test Program. . . . . . . . . . . . . . . . . . . . . .
Intentionally Blank Revision 5209/29/2016                                                   NAPS UFSAR                                         14-i Chapter 14: Initial Tests and Operation Table of Contents Section                                                Title                                                                Page 14      INITIAL TESTS AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                   14.0-1 14.0.1 Administration of the Preoperational Test Program . . . . . . . . . . . . . . . . . . . . . .                       14.0-1 14.0.2 Administration of the Start-Up Test Program . . . . . . . . . . . . . . . . . . . . . . . . . . .                   14.0-2 14.1 TEST PROGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .       14.1-1 14.1.1 Pre-Operational Test Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .           14.1-1 14.1.2 Initial Start-Up Test Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .         14.1-2 14.1.2.1    Initial Fuel Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-2 14.1.2.2    Initial Postloading Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-4 14.1.2.3    Initial Criticality and Low-Power Physics Tests . . . . . . . . . . . . . . . . . . . . . . .                 14.1-5 14.1.2.4    Power Level Escalation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-6 14.1.3 Start-Up Physics Test Program Differences Between Unit 1 and Unit 2 . . . . . .                                     14.1-7 14.1.4 Special Low-Power Tests - Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             14.1-8 14.1 Reference Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-9 14.2    AUGMENTATION OF VEPCOS STAFF FOR INITIAL TEST AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .           14.2-1 Appendix 14A NRC Questions and VEPCOs Responses Regarding the North Anna Power Station Unit 2 Modified Startup Physics Testing Program . . . . . . . . . . . . . . . . . . . . . . .                   14A-i
14.0-114.0.2Administration of the Start-Up Test Program. . . . . . . . . . . . . . . . . . . . . . . . . . .
14.0-214.1TEST PROGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-114.1.1Pre-Operational Test Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-114.1.2Initial Start-Up Test Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-2 14.1.2.1Initial Fuel Loading. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-214.1.2.2Initial Postloading Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-414.1.2.3Initial Criticality and Low-Power Physics Tests. . . . . . . . . . . . . . . . . . . . . . .14.1-5 14.1.2.4Power Level Escalation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-614.1.3Start-Up Physics Test Program Differences Between Unit 1 and Unit 2 . . . . . .14.1-714.1.4Special Low-Power Tests - Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-814.1Reference Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-914.2AUGMENTATION OF VEPCO'S STAFF FOR INITIAL TEST AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.2-1 Appendix 14ANRC Questions and VEPCO's Responses Regarding the North Anna Power Station Unit 2 Modified Startup Physics Testing Program. . . . . . . . . . . . . . . . . . . . . . .14A-i Revision 52-09/29/2016 NAPS UFSAR 14-iiChapter 14: Initial Tests and OperationList of TablesTableTitle PageTable 14.1-1List of Preoperational Tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-10Table 14.1-2Lists of Start-Up Tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-34Table 14.1-3Unit 2 Start-Up Physics Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-45 Table 14.1-4Physics Tests that Have Been Deleted For Unit 2. . . . . . . . . . . . . . . . .14.1-46 Table 14.1-5Summary of Unit 1 Measured Values, Design Values, Design Tolerance, and Accident Analysis Crit eria for Physics Tests That Have Been Deleted for Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-47Table 14A-1Unit 2  Isotherm al Temperature Coefficient, Boron Endpoint, Rod Worth Reactivity, and Boron Worth Tests and Review Criteria. . . . . . . . . . . .14A-7 Revision 52-09/29/2016 NAPS UFSAR 14-iiiChapter 14: Initial Tests and OperationList of Figures FigureTitle PageFigure 14.1-1Typical Pre-Operational Test Sequence. . . . . . . . . . . . . . . . . . . . . . . .14.1-50Figure 14.1-2Typical Start-Up Test Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-51Figure 14.1-3Cycle 1 BOL Physics Test Doppler Power Coefficient Used in Accident Analysis Unit 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . .14.1-52Figure 14A-1Secondary Source Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14A-8Figure 14A-2Part Length Control Rod Locations (Unit 1). . . . . . . . . . . . . . . . . . . .14A-9 Revision 52-09/29/2016 NAPS UFSAR 14-iv Intentionally Blank


Intentionally Blank Revision 52-09/29/2016 NAPS UFSAR 14.0-1CHAPTER 14INITIAL TESTS AND OPERATIONThis chapter describes the sc ope of tests and operations pe rformed over the time period when construction was sufficiently complete to operate and test individual components and systems through the acceptance run at full power. Th is time period is divi ded into two categories:1.Pre-operational testing: tests performed before the initial core loading.2.Initial start-up testing: tests and operations from the initial core loading through the acceptance tests.
Revision 5209/29/2016                                                   NAPS UFSAR                                           14-ii Chapter 14: Initial Tests and Operation List of Tables Table                                                  Title                                                                Page Table 14.1-1  List of Preoperational Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-10 Table 14.1-2   Lists of Start-Up Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-34 Table 14.1-3  Unit 2 Start-Up Physics Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-45 Table 14.1-4  Physics Tests that Have Been Deleted For Unit 2 . . . . . . . . . . . . . . . . . 14.1-46 Table 14.1-5  Summary of Unit 1 Measured Values, Design Values, Design Tolerance, and Accident Analysis Criteria for Physics Tests That Have Been Deleted for Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-47 Table 14A-1    Unit 2 Isothermal Temperature Coefficient, Boron Endpoint, Rod Worth Reactivity, and Boron Worth Tests and Review Criteria. . . . . . . . . . . . 14A-7
The preoperational and start-up programs, as outlined in Ta bles 14.1-1 and 14.1-2 , comply with the intent of Regulatory Guide 1.68, Preoperational and Initial Start-up Test Programs for Water-Cooled Power Reactors , dated November 1973, in most cases, and use the same wording as much as possible in order to more clearly address the NR C guide requirem ents. Detailed acceptance criteria were provided in each test procedure that was written to fulfill the testing requirements. The detailed criter ia of acceptability were based on various sources, such as equipment technical manuals, system descriptions, plant drawings, manufacturer specifications, and the North Anna Units 1 and 2 FSAR. The tests and their objectives are listed in Ta bles 14.1-1 and 14.1-2, which also provide a summary of each test. The acceptability of a test is contingent on the successful attainment of the objectives stated in Ta bles 14.1-1 and 14.1-2.Because of similarities and differences in the fuel and co re characteristics between the two units, certain tests performed for Unit 1 were not repeated for Unit 2, while specific tests were performed for Unit 2 only. A discussion of the start-up physics program diff er ences appears in Section 14.1.3.14.0.1 Administration of the Preoperational Test Program The management and direction of the preoperational test program was under the direct control of VEPCO, with the principal responsib ility lying with the Supervisor - Engineering Services. In most cases written preoperational test pr ocedures were prepar ed by the station engineering staff under the direction of the Supe rvisor - Engineering Services. In those areas where the station engineering staff was not know ledgeable, proced ures were provided by the architect-engineer or outside consultants, based on their expertise in the particular areas of concern. Test procedure format generally included the purpose of the test, in itial condition requirements, precautions and limi tations, instructions, and criteria for acceptability of data. Prior to issuance of test procedures fo r use in the field, they were reviewed by the Joint Test Group and approved by the Station Nuclear Safety and Operating Committee.
For those procedures provided by the architec t-engineer or outside consultants, the preoperational test procedure was used as a cover sheet to their proce dure in order to ensure review by the Joint Test Group and approval by the Station Nuclear Safety and Operating Revision 52-09/29/2016 NAPS UFSAR 14.0-2Committee. In some instances the preoperational te st procedures were used to review and approve test data from testing performed by equipment vendors off the site (e.g., vendor certifications).
In most instances the conduct and direction of th e preoperational test s were the direct responsibility of the VEPCO test engineers designated by the techni cal supervision at the station. In some instances architect-engineer personnel or outside consultants we re responsible for the conduct of tests under the dire ction of VEPCO by means of written administrative controls.
Changes to approved test procedures were documen ted and became part of the final test results.
Administrative controls for making changes to procedures prepar ed by the station engineering staff were provided in the Nuclear Power Station Quality Assu rance Manual. Administrative procedures for making changes to procedures provided by the architect-engineer or outside consultants were formulated by the architect-engineer a nd approved by VEPCO.
For preoperational testing, the Supervisor - Engineering Services and the Joint Te st Group reviewed and analyzed the test results. Assistance from the VEPCO system office, the nuclear steam supply system vendor, and the architect-engineer was solicited as deemed necessary. The test results and evaluations were reviewed by the Station Nuclear Safety and Operating Committee and approved if they were satisfactory. In inst ances where performance of components or systems deviated from predicted results, furthe r engineering evaluations were made to resolve the discrepancies before the test was considered satisfactory. Systems that had to be modified as a result of the preoperational tests were then retested to verify acceptable performance.
The completed test procedures , along with data and conclu sions, were documented and filed as part of the permanent plant records.
Minimum qualifications for the VEPC O test engineers were as follows:1.A bachelor's degree in engin eering or the physical sciences or the equivalent, and at least 1 year of applicable nuclear power plant experience, or:2.A high school diploma or the equivalent, and at least 3 years of applicable nuclear power plant experience. Credit for up to 2 years of nuclear experience may be given for related technical training on a one-for-one time basis.
Additional information relative to the preope rational test progra m is provided in the Nuclear Power Station Quality Assurance Manual, in VEPCO stat ion administrative procedures, and in the architect-engineer's administrative procedures.
14.0.2 Administration of the Start-Up Test Program The management and direction of the start-up test program ha s been under the direct control of VEPCO, with principal res ponsibility lying with the Supervisor - Engineering Services. Wr itten start-up test procedures were prepared by the station reactor engineers under the direction Revision 52-09/29/2016 NAPS UFSAR 14.0-3of the Supervisor - Engineering Services. Procedures from the Nuclear St eam Supply System Start-up Manual and assistance from Westinghouse personnel were ut ilized in many cases. Prior to issuance of test procedures for use in the fi eld, they were approved by the Station Nuclear Safety and Operating Committee.
The conduct and directi on of the start-up tests were th e responsibility of the reactor engineers designated by the Supervisor - Engineering Servi ces. Changes to approved test procedures were documente d and became part of the final results. Administ rative procedures for making these changes, includin g the review and approvals, we re formulated and utilized by VEPCO.For start-up testing the react or engineers and the Supervisor - Engineering Services reviewed and analyzed th e test results. The measurements a nd data analysis for start-up physics tests were performed by the VEPCO Fuel Resources Departme nt. Assistance from the VEPCO system office, the nuclear steam supply system vendor , and the archit ect-engineer wa s solicited as deemed necessary. Approval of test results was the responsibility of the Station Nuclear Safety and Operating Committee. The completed test pr ocedures, along with data and conclusions, were documented and filed as part of the permanent plant records.
The minimum qualifications for the reactor e ngineers, in terms of educational background and experience, are stated in Section 13.1. Minimum qualifications for the test engineers responsible for the preparat ion and performance of start-up tests were as follows:1.A bachelor's degree in engineering or the physical sciences or the equivalent and 2 years of applicable power plant experi ence, of which at least 1 year shall be appli cable nuclear power plant experience, or2.A high school diploma or the equivalent and 5 years of applicable power plant experience, of which at least 2 years shall be applicable nuclear power plant expe rience. Credit for up to 2 years of non-nuclear experi ence may be given for rela ted technical training on a one-for-one time basis.
Additional information relative to the start-up test progra m is provided in the Nu clear Power Station Quality Assurance Manual a nd in station administrative procedures.
Revision 52-09/29/2016 NAPS UFSAR 14.0-4 Intentionally Blank Revision 52-09/29/2016 NAPS UFSAR 14.1-1The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.14.1 TEST PROGRAM14.1.1 Pre-Operational Test ProgramThe pre-operational test program included tests, adjustments, calibrations, and system operations necessary to ensure that initial fuel loading, initial criticality , and subsequent power operation could be safely undertaken.
After installation of individual components and systems was comp leted, the installed components and systems were tested and evalua ted according to approve d testing procedures or check-off lists. Analyses of test results were made to verify that systems and components were performing satisfactorily or , if not, to provide a basis fo r recommended corrective action.
Whenever possible, these tests were perfo rmed under the same conditions to be experienced under subsequent station opera tions. During system tests for which unit parameters were not available, the systems were operationally tested as far as possible without these parameters. The remainder of the tests were performed under plan t conditions when the parameters were available. Ab normal unit conditions were simula ted during testing as required and when such conditions did no t endanger personnel or equipment, or contaminate systems


whose cleanliness had been established.
Revision 5209/29/2016                                    NAPS UFSAR                                        14-iii Chapter 14: Initial Tests and Operation List of Figures Figure                                    Title                                                            Page Figure 14.1-1  Typical Pre-Operational Test Sequence. . . . . . . . . . . . . . . . . . . . . . . .      14.1-50 Figure 14.1-2  Typical Start-Up Test Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-51 Figure 14.1-3  Cycle 1 BOL Physics Test Doppler Power Coefficient Used in Accident Analysis Unit 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-52 Figure 14A-1  Secondary Source Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14A-8 Figure 14A-2  Part Length Control Rod Locations (Unit 1) . . . . . . . . . . . . . . . . . . . .          14A-9
In general, pre-operational testing was comp leted before core loading. As individual systems were completed, pre-opera tional tests were performed to verify as nearly as possible the performance of the system under actual operating conditions. Where required, simulated signals or inputs were used to ve rify the full operating range of the system and to calibrate and align the systems and instruments at these conditions. Later, systems th at were used during normal operation were verified under actual operating conditions. Systems that are not used during normal plant operation, but s hould be in a state of readine ss to perform safety functions, were tested before plant start-up. Examples of these systems are the reactor trip system and engineered safety features system logic, operation checks, and se tpoint verifications.Testing performed during the pr e-operational test program is outlined in Table 14.1-1. A typical sequence of performance for operational test s is shown in Figure 14.1-1. The actual sequence of tests was formulated before the performance of the tests, considering equipment and system availability. In some cases, it was necessary to complete certain pre-operational tests after core loading. These included such tests as those performed on the complete rod control system, rod position indication, and complete incore mo vable detector system. These tests have been identified in Table 14.1-1.
 
Revision 52-09/29/2016 NAPS UFSAR 14.1-214.1.2 Initial Start-Up Test Program Fuel loading was begun when all prerequisite system tests and operations were satisfactorily completed. Upon completion of fuel loading, the reactor upper internals and pressure vessel head were installed, and additional mechanical and electrical tests were performed as discussed in pre-ope rational testing. The purpose of this phase of activities was to prepare the system for nuclear operation and to establish that all design requirements necessary for operation were achieved. The core-loading and postloading tests are described below.
Revision 5209/29/2016                  NAPS UFSAR 14-iv Intentionally Blank
 
Revision 5209/29/2016                                      NAPS UFSAR                        14.0-1 CHAPTER 14              INITIAL TESTS AND OPERATION This chapter describes the scope of tests and operations performed over the time period when construction was sufficiently complete to operate and test individual components and systems through the acceptance run at full power. This time period is divided into two categories:
: 1. Pre-operational testing: tests performed before the initial core loading.
: 2. Initial start-up testing: tests and operations from the initial core loading through the acceptance tests.
The preoperational and start-up programs, as outlined in Tables 14.1-1 and 14.1-2, comply with the intent of Regulatory Guide 1.68, Preoperational and Initial Start-up Test Programs for Water-Cooled Power Reactors, dated November 1973, in most cases, and use the same wording as much as possible in order to more clearly address the NRC guide requirements. Detailed acceptance criteria were provided in each test procedure that was written to fulfill the testing requirements. The detailed criteria of acceptability were based on various sources, such as equipment technical manuals, system descriptions, plant drawings, manufacturer specifications, and the North Anna Units 1 and 2 FSAR. The tests and their objectives are listed in Tables 14.1-1 and 14.1-2, which also provide a summary of each test. The acceptability of a test is contingent on the successful attainment of the objectives stated in Tables 14.1-1 and 14.1-2.
Because of similarities and differences in the fuel and core characteristics between the two units, certain tests performed for Unit 1 were not repeated for Unit 2, while specific tests were performed for Unit 2 only. A discussion of the start-up physics program differences appears in Section 14.1.3.
14.0.1 Administration of the Preoperational Test Program The management and direction of the preoperational test program was under the direct control of VEPCO, with the principal responsibility lying with the Supervisor - Engineering Services. In most cases written preoperational test procedures were prepared by the station engineering staff under the direction of the Supervisor - Engineering Services. In those areas where the station engineering staff was not knowledgeable, procedures were provided by the architect-engineer or outside consultants, based on their expertise in the particular areas of concern. Test procedure format generally included the purpose of the test, initial condition requirements, precautions and limitations, instructions, and criteria for acceptability of data. Prior to issuance of test procedures for use in the field, they were reviewed by the Joint Test Group and approved by the Station Nuclear Safety and Operating Committee.
For those procedures provided by the architect-engineer or outside consultants, the preoperational test procedure was used as a cover sheet to their procedure in order to ensure review by the Joint Test Group and approval by the Station Nuclear Safety and Operating
 
Revision 5209/29/2016                                    NAPS UFSAR                        14.0-2 Committee. In some instances the preoperational test procedures were used to review and approve test data from testing performed by equipment vendors off the site (e.g., vendor certifications).
In most instances the conduct and direction of the preoperational tests were the direct responsibility of the VEPCO test engineers designated by the technical supervision at the station.
In some instances architect-engineer personnel or outside consultants were responsible for the conduct of tests under the direction of VEPCO by means of written administrative controls.
Changes to approved test procedures were documented and became part of the final test results.
Administrative controls for making changes to procedures prepared by the station engineering staff were provided in the Nuclear Power Station Quality Assurance Manual. Administrative procedures for making changes to procedures provided by the architect-engineer or outside consultants were formulated by the architect-engineer and approved by VEPCO.
For preoperational testing, the Supervisor - Engineering Services and the Joint Test Group reviewed and analyzed the test results. Assistance from the VEPCO system office, the nuclear steam supply system vendor, and the architect-engineer was solicited as deemed necessary. The test results and evaluations were reviewed by the Station Nuclear Safety and Operating Committee and approved if they were satisfactory. In instances where performance of components or systems deviated from predicted results, further engineering evaluations were made to resolve the discrepancies before the test was considered satisfactory. Systems that had to be modified as a result of the preoperational tests were then retested to verify acceptable performance.
The completed test procedures, along with data and conclusions, were documented and filed as part of the permanent plant records.
Minimum qualifications for the VEPCO test engineers were as follows:
: 1. A bachelors degree in engineering or the physical sciences or the equivalent, and at least 1 year of applicable nuclear power plant experience, or:
: 2. A high school diploma or the equivalent, and at least 3 years of applicable nuclear power plant experience. Credit for up to 2 years of nuclear experience may be given for related technical training on a one-for-one time basis.
Additional information relative to the preoperational test program is provided in the Nuclear Power Station Quality Assurance Manual, in VEPCO station administrative procedures, and in the architect-engineers administrative procedures.
14.0.2 Administration of the Start-Up Test Program The management and direction of the start-up test program has been under the direct control of VEPCO, with principal responsibility lying with the Supervisor - Engineering Services.
Written start-up test procedures were prepared by the station reactor engineers under the direction
 
Revision 5209/29/2016                                    NAPS UFSAR                        14.0-3 of the Supervisor - Engineering Services. Procedures from the Nuclear Steam Supply System Start-up Manual and assistance from Westinghouse personnel were utilized in many cases. Prior to issuance of test procedures for use in the field, they were approved by the Station Nuclear Safety and Operating Committee.
The conduct and direction of the start-up tests were the responsibility of the reactor engineers designated by the Supervisor - Engineering Services. Changes to approved test procedures were documented and became part of the final results. Administrative procedures for making these changes, including the review and approvals, were formulated and utilized by VEPCO.
For start-up testing the reactor engineers and the Supervisor - Engineering Services reviewed and analyzed the test results. The measurements and data analysis for start-up physics tests were performed by the VEPCO Fuel Resources Department. Assistance from the VEPCO system office, the nuclear steam supply system vendor, and the architect-engineer was solicited as deemed necessary. Approval of test results was the responsibility of the Station Nuclear Safety and Operating Committee. The completed test procedures, along with data and conclusions, were documented and filed as part of the permanent plant records.
The minimum qualifications for the reactor engineers, in terms of educational background and experience, are stated in Section 13.1. Minimum qualifications for the test engineers responsible for the preparation and performance of start-up tests were as follows:
: 1. A bachelors degree in engineering or the physical sciences or the equivalent and 2 years of applicable power plant experience, of which at least 1 year shall be applicable nuclear power plant experience, or
: 2. A high school diploma or the equivalent and 5 years of applicable power plant experience, of which at least 2 years shall be applicable nuclear power plant experience. Credit for up to 2 years of non-nuclear experience may be given for related technical training on a one-for-one time basis.
Additional information relative to the start-up test program is provided in the Nuclear Power Station Quality Assurance Manual and in station administrative procedures.
 
Revision 5209/29/2016                  NAPS UFSAR 14.0-4 Intentionally Blank
 
Revision 5209/29/2016                                      NAPS UFSAR                          14.1-1 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
14.1    TEST PROGRAM 14.1.1 Pre-Operational Test Program The pre-operational test program included tests, adjustments, calibrations, and system operations necessary to ensure that initial fuel loading, initial criticality, and subsequent power operation could be safely undertaken.
After installation of individual components and systems was completed, the installed components and systems were tested and evaluated according to approved testing procedures or check-off lists. Analyses of test results were made to verify that systems and components were performing satisfactorily or, if not, to provide a basis for recommended corrective action.
Whenever possible, these tests were performed under the same conditions to be experienced under subsequent station operations. During system tests for which unit parameters were not available, the systems were operationally tested as far as possible without these parameters. The remainder of the tests were performed under plant conditions when the parameters were available. Abnormal unit conditions were simulated during testing as required and when such conditions did not endanger personnel or equipment, or contaminate systems whose cleanliness had been established.
In general, pre-operational testing was completed before core loading. As individual systems were completed, pre-operational tests were performed to verify as nearly as possible the performance of the system under actual operating conditions. Where required, simulated signals or inputs were used to verify the full operating range of the system and to calibrate and align the systems and instruments at these conditions. Later, systems that were used during normal operation were verified under actual operating conditions. Systems that are not used during normal plant operation, but should be in a state of readiness to perform safety functions, were tested before plant start-up. Examples of these systems are the reactor trip system and engineered safety features system logic, operation checks, and setpoint verifications.
Testing performed during the pre-operational test program is outlined in Table 14.1-1. A typical sequence of performance for operational tests is shown in Figure 14.1-1. The actual sequence of tests was formulated before the performance of the tests, considering equipment and system availability. In some cases, it was necessary to complete certain pre-operational tests after core loading. These included such tests as those performed on the complete rod control system, rod position indication, and complete incore movable detector system. These tests have been identified in Table 14.1-1.
 
Revision 5209/29/2016                                     NAPS UFSAR                       14.1-2 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
14.1.2 Initial Start-Up Test Program Fuel loading was begun when all prerequisite system tests and operations were satisfactorily completed. Upon completion of fuel loading, the reactor upper internals and pressure vessel head were installed, and additional mechanical and electrical tests were performed as discussed in pre-operational testing. The purpose of this phase of activities was to prepare the system for nuclear operation and to establish that all design requirements necessary for operation were achieved. The core-loading and postloading tests are described below.
14.1.2.1 Initial Fuel Loading The reactor containment structure was completed and tested before initial fuel loading.
14.1.2.1 Initial Fuel Loading The reactor containment structure was completed and tested before initial fuel loading.
Fuel-handling tools and equipment were checked out and dry runs con ducted in the use and operation of equipment.
Fuel-handling tools and equipment were checked out and dry runs conducted in the use and operation of equipment.
The reactor vessel and associated components were in a state of readiness to receive fuel. Water level was maintained above the bottom of the nozzles.
The reactor vessel and associated components were in a state of readiness to receive fuel.
The overall responsibility and direction for the initial core loading was exercised by the Station Manager assisted by the Superintendent - Station Op eration. The overall process of initial core loading was, in general, directed from the operating floor of the containment structure. Procedures for the control of personne l and the maintenance of containment security were in effect during initial fuel loading.The as-loaded core configuration was specif ied as part of the core design studies conducted in advance of core loading. In the event mechan ical damage to a fuel assembly occurred during core-loading ope rations, an evaluation would have been performed and a replacement assembly would have been procured if deemed necessary.The core was assembled in the reactor vessel, containing reactor-grade water with dissolved boric acid to maintain a calculated core effective multiplication factor of 0.95 or lower. The refueling cavity was kept dry duri ng the initial core loading. Core moderator chemistry conditions (particularly, boron concentration) were prescribed in the core-loading procedure document and were verified periodically by chemical analyses of moderator samples taken before and during core-loading operations.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Water level was maintained above the bottom of the nozzles.
Revision 52-09/29/2016 NAPS UFSAR 14.1-3Core-loading instrumentatio n consisted of two permanently instal led source range (pulse-type) nuclear channels and three te mporary incore source range channels. The permanent channels, when responding, were mon itored in the main cont rol room by licensed station operators; the temporary channels were monitored by fuel-loading personnel. One permanent channel was equipped with an audible count rate indicator. The neutron flux level from both plant channels was di splayed on a strip chart recorder. The temporary channels were indicated on rate meters with one channel recorded on a strip chart recorder. Minimum count rates of two counts per sec, attributable to core neutrons, were required on at least two of the five available nuclear source channels at all times following instal lation of the initial nucleus of eight fuel assemblies.
The overall responsibility and direction for the initial core loading was exercised by the Station Manager assisted by the Superintendent - Station Operation. The overall process of initial core loading was, in general, directed from the operating floor of the containment structure. Procedures for the control of personnel and the maintenance of containment security were in effect during initial fuel loading.
Fuel assemblies together with inserted components (contro l rod assemblies, burnable poison inserts, source spider, or thimble plugging device s) were placed in th e reactor vessel one at a time according to a previously establis hed and approved sequence developed to provide reliable core monitoring with minimum possibility of core mechan ical damage. The core-loading procedure documents included deta iled tabular check sheets that prescribed and were used to verify the successi ve movements of each fuel asse mbly and its specified inserts from its initial position in the storage racks to its final position in the core. Multiple checks were made of component serial numbers and types at successive transfer points to guard against possible inadvertent ex changes or substitutio ns of components, and fuel assembly status boards were maintained th roughout the core-loading operation.
The as-loaded core configuration was specified as part of the core design studies conducted in advance of core loading. In the event mechanical damage to a fuel assembly occurred during core-loading operations, an evaluation would have been performed and a replacement assembly would have been procured if deemed necessary.
An initial nucleus of eight fuel assemblies, the first of which contained an activated neutron source, is the minimum source-fuel nuc leus that permits subsequent meaningful inverse count rate ratio monitori ng. This initial nucleus has been determined by calculation and previous experience to be markedly subcritical ( less than or equal to 0.90) under the required conditions of loading.
The core was assembled in the reactor vessel, containing reactor-grade water with dissolved boric acid to maintain a calculated core effective multiplication factor of 0.95 or lower. The refueling cavity was kept dry during the initial core loading. Core moderator chemistry conditions (particularly, boron concentration) were prescribed in the core-loading procedure document and were verified periodically by chemical analyses of moderator samples taken before and during core-loading operations.
Each subsequent fuel addition was acco mpanied by detailed neutron count rate monitoring to determine that the just-loaded fu el assembly did not ex cessively increase the count rate and that the extrapolated inverse c ount rate ratio was not decreasing for unexplained reasons. The results of each lo ading step were evaluated before the next prescribed step was started.Criteria for safe loading require that loading operations stop immediately if:1.An unanticipated increase in the neutron count rates by a factor of two occurs on all responding nuclear channels during any single lo ading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated changes due to detector and/or source movement).The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
 
k eff Revision 52-09/29/2016 NAPS UFSAR 14.1-42.The neutron count rate on any individual nucle ar channel increases by a factor of five during any single loading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated cha nges due to detector and/
Revision 5209/29/2016                                      NAPS UFSAR                          14.1-3 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
or source movements).
Core-loading instrumentation consisted of two permanently installed source range (pulse-type) nuclear channels and three temporary incore source range channels. The permanent channels, when responding, were monitored in the main control room by licensed station operators; the temporary channels were monitored by fuel-loading personnel. One permanent channel was equipped with an audible count rate indicator. The neutron flux level from both plant channels was displayed on a strip chart recorder. The temporary channels were indicated on rate meters with one channel recorded on a strip chart recorder. Minimum count rates of two counts per sec, attributable to core neutrons, were required on at least two of the five available nuclear source channels at all times following installation of the initial nucleus of eight fuel assemblies.
An alarm in the containment and main cont rol room is coupled to the source range channels with a setpoint equal to or less than five times the baseline count rate. This alarm automatically alerts the loading operation personnel of high count rate and requires an immediate stop of all operations unt il the situation is evaluated.
Fuel assemblies together with inserted components (control rod assemblies, burnable poison inserts, source spider, or thimble plugging devices) were placed in the reactor vessel one at a time according to a previously established and approved sequence developed to provide reliable core monitoring with minimum possibility of core mechanical damage. The core-loading procedure documents included detailed tabular check sheets that prescribed and were used to verify the successive movements of each fuel assembly and its specified inserts from its initial position in the storage racks to its final position in the core. Multiple checks were made of component serial numbers and types at successive transfer points to guard against possible inadvertent exchanges or substitutions of components, and fuel assembly status boards were maintained throughout the core-loading operation.
Core-loading procedures specif ied the condition of fluid systems to prevent inadvertent dilution of the reactor coolant, specified the movement of fuel to preclude the possibility of mechanical damage, prescribed the conditions under which loading could proceed, identified responsibility and authority, and provided fo r continuous and complete fuel and core component accountability.
An initial nucleus of eight fuel assemblies, the first of which contained an activated neutron source, is the minimum source-fuel nucleus that permits subsequent meaningful inverse count rate ratio monitoring. This initial nucleus has been determined by calculation and previous experience to be markedly subcritical ( k eff less than or equal to 0.90) under the required conditions of loading.
Each subsequent fuel addition was accompanied by detailed neutron count rate monitoring to determine that the just-loaded fuel assembly did not excessively increase the count rate and that the extrapolated inverse count rate ratio was not decreasing for unexplained reasons. The results of each loading step were evaluated before the next prescribed step was started.
Criteria for safe loading require that loading operations stop immediately if:
: 1. An unanticipated increase in the neutron count rates by a factor of two occurs on all responding nuclear channels during any single loading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated changes due to detector and/or source movement).
 
Revision 5209/29/2016                                      NAPS UFSAR                        14.1-4 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
: 2. The neutron count rate on any individual nuclear channel increases by a factor of five during any single loading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated changes due to detector and/or source movements).
An alarm in the containment and main control room is coupled to the source range channels with a setpoint equal to or less than five times the baseline count rate. This alarm automatically alerts the loading operation personnel of high count rate and requires an immediate stop of all operations until the situation is evaluated.
Core-loading procedures specified the condition of fluid systems to prevent inadvertent dilution of the reactor coolant, specified the movement of fuel to preclude the possibility of mechanical damage, prescribed the conditions under which loading could proceed, identified responsibility and authority, and provided for continuous and complete fuel and core component accountability.
14.1.2.2 Initial Postloading Tests Upon completion of core loading, the reactor upper internals and the pressure vessel head were installed, and additional mechanical and electrical checks were performed before initial criticality. The final pressure test was conducted after filling and venting were completed to check the integrity of the vessel head installation.
14.1.2.2 Initial Postloading Tests Upon completion of core loading, the reactor upper internals and the pressure vessel head were installed, and additional mechanical and electrical checks were performed before initial criticality. The final pressure test was conducted after filling and venting were completed to check the integrity of the vessel head installation.
Mechanical and electrical te sts were performed on the co ntrol rod drive mechanisms.
Mechanical and electrical tests were performed on the control rod drive mechanisms.
These tests included a complete operational checkout of the mech anisms and calibration of the individual rod position indication.Tests were performed on the reactor trip circui ts to test manual trip operation. The actual control rod assembly drop times were measured for each control rod assembly. The reactor control and protection system wa s checked with simula ted signals to produce a trip signal for the various conditions that require plant trip.At all times when the control rod drive mechanisms were being tested, the boron concentration in the coolant-moderator was main tained such that the reactor would remain adequately shut down with all cont rol rod assemblies fully withdrawn.
These tests included a complete operational checkout of the mechanisms and calibration of the individual rod position indication.
A complete functional electrical and mechanic al check was made of the incore nuclear flux mapping system, and reactor coolant system flow measurements were take n to relate reactor coolant pump input power and elbow tap pressure differen tial to actual reactor coolant loop flow.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Tests were performed on the reactor trip circuits to test manual trip operation. The actual control rod assembly drop times were measured for each control rod assembly. The reactor control and protection system was checked with simulated signals to produce a trip signal for the various conditions that require plant trip.
Revision 52-09/29/2016 NAPS UFSAR 14.1-5 14.1.2.3 Initial Criticality and Low-Power Physics Tests On completion of postloading te sts, nuclear operation of the reactor was begun. This final phase of start-up and testing included initial criticality, low-power tes ting, and power level escalation. The purpose of these tests was to establish the operational characteristics of the unit and core, to acquire data for the proper calibration of se tpoints, and to ensure that operation was within license requirements. A brief description of the testing is presen ted in this section. Table 14.1-2 summarizes the major tests that were performed from initial core loading to rated power. Figure 14.1-2 depicts a typical sequence for these tests; the actual sequence of tests was formulated by station engineeri ng and operating personnel, consid ering test requirements and equipment availability.Initial criticality was estab lished by sequentially withdraw ing the shutdown and control banks of control rod assemblies from the core, l eaving the last withdraw n control bank inserted far enough in the core to provide effective contro l when criticality would later be achieved, and then diluting the heavily borated reactor coolant until criticality was achieved.
At all times when the control rod drive mechanisms were being tested, the boron concentration in the coolant-moderator was maintained such that the reactor would remain adequately shut down with all control rod assemblies fully withdrawn.
Successive stages of control rod assembly ba nk withdrawal and of boron concentration dilution were monitored by obse rving changes in neut ron count rate as indicated by the normal plant source range nuclear instru mentation as functions of ba nk position during rod motion and, subsequently, of reactor coolant boron concentr ation and primary-water addition to the reactor coolant system during dilution.
A complete functional electrical and mechanical check was made of the incore nuclear flux mapping system, and reactor coolant system flow measurements were taken to relate reactor coolant pump input power and elbow tap pressure differential to actual reactor coolant loop flow.
Throughout this period, sample s of the primary coolant were obtained and analyzed for boron concentration.
Inverse count rate ratio monito ring was used as an indication of the proximity and rate of approach to criticality of th e core during control rod assemb ly bank withdrawal and during reactor coolant boron dilution. The rate of dilution was reduced as the reactor approached the boron concentration extrapolated for criticality to ensure that effective control was maintained at all times. Written procedures specified the plant conditions, precautions, and specific instructions for the approach to criticality.After initial criticality, a prescribed program of reactor physics measurements was undertaken to verify that the basi c static and kinetic characteristics of the core were as expected and that the values of the kinetic coefficients assumed in the safeguards analysis were indeed conservative.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-6The measurements were made at low po wer and primarily at or near operating temperature and pressure. The measurements included verification of calculated values of control rod assembly bank reactivity worths, of isothermal temperature coefficient under various core conditions, of differential boron concentration reactivity worth, and of critical boron concentrations as functions of control rod assembly bank configuration.
In addition, measurements of the relative power distributions were made.
Concurrent tests were conducted on the instrumentation, including the source and intermediate range nuclear channels.Procedures were prepared to specify the sequence of test s and measurements conducted and the conditions under which each was to be performed to ensure both safety of operation and the validity and cons istency of the results ob tained. Had significant deviations from design predictions existed, or had unacceptable behavior be en revealed, or had apparent anomalies developed, then testing would have been suspe nded and the situation reviewed to determine whether a question of safety was invol ved before the resumption of testing.
14.1.2.4 Power Level Escalation When the operating characteristi cs of the reactor and unit were verified by low-power testing, a program of power level escalation in successive stages was used to bring the unit to its full rated ther mal power level. Both pr imary and secondary operati onal characteristics were examined at each stage of the power escalation program.
Measurements were made to determine the re lative power distribu tion in the core as functions of power level and control assembly bank position.
Secondary system heat balances ensured that the indica tions of power level were consistent and provided bases for calibration of the power range nuclear channels. The ability of the reactor coolant system to respond eff ectively to signals from primary and secondary instrumentation under a variety of conditions encountered in no rmal operations was verified.
At prescribed power levels the dynamic res ponse characteristics of the reactor coolant and steam systems were evaluated. The responses of the systems were measured for design step load changes of 10%, rapid 50% load re duction, and 50% and 100% power plant trips.
Adequacy of radiation shielding was de termined by gamma and neutron radiation surveys at selected points inside the containment and the outside area immediately adjacent to the containment at various power levels. Pe riodic sampling was performed to verify the chemical and radiochemical anal yses of the reactor coolant.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-7All precritical tests were completed and the re sults evaluated before initial criticality.
Prerequisites for performing a test were spec ified in the individual test procedure. The sequence of testing was outlined in a start-up test sequence, such that required prerequisite testing was completed before s ubsequent testing. Any special te st instruments required were specified to be installed, calibrated, and checked in the test procedure that specified the test equipment.14.1.3 Start-Up Physics Test Program Differences Between Un it 1 and Unit 2 After the initial start-up physics program for North Anna Unit 1 was completed, several changes to the program were made before the initial start-up physics program for Unit 2. Table 14.1-3 lists the physics tests that were performed as part of the Unit 2 start-up program. These tests were chosen to:1.Verify that the core was correctly loaded and that there were no anomalies present that could cause problems later in the cycle.2.Verify that the calculational model that had been used would correctly predict core behavior during the cycle.3.Verify the reactivity worth of the control rod banks.
4.Provide data for nuclear instrumentation calibration.
5.Demonstrate the sensitivity of this in strumentation to abnormal core conditions.
In addition, the chosen tests were selected to encompass the physics test goals listed in the NRC Branch Technical Position DOR-1, Guidance for Reload Submittals, Draft - Spring, 1978. Table 14.1-4 lists those physics tests that were performed during the Unit 1 start-up, and that were not repeated as part of the Unit 2 st art-up program. The deletion of these tests was justified for the following reasons:1.The successful performance of the abbreviated program was sufficient to achieve the physics testing program goals.2.The calculational model was verified as a result of the Unit 1 start-up.3.The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large margin exists between the measured parameter values and the design values used in the accident analyses. Evidence of this is shown in Table 14.1-5.
When the modified test program for Unit 2 was proposed, se veral questions were raised by the NRC relating to the modifications. The questions and VEPCO's responses are the subject of Appendix 14A.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-814.1.4 Special Low-Power Tests - Unit 2 This test program consisted of a series of natural circulati on tests that demonstrated the plant's cooldown capability in se veral simulated degraded modes of operation at power levels of up to 3% of rated thermal power.The objectives of the above tests and the methods used are described below.1.Natural Circulation TestObjective: To demonstrate the capability to remove decay heat by natural circulation.
Method: The reactor is at a pproximately 3% power and al l reactor coolant pumps are operating. All reactor coolant pum ps are tripped simultaneously , with the establishment of natural circulation indicated by the core exit thermocouples a nd the wide-range resistance temperature detectors.2.Natural Circulation With Simulated Loss of Offsite PowerObjective: To demonstrate that following a loss of offsite ac power, natural circulation can be established and maintained while being powered from the emergency diesel generators.
Method: The reactor is at a pproximately 3% power and al l reactor coolant pumps are operating. All reactor coolant pumps are tripped and a sta tion blackout is simulated. Alternating current power is returned by the diesel generators and natural circulation is verified.3.Natural Circulation With Loss of Pressurizer HeatersObjective: To demonstrate the ability to maintain natural circulation and saturation margin with the loss of pressurizer heaters.
Method: Establish natural circulation as in Test 1, and turn off the pressurizer heaters at the main control board. Monitor th e system pressures to determine the saturation margin, the depressurization rate, and the effects of charging/letdown flow and steam generator pressure on the saturation margin.4.Effect of Steam Generator Secondary-Side Isolation on Natural CirculationObjective: To determine the effects of steam generator secondary-side isolation on natural circulation.
Method: Establish natural circulation conditions as in Test 1 but at 1% power. Isolate the feedwater and steam line for one steam genera tor and establish equ ilibrium. Return the steam generator to service.5.Natural Circulation at Reduced PressureThe following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-9 14.1 REFERENCE DRAWINGSThe list of Station Drawings below is provided for information only. The referenced drawings are not part of the UFSAR. This is not intended to be a complete listing of all Station Drawings referenced from this section of the UFSAR. The contents of St ation Drawings are controlled by station procedure.
Drawing Number Description 1.11715-LSK-1-3AGenerator Breaker Closing 2.11715-LSK-1-3BLogic Diagram: Power Circuit Breaker Opening 3.11715-LSK-1-3CLogic Diagram: "
86" Protective Lockout Relays 4.11715-LSK-1-3DLogic Diagram: Main Tr ansformer Protection Relays, 86-TL 5.11715-LSK-1-3ELogic Diagram: Generator Lockout Relays 6.11715-LSK-1-3FLogic Diagram: Main Transformer Diff erential Lockout Relays, 86-GL & 86-PWIA 7.11715-LSK-1-3GLogic Diagram: Main Transformer Coolers 8.11715-LSK-1-2ALogic Diagram: External Turbine Trips, Sheet 1 9.11715-LSK-1-3HLogic Diagram: Main Transformer Alarms 10.11715-LSK-1-2BLogic Diagram: Turbine Trips, Sheet 211.11715-LSK-1-2CLogic Diagram: Turbine Trips, Sheet 3 12.11715-LSK-1-2DLogic Diagram: Turbine Trips, Sheet 4 13.11715-LSK-1-2ELogic Diagram: Turbine Trips, Sheet 5 14.11715-LSK-1-2FLogic Diagram: Turbine Trips, Sheet 6 15.11715-LSK-1-2GLogic Diagram: Turbine Trips, Sheet 7Objective: To demonstrate the ability to maintain natural circ ulation at reduced pressure and saturation margin. The accuracy of the saturation meter will also be verified.Method: The test method is the same as for Test 3, with the exceptio n that the pressure decrease can be acceler ated with the use of auxiliary pr essurizer sprays. The saturation margin will be decreased to approximately 20°F.The following information is HISTORICAL and is not intended or expec ted to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-10The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testing I. Plant Instrumentation1.Nuclear instrumentation (out of core)
Before core loading and initial criticality Before core loading, nuclear instru ments were aligned and source range detector response to a neutron source chec ked. Just before initial criticality all channels were checked to verify high-level trip functions , alarm setpoints, audible count rates where ap plicable, and opera tion of strip chart recorders and any auxiliary equipment.2.Process instrumentation (temperature, pressure, level, and flow instruments)
Ambient and/or at temperatureEquipment was aligned per manufacturer's instructions and applicable test procedures. Applicable alarm, trip, a nd control setpoints were checked for conformance with specified values.3.Seismic instrumentationBefore core loadingThis instrumentat ion was verified for correct installation and operability. A calibration record test was performed to verify operability of the magnetic tape playback units II. Reactor Coolant System1.Vibration and amplitudeBefore core loadingVibration sensors were placed on th e main coolant pumps and main cooling piping in order to check for excessive vibration while star ting and stopping the pumps2.Expansion and restraintBefore core loading, during heatup, and during cooldown.During the heatup to operating temper ature, selected points on cooldown components and piping of the reactor cool ant system were checked at various temperatures to verify unrestricted expansion. Points of interference detected during the heatup were corrected before increasing the temperature. Following cooldown to ambient temperature, the piping and components were checked to


confirm that they returned to their approximate base points.a.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Revision 5209/29/2016                                      NAPS UFSAR                        14.1-5 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-11 II. Reactor Coolant System (continued)3.Integrated hot functional tests Heatup, at temperature, and during cooldown.
14.1.2.3 Initial Criticality and Low-Power Physics Tests On completion of postloading tests, nuclear operation of the reactor was begun. This final phase of start-up and testing included initial criticality, low-power testing, and power level escalation. The purpose of these tests was to establish the operational characteristics of the unit and core, to acquire data for the proper calibration of setpoints, and to ensure that operation was within license requirements. A brief description of the testing is presented in this section.
(Hydrostatic testing has been satisfactorily completed and reactor coolant system instruments aligned and operational. Associated
Table 14.1-2 summarizes the major tests that were performed from initial core loading to rated power. Figure 14.1-2 depicts a typical sequence for these tests; the actual sequence of tests was formulated by station engineering and operating personnel, considering test requirements and equipment availability.
Initial criticality was established by sequentially withdrawing the shutdown and control banks of control rod assemblies from the core, leaving the last withdrawn control bank inserted far enough in the core to provide effective control when criticality would later be achieved, and then diluting the heavily borated reactor coolant until criticality was achieved.
Successive stages of control rod assembly bank withdrawal and of boron concentration dilution were monitored by observing changes in neutron count rate as indicated by the normal plant source range nuclear instrumentation as functions of bank position during rod motion and, subsequently, of reactor coolant boron concentration and primary-water addition to the reactor coolant system during dilution. Throughout this period, samples of the primary coolant were obtained and analyzed for boron concentration.
Inverse count rate ratio monitoring was used as an indication of the proximity and rate of approach to criticality of the core during control rod assembly bank withdrawal and during reactor coolant boron dilution. The rate of dilution was reduced as the reactor approached the boron concentration extrapolated for criticality to ensure that effective control was maintained at all times. Written procedures specified the plant conditions, precautions, and specific instructions for the approach to criticality.
After initial criticality, a prescribed program of reactor physics measurements was undertaken to verify that the basic static and kinetic characteristics of the core were as expected and that the values of the kinetic coefficients assumed in the safeguards analysis were indeed conservative.


auxiliary systems were to be operational.)The reactor coolant system was tested using pump heat to check heatup and cooldown procedures and to demonstrate satisfactorily performance of components and systems exposed to reactor coolant system temperature.
Revision 5209/29/2016                                    NAPS UFSAR                      14.1-6 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Proper operation of instrumentation, c ontrollers, and al arms was checked against operating conditions of auxili ary systems and setpoints verified.
The measurements were made at low power and primarily at or near operating temperature and pressure. The measurements included verification of calculated values of control rod assembly bank reactivity worths, of isothermal temperature coefficient under various core conditions, of differential boron concentration reactivity worth, and of critical boron concentrations as functions of control rod assembly bank configuration. In addition, measurements of the relative power distributions were made. Concurrent tests were conducted on the instrumentation, including the source and intermediate range nuclear channels.
Among the demonstrations performed were:a.To verify that water can be charged by the Chemical and Volume Control System at rated flow against normal reactor coolant pressures.b.To check letdown design flow rate for each operating mode.c.To check response of system to change in pressurizer level.
Procedures were prepared to specify the sequence of tests and measurements conducted and the conditions under which each was to be performed to ensure both safety of operation and the validity and consistency of the results obtained. Had significant deviations from design predictions existed, or had unacceptable behavior been revealed, or had apparent anomalies developed, then testing would have been suspended and the situation reviewed to determine whether a question of safety was involved before the resumption of testing.
d.To check response procedures and components used in boric acid batching and transfer operations.e.To check operation of the excess le tdown and seal-water flow paths.f.To check steam generator level in strumentation response to level changes.g.To check thermal expansion of system components and piping.
14.1.2.4 Power Level Escalation When the operating characteristics of the reactor and unit were verified by low-power testing, a program of power level escalation in successive stages was used to bring the unit to its full rated thermal power level. Both primary and secondary operational characteristics were examined at each stage of the power escalation program.
h.To perform isothermal calibration of resistance temperature detectors and incore thermocouples.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Measurements were made to determine the relative power distribution in the core as functions of power level and control assembly bank position.
Revision 52-09/29/2016 NAPS UFSAR 14.1-12 II. Reactor Coolant System (continued)i.To operationally check out the residual heat removal system.j.Visual and surface examination of the upper and lower core structures after the heatup and cooldown were completed (see item 6 below.)4.Component testsa.PressurizerAt operating temperatureDuring the hot functional testing, the pr essure-controlling capability of the pressurizer was demonstrated to be within the controlling band. After core loading, with the reactor coolant pumps operating and with full spray, the
Secondary system heat balances ensured that the indications of power level were consistent and provided bases for calibration of the power range nuclear channels. The ability of the reactor coolant system to respond effectively to signals from primary and secondary instrumentation under a variety of conditions encountered in normal operations was verified.
At prescribed power levels the dynamic response characteristics of the reactor coolant and steam systems were evaluated. The responses of the systems were measured for design step load changes of 10%, rapid 50% load reduction, and 50% and 100% power plant trips.
Adequacy of radiation shielding was determined by gamma and neutron radiation surveys at selected points inside the containment and the outside area immediately adjacent to the containment at various power levels. Periodic sampling was performed to verify the chemical and radiochemical analyses of the reactor coolant.


pressure-reducing capability of the pressurizer was verified. With the spray secured and all heaters energized, the pressure-increasing ca pability of the pressurizer was verified. Expected rate s of pressure decrease/increase with tolerances were specified in the test procedures.b.Reactor coolant system pumps and motors At ambient conditions, during heatup, and at temperature As the pumps and motors were placed in operation they were checked for:a.Direction of rotation.b.Vibration.c.Power requirements.
Revision 5209/29/2016                                        NAPS UFSAR                        14.1-7 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
d.Lubrication e.Cooling.
All precritical tests were completed and the results evaluated before initial criticality.
f.Recirculation flow.
Prerequisites for performing a test were specified in the individual test procedure. The sequence of testing was outlined in a start-up test sequence, such that required prerequisite testing was completed before subsequent testing. Any special test instruments required were specified to be installed, calibrated, and checked in the test procedure that specified the test equipment.
g.Flow and pressure characteristics.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1.3 Start-Up Physics Test Program Differences Between Unit 1 and Unit 2 After the initial start-up physics program for North Anna Unit 1 was completed, several changes to the program were made before the initial start-up physics program for Unit 2.
Revision 52-09/29/2016 NAPS UFSAR 14.1-13 II. Reactor Coolant System (continued)h.Megger and hi-pot tests (as applicable)i.Overload protection.
Table 14.1-3 lists the physics tests that were performed as part of the Unit 2 start-up program.
j.Correct power supply voltage During the reactor coolant system cold hydrostatic and hot f unctional tests, the pumps were operated to verify prope r installation. Follo wing core loading, measurements were made to determin e flow and input power relationships.c.Steam generatorsAt ambient conditions, during heatup, and at temperature. (The
These tests were chosen to:
: 1. Verify that the core was correctly loaded and that there were no anomalies present that could cause problems later in the cycle.
: 2. Verify that the calculational model that had been used would correctly predict core behavior during the cycle.
: 3. Verify the reactivity worth of the control rod banks.
: 4. Provide data for nuclear instrumentation calibration.
: 5. Demonstrate the sensitivity of this instrumentation to abnormal core conditions.
In addition, the chosen tests were selected to encompass the physics test goals listed in the NRC Branch Technical Position DOR-1, Guidance for Reload Submittals, Draft - Spring, 1978. Table 14.1-4 lists those physics tests that were performed during the Unit 1 start-up, and that were not repeated as part of the Unit 2 start-up program. The deletion of these tests was justified for the following reasons:
: 1. The successful performance of the abbreviated program was sufficient to achieve the physics testing program goals.
: 2. The calculational model was verified as a result of the Unit 1 start-up.
: 3. The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large margin exists between the measured parameter values and the design values used in the accident analyses. Evidence of this is shown in Table 14.1-5.
When the modified test program for Unit 2 was proposed, several questions were raised by the NRC relating to the modifications. The questions and VEPCOs responses are the subject of Appendix 14A.


secondary system had been satisfactorily hydrostatically tested.)
Revision 5209/29/2016                                      NAPS UFSAR                        14.1-8 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
The proper operation of instrumentat ion and control systems for steam generators was checked dur ing heatup and at temperature. The heat transfer capability of the steam generators wa s demonstrated. The functioning of the blowdown system was also checked.d.Pressurizer relief and safety valvesPressure conditionsThe setpoints of the relief and safety valves were verified from vendor certification data, by bench te sts, or by in-plant tests. When verified by in-plant
14.1.4 Special Low-Power Tests - Unit 2 This test program consisted of a series of natural circulation tests that demonstrated the plants cooldown capability in several simulated degraded modes of operation at power levels of up to 3% of rated thermal power.
The objectives of the above tests and the methods used are described below.
: 1. Natural Circulation Test Objective: To demonstrate the capability to remove decay heat by natural circulation.
Method: The reactor is at approximately 3% power and all reactor coolant pumps are operating. All reactor coolant pumps are tripped simultaneously, with the establishment of natural circulation indicated by the core exit thermocouples and the wide-range resistance temperature detectors.
: 2. Natural Circulation With Simulated Loss of Offsite Power Objective: To demonstrate that following a loss of offsite ac power, natural circulation can be established and maintained while being powered from the emergency diesel generators.
Method: The reactor is at approximately 3% power and all reactor coolant pumps are operating. All reactor coolant pumps are tripped and a station blackout is simulated.
Alternating current power is returned by the diesel generators and natural circulation is verified.
: 3. Natural Circulation With Loss of Pressurizer Heaters Objective: To demonstrate the ability to maintain natural circulation and saturation margin with the loss of pressurizer heaters.
Method: Establish natural circulation as in Test 1, and turn off the pressurizer heaters at the main control board. Monitor the system pressures to determine the saturation margin, the depressurization rate, and the effects of charging/letdown flow and steam generator pressure on the saturation margin.
: 4. Effect of Steam Generator Secondary-Side Isolation on Natural Circulation Objective: To determine the effects of steam generator secondary-side isolation on natural circulation.
Method: Establish natural circulation conditions as in Test 1 but at 1% power. Isolate the feedwater and steam line for one steam generator and establish equilibrium. Return the steam generator to service.
: 5. Natural Circulation at Reduced Pressure


tests, setpoints were checked by using a pr essure assist device that adds to the force due to pressure.Once the valve started to lift, this assi st device was vented, allowing the valve to reseat immediately. Following li fting and blowdown of any valve, the reseating of the valve was verified.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Revision 5209/29/2016                                    NAPS UFSAR                      14.1-9 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-14 II. Reactor Coolant System (continued)e.Main steam stop valves At operating temperature (steam flow no required)
Objective: To demonstrate the ability to maintain natural circulation at reduced pressure and saturation margin. The accuracy of the saturation meter will also be verified.
At hot conditions and with pressure equalized across the valve, the operation of the main steam stop valves was verifie
Method: The test method is the same as for Test 3, with the exception that the pressure decrease can be accelerated with the use of auxiliary pressurizer sprays. The saturation margin will be decreased to approximately 20°F.
: d. The operating times were verified to be within expected values as specified by the test procedure.f.Reactor coolant system (RCS) loop isolation valves At ambient conditions and at operating temperature and pressure conditions At ambient and at hot conditions, the oper ation of the loop isolation valves was checked.g.Main steam stop valve pipingBefore core loadingMain steam stop valve piping was checked for excessive vibration while closing the main steam stop valves with steam availabl e from the heatup of the reactor coolant by the reactor coolant pumps.h.Pressurizer relief valve discharge pipingPressure conditionsThe discharge piping associated with pressurizer relief valves was checked for excessive vibration during the opera tion (opening and closing) of the pressurizer relief valves. Following li fting and blowdown of any valve, the re-seating of the valve was verified. (N ote that this test may be done in conjunction with item d of this section.)The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1 REFERENCE DRAWINGS The list of Station Drawings below is provided for information only. The referenced drawings are not part of the UFSAR. This is not intended to be a complete listing of all Station Drawings referenced from this section of the UFSAR. The contents of Station Drawings are controlled by station procedure.
Revision 52-09/29/2016 NAPS UFSAR 14.1-15 II. Reactor Coolant System (continued)5.Pressure boundary integrity testsa.Hydrostatic testsBelow 200°F (after verification of cleanliness, and fill of system)
Drawing Number        Description
Cold hydrostatic testing of the reacto r coolant system pressure boundary was performed at test pressures as specif ied by ASME standards for the system.
: 1.     11715-LSK-1-3A        Generator Breaker Closing
Prior to pressurization, the system was heated above the minimum temperature for pressurization. The pressure was then increased in increm ents and at each increment inspections were made for le akage. Leaky valves or mechanical joints were not a basis for rejecting th e test. Relief valves were provided to prevent inadvertent over-pressurization of the system.b.Baseline data for inservice inspection During preoperational
: 2.      11715-LSK-1-3B        Logic Diagram: Power Circuit Breaker Opening
: 3.     11715-LSK-1-3C        Logic Diagram: 86 Protective Lockout Relays
: 4.     11715-LSK-1-3D        Logic Diagram: Main Transformer Protection Relays, 86-TL
: 5.     11715-LSK-1-3E        Logic Diagram: Generator Lockout Relays
: 6.     11715-LSK-1-3F        Logic Diagram: Main Transformer Differential Lockout Relays, 86-GL & 86-PWIA
: 7.      11715-LSK-1-3G        Logic Diagram: Main Transformer Coolers
: 8.     11715-LSK-1-2A        Logic Diagram: External Turbine Trips, Sheet 1
: 9.     11715-LSK-1-3H        Logic Diagram: Main Transformer Alarms
: 10. 11715-LSK-1-2B        Logic Diagram: Turbine Trips, Sheet 2
: 11. 11715-LSK-1-2C        Logic Diagram: Turbine Trips, Sheet 3
: 12. 11715-LSK-1-2D        Logic Diagram: Turbine Trips, Sheet 4
: 13. 11715-LSK-1-2E        Logic Diagram: Turbine Trips, Sheet 5
: 14. 11715-LSK-1-2F        Logic Diagram: Turbine Trips, Sheet 6
: 15. 11715-LSK-1-2G        Logic Diagram: Turbine Trips, Sheet 7


testing Systems and components that require inspections in accordance with  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing I. Plant Instrumentation
: 1. Nuclear instrumentation      Before core loading and    Before core loading, nuclear instruments were aligned and source range Revision 5209/29/2016 (out of core)                initial criticality        detector response to a neutron source checked. Just before initial criticality all channels were checked to verify high-level trip functions, alarm setpoints, audible count rates where applicable, and operation of strip chart recorders and any auxiliary equipment.
: 2. Process instrumentation      Ambient and/or at          Equipment was aligned per manufacturers instructions and applicable test (temperature, pressure,      temperature                procedures. Applicable alarm, trip, and control setpoints were checked for level, and flow instruments)                            conformance with specified values.
: 3. Seismic instrumentation      Before core loading        This instrumentation was verified for correct installation and operability. A calibration record test was performed to verify operability of the magnetic tape playback units II. Reactor Coolant System
: 1. Vibration and amplitude            Before core loading        Vibration sensors were placed on the main coolant pumps and main cooling piping in order to check for excessive vibration while starting and stopping the pumps
: 2. Expansion and restraint            Before core loading,        During the heatup to operating temperature, selected points on cooldown NAPS UFSAR during heatup, and during components and piping of the reactor coolant system were checked at various cooldown.                  temperatures to verify unrestricted expansion. Points of interference detected during the heatup were corrected before increasing the temperature. Following cooldown to ambient temperature, the piping and components were checked to confirm that they returned to their approximate base points.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.                                                                                                                      14.1-10


Section XI of the ASME Code were examined for baseline data either
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: 3. Integrated hot functional          Heatup, at temperature,      The reactor coolant system was tested using pump heat to check heatup and Revision 5209/29/2016 tests                              and during cooldown.          cooldown procedures and to demonstrate satisfactorily performance of (Hydrostatic testing has      components and systems exposed to reactor coolant system temperature.
been satisfactorily          Proper operation of instrumentation, controllers, and alarms was checked completed and reactor        against operating conditions of auxiliary systems and setpoints verified.
coolant system                Among the demonstrations performed were:
instruments aligned and          a. To verify that water can be charged by the Chemical and Volume Control operational. Associated              System at rated flow against normal reactor coolant pressures.
auxiliary systems were to be operational.)
: b. To check letdown design flow rate for each operating mode.
: c. To check response of system to change in pressurizer level.
: d. To check response procedures and components used in boric acid batching and transfer operations.
: e. To check operation of the excess letdown and seal-water flow paths.
: f. To check steam generator level instrumentation response to level                      NAPS UFSAR changes.
: g. To check thermal expansion of system components and piping.
: h. To perform isothermal calibration of resistance temperature detectors and incore thermocouples.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-11


following the cold hydrostatic test or following hot functional testing, depending on the system and component an d its availability and accessibility.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Data from these inspections provided ba seline data for inservice inspectionsc.Nondestructive testing of stainless steel safe ends and critical componentsBefore hydrostatic testAll reactor coolant system weld joints were nondestructively tested using liquid penetrant and/or radiographic tests as required by Section III of the ASME Code.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Table 14.1-1 (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-16 II. Reactor Coolant System (continued)6.Vibration monitoring on reactor internals During and after hot functional testing Comprehensive vibration measurements had been made during hot functional testing before core loading for Carolina Power & Light Company's H. B. Robinson Unit 2. The results of these te sts had been documented and submitted to the Directorate of Reactor Licen sing. These data were the basis for acceptance of following plants, such as North Anna Units 1 and 2, without
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: i. To operationally check out the residual heat removal system.
Revision 5209/29/2016
: j. Visual and surface examination of the upper and lower core structures after the heatup and cooldown were completed (see item 6 below.)
: 4. Component tests
: a. Pressurizer                    At operating temperature            During the hot functional testing, the pressure-controlling capability of the pressurizer was demonstrated to be within the controlling band. After core loading, with the reactor coolant pumps operating and with full spray, the pressure-reducing capability of the pressurizer was verified. With the spray secured and all heaters energized, the pressure-increasing capability of the pressurizer was verified. Expected rates of pressure decrease/increase with tolerances were specified in the test procedures.
: b. Reactor coolant system          At ambient conditions,              As the pumps and motors were placed in operation they were checked for:
pumps and motors                during heatup, and at                  a. Direction of rotation.
temperature
: b. Vibration.
: c. Power requirements.
NAPS UFSAR
: d. Lubrication
: e. Cooling.
: f. Recirculation flow.
: g. Flow and pressure characteristics.
: a. The preoperational test program for the emergency   core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-12


repeating these tests. During hot functi onal testing, the plant was operated with full flow for a minimum of 240 hours in order to achieve approximately 20 million cycles on the internal componen ts. Following hot f unctional testing, the internals were removed and inspected for vibration effects before core loading.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
III. Reactivity Control System1.Chemical and volume control system At ambient and/or at operating conditions.
Table 14.1-1 (continued)
System components were
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: h. Megger and hi-pot tests (as applicable)
Revision 5209/29/2016
: i. Overload protection.
: j. Correct power supply voltage During the reactor coolant system cold hydrostatic and hot functional tests, the pumps were operated to verify proper installation. Following core loading, measurements were made to determine flow and input power relationships.
: c. Steam generators                At ambient conditions,        The proper operation of instrumentation and control systems for steam during heatup, and at        generators was checked during heatup and at temperature. The heat transfer temperature. (The            capability of the steam generators was demonstrated. The functioning of the secondary system had          blowdown system was also checked.
been satisfactorily hydrostatically tested.)
: d. Pressurizer relief and          Pressure conditions          The setpoints of the relief and safety valves were verified from vendor safety valves                                                  certification data, by bench tests, or by in-plant tests. When verified by in-plant tests, setpoints were checked by using a pressure assist device that adds to the force due to pressure.                                                                      NAPS UFSAR Once the valve started to lift, this assist device was vented, allowing the valve to reseat immediately. Following lifting and blowdown of any valve, the reseating of the valve was verified.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-13


operationally checked out before fuel loading.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Makeup and letdown operations were conducted with the Chemical and Volume Control System to check out the difference modes of dilution and boration and verify flows in the different modes.The adequacy of heat tracing to maintain the highest concentration in solution was verified. The ability to adequate ly sample and the sampling techniques were demonstrated.2.Emergency boron shutdown system During hot functional
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: e. Main steam stop valves          At operating temperature At hot conditions and with pressure equalized across the valve, the operation of Revision 5209/29/2016 (steam flow no required) the main steam stop valves was verified. The operating times were verified to be within expected values as specified by the test procedure.
: f. Reactor coolant system          At ambient conditions and At ambient and at hot conditions, the operation of the loop isolation valves was (RCS) loop isolation            at operating temperature checked.
valves                          and pressure conditions
: g. Main steam stop valve            Before core loading          Main steam stop valve piping was checked for excessive vibration while piping                                                        closing the main steam stop valves with steam available from the heatup of the reactor coolant by the reactor coolant pumps.
: h. Pressurizer relief valve        Pressure conditions          The discharge piping associated with pressurizer relief valves was checked for discharge piping                                              excessive vibration during the operation (opening and closing) of the pressurizer relief valves. Following lifting and blowdown of any valve, the re-seating of the valve was verified. (Note that this test may be done in conjunction with item d of this section.)
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with  NAPS UFSAR clarifications noted in Section 3A.40.
14.1-14


testingThe pressure/flow characteristics of the emergency boration system were verified by pumping into the reactor coolant system.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-17III. Reactivity Contro l System (continued)3.Automatic reactor power control system Preoperational conditions (installation checks had
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: 5. Pressure boundary integrity tests Revision 5209/29/2016
: a. Hydrostatic tests          Below 200°F (after          Cold hydrostatic testing of the reactor coolant system pressure boundary was verification of cleanliness, performed at test pressures as specified by ASME standards for the system.
and fill of system)          Prior to pressurization, the system was heated above the minimum temperature for pressurization. The pressure was then increased in increments and at each increment inspections were made for leakage. Leaky valves or mechanical joints were not a basis for rejecting the test. Relief valves were provided to prevent inadvertent over-pressurization of the system.
: b. Baseline data for          During preoperational        Systems and components that require inspections in accordance with inservice inspection      testing                      Section XI of the ASME Code were examined for baseline data either following the cold hydrostatic test or following hot functional testing, depending on the system and component and its availability and accessibility.
Data from these inspections provided baseline data for inservice inspections
: c. Nondestructive testing of Before hydrostatic test      All reactor coolant system weld joints were nondestructively tested using liquid stainless steel safe ends                              penetrant and/or radiographic tests as required by Section III of the ASME and critical components                                Code.                                                                                              NAPS UFSAR
: a. The preoperational test program for the emergency   core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-15


been made)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
The system alignment was ve rified at preoperational conditions to demonstrate the response of the system to simulated inputs. These tests were performed to verify that the systems would operate sa tisfactorily at power. The alignment of the system was verified at power by programmed step changes and under actual test transient conditions to verify that controlled parameters were within tolerances specified by test procedures.4.Incore monitor systema.Incore thermocouplesDuring heatup and at temperature During heatup and at temperature, the inco re thermocouples were calibrated to the average of the reactor coolant system resistance temperat ure detectors. All readout and temperature-compensatin g equipment was checked during the calibration, and isothermal corrections for the operative th ermocouples were determined.b.Movable detector systemAt ambient conditions, before core loading, and
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing II. Reactor Coolant System (continued)
: 6. Vibration monitoring on            During and after hot          Comprehensive vibration measurements had been made during hot functional Revision 5209/29/2016 reactor internals                  functional testing            testing before core loading for Carolina Power & Light Companys H. B.
Robinson Unit 2. The results of these tests had been documented and submitted to the Directorate of Reactor Licensing. These data were the basis for acceptance of following plants, such as North Anna Units 1 and 2, without repeating these tests. During hot functional testing, the plant was operated with full flow for a minimum of 240 hours in order to achieve approximately 20 million cycles on the internal components. Following hot functional testing, the internals were removed and inspected for vibration effects before core loading.
III. Reactivity Control System
: 1. Chemical and volume      At ambient and/or at        Makeup and letdown operations were conducted with the Chemical and control system          operating conditions.        Volume Control System to check out the difference modes of dilution and System components were boration and verify flows in the different modes.
operationally checked out The adequacy of heat tracing to maintain the highest concentration in solution before fuel loading.        was verified. The ability to adequately sample and the sampling techniques were demonstrated.                                                                                     NAPS UFSAR
: 2. Emergency boron shutdown During hot functional        The pressure/flow characteristics of the emergency boration system were system                  testing                      verified by pumping into the reactor coolant system.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-16


after core loading and critical testingBefore core loading, the installation checkout of the movable detector system was completed. The response of each ch annel was verified using simulated detector inputs. After core loading and insertion of th e thimbles in the core, a dummy cable was used to check indexing and to ensure free passage to all positions and set the limit switches based on data obtained during critical testing. During flux mapping at power, the detector responses to neutron flux were verified.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-18III. Reactivity Contro l System (continued)5.Control rod systema.Rod control systemAmbient conditions, before core loading, and hot conditions after core loadingDuring the installation check of this system, it was energized and operationally checked out with mechanisms connected to each power supply. The ability of the system to step the mechanism was ve rified, the alarm a nd inhibit functions checked out, and correct values of system parameters adjusted to specified values. After core loading, the operation of each rod over its full range of travel was demonstrated.b.Rod drop testsCold and hot plant conditions after core loading At cold and hot plant conditions afte r core loading, the drop times of the full-length rods were measured. The dr op time was measured from the release of the rod until the rod enters the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications.c.Rod position indicationA t ambient conditions and at temperature after core
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing III. Reactivity Control System (continued)
: 3. Automatic reactor power            Preoperational conditions The system alignment was verified at preoperational conditions to demonstrate Revision 5209/29/2016 control system                    (installation checks had      the response of the system to simulated inputs. These tests were performed to been made)                    verify that the systems would operate satisfactorily at power. The alignment of the system was verified at power by programmed step changes and under actual test transient conditions to verify that controlled parameters were within tolerances specified by test procedures.
: 4. Incore monitor system
: a. Incore thermocouples            During heatup and at                During heatup and at temperature, the incore thermocouples were calibrated to temperature                        the average of the reactor coolant system resistance temperature detectors. All readout and temperature-compensating equipment was checked during the calibration, and isothermal corrections for the operative thermocouples were determined.
: b. Movable detector system At ambient conditions,                      Before core loading, the installation checkout of the movable detector system before core loading, and                    was completed. The response of each channel was verified using simulated after core loading and                      detector inputs. After core loading and insertion of the thimbles in the core, a critical testing                            dummy cable was used to check indexing and to ensure free passage to all               NAPS UFSAR positions and set the limit switches based on data obtained during critical testing. During flux mapping at power, the detector responses to neutron flux were verified.
: a. The preoperational test program for the emergency   core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-17


loading During rod control system tests, the ro d position indication system was aligned to provide rod movement indication. Rod setpoints were also adjusted during  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing III. Reactivity Control System (continued)
: 5. Control rod system Revision 5209/29/2016
: a. Rod control system              Ambient conditions,      During the installation check of this system, it was energized and operationally before core loading, and  checked out with mechanisms connected to each power supply. The ability of hot conditions after core the system to step the mechanism was verified, the alarm and inhibit functions loading                  checked out, and correct values of system parameters adjusted to specified values. After core loading, the operation of each rod over its full range of travel was demonstrated.
: b. Rod drop tests                  Cold and hot plant        At cold and hot plant conditions after core loading, the drop times of the conditions after core    full-length rods were measured. The drop time was measured from the release loading                  of the rod until the rod enters the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications.
: c. Rod position indication          At ambient conditions and During rod control system tests, the rod position indication system was aligned at temperature after core to provide rod movement indication. Rod setpoints were also adjusted during loading                  these tests. After plant heatup, individual rod positions were calibrated to within tolerances specified by the test procedure.
NAPS UFSAR
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-18


these tests. After plant heatup, individua l rod positions were calibrated to within tolerances specified by the test procedure.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-19III. Reactivity Contro l System (continued)6.Auxiliary start-up instrumentation testBefore core loadingThree separate temporary source range instruments were installed in the core during core-loading operations. One of these channels served as a spare to the other two channels. During the core lo ading operations, these detectors were relocated at specific loading steps to provide the most meaningful neutron count rate within minimum acceptable le vels, as specified by the core-loading procedures. The response of each channel to a neutron source was verified before core loading.IV. Protection System1.Reactor protection systemBefore core loading (installation checks had been performed)
Table 14.1-1 (continued)
Before core loading, the reactor trip system was tested to demonstrate operability, proper logic, redundancy, coincidence, independence, and safe failure on power loss. The protection cha nnels were verified through to tripping of the reactor trip breakers. The trip time of each reactor protection signal was  
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing III. Reactivity Control System (continued)
: 6. Auxiliary start-up                 Before core loading          Three separate temporary source range instruments were installed in the core Revision 5209/29/2016 instrumentation test                                            during core-loading operations. One of these channels served as a spare to the other two channels. During the core loading operations, these detectors were relocated at specific loading steps to provide the most meaningful neutron count rate within minimum acceptable levels, as specified by the core-loading procedures. The response of each channel to a neutron source was verified before core loading.
IV. Protection System
: 1. Reactor protection system          Before core loading       Before core loading, the reactor trip system was tested to demonstrate (installation checks had  operability, proper logic, redundancy, coincidence, independence, and safe been performed)            failure on power loss. The protection channels were verified through to tripping of the reactor trip breakers. The trip time of each reactor protection signal was also measured from the output of the sensor to tripping of the reactor trip breaker. These times were verified to be less than the values identified in the safety analysis report.
NAPS UFSAR
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-19


also measured from the output of the se nsor to tripping of the reactor trip breaker. These times were verified to be less than the values identified in the safety analysis report.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-20IV. Protection System (continued)2.Engineered safety featuresBefore core loading (installation checks had been performed)
Table 14.1-1 (continued)
Before core loading, the engi neered safety features logi c systems were tested to demonstrate operability, proper logic, redundancy, coincidence, and independence. The protection channels were verified through to actuation of the output relays. The response time of each protection signal was also measured from the output of the sensor to actuation of the output relay. Their times were verified to be less than the values identified in the safety analysis report. Operation of the engineered sa fety features components (i.e., motors, valves, diesel generators) was checked in other tests.V. Power Conversion System1.System testsa.Vibration frequency and amplitude Hot functional testing and  
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing IV. Protection System (continued)
: 2. Engineered safety features        Before core loading           Before core loading, the engineered safety features logic systems were tested to Revision 5209/29/2016 (installation checks had      demonstrate operability, proper logic, redundancy, coincidence, and been performed)              independence. The protection channels were verified through to actuation of the output relays. The response time of each protection signal was also measured from the output of the sensor to actuation of the output relay. Their times were verified to be less than the values identified in the safety analysis report. Operation of the engineered safety features components (i.e., motors, valves, diesel generators) was checked in other tests.
V. Power Conversion System
: 1. System tests
: a. Vibration frequency and         Hot functional testing and When the main turbine was rolled, vibration readings were monitored. (Turbine amplitude                      or plant heatup after initial vibrations were also monitored throughout the power escalation program.)
criticality Major equipment (e.g., feedwater pumps and condensate pumps) was operated as it became available and was observed for indications of excessive vibration.
: b. Expansion and restraint          During heatup, at            During heatup to operating temperature, selected points on the components and NAPS UFSAR temperature, and              piping of the systems were checked at various temperatures to verify that they cooldown before core          could expand unrestricted. After cooldown, these components were verified to loading                      have returned to their approximate cold position.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-20


or plant heatup after initial criticalityWhen the main turbine was rolled, vibration readings were monitored. (Turbine vibrations were also monitored throughout the power escalation program.)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Major equipment (e.g., feedwater pumps and condensate pumps) was operated as it became available and was observed for indications of excessive vibration.b.Expansion and restraintDuring heatup, at temperature, and cooldown before core loading During heatup to operating temperature, selected points on the components and piping of the systems were checked at vari ous temperatures to verify that they could expand unrestricted. After cooldown, these components were verified to have returned to their approximate cold position.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Table 14.1-1 (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-21V. Power Conversion System (continued)2.Components and individual systemsa.Steam generator pressure relief and safety valvesPressure conditionsThe setpoints of safety valves were verified from vendor certification data, by bench tests, or by in-plant tests, set points were checked by using a pressure assist device that adds to the force due to pressure. Once the valve left the seated position, the assist device was vented, allowing the valve to re-seat immediately. Steam relief valve set points were made during instrument alignment and verified by plant transient tests.b.Emergency feedwater (auxiliary) systemBefore initial criticalityDuring hot functional testing before initial criticality, the emergency feedwater system was checked out to verify its ability to feed the steam generators.
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing V. Power Conversion System (continued)
Automatic starting was verified during te sting of the safeguards logic system tests. The auxiliary feedwa ter piping was checked for excessive vibration while starting and stopping the auxiliary feedwater pumps with normal operation of the associated motor-operated and hand-control discharge valves in the auxiliary feedwater system.c.Turbine control and bypass valves Hot functional testing and/or power operation after initial criticalityDuring hot functional testing, the turbine control system was demonstrated in turbine operation up to and including a period of operation at synchronous speed. The turbine bypass valves to the condenser and their associated control  
: 2. Components and individual systems Revision 5209/29/2016
: a. Steam generator pressure Pressure conditions                        The setpoints of safety valves were verified from vendor certification data, by relief and safety valves                                            bench tests, or by in-plant tests, setpoints were checked by using a pressure assist device that adds to the force due to pressure. Once the valve left the seated position, the assist device was vented, allowing the valve to re-seat immediately. Steam relief valve setpoints were made during instrument alignment and verified by plant transient tests.
: b. Emergency feedwater             Before initial criticality          During hot functional testing before initial criticality, the emergency feedwater (auxiliary) system                                                  system was checked out to verify its ability to feed the steam generators.
Automatic starting was verified during testing of the safeguards logic system tests. The auxiliary feedwater piping was checked for excessive vibration while starting and stopping the auxiliary feedwater pumps with normal operation of the associated motor-operated and hand-control discharge valves in the auxiliary feedwater system.
: c. Turbine control and             Hot functional testing             During hot functional testing, the turbine control system was demonstrated in bypass valves                    and/or power operation              turbine operation up to and including a period of operation at synchronous             NAPS UFSAR after initial criticality          speed. The turbine bypass valves to the condenser and their associated control systems were operationally checked out before and during hot functional testing. Other testing on the turbine bypass valves was completed after initial criticality.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-21


systems were operationally checked out before and during hot functional testing. Other testing on the turbine bypa ss valves was comple ted after initial criticality.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-22V. Power Conversion System (continued)d.Feedwater and feedwater control system Before hot functional testing and at power The feedwater and condensate pumps we re operationally checked out before hot functional testing. During power escalation, the power was slowly increased and the ability of the feed water pumps and control system to maintain level in the steam generators was verified. Steam generator level indicators were aligned befo re filling the system, and during fill the system was used to monitor the level in the steam generator. Before start-up, the feedwater-regulating valve control system was calibrated using simulated signals. During start-up when at power the ability of the system to control level within specified tolerances under tr ansient conditions was also verifiede.Condenser circulating waterBefore initial core loading and at powerBefore core loading, the main circulating water pumps and circulating water  
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing V. Power Conversion System (continued)
: d. Feedwater and feedwater Before hot functional         The feedwater and condensate pumps were operationally checked out before Revision 5209/29/2016 control system          testing and at power          hot functional testing. During power escalation, the power was slowly increased and the ability of the feedwater pumps and control system to maintain level in the steam generators was verified. Steam generator level indicators were aligned before filling the system, and during fill the system was used to monitor the level in the steam generator. Before start-up, the feedwater-regulating valve control system was calibrated using simulated signals. During start-up when at power the ability of the system to control level within specified tolerances under transient conditions was also verified
: e. Condenser circulating   Before initial core loading Before core loading, the main circulating water pumps and circulating water water                  and at power                  system valves were tested to verify operability. During unit start-up, acceptable condenser operation was verified in accordance with operating procedures.
: f. Makeup water and        During steam generator        The makeup system to the steam generators was checked out during fill of the chemical treatment      fill, hot functional testing, steam generators during hot functional testing and at power. The chemical systems                and at power                  treatment system was checked out when chemicals were added to the steam generators at heatup and at operating conditions.                                                    NAPS UFSAR
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-22


system valves were tested to verify operability. During unit start-up, acceptable condenser operation was verified in accordance with operating procedures.f.Makeup water and chemical treatment systems During steam generator fill, hot functional testing, and at power The makeup system to the steam generato rs was checked out during fill of the steam generators during hot functional testing and at power. The chemical treatment system was checked out when chemicals were added to the steam generators at heatup and at operating conditions.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-23 VI. Auxiliary Systems1.Reactor coolant system makeup (Chemical and Volume Control System (CVCS))See III, item 1.2.Seal and pump cooling water (CVCS)
Table 14.1-1 (continued)
Before heatup and at temperature Before reactor coolant pump operation and with the system pr essurized, flow to the pump seals and cooling water flow was adjusted to specified values using  
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing VI. Auxiliary Systems
: 1. Reactor coolant system                                              See III, item 1.
Revision 5209/29/2016 makeup (Chemical and Volume Control System (CVCS))
: 2. Seal and pump cooling             Before heatup and at       Before reactor coolant pump operation and with the system pressurized, flow to water (CVCS)                      temperature                the pump seals and cooling water flow was adjusted to specified values using installed instruments. During hot functional testing when at operating temperature and pressure, seal and cooling flows and temperatures were checked.
: 3. Vent and drain system              During initial primary fill Venting of the reactor coolant system was done during initial filling by venting and pressurization and      the reactor vessel head and pressurizer. During hot functional testing and after during hot functional      core loading, the secondary system was vented while pressurizing the testing                    secondary system. Secondary drains were tested for unrestricted flow in accordance with operating procedures.
: 4. Component cooling system          Ambient and/or hot plant            Component cooling flow to the various components in the system was adjusted, conditions                          the system operationally checked out, and setpoints adjusted. Data were taken          NAPS UFSAR to verify that adequate cooling was provided to each cooled component and, when load was available, that temperature limits were being maintained.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-23


installed instruments. During hot f unctional testing when at operating temperature and pressure, seal and c ooling flows and temperatures were checked.3.Vent and drain systemDu ring initial primary fill and pressurization and during hot functional testingVenting of the reactor coolant system was done during initial filling by venting the reactor vessel head and pressurizer. During hot functional testing and after core loading, the secondary system was vented while pressurizing the secondary system. Secondary drains were tested for unrestricted flow in  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing VI. Auxiliary Systems (continued)
: 5. Residual heat removal      Before and during hot        This system was tested by verifying pressure and flow characteristics of the Revision 5209/29/2016 system                    functional testing          pumps and operation of the isolation valves. During cooldown after hot functional testing, the heat removal capability and cooldown rate of the system was demonstrated. The residual heat removal system piping was checked for excessive vibration while starting and stopping the residual heat removal pumps with normal operation of the valve used to control flow.
: 6. Purification system (CVCS) Operating temperature        During hot functional testing with the demineralizers charged with resin, before core loading          operation of the purification system was demonstrated by verification of flow, pressure drops, temperatures, and conditioning of ion-exchange resins (see III, item 1).
: 7. Fire protection system    Before initial core loading The water fire protection system motor and diesel-driven pumps and pressure maintenance equipment were tested to verify proper operation in conformance with fire insurance requirements. The carbon dioxide fire protection system was tested by individual component checks and by puff tests in various fire-protected areas by simulating system initiating conditions. The Halon 1301 fire protection system was checked for operability and proper installation.                            NAPS UFSAR
: 8. Service water system      Before initial core loading The system was operationally checked out to verify pressure and flow. Service water flow was verified to components in the system.
: 9. Auxiliary building        Before initial core loading The system was operated to test for leaks and air flows to the areas supplied ventilation                                            from the system and to verify motor currents and speeds, verify setpoints, and check alarms (see also IX.)
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-24


accordance with operating procedures.4.Component cooling systemAmbient and/or hot plant conditions Component cooling flow to the various components in the system was adjusted, the system operationally checked out, and setpoints adjusted. Data were taken to verify that adequate cooling was provided to each cooled component and, when load was available, that temperature limits were being maintained.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-24 VI. Auxiliary Systems (continued)5.Residual heat removal system Before and during hot functional testing This system was tested by verifying pressure and flow characteristics of the pumps and operation of th e isolation valves. Du ring cooldown after hot functional testing, the heat removal capabi lity and cooldown rate of the system was demonstrated. The resi dual heat removal system piping was checked for excessive vibration while starting a nd stopping the residual heat removal pumps with normal operation of the valve used to control flow.6.Purification system (CVCS)Operating temperature before core loading During hot functional testing with the demineralizers charged with resin, operation of the purification system was demonstrated by verification of flow, pressure drops, temperatures, and conditioning of ion-exchange resins (see III, item 1).7.Fire protection systemBefore initial core loadingThe water fire protection syst em motor and diesel-driven pumps and pressure maintenance equipment were tested to verify proper operation in conformance with fire insurance requirements. The carbon dioxide fire protection system was tested by individual component checks and by puff tests in various fire-protected areas by simulating syst em initiating condi tions. The Halon 1301 fire protection system was checked fo r operability and proper installation.8.Service water systemBefore initial core loadingThe system was operationally checked out to verify pressure and flow. Service water flow was verified to components in the system.9.Auxiliary building ventilationBefore initial core loadingThe system was operated to test for leaks and air flows to the areas supplied from the system and to verify motor cu rrents and speeds, veri fy setpoints, and check alarms (see also IX.)The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
Table 14.1-1 (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-25 VI. Auxiliary Systems (continued)10.Compressed gas system (used for safety-related functions)Before initial core loadingThe instrument air system , including air receivers and compressors, was tested to verify proper operation. A loss-of-i nstrument-air test was conducted by securing the makeup air to each dedicated air accumulator supplying each safety-related component that is re quired to operate following a loss of instrument air. The capacity of each de dicated air accumulator was verified by operating the safety-related component a specified number of times over a specified time interval. Air-operated co mponents were tested to ensure that they fail in the safe mode upon loss of operating pressure. Other compressed gas systems were verified for proper operation.11.Control-rod drive mechanism and rod position indication coil cooling  
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing VI. Auxiliary Systems (continued)
: 10. Compressed gas system       Before initial core loading The instrument air system, including air receivers and compressors, was tested Revision 5209/29/2016 (used for safety-related                                 to verify proper operation. A loss-of-instrument-air test was conducted by functions)                                                securing the makeup air to each dedicated air accumulator supplying each safety-related component that is required to operate following a loss of instrument air. The capacity of each dedicated air accumulator was verified by operating the safety-related component a specified number of times over a specified time interval. Air-operated components were tested to ensure that they fail in the safe mode upon loss of operating pressure. Other compressed gas systems were verified for proper operation.
: 11. Control-rod drive           Before and/or during hot The system was operationally checked out to verify air flow, temperatures, mechanism and rod position functional testing            motor current and speed.
indication coil cooling system
: 12. Neutron shield tank cooling Before initial core loading The system was operationally checked out to verify pump and heat exchanger system                                                    operability.
: 13. Leak detection system        Before and during            Temperature detectors and their alarm functions in the drain lines from (sensitivity and accuracy to preoperational tests        pressurizer safety valves and the reactor vessel head seal were checked.
NAPS UFSAR detect leaks)                                            Pressurizer relief tank level and temperature sensors were calibrated and their associated alarms checked.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-25


system Before and/or during hot functional testing The system was operationally checked out to verify air flow, temperatures, motor current and speed.12.Neutron shield tank cooling systemBefore initial core loadingThe system was operationa lly checked out to verify pump and heat exchanger operability.13.Leak detection system (sensitivity and accuracy to detect leaks)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Before and during preoperational testsTemperature detectors and their alarm functions in the drain lines from pressurizer safety valves and the r eactor vessel head seal were checked.
Table 14.1-1 (continued)
Pressurizer relief tank level and temper ature sensors were calibrated and their associated alarms checked.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing VI. Auxiliary Systems (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-26 VI. Auxiliary Systems (continued)14.Primary sampling systemBefore and/or during hot functional testing Operations were performed to:a.Established purge times.b.Demonstrate that liquid and gas sa mples can be obtained from sample points.c.Demonstrate that valves, instruments and controls function properly.
: 14. Primary sampling system            Before and/or during hot Operations were performed to:
d.Verify proper functioning of the sample cooler.
Revision 5209/29/2016 functional testing            a. Established purge times.
e.Demonstrate that sample vessels ca n be removed and replaced without problems.15.Primary pressure relief system Before hot functional testing and at pressure  
: b. Demonstrate that liquid and gas samples can be obtained from sample points.
: c. Demonstrate that valves, instruments and controls function properly.
: d. Verify proper functioning of the sample cooler.
: e. Demonstrate that sample vessels can be removed and replaced without problems.
: 15. Primary pressure relief           Before hot functional               The pressurizer relief tank, associated valves, and instrumentation were system                            testing and at pressure             checked out to verify performance of design functions. (See II, item 4.3, for conditions                          testing of pressurizer relief and safety valves.)
VII. Electrical Systems
: 1. Normal distribution test    Throughout plant start-up The integrity and operation of these components were verified before being (transformers, motor, relay and before applicable      energized by meggering, hi-pot testing, continuity checks, and operational switches, power supplies    equipment operation        verification of controlling devices as applicable. After being energized, phasing NAPS UFSAR etc.; phasing and meggering                            and voltage regulation tests were performed and channel and train separation where applicable)                                      and redundancy features were verified as applicable.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-26


conditions The pressurizer relief tank, associated valves, and instrumentation were checked out to verify performance of design functions. (See II, item 4.3, for  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing VII. Electrical Systems (continued)
: 2. Vital bus test (full-load test Before initial core loading Verification that the vital bus load could be supplied under normal and Revision 5209/29/2016 using all power sources)                                    power-failure conditions was made. In particular, transfers that take place under loss of power and redundant features function per design were verified.
: 3. Direct current systems        Before core loading          The redundant features of the battery, battery charger, and inverters were (full-load and duration test)                              checked out. The capacity of the battery and voltage regulation was verified.
The recharging of a discharged battery within a specified period was also verified, The ability of each inverter to maintain design output under varying direct current input was also verified.
: 4. Communications systems        Before fuel loading and      To verify proper communications between all onsite stations and (telephone, public address, during power operation          interconnection to commercial telephone service. To balance and adjust intercoms, and evacuation                                  amplifiers and speakers and verify that evacuation alarms could be heard at all signals)                                                    stations throughout the plant. Also, to verify that all temporary communications at the fuel-loading stations and control stations were functioning properly.
: 5. Emergency power systems Before initial core loading The automatic starting and loading of the diesel generators was demonstrated (manual start and                                          under loss of emergency bus alternating current power. The operation of the synchronization, full NAPS UFSAR logic and sequencing of circuit breakers were demonstrated along with the automatic loading tests,                                   proper safety-related bus stripping and separation of non-vital loads. Load under loss of all alternating current voltage)                                            duration tests were demonstrated over several hours of operation along with voltage and frequency regulation tests under transient and steady-state conditions.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-27


testing of pressurizer re lief and safety valves.)VII. Electrical Systems1.Normal distribution test (transformers, motor, relay
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing VIII. Containment Systems
: 1. Reactor containment        Before core loading          A containment structural test was performed. Containment Type A, B, and C Revision 5209/29/2016 leakage tests were performed in accordance with Appendix J to 10 CFR 50.
: 2. Ventilation system          Before and/or during hot The system was operated to balance air flows and to verify ability to maintain functional testing           temperatures below maximum allowable limits.
: 3. Post-accident heat removal Before initial criticality    Tests were performed to verify pump operating characteristics and response to system (containment sprays)                              control signals, sequencing of the pumps, valves, and controllers, and to ensure that spray nozzles were unobstructed. The time required to actuate the system after a containment high-pressure signal is received was verified.
: 4. Containment isolation      Before core loading          The operation of actuation systems and components used for containment isolation was verified.
: 5. Hydrogen removal system Before initial criticality        Operability of flow paths and heaters associated with the recombiners were verified.
IX. Gaseous Radioactivity Removal Systems Filtration system (testing              Before core loading        Testing was performed to verify flows, pressure drops, and effectiveness of performed on particulate filter                                    these systems in performing their function.                                                     NAPS UFSAR system in containment and auxiliary structures for post-accident and routine release of gaseous effluent)
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-28


switches, power supplies
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing X. Emergency Core Cooling Systema
: 1. System tests (expansion and Before and/or during hot Movement of piping that connects to the reactor coolant system was checked Revision 5209/29/2016 restraints, vibration)      functional testing        by the test described in II, item 2. Pumps, motors, and piping were observed for excessive vibration.
: 2. High-pressure safety        Before core loading        This system was operationally tested to adjust pressure/flow values. Tests were injection                                              also conducted to check pump operating characteristics and to verify operation from normal and emergency power sources. More specifically that:
: a. Valves installed for redundant flow paths operated as designed.
: b. Pump operating characteristics were verified and the capability of the high-head safety injection pumps to take suction from the low-head pumps was demonstrated with the reactor coolant systems at ambient conditions.
: c. Valves and pumps operated on operator initiation and/or automatically on initiation of a safety injection signal.
: d. The fail position on loss of power for each remotely operated valve was as specified.
: e. Level and pressure instruments were properly calibrated.                        NAPS UFSAR
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-29


etc.; phasing and meggering where applicable)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Throughout plant start-up
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing X. Emergency Core Cooling Systema (continued)
: 3. Low-pressure safety                Before core loading      The low-head safety injection system was checked to verify design flow, flow Revision 5209/29/2016 injection                                                  paths, and pump operating characteristics. Tests were conducted to verify operation from the normal power source. More specifically, that:
: a. Valves installed for redundant flow paths operated as designed.
: b. Pump operating characteristics were verified with the reactor coolant system at ambient conditions.
: c. Valves and motors operated on operator initiation and/or automatically on initiation of a safety injection signal.
: d. The fail position on loss of power for each remotely operated valve was as specified.
: e. Level and pressure instruments were properly calibrated.
: 4. Accumulator                        Before core loading                Flow through the accumulator discharge lines was initiated to demonstrate that the motor-operated valves stroked properly and the check valves were free to open. Tests were also made to verify that accumulator pressure could be maintained.
NAPS UFSAR
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-30


and before applicable equipment operation The integrity and operation of these co mponents were verified before being energized by meggering, hi-pot testing, continuity checks, and operational verification of controlling devices as applicable. After being energized, phasing and voltage regulation test s were performed and channel and train separation and redundancy features were verified as applicable.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-27 VII. Electrical Systems (continued)2.Vital bus test (full-load test using all power sources)Before initial core loadingVerif ication that the vital bus load could be supplie d under normal and power-failure conditions was made. In particular, transfers that take place under loss of power and redundant features function per design were verified.3.Direct current systems (full-load and duration test)Before core loadingThe redundant features of the battery, battery charger, and inverters were checked out. The capacity of the batter y and voltage regulation was verified. The recharging of a discharged batter y within a specified period was also verified, The ability of each inverter to maintain design output under varying direct current input was also verified.4.Communications systems (telephone, public address, intercoms, and evacuation
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing XI. Fuel Storage and Handling System
: 1. Spent-fuel pit cooling and    Before core loading          Tests were performed to verify operability of the spent-fuel pit cooling pumps; Revision 5209/29/2016 refueling purification                                    operability of the refueling purification pumps; flow through the spent-fuel pit system                                                    heat exchange loops; operation of the skimmer loops; flows through the refueling purification filters and ion exchanger; alarm setpoints; and correct functioning of valves, instruments, and controls.
: 2. Refueling equipment (hand Before storage of new fuel Tests were performed before core loading to demonstrate the functioning of the tools and power equipment, and initial core loading        fuel transfer system and the fuel handling equipment using a dummy assembly, including protective                                      in accordance with design drawings and instruction manuals. The sections that interlocks)                                                involve the spent-fuel facility were checked before the storage of new fuel in the spent-fuel storage pool.
: 3. Operability and leak tests of Before initial core loading During the initial filling of the spent-fuel storage pool, operability and leaking sectionalizing devices in                                  testing of the sectionalizing devices was performed.
fuel storage pool and refueling canal
: 4. Spent fuel storage building Before plant start-up          This is part of the auxiliary building ventilation system (refer to VI, item 1).
ventilation system
: 5. Spent-fuel storage radiation Before plant start-up        Refer to XIII, item 1.
NAPS UFSAR monitoring equipment
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-31


signals)Before fuel loading and during power operationTo verify proper communications between al l onsite stations and interconnection to commercial telephone service. To balance and adjust amplifiers and speakers and verify that evacuation alarms could be heard at all stations throughout the plant. Also , to verify that all temporary communications at the fuel-loading st ations and control stations were functioning properly.5.Emergency power systems (manual start and synchronization, full
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-1 (continued)
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement        Condition/Prerequisite                      Test Objective and Summary of Testing XII. Reactors Components Handling System Reactor components handling          Before use for installation Testing was conducted on the polar crane in accordance with standard crane Revision 5209/29/2016 system (polar crane)                  of components within the testing procedures during the construction of the station.
containment XIII. Radiation Protection System
: 1. Process, criticality, and area Before core loading and    Before core loading, the radiation alarms associated with core loading were monitors                      plant operation            checked out and alarm setpoints were verified. Process and area monitor sensors and channels were calibrated and alarm setpoints made.
: 2. Personnel monitor and         Before core loading and/or Before core loading and required equipment use, instruments were calibrated.
survey instruments            initial criticality        After this initial calibration, the instruments are periodically checked for recalibration.
: 3. Laboratory equipment          Before core loading and    Laboratory equipment was checked to verify equipment performance and initial criticality        calibration. Chemical analyses performed on standard samples. During start-up the equipment received additional verification by normal usage.
: a. The preoperational test program for the emergency  core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
NAPS UFSAR 14.1-32


automatic loading tests, under loss of all alternating current voltage)Before initial core loadingThe automatic starting and loading of the diesel generators was demonstrated under loss of emergency bus alternating current power. The operation of the logic and sequencing of circuit breake rs were demonstrated along with the proper safety-related bus stripping and separation of non-vital loads. Load duration tests were demonstrated ove r several hours of operation along with voltage and frequency regulation te sts under transient and steady-state conditions.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-28 VIII. Containment Systems1.Reactor containmentBefore core loadingA containment stru ctural test was performed. Containment Type A, B, and C leakage tests were performed in acco rdance with Appendix J to 10 CFR 50.2.Ventilation systemBefore and/or during hot functional testing The system was operated to balance air fl ows and to verify ability to maintain temperatures below maximum allowable limits.3.Post-accident heat removal system (containment sprays)
Table 14.1-1 (continued)
Before initial criticalityTests were performed to verify pum p operating characteristics and response to control signals, sequencing of the pumps, valves, and controllers, and to ensure that spray nozzles were unobstructed. The time required to actuate the system after a containment high-pressure signal is received was verified.4.Containment isolationBefore core loadingThe operation of actuation system s and components used for containment isolation was verified.5.Hydrogen removal systemBefore initial criticalityOperability of flow paths and heaters associat ed with the recombiners were verified.IX. Gaseous Radioactivity Removal Systems Filtration system (testing
LIST OF PREOPERATIONAL TESTS Plant Test or Measurement         Condition/Prerequisite                      Test Objective and Summary of Testing XIV. Radioactive Waste System Radioactive waste system              Before initial criticality  Tests were performed to establish the satisfactorily performance of pumps and Revision 5209/29/2016 instruments, leaktightness of piping and equipment, and the operation of packaging and waste reduction equipment; and to verify proper operation of alarms and controls. More specifically, to ensure that:
: a. Manual and automatic valves were operable
: b. Instrument controllers operated properly.
: c. Alarms were operable.
: d. Pumps performed their system function satisfactorily.
: e. The waste gas compressors operated properly.
: f. The gas analyzers operated properly.
: g. The waste evaporator was operational.
: h. The hydrogen and nitrogen supply packages were sufficient for operation of the system.
NAPS UFSAR
: a. The preoperational test program for the emergency   core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
14.1-33


performed on particulate filter system in containment and auxiliary structures for post-accident and routine release of gaseous effluent)Before core loadingTesting was performed to verify flows, pressure drops, and effectiveness of these systems in performing their function.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-29X. Emergency Core Cooling System a1.System tests (expansion and restraints, vibration)
Table 14.1-2 LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading
Before and/or during hot functional testing Movement of piping that connects to th e reactor coolant system was checked by the test described in II, item 2. Pump s, motors, and piping were observed for excessive vibration.2.High-pressure safety injectionBefore core loadingThis system wa s operationally tested to adjust pressure/flow values. Tests were also conducted to check pump operating ch aracteristics and to verify operation from normal and emergency power sources. More specifically that:a.Valves installed for redundant fl ow paths operated as designed.b.Pump operating characteristics were verified and the capability of the high-head safety injection pumps to take suction from the low-head pumps was demonstrated with the reactor coolant systems at ambient conditions.c.Valves and pumps operated on operator initiation and/or automatically on initiation of a safety injection signal.d.The fail position on loss of power for each remotely operated valve was as specified.e.Level and pressure instrume nts were properly calibrated.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
: 1. Mechanical and instrument                  Before initial criticality Operational testing of the rod control systems was conducted to check the Revision 5209/29/2016 tests on control rod drive and                                           controlling features, adjusts setpoints, and verify rod speeds and sequencing rod position indicators                                                  of power to the rod drives. After core loading and installation of the rod mechanisms, tests were conducted to verify operation of the rod drive mechanisms, over their full travel, the latching and releasing features were demonstrated, and calibration of the position indicators was performed over the rod full-range travel per tolerances specified in the test procedure.
Revision 52-09/29/2016 NAPS UFSAR 14.1-30X. Emergency Core Cooling System a (continued)3.Low-pressure safety injectionBefore core loadingThe low-head safety injection system was checked to verify design flow, flow paths, and pump operating characteristics. Tests were conducted to verify operation from the normal power source. More specifically, that:a.Valves installed for redundant fl ow paths operated as designed.b.Pump operating characteristics were verified with the reactor coolant system at ambient conditions.c.Valves and motors operated on oper ator initiation and/or automatically on initiation of a safety injection signal.d.The fail position on loss of power for each remotely operated valve was as specified.e.Level and pressure instrume nts were properly calibrated.4.AccumulatorBefore core loadingFlow through the accumulator discharge lines was initiat ed to demonstrate that the motor-operated valves stroked properl y and the check valves were free to open. Tests were also made to verify that accumulator pressure could be maintained.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
: 2. Reactor trip circuit and                   Before initial criticality Operational testing was conducted to verify the reactor protection circuits in manual trip tests                                                        the various modes of tripping, including manual reactor trip up to the tripping of the reactor trip breakers. After core loading, the release and insertion of each full-length mechanism was demonstrated.
Revision 52-09/29/2016 NAPS UFSAR 14.1-31XI. Fuel Storage and Handling System1.Spent-fuel pit cooling and refueling purification systemBefore core loadingTests were pe rformed to verify operability of the spent-fuel pit cooling pumps; operability of the refueling purificati on pumps; flow through the spent-fuel pit heat exchange loops; operation of the skimmer loops; flows through the refueling purification filters and ion exchanger; alarm setpoints; and correct functioning of valves, instruments, and controls. 2.Refueling equipment (hand tools and power equipment, including protective
: 3. Rod drop measurement cold                  Before initial criticality At cold and hot plant conditions after core loading, the drop times of the and hot at rated flow and no                                            full-length rods were measured. The drop time was measured from the flow                                                                    beginning decay of the stationary gripper coil voltage until the rod entered the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications. Ten additional measurements were made for the fastest and slowest rods.
NAPS UFSAR
: 4. Pressure test of reactor                    Before initial criticality After core loading and installation of the reactor vessel head and torquing of coolant system                                                           the reactor vessel head studs, pressure testing was performed at 100 psi above operating pressure to verify that no leakage occurred past the head and vessel seal.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-34


interlocks)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Before storage of new fuel and initial core loadingTests were performed before core loadi ng to demonstrate the functioning of the fuel transfer system and the fuel ha ndling equipment using a dummy assembly, in accordance with design dr awings and instruction manuals. The sections that involve the spent-fuel facility were chec ked before the storage of new fuel in the spent-fuel storage pool.3.Operability and leak tests of sectionalizing devices in fuel storage pool and
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement          Condition/Prerequisite                  Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading (continued)
: 5. Chemical tests (to establish              Before heatup              Water for reactor coolant system fill and makeup was analyzed for chloride Revision 5209/29/2016 water quality)                                                        content, conductivity, total suspended solids, pH, clarity, and fluorides to requirements specified by the chemistry manual for NSSS. During pre-operational testing, hydrazine was added to scavenge oxygen. After core loading and before exceeding 250°F, hydrogen was added to scavenge oxygen during critical operation. After initially establishing chemistry, analysis was performed to verify requirements.
: 6. Nuclear instrumentation                    Before core loading        Before core loading, the source range channels were aligned and operational calibration and neutron                                                based on data derived from using a neutron source. After a power history had response                                                              been established on the core, the detector anode and discriminator voltages were reset based on obtained data.
: 7. Mechanical and electrical                  Before initial criticality The movable detector systems were checked out in accordance with the tests of incore movable                    and during physics          operating procedures and ICPs. After core loading and insertion of the detectors                                  testing                    detector thimbles, the system was again operationally checked out by ensuring the free passage of detectors into all inserted thimbles. Electrical tests were performed using simulated signals to check out the recorders.
During physics measurements the system was operationally checked and NAPS UFSAR limit switches set based on flux mapping data. Incore thermocouples were checked out during hot functional testing (see Table 14.1-1, III, item 4.a).
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-35


refueling canalBefore initial core loadingDuring th e initial filling of the spent-fuel storage pool, operability and leaking testing of the sectionali zing devices was performed.4.Spent fuel storage building ventilation systemBefore plant start-upThis is part of the auxiliar y building ventilation system (refer to VI, item 1).5.Spent-fuel storage radiation monitoring equipment Before plant start-upRefer to XIII, item 1.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-32 XII. Reactors Components Handling System Reactor components handling system (polar crane)Before use for installation
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading (continued)
: 8. Reactor coolant flow                        Before initial criticality After core loading, measurements were made of elbow tap differential Revision 5209/29/2016 measurement                                                            pressures to make relative comparison. At hot shutdown conditions after core loading, measurements of loop elbow differential pressure drops were made.
Using these data with the reactor coolant pump performance curve, the calculated flow was verified to the design flow. Flow coastdown and transients after reactor coolant pump trips were also determined at shutdown conditions after core loading.
: 9. Pressurizer effectiveness test             At hot shutdown after      At hot no-load temperature and pressure the effectiveness of the pressurizer core loading                heaters in maintaining and increasing system was demonstrated. The heaters were energized and the pressure was compared with an expected pressure rise given in the procedure. The ability of the spray system to reduce pressure was also demonstrated. The spray valves were opened and the pressure decrease compared with the expected pressure decrease given in the procedure.
: 10. Vibration monitoring on                    --                          No vibration monitoring was done after core loading (refer to test identified reactor internals                                                      in Table 14.1-1, II. item 6)
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for NAPS UFSAR a listing of symbols used in these figures.
14.1-36


of components within the  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement          Condition/Prerequisite                  Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests
: 1. Initial criticality                        Plant at hot shutdown        The objective was to bring the reactor critical for the first time from the plant Revision 5209/29/2016 conditions specified. Before the start of rod withdrawal, the nuclear instrumentation had been aligned and checked, and conservative reactor trip setpoints made per the test procedures. All rods were withdrawn except the last controlling bank, which was left partially inserted for control once criticality was achieved by boron dilution. At preselected points in rod withdrawal and boron dilution, data were taken and inverse count rate ratio pots were made to enable extrapolation to the expected critical point.
: 2. Radiation surveys                          At steady-state              Radiation surveys were made during the power escalation to determine dose conditions during power rate levels at preselected points inside containment due to neutron and escalation                    gamma radiation. Instruments used were calibrated to known sources, and the calibration rechecked following the survey.
: 3. Calibration of nuclear                      After start-up and during After initial criticality and during escalation into the intermediate and power instruments with thermal                    escalation                    ranges, data were taken to verify overlap between the source, intermediate, power and determination of                                                and power range channels and to verify the alarm and protective functions.
overlap                                                                  These data were collected until the overlaps were firmly established. During low power escalation, the power range detector currents were monitored and NAPS UFSAR compared with the intermediate range currents to verify response of the power range detectors. The power range nuclear channels were calibrated to reactor thermal output based on measurement of secondary plant feedwater flow, feedwater temperature, and steam pressure.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-37


containmentTesting was conducted on the polar crane in accordance with standard crane testing procedures during the construction of the station.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
XIII. Radiation Protection System1.Process, criticality, and area monitors Before core loading and plant operation Before core loading, the radiation alarms associated with core loading were checked out and alarm setpoints were verified. Process and area monitor sensors and channels were calibr ated and alarm setpoints made.2.Personnel monitor and survey instruments Before core loading and/or initial criticality Before core loading and required equipm ent use, instruments were calibrated.
Table 14.1-2 (continued)
After this initial calibration, the in struments are periodically checked for recalibration.3.Laboratory equipmentBef ore core loading and initial criticalityLaboratory equipment was checked to verify equipment performance and calibration. Chemical analyses performe d on standard samples. During start-up the equipment received additiona l verification by normal usage.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-33XIV. Radioactive Waste SystemRadioactive waste systemBefore initial criticalityTests were performed to establish the satisfactorily performance of pumps and instruments, leaktightness of piping and equipment, and the operation of packaging and waste reduction equipmen t; and to verify proper operation of alarms and controls. More specifically, to ensure that:a.Manual and automatic valves were operableb.Instrument controllers operated properly.c.Alarms were operable.
: 4. Effluent radiation monitors                Before plant start-up        These instruments were calibrated to a known radiation source or to analog Revision 5209/29/2016 (calibration against known                                              signals which had been calibrated to known radiation sources.
d.Pumps performed their system function satisfactorily.e.The waste gas compressors operated properly.f.The gas analyzers operated properly.g.The waste evaporator was operational.h.The hydrogen and nitrogen supply packages were sufficient for operation of the system.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-1 (continued)LIST OF PREOPERATIONAL TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.
concentration)
Revision 52-09/29/2016 NAPS UFSAR 14.1-34The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2  LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of TestingI. Precritical Tests After Fuel Loading1.Mechanical and instrument tests on control rod drive and rod position indicators Before initial criticalityOperational testing of the rod contro l systems was conducted to check the controlling features, adjust s setpoints, and verify rod speeds and sequencing of power to the rod drives. After core loading and installation of the rod mechanisms, tests were conducted to verify operation of the rod drive mechanisms, over their full travel, the latching and releasi ng features were demonstrated, and calibration of the pos ition indicators was performed over the rod full-range travel per toleran ces specified in the test procedure.2.Reactor trip circuit and manual trip tests Before initial criticalityOperational testing was conducted to ve rify the reactor protection circuits in the various modes of tripping, including manual reactor trip up to the tripping of the reactor trip breakers. After core loading, the release and insertion of each full-length mechan ism was demonstrated.3.Rod drop measurement cold and hot at rated flow and no flow Before initial criticality At cold and hot plant conditions afte r core loading, the drop times of the full-length rods were measured. Th e drop time was measured from the beginning decay of the statio nary gripper coil voltage until the rod entered the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications. Ten additional measurements were made for the fastest and slowest rods.4.Pressure test of reactor coolant systemBefore initial criticalityAfter core loading and installation of the re actor vessel head and torquing of the reactor vessel head studs, pressure testing was performed at 100 psi above operating pressure to verify that no leakage occurred past the head and vessel seal.a.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
: 5. Moderator temperature                      Hot zero power                    At normal no-load temperature and no nuclear heating, reactor coolant reactivity coefficient                                                        system cooldown and heatup were accomplished using the steam dump and reactor coolant pumps operation as required. An approximate 5°F change in temperature was initiated, and during these changes the average temperature and reactivity were recorded on an X-Y plotter. From these data the moderator temperature coefficient was determined.
Revision 52-09/29/2016 NAPS UFSAR 14.1-35I. Precritical Tests Afte r Fuel Loading (continued)5.Chemical tests (to establish water quality)Before heatupWater for reactor coolant system fill and makeup was analyzed for chloride content, conductivity, total suspended solids, pH, clarity, and fluorides to requirements specified by the ch emistry manual for NSSS. During pre-operational testing, hydr azine was added to scavenge oxygen. After core loading and before exceeding 250°F, hydrogen was added to scavenge oxygen during critical opera tion. After initially establishing chemistry, analysis was performed to verify requirements.6.Nuclear instrumentation calibration and neutron responseBefore core loadingBefore core loading, the source range channels were aligned and operational based on data derived from using a neutron source.
: 6. Pressure reactivity coefficient --                                            Direct measurements of the pressure coefficient of reactivity were not made, measurements                                                                  since the effects of pressure on reactivity are of second order when compared with other effects.
After a power history had been established on the core, the dete ctor anode and discriminator voltages were reset based on obtained data.7.Mechanical and electrical tests of incore movable
: 7. Control rod reactivity worth              Hot zero power                    Under zero-power conditions at near operating temperature and pressure, the determination of differential                                                nuclear design predictions for rod cluster control assembly (RCCA) group and integral worth and                                                       differential worths were validated. These validations were made from boron verification of worth for                                                    concentration sampling data, RCCA bank positions, and recorder traces of shutdown capability reactivity. From this data the integral RCCA group worths were determined,                                 NAPS UFSAR including verification of rod insertion limits to ensure adequate shutdown margin. The minimum boron concentration for maintaining the reactor shutdown with the most reactive rod cluster control assembly stuck in the full-out position was determined for Unit 1. The determination was made from analysis of boron concentration and RCCS worths.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-38


detectorsBefore initial criticality and during physics testing The movable detector systems were checked out in accordance with the operating procedures and ICPs. After core loading and insertion of the detector thimbles, the system was again operationally checked out by ensuring the free passage of detectors into all inserted thimbles. Electrical tests were performed using simulated signals to check out the recorders.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
During physics measurements the syst em was operationally checked and limit switches set based on flux mappi ng data. Incore thermocouples were checked out during hot functional testing (see Table 14.1-1, III, item 4.a).The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2 (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
Table 14.1-2 (continued)
Revision 52-09/29/2016 NAPS UFSAR 14.1-36I. Precritical Tests Afte r Fuel Loading (continued)8.Reactor coolant flow measurement Before initial criticalityAfter core loading, measurements were made of elbow tap differential pressures to make relative comparison. At hot shutdo wn conditions after core loading, measurements of loop elbow differential pressure drops were made.
LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests (continued)
Using these data with the reactor coolant pump performance curve, the calculated flow was verified to the design flow. Flow coastdown and transients after reactor coolant pump trips were also determined at shutdown conditions after core loading.9.Pressurizer effectiveness testAt hot shutdown after core loading At hot no-load temperature and pressure the effectiveness of the pressurizer heaters in maintaining and increasing system was demonstrated. The heaters were energized and the pressure was compared with an expected pressure rise given in the procedure. The ability of the spray system to reduce pressure was also demonstrated. The spra y valves were opened and the pressure decrease compared with the expected pressure decrease given in the procedure.10.Vibration monitoring on reactor internals--No vibration monitoring was done after co re loading (refer to test identified in Table 14.1-1, II. item 6)The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-(continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
: 8. Boron reactivity worth                      Zero power                  Differential boron worth measurements were made by monotonically Revision 5209/29/2016 measurement                                                              increasing or decreasing reactor coolant boron concentration. Compensation for the reactivity effect of the boron concentration change was made by withdrawing or inserting respective control rods to maintain moderator average temperature and power level constant and observing the resultant accumulated change in core reactivity corresponding to these successive rod movements.
Revision 52-09/29/2016 NAPS UFSAR 14.1-37II. Initial Criticality and Low-Power Tests1.Initial criticalityPlant at hot shutdownThe objective was to bring the reactor critical for the first time from the plant conditions specified. Before the star t of rod withdrawal, the nuclear instrumentation had been aligned and ch ecked, and conservative reactor trip setpoints made per the test procedures. All rods were withdrawn except the last controlling bank, which was left partially inserted for control once criticality was achieved by boron dilu tion. At preselected points in rod withdrawal and boron dilution, data were taken and inverse count rate ratio pots were made to enable extrapolat ion to the expected critical point.2.Radiation surveysAt steady-state conditions during power escalation Radiation surveys were made during th e power escalation to determine dose rate levels at preselected points in side containment due to neutron and gamma radiation. Instrument s used were calibrated to known sources, and the calibration rechecked following the survey.3.Calibration of nuclear instruments with thermal power and determination of
: 9. Determination of boron                      Zero power                  These determinations are described under II, item 1 above.
concentration of initial criticality and reactivity allocation
: 10. Flux distribution                Zero power                                  Flux distribution measurements with normal rod patterns were taken during measurement with normal rod                                                  the zero-power physics tests.
patterns
: 11. Chemical tests to demonstrate Before criticality and                          Before criticality, the procedures and equipment for performing chemical ability to control water quality during power escalation                      analyses of primary and secondary systems were demonstrated. During power escalation, sampling was performed and analysis done to verify that                                  NAPS UFSAR plant chemistry was within specifications.
: 12. Pseudo-rod-ejection test, to               Zero power                        Incore measurements were made for Unit 1 under pseudo-ejected-rod verify safety analysis (hot)                                                 conditions simulating the zero-power accident to determine the hot-channel factors and verify that they were within assumptions made in the accident analysis.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-39


overlap After start-up and during escalationAfter initial criticality and during escalation into the intermediate and power ranges, data were taken to verify ov erlap between the source, intermediate, and power range channels and to verify the alarm and protective functions.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
These data were collected until the overl aps were firmly established. During low power escalation, the power range de tector currents were monitored and compared with the intermediate range currents to verify response of the power range detectors. The power range nuclear channels were calibrated to
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement          Condition/Prerequisite                  Test Objective and Summary of Testing III. Power Ascension Tests
: 1. Natural circulation test to    --                      The ability of natural circulation to remove decay heat has been demonstrated Revision 5209/29/2016 confirm sufficient cooling                              at the Carolina Power & Light Companys H. B. Robinson Unit 2. Tests have capacity                                                shown natural circulation flow to be more than adequate to remove decay heat, and such a test was not repeated on North Anna Unit 1. However, special tests were conducted for Unit 2, as described in Section 14.1.4.
: 2. Power reactivity coefficient  During power escalation During each power escalation for Unit 1, recorder traces were made of evaluation and power defect                            reactor power and reactivity changes. From these traces, the power measurements (30, 50, 75 and                           coefficient of reactivity and power defects were determined.
100%)
: 3. Plant response to load swings, During power escalation Plant response to the following load changes was demonstrated:
including automatic control                                a. +/-10% step load change from 30, 75 and 100% power.
system checkout (30, 50, 75 and 100%)                                                  b. 50% load reduction from 75 and 100% power.
: c. Plant trip from 100% power level.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
NAPS UFSAR 14.1-40


reactor thermal output based on measur ement of secondary plant feedwater flow, feedwater temperatur e, and steam pressure.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2 (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-38II. Initial Criticality and Low-Power Tests (continued)4.Effluent radiation monitors (calibration against known concentration)Before plant start-upThese instruments were calibrated to a known radiation source or to analog signals which had been calibra ted to known radiation sources.5.Moderator temperature reactivity coefficientHot zero powerAt normal no-lo ad temperature and no nuclear heating, reactor coolant system cooldown and heatup were acco mplished using the steam dump and reactor coolant pumps opera tion as required. An approximate 5°F change in temperature was initiated, and during these changes the average temperature and reactivity were recorded on an X-Y plotter. From these data the moderator temperature coefficient was determined.6.Pressure reactivity coefficient measurements--Direct measurements of the pressure coefficient of reactivity were not made, since the effects of pressu re on reactivity are of s econd order when compared with other effects.7.Control rod reactivity worth determination of differential and integral worth and
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing III. Power Ascension Tests (continued)
The data collected from the performance of these tests were analyzed for Revision 5209/29/2016 control system behavior and requirements for realignment. Acceptance criteria, such as the plant not tripping (where applicable), relief and safety valves not lifting, and steam dump operating correctly, were identified in the individual procedures. At approximately 30% power, the automatic control systems were checked by initiating a perturbation and observing controller response. During the transient tests these systems were operationally checked under actual design load changing conditions.
: 4. Chemical analysis (30, 50, 75, During power escalation During low-power physics tests and at 30, 50, 75, and 100% power, samples 100%)                                                    of reactor coolant were taken and analysis performed to verify that coolant chemistry requirements could be maintained.
: 5. Effluents and effluent        During power escalation Installed effluent monitors were operated continuously at selected locations monitoring systems (30, 50,                              in the plant to monitor for radioactive constituents in the effluents.
75, 100%)                                                Instruments detected any changes in activity and alerted the operator when radiochemical analysis should be performed
: 6. Evaluation of core            During power escalation At steady-state power points, incore data were obtained and analysis performance (30, 50, 75,                                  performed to verify that the core performance margins were within design NAPS UFSAR 100%)                                                    predictions, for expected normal and abnormal rod configurations.
: 7. Loss of flow                  Before criticality        Reactor coolant system response to loss of flow for various combinations of pump trips was determined from hot shutdown conditions.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-41


verification of worth for  
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement          Condition/Prerequisite                  Test Objective and Summary of Testing III. Power Ascension Tests (continued)
: 8. Turbine trip      (100%)a                  At power                  This test verified that the pressurizer safety valves did not lift and that the Revision 5209/29/2016 plant could be maintained in a hot shutdown condition. The turbine trip from 100% power was conducted as an integral part of the generator trip from 100% power.
: 9. Generator trip (100%)a                      At power                  Generator trip was performed at 100% power to verify the plants capability of withstanding an instantaneous reduction in load from 100 to 0%. A generator trip was initiated by manually opening the main generator breakers.
This would be automatically initiate a turbine trip.
: 10. Shutdown from outside the                  Greater than or equal to The ability to bring the plant to and maintain the plant in hot shutdown control room                              10% generator power      conditions after a trip from greater than or equal to 10% power was demonstrated using instrumentation and controls outside the control room.
: 11. Loss of offsite power                      Greater than or equal to Tests were performed in which loss of voltage was simulated. Starting of the 10% generator power      diesels and connecting of the emergency loads on the emergency bus was demonstrated.
: 12. Radiation surveys and                      At power                  The surveys to determine the effectiveness of the shielding have been shielding effectiveness (50                                          discussed under Radiation Survey (Item II.2). These surveys were conducted and 100%)                                                            up to and including 100% power.
NAPS UFSAR
: 13. Part-length rod                            Approximately 75%        Technical Specifications required part-length rods for Unit 1 to remain fully insertion/withdrawal (75%)                power                    withdrawn; therefore no testing was performed. No part-length rods were installed in Unit 2.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-42


shutdown capabilityHot zero powerUnder zero-power conditions at near operating te mperature and pressure, the nuclear design predictions for rod cl uster control assembly (RCCA) group differential worths were validated. These validati ons were made from boron concentration sampling data, RCCA bank positions, and recorder traces of reactivity. From this data the integr al RCCA group worths were determined, including verification of rod insertion limits to ensure adequate shutdown margin. The minimum boron concentration for maintaining the reactor shutdown with the most r eactive rod cluster control assembly stuck in the full-out position was determined for Unit 1. The determination was made from analysis of boron concentration and RCCS worths.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2 (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Revision 52-09/29/2016 NAPS UFSAR 14.1-39II. Initial Criticality and Low-Power Tests (continued)8.Boron reactivity worth measurementZero powerDifferential boron worth meas urements were made by monotonically increasing or decreasing reactor c oolant boron concentration. Compensation for the reactivity effect of the boron concentration ch ange was made by withdrawing or inserting respective c ontrol rods to maintain moderator average temperature and power level constant and observing the resultant accumulated change in core reactiv ity corresponding to these successive rod movements.9.Determination of boron concentration of initial criticality and reactivity
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement           Condition/Prerequisite                  Test Objective and Summary of Testing III. Power Ascension Tests (continued)
: 14. Dropped rod-effectiveness of Greater than or equal to Automatic turbine runback and rod withdrawal stop is not necessary as a Revision 5209/29/2016 instruments to detect dropped 50% reactor power        result of a dropped rod, and the circuitry required for such action does not rod and verification of                                exist in this plant. Rod drop tests based on common failure criteria were associated automatic action                            performed dynamically to demonstrate the negative rate trip function from greater than or equal to 50% reactor power.
: 15. Vibration measurements on      --                      These measurements were not performed at power. Refer to II, item 6, above reactor internals (30, 50, 75,                        for measurements before operation.
and 100%)
: 16. Pseudo-rod-ejection test to    30% power              Incore measurements were made for Unit 1 with individual rods withdrawn verify safety analysis                                out of bank position to determine the resulting hot-channel factors and verify that they are within expected limits. These determinations were made from movable detector and thermocouple data. This measurement was not performed on Unit 2 because of the negligible worth of a control rod withdrawn from its full-power insertion limit, and the large magnitude of margin remaining to hot-channel factor limits in the ejected-rod configuration (see Section 14.1.3). This was verified by the test performed for Unit 1.
: 17. Evaluation of flux asymmetry 50% power                Incore flux measurements were made with a single rod assembly moving                                                              NAPS UFSAR partially below bank position and fully inserted to demonstrate that core limits are not exceeded.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
14.1-43


allocationZero powerThese determinations are described under II, item 1 above.10.Flux distribution measurement with normal rod
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Table 14.1-2 (continued)
LISTS OF START-UP TESTS Plant Test or Measurement          Condition/Prerequisite                  Test Objective and Summary of Testing III. Power Ascension Tests (continued)
: 18. Process computer (30, 50,                During power escalation When available during power escalation, the process computer was checked Revision 5209/29/2016 100%)                                                              out and comparisons made between process signals and those assessed by the process computer. (No safety-related functions are performed by the computer.)
: 19. Moisture carryover                        At power                Radioactive tracer of sodium-24 was injected into the steam generators.
measurement                                                        Samples obtained from the steam generator upper shell, main steam line taps, and the feedwater system were analyzed.
: a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
NAPS UFSAR 14.1-44


patterns Zero power Flux distribution measurements with normal rod patterns were taken during the zero-power physics tests. 11.Chemical tests to demonstrate ability to control water quality Before criticality and during power escalationBefore criticality, the procedures and equipment for performing chemical analyses of primary and secondary systems were demonstrated. During power escalation, sampling was performed and analysis done to verify that plant chemistry was within specifications.12.Pseudo-rod-ejection test, to verify safety analysis (hot)
Revision 5209/29/2016                                  NAPS UFSAR                      14.1-45 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Zero power Incore measurements were made for Unit 1 under pseudo-ejected-rod conditions simulating the zero-power accident to determine the hot-channel factors and verify that they were with in assumptions made in the accident analysis.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2 (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
Table 14.1-3 UNIT 2 START-UP PHYSICS TESTS I. Hot Zero Power Tests
Revision 52-09/29/2016 NAPS UFSAR 14.1-40III. Power Ascension Tests1.Natural circulation test to confirm sufficient cooling capacity--The ability of natural circ ulation to remove decay he at has been demonstrated at the Carolina Power & Light Company's H. B. Robinson Unit 2. Tests have shown natural circulation flow to be more than adequate to remove decay heat, and such a test was not repeated on North Anna Unit 1. However, special tests were conducted for Unit 2, as described in Section 14.1.4.2.Power reactivity coefficient evaluation and power defect measurements (30, 50, 75 and
: 1. Reactivity computer checkout.
: 2. Isothermal temperature coefficient at ARO and D bank in (also D, C banks in if MTC for D bank in is greater than or equal to 0 pcm/°F).
: 3. Boron endpoints at ARO; D bank in; D, C banks in; D, C, B banks in; D, C, B, A banks in; shutdown bank B in with all other rods out; and shutdown bank A in with all other rods out.
: 4. Reactivity worths of all control and shutdown rod banks.
: 5. Boron worth over the range of control banks A through D moving during rod insertion and withdrawal.
: 6. Power distribution measurements for ARO and D bank in.
II. Power Ascension Tests
: 1. 30% power flux map.
: 2. 50% power flux map.
: 3. Pseudo-dropped-rod test (RCCA D-10) and associated power distribution measurements at 50% power.
: 4. Incore/ex-core detector calibration flux maps at 75% power.
: 5. APDMS flux maps at or below 95% power.
: 6. Flux maps at 90% and 100% power (equilibrium conditions).


100%)During power escalationDuring each power escalati on for Unit 1, recorder traces were made of reactor power and reactivity change
Revision 5209/29/2016                                  NAPS UFSAR                      14.1-46 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
: s. From these traces, the power coefficient of reactivity and power defects were determined.3.Plant response to load swings, including automatic control system checkout (30, 50, 75
Table 14.1-4 PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 I. Hot Zero Power Tests
: 1. Isothermal temperature coefficient at D, C banks in; D, C, B banks in; and D, C, B, A banks in.
: 2. Boron endpoint for the N-1 rods-in configuration.
: 3. Reactivity worth of N-1 rods.
: 4. Pseudo-rod-ejection and associated power distribution measurements.
II. Power Ascension
: 1. Pseudo-rod-ejection and associated power distribution measurement at 30% power.
: 2. Pseudo-dropped-rod test (RCCA H-6) and associated power distribution measurement.
: 3. Power coefficients.
: 4. Integral power defect.
: 5. Doppler-only power coefficients.


and 100%)During power escalationPlant response to the following load changes was demonstrated:
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
a.+/-10% step load change from 30, 75 and 100% power.b.50% load reduction from 75 and 100% power.c.Plant trip from 100% power level.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2  (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
Table 14.1-5
Revision 52-09/29/2016 NAPS UFSAR 14.1-41III. Power Ascension Tests (continued)
The data collected from the performanc e of these tests were analyzed for control system behavior and requirements for realignment. Acceptance criteria, such as the plant not tripping (where applicable), relief and safety valves not lifting, and steam dump operating correctly, were identified in the individual procedures. At approximately 30% power, the automatic control systems were checked by initiating a perturbation and observing controller response. During the transi ent tests these systems we re operationally checked under actual design load changing conditions.4.Chemical analysis (30, 50, 75, 100%)During power escalationDuring low-power physics tests and at 30, 50, 75, and 100% power, samples of reactor coolant were taken and analys is performed to verify that coolant chemistry requirements could be maintained.5.Effluents and effluent monitoring systems (30, 50, 75, 100%)During power escalationInstalled effluent monitors were operated c ontinuously at selected locations in the plant to monitor for radioactive constituents in the effluents.
Instruments detected any changes in ac tivity and alerted the operator when radiochemical analysis should be performed6.Evaluation of core performance (30, 50, 75, 100%)During power escalationAt steady-state power points, incore data were obtained and analysis performed to verify that the core performance margins were within design predictions, for expected normal and abnormal rod configurations.7.Loss of flowBefore criticalityReact or coolant system response to loss of flow for various combinations of pump trips was determined fr om hot shutdown conditions.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2  (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
Revision 52-09/29/2016 NAPS UFSAR 14.1-42III. Power Ascension Tests (continued)8.Turbine trip (100%)
a At powerThis test verified that the pressurizer safety valves did not lift and that the plant could be maintained in a hot s hutdown condition. The turbine trip from 100% power was conducted as an integral part of the generator trip from 100% power.9.Generator trip (100%)
a At power Generator trip was performed at 100% power to verify the plant's capability of withstanding an instantaneous re duction in load from 100 to 0%. A generator trip was initiated by manual ly opening the main generator breakers. This would be automatically initiate a turbine trip.10. Shutdown from outside the control room Greater than or equal to


10% generator power The ability to bring the plant to a nd maintain the plant in hot shutdown conditions after a trip from greater than or equal to 10% power was demonstrated using instrumentation an d controls outside the control room.11. Loss of offsite powerGreater than or equal to 10% generator powerTests were performed in which loss of voltage was simulated. Starting of the diesels and connecting of the emergency loads on the emergency bus was
==SUMMARY==
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured      life (BOL),          Design          Accident Analysis Revision 5209/29/2016 Test Description    Core Condition        Parameter            Value        Best Estimate)      Tolerance                Criterion
: 1. Isothermal      Banks D, C in                T          -7.86 pcm/°F      -8.9 pcm/°F      +/-3 pcm/°F              -2.107 pcm/°F temperature    Banks D, C, B in            T          -13.48 pcm/°F      -14.1 pcm/°F      +/-3 pcm/°F              -2.134 pcm/°F coefficient    Banks D, C, B,              T          -14.07 pcm/°F      -13.8 pcm/°F      +/-3 pcm/°F              -2.135 pcm/°F A in
: 2. Boron          N-1 rods inserted          CB              601 ppm            580 ppm          +/-50 ppm              x CB  24000 endpoint                                                                                                              pcm where =
11.08 pcm/ppm
: 3. Rod worth      N-1 rods                  IN-1 a             8015            7893 pcm          +/-789 pcm            (IN-1)/1.04  5780 pcm
: 4. Pseudo-        hot zero power              FQ              6.85              10.8              NA                      13.0 ejected        (HZP), Bank C at control rod    120 steps, Bank D          IB-8 a           443 pcm            464 pcm          +/-46 pcm              (IB-8) x 1.04 at 0 steps, RCCA                                                                                        785 pcm B-8 at 228 steps.                                                                                                        NAPS UFSAR 30% power, Bank              FQ                2.1                2.1              NA                      7.07 D at 194 steps, RCCA B-8 at 228            IB-8            3 pcm              7 pcm          +/-1 pcm b              (IB-8) x 1.04 steps.                                                                                                   200 pcm N
: 5. Pseudo-        50% power,                  F                1.62              1.70              NA                      1.69 c dropped                                        H RCCA H-6 control rod                                IH-6 a          138 pcm            146 pcm          +/-22 pcm              (IH-6) x 1.04 250 pcm        14.1-47


demonstrated.12. Radiation surveys and shielding effectiveness (50 and 100%)At powerThe surveys to determine the effe ctiveness of the shielding have been discussed under Radiation Survey (Item II.2). These surveys were conducted up to and including 100% power.13. Part-length rod insertion/withdrawal (75%)
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Approximately 75%
Table 14.1-5 (continued)
powerTechnical Specifications re quired part-length rods for Unit 1 to remain fully withdrawn; therefore no testing was performed. No part-length rods were installed in Unit 2.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-(continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
Revision 52-09/29/2016 NAPS UFSAR 14.1-43III. Power Ascension Tests (continued)14. Dropped rod-effectiveness of instruments to detect dropped rod and verification of


associated automatic action Greater than or equal to 50% reactor power Automatic turbine runback and rod wit hdrawal stop is not necessary as a result of a dropped rod, and the circui try required for such action does not exist in this plant. Rod drop tests based on common failure criteria were performed dynamically to de monstrate the negative rate trip function from greater than or equal to 50% reactor power.15. Vibration measurements on reactor internals (30, 50, 75, and 100%)--These measurements were not performed at power. Refer to II, item 6, above for measurements before operation.16.Pseudo-rod-ejection test to verify safety analysis30% powerIncore measurements were made for Unit 1 with individual rods withdrawn out of bank position to determine the resulting hot-channel factors and verify that they are within expected limits. These determinations were made from movable detector and thermocouple data. This measurement was not performed on Unit 2 because of the negligible worth of a control rod withdrawn from its full-power insertion limit, and the large magnitude of margin remaining to hot-channel factor limits in the ejecte d-rod configuration (see Section 14.1.3). This was verified by the test performed for Unit 1.17.Evaluation of flux asymmetry50% power Incore flux measurements were made with a single rod assembly moving partially below bank position and fully inserted to demonstrate that core limits are not exceeded.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-2  (continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
==SUMMARY==
Revision 52-09/29/2016 NAPS UFSAR 14.1-44III. Power Ascension Tests (continued)18.Process computer (30, 50, 100%)During power escalationWhen ava ilable during power escalation, the process co mputer was checked out and comparisons made between process signals a nd those assessed by the process computer. (No safety-relat ed functions are performed by the computer.)19.Moisture carryover measurementAt powerRadioactive tracer of sodium-24 was injected into the steam generators.
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured      life (BOL),        Design            Accident Analysis Revision 5209/29/2016 Test Description    Core Condition        Parameter            Value        Best Estimate)      Tolerance              Criterion
Samples obtained from the steam generato r upper shell, main steam line taps, and the feedwater system were analyzed.The following information is HISTORICAL and is not intende d or expected to be updated for the life of the plant.Table 14.1-(continued)LISTS OF START-UP TESTSTest or Measurement Plant Condition/PrerequisiteTest Objective and Summary of Testinga.Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all avai lable setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.
: 6. Power         30% power              (  Q ) power     -15.24 pcm/%  -14.02 pcm/%      +/-4.57 pcm/%              NA coefficient                                                      power          power            power 50% power              (   Q ) power    -12.74 pcm/-13.75 pcm/%      +/-3.82 pcm/%               NA power          power           power 75% power               (   Q ) power     -13.57 pcm/%   -13.39 pcm/%      +/-4.07 pcm/%               NA power         power            power 90% power               (   Q ) power    -10.70 pcm/%  -13.31 pcm/%      +/-3.21 pcm/%              NA power          power            power
Revision 52-09/29/2016 NAPS UFSAR 14.1-45 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.Table 14.1-3UNIT 2 START-UP PHYSICS TESTSI. Hot Zero Power Tests1.Reactivity computer checkout.
: 7. Power defect  0 - 100% power        Reactivity worth         1270 pcm      1299 pcm        +/-191 pcm                  NA
2.Isothermal temperature coefficient at ARO an d D bank in (also D, C banks in if MTC for D bank in is greater than or equal to 0 pcm/°F).3.Boron endpoints at ARO; D bank in; D, C banks in; D, C, B banks in; D, C, B, A banks in; shutdown bank B in with all ot her rods out; and shut down bank A in with all other rods out.4.Reactivity worths of all control and shutdown rod banks.
: 8. Doppler-only  30% power                                    -13.62 pcm/%  -11.35 pcm/%      +/-4.09 pcm/%       Inferred value power                                 (   Q ) inferred Doppler        power          power            power         +/-30% uncertainty coefficient                                                                                                    must overlap allowance range of Figure 15.1-3 NAPS UFSAR 50% power             (  Q ) inferred Doppler
5.Boron worth over the range of control banks A through D moving during rod insertion and withdrawal.6.Power distribution measurem ents for ARO and D bank in.II. Power Ascension Tests 1.30% power flux map.
                                                                -10.77 pcm/%  -10.75 pcm/%      +/-3.23 pcm/%      Inferred value power          power            power          +/-30% uncertainty must overlap allowance range of Figure 15.1-3 14.1-48
2.50% power flux map.
 
3.Pseudo-dropped-rod test (RCCA D-10) and associated power di stribution measurements at 50% power.
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
4.Incore/ex-core detector calib ration flux maps at 75% power.
Table 14.1-5 (continued)
5.APDMS flux maps at or below 95% power.6.Flux maps at 90% and 100%
power (equilibrium conditions).
Revision 52-09/29/2016 NAPS UFSAR 14.1-46 The following information is HIST ORICAL and is not intended or expected to be updated for the life of the plant.
T able 14.1-4PHYSICS TESTS THAT HAV E BEEN DELETED FOR UNIT 2I. Hot Zero Power Tests1.Isothermal temperature coefficient at D, C banks in; D, C, B banks in; and D, C, B, A banks in.2.Boron endpoint for the N-1 rods-in configuration.3.Reactivity worth of N-1 rods.
4.Pseudo-rod-ejection and associated power distribution measurements.
II. Power Ascension 1.Pseudo-rod-ejection and associated power distribution measurement at 30% power.
2.Pseudo-dropped-rod test (RCCA H-6) and as sociated power distribution measurement.3.Power coefficients.
4.Integral power defect.
5.Doppler-only power coefficients.
Revision 52-09/29/2016 NAPS UFSAR 14.1-47The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.Table 14.1-5


==SUMMARY==
==SUMMARY==
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE,AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2Test DescriptionCore ConditionParameterUnit 1 Measured ValueDesign Value (beginning of life (BOL), Best Estimate)
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured      life (BOL),         Design            Accident Analysis Revision 5209/29/2016 Test Description    Core Condition        Parameter            Value        Best Estimate)       Tolerance              Criterion
Design Tolerance Accident Analysis Criterion1.Isothermal temperature coefficient Banks D, C in  
: 8. Doppler-only        75% power                      (  Q ) inferred Doppler
                                                                                  -11.08 pcm/%              -9.96 pcm/%  +/-3.32 pcm/%  Inferred value power                                                                              power                    power        power      +/-30% uncertainty coefficient                                                                                                                          must overlap (continued)                                                                                                                          allowance range of Figure 15.1-3 90% power                      (  Q ) inferred Doppler
                                                                                    -7.59 pcm/%              -9.38 pcm/%  +/-2.28 pcm/%  All inferred values power                    power        power      fell within range of Figure 15.1-3, as shown on Figure 14.1-3
: a. IN-1 = integrated reactivity worth of all control rods except the most reactive rod (N-1).
IB-8 = integrated reactivity worth of rod cluster control assembly (RCCA) B-8.
IH-6 = integrated reactivity worth of RCCA H-6.
: b. Violation of design tolerance was evaluated to be insignificant due to low value of reactivity worth.
NAPS UFSAR
: c. Accident analysis referenced to hot full power.
14.1-49
 
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Figure 14.1-1 TYPICAL PRE-OPERATIONAL TEST SEQUENCE Revision 5209/29/2016 NAPS UFSAR 14.1-50
 
The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Figure 14.1-2 TYPICAL START-UP TEST SEQUENCE Revision 5209/29/2016 NAPS UFSAR 14.1-51
 
Revision 5209/29/2016                                NAPS UFSAR                    14.1-52 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Figure 14.1-3 CYCLE 1 BOL PHYSICS TEST DOPPLER POWER COEFFICIENT USED IN ACCIDENT ANALYSIS UNIT 1
 
Revision 5209/29/2016                                      NAPS UFSAR                        14.2-1 14.2  AUGMENTATION OF VEPCOS STAFF FOR INITIAL TEST AND OPERATION The start-up organization used during the period of initial operation consisted of all personnel in the Station Operations Department, with additional support provided by the Engineering Services Department and the Chemistry and Health Physics Department.
In operations, there were, for one-unit operation, five senior licensed shift supervisors, five licensed control room operators, and a combined group of 14 assistant control room operators and auxiliary operators with a minimum of two licensed assistant control room operators. For two-unit operations, there were five senior licensed shift supervisors, five senior licensed assistant shift supervisors, 10 licensed control room operators, and a combined group of 18 assistant control room operators and auxiliary operators with a minimum of six licensed assistant control room operators. Shifts were scheduled to ensure that a minimum of three licensed reactor operators and two licensed senior reactor operators are on duty at all times during two-unit operations.
Technical support was provided during start-up using the services of graduate-level engineers. A trained power engineer was assigned through the architect-engineer to assist in preliminary operations for both units. In addition, engineering representatives were assigned at the station by the supplier of the nuclear steam supply system to render start-up support.
VEPCO had overall responsibility during plant start-up, including precriticality tests, approach to criticality, and postcriticality operations. The station staff was assisted by the architect-engineer and the supplier of the nuclear steam supply system. The Stone & Webster start-up engineer was assigned to the station from the start of flushing operations through commercial operation. The start-up engineer reported directly to the Station Manager and received instructions from him.
Experienced Westinghouse reactor engineers were also assigned to the station for fuel loading, initial criticality, and physics testing. These reactor engineers were qualified and knowledgeable in reactor operations.
They reported directly to the VEPCO reactor engineers and received instructions from them. The Westinghouse reactor engineers acted in an advisory capacity only; VEPCO retained responsibility for, and control of, the unit. Reactor specialists (e.g., control engineers) were available and utilized as required.


Banks D, C, B in
Revision 5209/29/2016                  NAPS UFSAR 14.2-2 Intentionally Blank


Banks D, C, B, A inTTT -7.86 pcm/°F
Revision 5209/29/2016                        NAPS UFSAR      14A-i Appendix 14A NRC Questions and VEPCOs Responses Regarding the North Anna Power Station Unit 2 Modified Startup Physics Testing Program
-13.48 pcm/°F
-14.07 pcm/°F
-8.9 pcm/°F
-14.1 pcm/°F


-13.8 pcm/°F
Revision 5209/29/2016                  NAPS UFSAR 14A-ii Intentionally Blank
+/-3 pcm/°F+/-3 pcm/°F+/-3 pcm/°F -2.107 pcm/°F -2.134 pcm/°F -2.135 pcm/°F2.Boron endpointN-1 rods insertedC B601 ppm580 ppm
+/-50 ppm x C B  24000 pcm where =  11.08 pcm/ppm3.Rod worthN-1 rodsI N-1 a80157893 pcm
+/-789 pcm(IN-1)/1.04 5780 pcm4.Pseudo- ejected control rod hot zero power (HZP), Bank C at


120 steps, Bank D at 0 steps, RCCA B-8 at 228 steps.
Revision 5209/29/2016                                      NAPS UFSAR                        14A-1 APPENDIX 14A NRC QUESTIONS AND VEPCOS RESPONSES REGARDING THE NORTH ANNA POWER STATION UNIT 2 MODIFIED STARTUP PHYSICS TESTING PROGRAM Question 1 With respect to Item B.3 on Table 14.1-3 and Item B.2 on Table 14.1-4, what is the reason for performing the pseudo-dropped-rod test with RCCA D-10 instead of RCCA H-6?
F Q I B-8 a 6.85 443 pcm 10.8 464 pcm NA+/-46 pcm 13.0 (I B-8) x 1.04785 pcm30% power, Bank


D at 194 steps, RCCA B-8 at 228 steps.F Q I B-8 2.1 3 pcm 2.1 7 pcm NA+/-1 pcm b 7.07 (I B-8) x 1.04200 pcm5.Pseudo- dropped control rod50% power, RCCA H-6 I H-6 a 1.62 138 pcm 1.70 146 pcm NA+/-22 pcm 1.69 c (I H-6) x 1.04250 pcm F NH Revision 52-09/29/2016 NAPS UFSAR 14.1-486.Power coefficient30% power-15.24 pcm/%
===Response===
power-14.02 pcm/%
This test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. The evaluation of the results associated with these tests indicated that of the two rods, RCCA D-10 resulted in the more limiting radial power distribution and consequently had the minimum margin to departure from nucleate boiling. This was the basis for choosing RCCA D-10 for the Unit 2 test.
power+/-4.57 pcm/%
Question 2 Describe any known differences between the fuel and core of North Anna Unit 1 and the fuel and core of North Anna Unit 2.
power NA50% power-12.74 pcm/%
power-13.75 pcm/%
power+/-3.82 pcm/%
power NA75% power-13.57 pcm/%
power-13.39 pcm/%
power+/-4.07 pcm/%
power NA90% power-10.70 pcm/%
power-13.31 pcm/%
power+/-3.21 pcm/%
power NA7.Power defect0 - 100% powerReactivity worth1270 pcm1299 pcm
+/-191 pcmNA8.Doppler-only power coefficient 30% power-13.62 pcm/%
power-11.35 pcm/%
power+/-4.09 pcm/%
power Inferred value
+/-30% uncertainty must overlap allowance range of Figure 15.1-350% power-10.77 pcm/%
power-10.75 pcm/%
power+/-3.23 pcm/%
power Inferred value


+/-30% uncertainty must overlap
===Response===
Three differences have been identified between the Unit 1 and Unit 2 fuel and core. They are:
: 1. The location of the secondary sources within the core.
: 2. The part-length control rods have been removed.
: 3. The fuel rods have been prepressurized to a different pressure.
The core locations of the secondary sources for Unit 1 and Unit 2 are shown in Figure 14A-1. It is not expected that this change will lead to a measurable difference in the physics characteristics between the Unit 1 and Unit 2 cores.
The core location of the part-length control rods for Unit 1 is shown in Figure 14A-2. This change will not lead to a measurable difference in the physics characteristics between the Unit 1 and Unit 2 cores because the use of the part-length control rods is not permitted during Unit 1 core operation. It is planned that these rods will be removed from Unit 1 following the end of Cycle 1 operation.
Unit 2 fuel has a prepressurization value that is approximately 50 psi lower than that used for Unit 1 fuel. This difference will have no perceptible effect on the physics characteristics of the


allowance range of
Revision 5209/29/2016                                      NAPS UFSAR                        14A-2 core. In addition, an evaluation has shown that there will be no adverse impact on fuel or core performance.
Question 3 Describe any differences between the physics test methods that were used for Unit 1 and the physics test methods that will be used for Unit 2.


Figure 15.1-3 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.Table 14.1-5  (continued)
===Response===
For Unit 1, the reactivity worth of shutdown bank B was determined with control banks A through D fully inserted into the core, using the dilution-boration technique. The worth of shutdown bank A was determined with control banks A through D and shutdown bank B fully inserted into the core. Shutdown bank A underwent an exchange with the most reactive rod (RCCA B-8) followed by a dilution of the reactor coolant system in order to fully insert shutdown bank A.
For Unit 2, the reactivity worths of shutdown banks A and B will be determined individually with all other control rod banks out of the core. The worth of shutdown bank B will be determined using the conventional dilution/boration technique. A boron endpoint determination will be made for this control rod configuration. The worth of shutdown bank A will be determined by using rod exchange with one of the rod banks, and if necessary, dilution/boration of the reactor coolant system in order to reach the desired state point, i.e.,
shutdown bank A fully inserted with all other rods out. A boron endpoint determination will be made for this control rod configuration.
Question 4 For each of the start-up physics tests that were performed for Unit 1 but are not going to be performed for Unit 2, give the technical basis for not performing those tests.
 
===Response===
The tests that are not going to be performed for Unit 2 are listed in Table 14.1-4. Deletion of these physics tests from the start-up program is justified for the following reasons:
: 1. The successful performance of the abbreviated program is sufficient to
: a. Verify that the core was correctly loaded and that there are no anomalies present that could cause problems later in the cycle.
: b. Verify that the calculational model that has been used will correctly predict core behavior during the cycle.
: c. Verify the reactivity worth of the control rod banks.


==SUMMARY==
Revision 5209/29/2016                                     NAPS UFSAR                         14A-3
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE,AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2Test DescriptionCore ConditionParameterUnit 1 Measured ValueDesign Value (beginning of life (BOL), Best Estimate)
: d. Provide data for nuclear instrumentation calibration.
Design Tolerance Accident Analysis CriterionQ()powerQ()powerQ()powerQ()powerQ()inferredDopplerQ()inferredDoppler Revision 52-09/29/2016 NAPS UFSAR 14.1-498.Doppler-only power coefficient (continued)75% power-11.08 pcm/%
: e. Demonstrate the sensitivity of this instrumentation to abnormal core conditions.
power-9.96 pcm/%
: 2. The calculation model was verified as a result of the Unit 1 start-up.
power+/-3.32 pcm/%
: 3. The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large margin exists between the measured parameter values and the design values used in the safety analyses.
power Inferred value
Each of the tests that are not going to be performed for Unit 2 is listed below, together with the specific technical basis for not performing these tests as part of the Unit 2 start-up physics testing program.
+/-30% uncertainty must overlap allowance range of Figure 15.1-390% power-7.59 pcm/%
A1. Isothermal Temperature coefficient at D, C banks in, D, C, B banks in, and D, C, B, A banks in The Core Operating Limits Report will require that a nonpositive value for the moderator temperature coefficient be maintained during normal operation. Based on the results of design calculations and the Unit 1 moderator temperature coefficient test results, it is expected that performance of the moderator temperature coefficient tests with all rods out and with control bank D in will be adequate to demonstrate a nonpositive moderator temperature coefficient value and also provide enough data to establish control rod withdrawal limits, should they be necessary. The successful completion of these tests will verify the design model used to predict the isothermal temperature coefficient values. Additionally, review criteria have been developed for the Unit 2 isothermal temperature coefficient tests that are based on the Unit 1 test results (Table 14A-1).
power-9.38 pcm/%
The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All of the Unit 1 measured temperature coefficient values were acceptable. The Unit 1 test results and review criteria for the isothermal temperature coefficients at D, C banks in, D, C, B banks in, and D, C, B, A banks in are listed in Table 14.1-5, Item 1.
power+/-2.28 pcm/%
A2. Boron Endpoint for the N-1 rods-in configuration Boron endpoint measurements will be made following each of the rod worth tests. The successful completion of these tests will verify the design model used to predict the boron endpoint values. Additionally, review criteria have been developed for the Unit 2 boron endpoint measurements that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured endpoint values were acceptable. The Unit 1 test results and review criterion for the boron endpoint for the N-1 rods-in configuration are listed in Table 14.1-5, Item 2.
powerAll inferred values fell within range of


Figure 15.1-3, as shown on Figure 14.1-3a.I N-1 = integrated reactivity worth of all control rods except the most reactive rod (N-1).
Revision 5209/29/2016                                      NAPS UFSAR                        14A-4 A3. Reactivity worth of N-1 rods As described in the response to Question 3, the reactivity worth of the control and shutdown rod banks will be measured as part of the physics testing program. The successful completion of these measurements will verify the design models used to predict the reactivity worth of the rod banks. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured rod worth values (including the reactivity worth of N-1 rods) were acceptable, and demonstrated that a large margin existed with respect to the shutdown margin limit. The Unit 1 test results and review criterion for the reactivity worth of N-1 rods are listed in Table 14.1-5, Item 3.
I B-8 = integrated reactivity worth of rod cluster control assembly (RCCA) B-8.
A4. Pseudo-rod-ejection and associated power distribution measurements (HZP)
I H-6 = integrated reactivity worth of RCCA H-6.b.Violation of design tolerance was evaluated to be insignificant due to low value of reactivity worth.c.Accident analysis referenced to hot full power.The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.Table 14.1-5 (continued)
The successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Since the same design model is used to predict all rod worths, including the worth of an ejected rod, additional verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurements (HZP) are listed in Table 14.1-5, Item 4. These results indicated that the measured rod worth value and the heat flux hot-channel factor value were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.
B1. Pseudo-rod-ejection and associated power distribution measurement at 30% power The successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Since the same design model is used to predict all rod worths, including the worth of an ejected rod, additional verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurement at 30% power are listed in Table 14.1-5, Item 4. These results indicated that the measured rod worth value and the heat flux hot-channel factor value were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.


==SUMMARY==
Revision 5209/29/2016                                       NAPS UFSAR                       14A-5 B2. Pseudo-dropped-rod test (RCCA H-6) and associated power distribution measurement As described in the response to Question 1, this test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. For Unit 2, this test will be performed using the limiting rod, RCCA D-10. The successful completion of this test will verify the design models and demonstrate margin to the values used in the safety analysis. Additionally, the use of review criteria that are based on Unit 1 test results for other Unit 2 tests (Table 14A-1) will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 results for both dropped rod tests were acceptable and demonstrated margin with respect to the values used in the safety analysis. The Unit 1 test results and review criteria for the pseudo-dropped-rod test and associated power distribution measurement using RCCA H-6 are listed in Table 14.1-5, Item 5.
OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE,AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2Test DescriptionCore ConditionParameterUnit 1 Measured ValueDesign Value (beginning of life (BOL), Best Estimate)
B3. Power coefficient tests B4. Integral power defect B5. Doppler-only power coefficients The successful completion of the isothermal temperature coefficient tests, the boron endpoint measurements, and the rod bank reactivity tests, together with the acceptability of these tests with respect to their respective review criteria, will service to further demonstrate the similarity between the Unit 1 and Unit 2 cores. As indicated in Table 14.1-5, Items 6, 7, and 8, the Unit 1 measured values for the total power coefficient, the integral power defect, and the Doppler-only power coefficient verified the design models used to predict the values of these parameters and were acceptable with respect to the values used in the safety analyses. An additional description of the Unit 1 test results and their evaluation has been provided in a letter from Mr. C. M. Stallings, VEPCO, to Mr. H. R. Denton, USNRC, Ser. No. 169, dated March 20, 1979.
Design Tolerance Accident Analysis CriterionQ()inferredDopplerQ()inferredDoppler Revision 52-09/29/2016 NAPS UFSAR 14.1-50The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
In summary, this information provides a sufficient technical basis for the deletion of these tests from the Unit 2 physics testing program.
Figure 14.1-1TYPICAL PRE-OPERATIONAL TEST SEQUENCE Revision 52-09/29/2016 NAPS UFSAR 14.1-51The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Question 5 It is suggested that review criteria be established, where appropriate, to compare the Unit 2 test results with the Unit 1 test results for the isothermal temperature coefficient measurements, the boron endpoint measurements, the rod bank reactivity worth measurements, and the boron worth measurement. For each of these tests, list the specific review criteria that will be used. Also, indicate the action that will be taken if the review criteria are not met.
Figure 14.1-2TYPICAL START-UP TEST SEQUENCE Revision 52-09/29/2016 NAPS UFSAR 14.1-52The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.
Figure 14.1-3CYCLE 1 BOL PHYSICS TEST DOPPLER POWER COEFFICIENT USED IN ACCIDENT ANALYSIS UNIT 1
Revision 52-09/29/2016 NAPS UFSAR 14.2-1 14.2 AUGMENTATION OF VEPCO'S STAFF FOR INITIAL TEST AND OPERATIONThe start-up organization used during the period of initia l operation consisted of all personnel in the St ation Oper ations Department, with a dditional support provided by the Engineering Services Department and the Chemistry and Health Physics Department.
In operations, there were, for one-unit operation, fi ve senior licensed shift supervisors, five licensed control room operato rs, and a combined group of 14 assistant control room operators and auxiliary operators with a minimum of two licensed assistant control room operators. For two-unit operations, there were five senior licensed shift s upervisors, five senior licensed assistant shift supervisors, 10 licensed control room operator s, and a combined group of 18 assistant control room operators and auxiliary operator s with a minimum of six licensed assistant control room operators. Shifts were scheduled to ensure that a minimum of three licensed reactor operators and two licensed senior reactor operators are on duty at all times during two-unit operations.Technical support was provided during start-up using the services of graduate-level engineers. A trained power engineer was assigne d through the architect-engineer to assist in preliminary operati ons for both units. In addi tion, engineering representa tives were assigned at the station by the supplier of the nuclear st eam supply system to render start-up support.
VEPCO had overall responsibility during plant star t-up, including precriticality tests, approach to criticality, and post criticality operations. The station staff was assisted by the architect-engineer and the supplier of the nuclear steam supply system. The Stone & Webster start-up engineer was assigned to the station from the start of flushing operations through commercial operation. The start-up engineer reported directly to the Station Manager and received instructions from him.Experienced Westinghouse reacto r engineers were al so assigned to the station for fuel loading, initial criticality, and physics testing. These reac tor engineers were qualified and knowledgeable in reactor operations.
They reported directly to the VEPCO react or engineers and received instructions from them. The Westinghouse reactor engi neers acted in an advisory capacity only; VEPCO retained responsibility for , and control of, the unit. Reactor specialist s (e.g., control engineers) were available and utilized as required.
Revision 52-09/29/2016 NAPS UFSAR 14.2-2 Intentionally Blank Revision 52-09/29/2016 NAPS UFSAR 14A-i Appendix 14ANRC Questions and VEPCO's Responses Regarding the North Anna Power Station Unit 2 Modified S tartup Physics Testing Program Revision 52-09/29/2016 NAPS UFSAR 14A-ii Intentionally Blank Revision 52-09/29/2016 NAPS UFSAR 14A-1 APPENDIX 14ANRC QUESTIONS AND VEPCO'S RESPONSES REGARDING THE NORTH ANNA POWER STATION UNIT 2 M ODIFIED STARTUP PHYSICS TESTING PROGRAM Question 1With respect to Item B.3 on Table 14.1-3 and Item B.2 on Table 14.1-4 , what is the reason for performing the pseudo-dropped-rod test with RCCA D-10 instead of RCCA H-6?ResponseThis test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. The evaluation of the results associated with these tests indicated that of the two rods, RCCA D-10 resulted in the more limiting radial power distribution and consequently had the minimum margin to departure from nucleate boiling. This was the basis for choosing RCCA D-10 for the Unit 2 test.Question 2Describe any known differ ences between the fuel and core of North Anna Unit 1 and the fuel and core of North Anna Unit 2.ResponseThree differences have been identified between the Unit 1 and Unit 2 fuel and core. They are:1.The location of the secondary sources within the core.2.The part-length control rods have been removed.3.The fuel rods have been prepressurized to a diff erent pressure.
The core locations of the secondary sources for Unit 1 and Unit 2 are shown in Figure 14A-1. It is not expected that this change will lead to a measurable difference in the physics characteristics between the Unit 1 and Unit 2 cores.The core location of the part-length control rods for Unit 1 is shown in Figure 14A-2. This change will not lead to a measurable diff erence in the physics characteristics between the Unit 1 and Unit 2 cores because the use of th e part-length control rods is not permitted during Unit 1 core operation. It is planned that these rods will be removed from Unit 1 following the end of Cycle 1 operation.
Unit 2 fuel has a prepressurization value that is approximately 50 psi lower than that used for Un it 1 fuel. This difference will have no perceptible effect on the physics characteristics of the Revision 52-09/29/2016 NAPS UFSAR 14A-2 core. In addition, an evaluation has shown that there will be no adverse impact on fuel or core performance.
Question 3Describe any differences between the physic s test methods that were used for Unit 1 and the physics test methods that will be used for Unit 2.Response For Unit 1, the reactivity wo rth of shutdown bank B was determined with control banks A through D fully inserted into the core, using th e dilution-boration technique. The worth of shutdown bank A was determined with control banks A through D and shutdown bank B fully inserted into the core. Shutdown bank A underwent an exchange wi th the most reactive rod (RCCA B-8) followed by a dilution of the reactor coolant system in order to fully insert shutdown bank A.For Unit 2, the reactivity worths of shutdown banks A and B will be determined individually with all other c ontrol rod banks out of the co re. The worth of shutdown bank B will be determined using the conventional di lution/boration techni que. A boron endpoint determination will be made for this control rod configuration. The worth of shutdown bank A will be determined by using rod exchange with one of the rod banks, and if necessary, dilution/boration of the reactor coolant system in order to reach the desired state point, i.e., shutdown bank A fully inserted w ith all other rods out. A boron e ndpoint determination will be made for this control rod configuration.
Question 4 For each of the start-up physics te sts that were performed for Unit 1 but are not going to be performed for Unit 2, give the technical basis for not performing those tests.


===Response===
===Response===
The tests that are not going to be performed for Unit 2 are listed in Table 14.1-4. Deletion of these physics tests from the start-up program is justified for the following reasons:1.The successful performance of the abbreviated program is suff icient toa.Verify that the core was correctly loaded and that there are no anomalies present that could cause problems later in the cycle.b.Verify that the calculational model that has been used will correctly predict core behavior during the cycle.c.Verify the reactivity worth of the control rod banks.
The tests and the specific test review criteria that will be used are listed on Table 14A-1. As described in the response to Question 3, the reactivity worth and boron endpoint measurements associated with shutdown banks A and B that will be performed for Unit 2 are not direct
Revision 52-09/29/2016 NAPS UFSAR 14A-3d.Provide data for nuclear instrumentation calibration.e.Demonstrate the sensitivity of this in strumentation to abnormal core conditions.2.The calculation model was verified as a result of the Unit 1 start-up.
 
3.The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large mar gin exists between the measured parameter values and the design values used in the safety analyses.Each of the tests that are not going to be performed for Unit 2 is listed below, together with the specific technical basis for not performing these te sts as part of the Unit 2 start-up physics testing program.A1.Isothermal Temperature coefficient at D, C banks in, D, C, B banks i n, and D, C, B, A banks in The Core Operating Limits Report will require that a nonpositive va lue for the moderator temperature coefficient be maintained during norm al operation. Base d on the results of design calculations and the Unit 1 moderator temperature coefficient test results, it is expected that performance of the moderator temperature coefficien t tests with all rods out and with control bank D in will be adequate to demonstrate a nonpositive moderato r temperature coef ficient value and also provide enough data to establish control rod withdrawal limits, should they be necessary. The successful completion of these test s will verify the design model used to predict the isothermal temperature coefficient values. Additionally, revi ew criteria have been developed for the Unit 2 isothermal temperature coef ficien t tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All of the Unit 1 measured temperature coefficient values were acceptable. The Unit 1 test results and review criteria for the isothermal temperature coefficients at D, C banks in, D, C, B banks in, and D, C, B, A banks in are listed in Table 14.1-5 , Item 1.A2.Boron Endpoint for the N-1 rods-in configurationBoron endpoint measurements will be made fo llowing each of the rod worth tests. The successful completion of these tests will verify th e design model used to predict the boron endpoint values. Additionally, review criteria have been developed for the Unit 2 boron endpoint measurements that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured endpoint values were acceptable. The Unit 1 test results and review criterion for the boron endpoint for the N-1 rods-i n configuration are listed in Table 14.1-5 , Item 2.
Revision 5209/29/2016                                   NAPS UFSAR                         14A-6 duplicates of the tests that were performed during the Unit 1 testing program. Therefore, review criteria based on Unit 1 test results would be inappropriate. The results of these tests will be reviewed, instead, with respect to design values (best-estimate predictions) and the standard design tolerances.
Revision 52-09/29/2016 NAPS UFSAR 14A-4A3.Reactivity worth of N-1 rods As described in the response to Question 3 , the reactivity worth of the control and shutdown rod banks will be measured as part of the physics testing program. The successful completion of these measurements will verify the design models used to predic t the re activity wo rth of the rod banks. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will fu rther demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured rod worth values (includi ng the reactivity worth of N-1 rods) were acceptable, and demonstrated that a large margin existed with re spect to the shutdown margin limit. The Unit 1 test results and review criterion for the reactivit y worth of N-1 rods are listed in Table 14.1-5 , Item 3.A4.Pseudo-rod-ejection and associated power distribution measurements (HZP)
As stated in the main body of the FSAR and as required by the VEPCO Nuclear Power Station Quality Assurance Manual, test results will be reviewed and evaluated by the Station Nuclear Safety and Operating Committee. Should the results of any of these tests fail to meet the review criteria, the Committee may decide to perform additional testing. This additional testing may be a repeat of the original test or may be the performance of a test that had been deleted from the Unit 2 physics testing program. In addition, the NRC Region II Resident Inspector will be notified verbally in a timely manner, and a report will be sent to Nuclear Reactor Regulation (NRR).
The successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Sinc e the same design model is used to predict all rod worths, including the worth of an ejected rod, additiona l verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstr ate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurements (HZP) are listed in Table 14.1-5 , Item 4. These results indicated that the measured rod worth value and the heat flux hot-channel factor value were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.
 
B1.Pseudo-rod-ejection and asso ciated power distribution measurement at 30% powerThe successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Sinc e the same design model is used to predict all rod worths, including the worth of an ejected rod, additiona l verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstr ate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurement at 30% power are listed in Table 14.1-5 , Item 4. These results indicated that the measured rod worth value and the heat flux hot-c hannel factor valu e were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.
Revision 5209/29/2016                                     NAPS UFSAR                           14A-7 Table 14A-1 UNIT 2 ISOTHERMAL TEMPERATURE COEFFICIENT, BORON ENDPOINT, ROD WORTH REACTIVITY, AND BORON WORTH TESTS AND REVIEW CRITERIA Review Criteria Test Description             Unit 1 Measured Value            Tolerance Isothermal temperature coefficient ARO                               0.98 pcm/°F                     +/-2 pcm/°F D bank in                         -4.29 pcm/°F                   +/-2 pcm/°F Boron endpoint ARO                               1322 ppm                       +/-24 ppm D bank in                          1193 ppm                       +/-24 ppm D, C banks in                     1075 ppm                       +/-24 ppm D, C, B banks in                   884 ppm                         +/-24 ppm D, C, B, A banks in               781 ppm                         +/-24 ppm Shutdown bank A in                 1220 ppm (design)               +/-21 ppm Shutdown bank B in                 1224 ppm (design)               +/-20 ppm Control rod worth D bank                             1463 pcm                       +/-100 pcm C bank                             1303 pcm                       +/-98 pcm B bank                             2036 pcm                       +/-153 pcm A bank                             1309 pcm                       +/-98 pcm Total D through A                  6111 pcm                       +/-306 pcm Shutdown bank A                    1114 pcm (design)               +/-111 pcm Shutdown bank B                   1043 pcm (design)               +/-104 pcm Boron worth pcm                            pcm ARO through A bank                 11.08 -----------               +/-0.55 -----------
Revision 52-09/29/2016 NAPS UFSAR 14A-5B2.Pseudo-dropped-rod test (RCCA H-6) and associated power distribution measurement As described in the response to Ques tion 1, this test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. For Unit 2, this test will be performed using the limiting rod, RCCA D-10. The successful completion of this test will verify the design models and demonstrate margin to the values used in the safety analysis. Additionally, the use of review criteria that are based on Unit 1 test results for other Unit 2 tests (Table 14A-1) will further demonstrate the similar ity between the Unit 1 and Unit 2 cores. The Unit 1 results for both dropped rod tests were acceptable and demonstrated marg in with resp ect to the values used in the safety analysis. The Unit 1 test results and review criteria for the pseudo-dropped-rod test and associated power distribut ion measurement using RCCA H-6 are listed in Table 14.1-5 , Item 5.B3.Power coefficient testsB4.Integral power defectB5.Doppler-only power coefficientsThe successful completion of the isothermal temperature coefficient tests, the boron endpoint measurements, a nd the rod bank reacti vity tests, together with the acceptability of these tests with respect to their respective review criteria, will service to further demonstrate the similarity between the Unit 1 and Unit 2 cores. As indicated in Table 14.1-5 , Items 6, 7, and 8, the Unit 1 measured values for the total power coeffi cient, the integral power defect, and the Doppler-only power coef ficient veri fied the design models used to predict the values of these parameters and were acceptable wi th respect to the values used in the safety analyses. An additional description of the Unit 1 test results and their evaluation has been provided in a letter from Mr. C. M. Stallings, VEPCO, to Mr. H. R. Denton, US NRC, Ser. No.
ppm                              ppm
169, dated March 20, 1979.In summary, this information provides a suffic ient technical basis fo r the deletion of these tests from the Unit 2 physics testing program.
 
Question 5 It is suggested that review criteria be established, where appropriate, to compare the Unit 2 test results with the Unit 1 test results for the isothermal temperature coefficient measurements, the boron endpoint measurements, the rod bank reactivity worth measurements, and the boron worth measurement. For each of these tests, list the specific review criteria that will be used. Also, indicate the action that will be take n if the review criteria are not met.
Revision 5209/29/2016                     NAPS UFSAR 14A-8 Figure 14A-1 SECONDARY SOURCE LOCATIONS
ResponseThe tests and the specific test review criteria that wi ll be used are listed on Table 14A-1. As described in the response to Question 3 , the reactivity worth and bo ron endpoint measurements associated with shutdown banks A and B that will be performed for Unit 2 are not direct Revision 52-09/29/2016 NAPS UFSAR 14A-6 duplicates of the tests that were performed during the Unit 1 testing program. Therefore, review criteria based on Unit 1 test results would be inappropriate. The results of these tests will be reviewed, instead, with respect to design values (best-estimate predictions) and the standard design tolerances.
 
As stated in the main body of the FSAR and as required by the VEPCO Nuclear Power Station Quality Assurance Manual, test results will be reviewed and evaluated by the Station Nuclear Safety and Operating Commit tee. Should the results of any of these tests fail to meet the review criteria, the Committee may decide to pe rform additional testing. This additional testing may be a repeat of the original test or may be the performance of a test that had been deleted from the Unit 2 physics testing program.
Revision 5209/29/2016                     NAPS UFSAR     14A-9 Figure 14A-2 PART LENGTH CONTROL ROD LOCATIONS (UNIT 1)
In addition, the NRC Region II Resident Inspector will be notified verbally in a timely manner, and a report will be sent to Nuclear Reactor Regulation (NRR).
 
Revision 52-09/29/2016 NAPS UFSAR 14A-7Table 14A-1 UNIT 2 ISOTHERMAL TEMPERATURE COEFFICIENT, BORON ENDPOINT, ROD WORTH REACTIVITY, AND BORON WORTH TESTS AND REVIEW CRITERIA Review CriteriaTest Description Unit 1 Measured ValueToleranceIsothermal temperature coefficient ARO 0.98 pcm/°F
Revision 5209/29/2016                   NAPS UFSAR 14A-10 Intentionally Blank}}
+/-2 pcm/°F D bank in-4.29 pcm/°F
+/-2 pcm/°F Boron endpoint ARO 1322 ppm+/-24 ppm D bank in1193 ppm+/-24 ppm D, C banks in 1075 ppm+/-24 ppm D, C, B banks in 884 ppm+/-24 ppm D, C, B, A banks in 781 ppm+/-24 ppm Shutdown bank A in 1220 ppm (design)
+/-21 ppm Shutdown bank B in 1224 ppm (design)
+/-20 ppm Control rod worth D bank 1463 pcm+/-100 pcm C bank 1303 pcm+/-98 pcm B bank 2036 pcm+/-153 pcm A bank 1309 pcm+/-98 pcmTotal D through A6111 pcm+/-306 pcm Shutdown bank A1114 pcm (design)
+/-111 pcm Shutdown bank B 1043 pcm (design)
+/-104 pcm Boron worth ARO through A bank 1 1.08 +/-0.55 pcm ppm----------
-pcm ppm----------
-
Revision 52-09/29/2016 NAPS UFSAR 14A-8 Figure 14A-1SECONDARY SOURCE LOCATIONS Revision 52-09/29/2016 NAPS UFSAR 14A-9 Figure 14A-2PART LENGTH CONTROL ROD LOCATIONS (UNIT
: 1)
Revision 52-09/29/2016 NAPS UFSAR 14A-10 Intentionally Blank}}

Latest revision as of 08:53, 30 October 2019

Redacted Updated Final Safety Analysis Report Chapter 14
ML17033B575
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 09/29/2016
From: V Sreenivas
Plant Licensing Branch II
To: Heacock D
Virginia Electric & Power Co (VEPCO)
Sreenivas V, NRR/DORL/LPL2-1, 415-2597
Shared Package
ML17033B477 List:
References
Download: ML17033B575 (76)


Text

North Anna Power Station Updated Final Safety Analysis Report Chapter 14

Intentionally Blank Revision 5209/29/2016 NAPS UFSAR 14-i Chapter 14: Initial Tests and Operation Table of Contents Section Title Page 14 INITIAL TESTS AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.0-1 14.0.1 Administration of the Preoperational Test Program . . . . . . . . . . . . . . . . . . . . . . 14.0-1 14.0.2 Administration of the Start-Up Test Program . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.0-2 14.1 TEST PROGRAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-1 14.1.1 Pre-Operational Test Program. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-1 14.1.2 Initial Start-Up Test Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-2 14.1.2.1 Initial Fuel Loading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-2 14.1.2.2 Initial Postloading Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-4 14.1.2.3 Initial Criticality and Low-Power Physics Tests . . . . . . . . . . . . . . . . . . . . . . . 14.1-5 14.1.2.4 Power Level Escalation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-6 14.1.3 Start-Up Physics Test Program Differences Between Unit 1 and Unit 2 . . . . . . 14.1-7 14.1.4 Special Low-Power Tests - Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-8 14.1 Reference Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-9 14.2 AUGMENTATION OF VEPCOS STAFF FOR INITIAL TEST AND OPERATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.2-1 Appendix 14A NRC Questions and VEPCOs Responses Regarding the North Anna Power Station Unit 2 Modified Startup Physics Testing Program . . . . . . . . . . . . . . . . . . . . . . . 14A-i

Revision 5209/29/2016 NAPS UFSAR 14-ii Chapter 14: Initial Tests and Operation List of Tables Table Title Page Table 14.1-1 List of Preoperational Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-10 Table 14.1-2 Lists of Start-Up Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-34 Table 14.1-3 Unit 2 Start-Up Physics Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-45 Table 14.1-4 Physics Tests that Have Been Deleted For Unit 2 . . . . . . . . . . . . . . . . . 14.1-46 Table 14.1-5 Summary of Unit 1 Measured Values, Design Values, Design Tolerance, and Accident Analysis Criteria for Physics Tests That Have Been Deleted for Unit 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-47 Table 14A-1 Unit 2 Isothermal Temperature Coefficient, Boron Endpoint, Rod Worth Reactivity, and Boron Worth Tests and Review Criteria. . . . . . . . . . . . 14A-7

Revision 5209/29/2016 NAPS UFSAR 14-iii Chapter 14: Initial Tests and Operation List of Figures Figure Title Page Figure 14.1-1 Typical Pre-Operational Test Sequence. . . . . . . . . . . . . . . . . . . . . . . . 14.1-50 Figure 14.1-2 Typical Start-Up Test Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-51 Figure 14.1-3 Cycle 1 BOL Physics Test Doppler Power Coefficient Used in Accident Analysis Unit 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14.1-52 Figure 14A-1 Secondary Source Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14A-8 Figure 14A-2 Part Length Control Rod Locations (Unit 1) . . . . . . . . . . . . . . . . . . . . 14A-9

Revision 5209/29/2016 NAPS UFSAR 14-iv Intentionally Blank

Revision 5209/29/2016 NAPS UFSAR 14.0-1 CHAPTER 14 INITIAL TESTS AND OPERATION This chapter describes the scope of tests and operations performed over the time period when construction was sufficiently complete to operate and test individual components and systems through the acceptance run at full power. This time period is divided into two categories:

1. Pre-operational testing: tests performed before the initial core loading.
2. Initial start-up testing: tests and operations from the initial core loading through the acceptance tests.

The preoperational and start-up programs, as outlined in Tables 14.1-1 and 14.1-2, comply with the intent of Regulatory Guide 1.68, Preoperational and Initial Start-up Test Programs for Water-Cooled Power Reactors, dated November 1973, in most cases, and use the same wording as much as possible in order to more clearly address the NRC guide requirements. Detailed acceptance criteria were provided in each test procedure that was written to fulfill the testing requirements. The detailed criteria of acceptability were based on various sources, such as equipment technical manuals, system descriptions, plant drawings, manufacturer specifications, and the North Anna Units 1 and 2 FSAR. The tests and their objectives are listed in Tables 14.1-1 and 14.1-2, which also provide a summary of each test. The acceptability of a test is contingent on the successful attainment of the objectives stated in Tables 14.1-1 and 14.1-2.

Because of similarities and differences in the fuel and core characteristics between the two units, certain tests performed for Unit 1 were not repeated for Unit 2, while specific tests were performed for Unit 2 only. A discussion of the start-up physics program differences appears in Section 14.1.3.

14.0.1 Administration of the Preoperational Test Program The management and direction of the preoperational test program was under the direct control of VEPCO, with the principal responsibility lying with the Supervisor - Engineering Services. In most cases written preoperational test procedures were prepared by the station engineering staff under the direction of the Supervisor - Engineering Services. In those areas where the station engineering staff was not knowledgeable, procedures were provided by the architect-engineer or outside consultants, based on their expertise in the particular areas of concern. Test procedure format generally included the purpose of the test, initial condition requirements, precautions and limitations, instructions, and criteria for acceptability of data. Prior to issuance of test procedures for use in the field, they were reviewed by the Joint Test Group and approved by the Station Nuclear Safety and Operating Committee.

For those procedures provided by the architect-engineer or outside consultants, the preoperational test procedure was used as a cover sheet to their procedure in order to ensure review by the Joint Test Group and approval by the Station Nuclear Safety and Operating

Revision 5209/29/2016 NAPS UFSAR 14.0-2 Committee. In some instances the preoperational test procedures were used to review and approve test data from testing performed by equipment vendors off the site (e.g., vendor certifications).

In most instances the conduct and direction of the preoperational tests were the direct responsibility of the VEPCO test engineers designated by the technical supervision at the station.

In some instances architect-engineer personnel or outside consultants were responsible for the conduct of tests under the direction of VEPCO by means of written administrative controls.

Changes to approved test procedures were documented and became part of the final test results.

Administrative controls for making changes to procedures prepared by the station engineering staff were provided in the Nuclear Power Station Quality Assurance Manual. Administrative procedures for making changes to procedures provided by the architect-engineer or outside consultants were formulated by the architect-engineer and approved by VEPCO.

For preoperational testing, the Supervisor - Engineering Services and the Joint Test Group reviewed and analyzed the test results. Assistance from the VEPCO system office, the nuclear steam supply system vendor, and the architect-engineer was solicited as deemed necessary. The test results and evaluations were reviewed by the Station Nuclear Safety and Operating Committee and approved if they were satisfactory. In instances where performance of components or systems deviated from predicted results, further engineering evaluations were made to resolve the discrepancies before the test was considered satisfactory. Systems that had to be modified as a result of the preoperational tests were then retested to verify acceptable performance.

The completed test procedures, along with data and conclusions, were documented and filed as part of the permanent plant records.

Minimum qualifications for the VEPCO test engineers were as follows:

1. A bachelors degree in engineering or the physical sciences or the equivalent, and at least 1 year of applicable nuclear power plant experience, or:
2. A high school diploma or the equivalent, and at least 3 years of applicable nuclear power plant experience. Credit for up to 2 years of nuclear experience may be given for related technical training on a one-for-one time basis.

Additional information relative to the preoperational test program is provided in the Nuclear Power Station Quality Assurance Manual, in VEPCO station administrative procedures, and in the architect-engineers administrative procedures.

14.0.2 Administration of the Start-Up Test Program The management and direction of the start-up test program has been under the direct control of VEPCO, with principal responsibility lying with the Supervisor - Engineering Services.

Written start-up test procedures were prepared by the station reactor engineers under the direction

Revision 5209/29/2016 NAPS UFSAR 14.0-3 of the Supervisor - Engineering Services. Procedures from the Nuclear Steam Supply System Start-up Manual and assistance from Westinghouse personnel were utilized in many cases. Prior to issuance of test procedures for use in the field, they were approved by the Station Nuclear Safety and Operating Committee.

The conduct and direction of the start-up tests were the responsibility of the reactor engineers designated by the Supervisor - Engineering Services. Changes to approved test procedures were documented and became part of the final results. Administrative procedures for making these changes, including the review and approvals, were formulated and utilized by VEPCO.

For start-up testing the reactor engineers and the Supervisor - Engineering Services reviewed and analyzed the test results. The measurements and data analysis for start-up physics tests were performed by the VEPCO Fuel Resources Department. Assistance from the VEPCO system office, the nuclear steam supply system vendor, and the architect-engineer was solicited as deemed necessary. Approval of test results was the responsibility of the Station Nuclear Safety and Operating Committee. The completed test procedures, along with data and conclusions, were documented and filed as part of the permanent plant records.

The minimum qualifications for the reactor engineers, in terms of educational background and experience, are stated in Section 13.1. Minimum qualifications for the test engineers responsible for the preparation and performance of start-up tests were as follows:

1. A bachelors degree in engineering or the physical sciences or the equivalent and 2 years of applicable power plant experience, of which at least 1 year shall be applicable nuclear power plant experience, or
2. A high school diploma or the equivalent and 5 years of applicable power plant experience, of which at least 2 years shall be applicable nuclear power plant experience. Credit for up to 2 years of non-nuclear experience may be given for related technical training on a one-for-one time basis.

Additional information relative to the start-up test program is provided in the Nuclear Power Station Quality Assurance Manual and in station administrative procedures.

Revision 5209/29/2016 NAPS UFSAR 14.0-4 Intentionally Blank

Revision 5209/29/2016 NAPS UFSAR 14.1-1 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

14.1 TEST PROGRAM 14.1.1 Pre-Operational Test Program The pre-operational test program included tests, adjustments, calibrations, and system operations necessary to ensure that initial fuel loading, initial criticality, and subsequent power operation could be safely undertaken.

After installation of individual components and systems was completed, the installed components and systems were tested and evaluated according to approved testing procedures or check-off lists. Analyses of test results were made to verify that systems and components were performing satisfactorily or, if not, to provide a basis for recommended corrective action.

Whenever possible, these tests were performed under the same conditions to be experienced under subsequent station operations. During system tests for which unit parameters were not available, the systems were operationally tested as far as possible without these parameters. The remainder of the tests were performed under plant conditions when the parameters were available. Abnormal unit conditions were simulated during testing as required and when such conditions did not endanger personnel or equipment, or contaminate systems whose cleanliness had been established.

In general, pre-operational testing was completed before core loading. As individual systems were completed, pre-operational tests were performed to verify as nearly as possible the performance of the system under actual operating conditions. Where required, simulated signals or inputs were used to verify the full operating range of the system and to calibrate and align the systems and instruments at these conditions. Later, systems that were used during normal operation were verified under actual operating conditions. Systems that are not used during normal plant operation, but should be in a state of readiness to perform safety functions, were tested before plant start-up. Examples of these systems are the reactor trip system and engineered safety features system logic, operation checks, and setpoint verifications.

Testing performed during the pre-operational test program is outlined in Table 14.1-1. A typical sequence of performance for operational tests is shown in Figure 14.1-1. The actual sequence of tests was formulated before the performance of the tests, considering equipment and system availability. In some cases, it was necessary to complete certain pre-operational tests after core loading. These included such tests as those performed on the complete rod control system, rod position indication, and complete incore movable detector system. These tests have been identified in Table 14.1-1.

Revision 5209/29/2016 NAPS UFSAR 14.1-2 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

14.1.2 Initial Start-Up Test Program Fuel loading was begun when all prerequisite system tests and operations were satisfactorily completed. Upon completion of fuel loading, the reactor upper internals and pressure vessel head were installed, and additional mechanical and electrical tests were performed as discussed in pre-operational testing. The purpose of this phase of activities was to prepare the system for nuclear operation and to establish that all design requirements necessary for operation were achieved. The core-loading and postloading tests are described below.

14.1.2.1 Initial Fuel Loading The reactor containment structure was completed and tested before initial fuel loading.

Fuel-handling tools and equipment were checked out and dry runs conducted in the use and operation of equipment.

The reactor vessel and associated components were in a state of readiness to receive fuel.

Water level was maintained above the bottom of the nozzles.

The overall responsibility and direction for the initial core loading was exercised by the Station Manager assisted by the Superintendent - Station Operation. The overall process of initial core loading was, in general, directed from the operating floor of the containment structure. Procedures for the control of personnel and the maintenance of containment security were in effect during initial fuel loading.

The as-loaded core configuration was specified as part of the core design studies conducted in advance of core loading. In the event mechanical damage to a fuel assembly occurred during core-loading operations, an evaluation would have been performed and a replacement assembly would have been procured if deemed necessary.

The core was assembled in the reactor vessel, containing reactor-grade water with dissolved boric acid to maintain a calculated core effective multiplication factor of 0.95 or lower. The refueling cavity was kept dry during the initial core loading. Core moderator chemistry conditions (particularly, boron concentration) were prescribed in the core-loading procedure document and were verified periodically by chemical analyses of moderator samples taken before and during core-loading operations.

Revision 5209/29/2016 NAPS UFSAR 14.1-3 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Core-loading instrumentation consisted of two permanently installed source range (pulse-type) nuclear channels and three temporary incore source range channels. The permanent channels, when responding, were monitored in the main control room by licensed station operators; the temporary channels were monitored by fuel-loading personnel. One permanent channel was equipped with an audible count rate indicator. The neutron flux level from both plant channels was displayed on a strip chart recorder. The temporary channels were indicated on rate meters with one channel recorded on a strip chart recorder. Minimum count rates of two counts per sec, attributable to core neutrons, were required on at least two of the five available nuclear source channels at all times following installation of the initial nucleus of eight fuel assemblies.

Fuel assemblies together with inserted components (control rod assemblies, burnable poison inserts, source spider, or thimble plugging devices) were placed in the reactor vessel one at a time according to a previously established and approved sequence developed to provide reliable core monitoring with minimum possibility of core mechanical damage. The core-loading procedure documents included detailed tabular check sheets that prescribed and were used to verify the successive movements of each fuel assembly and its specified inserts from its initial position in the storage racks to its final position in the core. Multiple checks were made of component serial numbers and types at successive transfer points to guard against possible inadvertent exchanges or substitutions of components, and fuel assembly status boards were maintained throughout the core-loading operation.

An initial nucleus of eight fuel assemblies, the first of which contained an activated neutron source, is the minimum source-fuel nucleus that permits subsequent meaningful inverse count rate ratio monitoring. This initial nucleus has been determined by calculation and previous experience to be markedly subcritical ( k eff less than or equal to 0.90) under the required conditions of loading.

Each subsequent fuel addition was accompanied by detailed neutron count rate monitoring to determine that the just-loaded fuel assembly did not excessively increase the count rate and that the extrapolated inverse count rate ratio was not decreasing for unexplained reasons. The results of each loading step were evaluated before the next prescribed step was started.

Criteria for safe loading require that loading operations stop immediately if:

1. An unanticipated increase in the neutron count rates by a factor of two occurs on all responding nuclear channels during any single loading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated changes due to detector and/or source movement).

Revision 5209/29/2016 NAPS UFSAR 14.1-4 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

2. The neutron count rate on any individual nuclear channel increases by a factor of five during any single loading step after the initial nucleus of eight fuel assemblies is loaded (excluding anticipated changes due to detector and/or source movements).

An alarm in the containment and main control room is coupled to the source range channels with a setpoint equal to or less than five times the baseline count rate. This alarm automatically alerts the loading operation personnel of high count rate and requires an immediate stop of all operations until the situation is evaluated.

Core-loading procedures specified the condition of fluid systems to prevent inadvertent dilution of the reactor coolant, specified the movement of fuel to preclude the possibility of mechanical damage, prescribed the conditions under which loading could proceed, identified responsibility and authority, and provided for continuous and complete fuel and core component accountability.

14.1.2.2 Initial Postloading Tests Upon completion of core loading, the reactor upper internals and the pressure vessel head were installed, and additional mechanical and electrical checks were performed before initial criticality. The final pressure test was conducted after filling and venting were completed to check the integrity of the vessel head installation.

Mechanical and electrical tests were performed on the control rod drive mechanisms.

These tests included a complete operational checkout of the mechanisms and calibration of the individual rod position indication.

Tests were performed on the reactor trip circuits to test manual trip operation. The actual control rod assembly drop times were measured for each control rod assembly. The reactor control and protection system was checked with simulated signals to produce a trip signal for the various conditions that require plant trip.

At all times when the control rod drive mechanisms were being tested, the boron concentration in the coolant-moderator was maintained such that the reactor would remain adequately shut down with all control rod assemblies fully withdrawn.

A complete functional electrical and mechanical check was made of the incore nuclear flux mapping system, and reactor coolant system flow measurements were taken to relate reactor coolant pump input power and elbow tap pressure differential to actual reactor coolant loop flow.

Revision 5209/29/2016 NAPS UFSAR 14.1-5 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

14.1.2.3 Initial Criticality and Low-Power Physics Tests On completion of postloading tests, nuclear operation of the reactor was begun. This final phase of start-up and testing included initial criticality, low-power testing, and power level escalation. The purpose of these tests was to establish the operational characteristics of the unit and core, to acquire data for the proper calibration of setpoints, and to ensure that operation was within license requirements. A brief description of the testing is presented in this section.

Table 14.1-2 summarizes the major tests that were performed from initial core loading to rated power. Figure 14.1-2 depicts a typical sequence for these tests; the actual sequence of tests was formulated by station engineering and operating personnel, considering test requirements and equipment availability.

Initial criticality was established by sequentially withdrawing the shutdown and control banks of control rod assemblies from the core, leaving the last withdrawn control bank inserted far enough in the core to provide effective control when criticality would later be achieved, and then diluting the heavily borated reactor coolant until criticality was achieved.

Successive stages of control rod assembly bank withdrawal and of boron concentration dilution were monitored by observing changes in neutron count rate as indicated by the normal plant source range nuclear instrumentation as functions of bank position during rod motion and, subsequently, of reactor coolant boron concentration and primary-water addition to the reactor coolant system during dilution. Throughout this period, samples of the primary coolant were obtained and analyzed for boron concentration.

Inverse count rate ratio monitoring was used as an indication of the proximity and rate of approach to criticality of the core during control rod assembly bank withdrawal and during reactor coolant boron dilution. The rate of dilution was reduced as the reactor approached the boron concentration extrapolated for criticality to ensure that effective control was maintained at all times. Written procedures specified the plant conditions, precautions, and specific instructions for the approach to criticality.

After initial criticality, a prescribed program of reactor physics measurements was undertaken to verify that the basic static and kinetic characteristics of the core were as expected and that the values of the kinetic coefficients assumed in the safeguards analysis were indeed conservative.

Revision 5209/29/2016 NAPS UFSAR 14.1-6 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

The measurements were made at low power and primarily at or near operating temperature and pressure. The measurements included verification of calculated values of control rod assembly bank reactivity worths, of isothermal temperature coefficient under various core conditions, of differential boron concentration reactivity worth, and of critical boron concentrations as functions of control rod assembly bank configuration. In addition, measurements of the relative power distributions were made. Concurrent tests were conducted on the instrumentation, including the source and intermediate range nuclear channels.

Procedures were prepared to specify the sequence of tests and measurements conducted and the conditions under which each was to be performed to ensure both safety of operation and the validity and consistency of the results obtained. Had significant deviations from design predictions existed, or had unacceptable behavior been revealed, or had apparent anomalies developed, then testing would have been suspended and the situation reviewed to determine whether a question of safety was involved before the resumption of testing.

14.1.2.4 Power Level Escalation When the operating characteristics of the reactor and unit were verified by low-power testing, a program of power level escalation in successive stages was used to bring the unit to its full rated thermal power level. Both primary and secondary operational characteristics were examined at each stage of the power escalation program.

Measurements were made to determine the relative power distribution in the core as functions of power level and control assembly bank position.

Secondary system heat balances ensured that the indications of power level were consistent and provided bases for calibration of the power range nuclear channels. The ability of the reactor coolant system to respond effectively to signals from primary and secondary instrumentation under a variety of conditions encountered in normal operations was verified.

At prescribed power levels the dynamic response characteristics of the reactor coolant and steam systems were evaluated. The responses of the systems were measured for design step load changes of 10%, rapid 50% load reduction, and 50% and 100% power plant trips.

Adequacy of radiation shielding was determined by gamma and neutron radiation surveys at selected points inside the containment and the outside area immediately adjacent to the containment at various power levels. Periodic sampling was performed to verify the chemical and radiochemical analyses of the reactor coolant.

Revision 5209/29/2016 NAPS UFSAR 14.1-7 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

All precritical tests were completed and the results evaluated before initial criticality.

Prerequisites for performing a test were specified in the individual test procedure. The sequence of testing was outlined in a start-up test sequence, such that required prerequisite testing was completed before subsequent testing. Any special test instruments required were specified to be installed, calibrated, and checked in the test procedure that specified the test equipment.

14.1.3 Start-Up Physics Test Program Differences Between Unit 1 and Unit 2 After the initial start-up physics program for North Anna Unit 1 was completed, several changes to the program were made before the initial start-up physics program for Unit 2.

Table 14.1-3 lists the physics tests that were performed as part of the Unit 2 start-up program.

These tests were chosen to:

1. Verify that the core was correctly loaded and that there were no anomalies present that could cause problems later in the cycle.
2. Verify that the calculational model that had been used would correctly predict core behavior during the cycle.
3. Verify the reactivity worth of the control rod banks.
4. Provide data for nuclear instrumentation calibration.
5. Demonstrate the sensitivity of this instrumentation to abnormal core conditions.

In addition, the chosen tests were selected to encompass the physics test goals listed in the NRC Branch Technical Position DOR-1, Guidance for Reload Submittals, Draft - Spring, 1978. Table 14.1-4 lists those physics tests that were performed during the Unit 1 start-up, and that were not repeated as part of the Unit 2 start-up program. The deletion of these tests was justified for the following reasons:

1. The successful performance of the abbreviated program was sufficient to achieve the physics testing program goals.
2. The calculational model was verified as a result of the Unit 1 start-up.
3. The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large margin exists between the measured parameter values and the design values used in the accident analyses. Evidence of this is shown in Table 14.1-5.

When the modified test program for Unit 2 was proposed, several questions were raised by the NRC relating to the modifications. The questions and VEPCOs responses are the subject of Appendix 14A.

Revision 5209/29/2016 NAPS UFSAR 14.1-8 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

14.1.4 Special Low-Power Tests - Unit 2 This test program consisted of a series of natural circulation tests that demonstrated the plants cooldown capability in several simulated degraded modes of operation at power levels of up to 3% of rated thermal power.

The objectives of the above tests and the methods used are described below.

1. Natural Circulation Test Objective: To demonstrate the capability to remove decay heat by natural circulation.

Method: The reactor is at approximately 3% power and all reactor coolant pumps are operating. All reactor coolant pumps are tripped simultaneously, with the establishment of natural circulation indicated by the core exit thermocouples and the wide-range resistance temperature detectors.

2. Natural Circulation With Simulated Loss of Offsite Power Objective: To demonstrate that following a loss of offsite ac power, natural circulation can be established and maintained while being powered from the emergency diesel generators.

Method: The reactor is at approximately 3% power and all reactor coolant pumps are operating. All reactor coolant pumps are tripped and a station blackout is simulated.

Alternating current power is returned by the diesel generators and natural circulation is verified.

3. Natural Circulation With Loss of Pressurizer Heaters Objective: To demonstrate the ability to maintain natural circulation and saturation margin with the loss of pressurizer heaters.

Method: Establish natural circulation as in Test 1, and turn off the pressurizer heaters at the main control board. Monitor the system pressures to determine the saturation margin, the depressurization rate, and the effects of charging/letdown flow and steam generator pressure on the saturation margin.

4. Effect of Steam Generator Secondary-Side Isolation on Natural Circulation Objective: To determine the effects of steam generator secondary-side isolation on natural circulation.

Method: Establish natural circulation conditions as in Test 1 but at 1% power. Isolate the feedwater and steam line for one steam generator and establish equilibrium. Return the steam generator to service.

5. Natural Circulation at Reduced Pressure

Revision 5209/29/2016 NAPS UFSAR 14.1-9 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Objective: To demonstrate the ability to maintain natural circulation at reduced pressure and saturation margin. The accuracy of the saturation meter will also be verified.

Method: The test method is the same as for Test 3, with the exception that the pressure decrease can be accelerated with the use of auxiliary pressurizer sprays. The saturation margin will be decreased to approximately 20°F.

14.1 REFERENCE DRAWINGS The list of Station Drawings below is provided for information only. The referenced drawings are not part of the UFSAR. This is not intended to be a complete listing of all Station Drawings referenced from this section of the UFSAR. The contents of Station Drawings are controlled by station procedure.

Drawing Number Description

1. 11715-LSK-1-3A Generator Breaker Closing
2. 11715-LSK-1-3B Logic Diagram: Power Circuit Breaker Opening
3. 11715-LSK-1-3C Logic Diagram: 86 Protective Lockout Relays
4. 11715-LSK-1-3D Logic Diagram: Main Transformer Protection Relays, 86-TL
5. 11715-LSK-1-3E Logic Diagram: Generator Lockout Relays
6. 11715-LSK-1-3F Logic Diagram: Main Transformer Differential Lockout Relays, 86-GL & 86-PWIA
7. 11715-LSK-1-3G Logic Diagram: Main Transformer Coolers
8. 11715-LSK-1-2A Logic Diagram: External Turbine Trips, Sheet 1
9. 11715-LSK-1-3H Logic Diagram: Main Transformer Alarms
10. 11715-LSK-1-2B Logic Diagram: Turbine Trips, Sheet 2
11. 11715-LSK-1-2C Logic Diagram: Turbine Trips, Sheet 3
12. 11715-LSK-1-2D Logic Diagram: Turbine Trips, Sheet 4
13. 11715-LSK-1-2E Logic Diagram: Turbine Trips, Sheet 5
14. 11715-LSK-1-2F Logic Diagram: Turbine Trips, Sheet 6
15. 11715-LSK-1-2G Logic Diagram: Turbine Trips, Sheet 7

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing I. Plant Instrumentation

1. Nuclear instrumentation Before core loading and Before core loading, nuclear instruments were aligned and source range Revision 5209/29/2016 (out of core) initial criticality detector response to a neutron source checked. Just before initial criticality all channels were checked to verify high-level trip functions, alarm setpoints, audible count rates where applicable, and operation of strip chart recorders and any auxiliary equipment.
2. Process instrumentation Ambient and/or at Equipment was aligned per manufacturers instructions and applicable test (temperature, pressure, temperature procedures. Applicable alarm, trip, and control setpoints were checked for level, and flow instruments) conformance with specified values.
3. Seismic instrumentation Before core loading This instrumentation was verified for correct installation and operability. A calibration record test was performed to verify operability of the magnetic tape playback units II. Reactor Coolant System
1. Vibration and amplitude Before core loading Vibration sensors were placed on the main coolant pumps and main cooling piping in order to check for excessive vibration while starting and stopping the pumps
2. Expansion and restraint Before core loading, During the heatup to operating temperature, selected points on cooldown NAPS UFSAR during heatup, and during components and piping of the reactor coolant system were checked at various cooldown. temperatures to verify unrestricted expansion. Points of interference detected during the heatup were corrected before increasing the temperature. Following cooldown to ambient temperature, the piping and components were checked to confirm that they returned to their approximate base points.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40. 14.1-10

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

3. Integrated hot functional Heatup, at temperature, The reactor coolant system was tested using pump heat to check heatup and Revision 5209/29/2016 tests and during cooldown. cooldown procedures and to demonstrate satisfactorily performance of (Hydrostatic testing has components and systems exposed to reactor coolant system temperature.

been satisfactorily Proper operation of instrumentation, controllers, and alarms was checked completed and reactor against operating conditions of auxiliary systems and setpoints verified.

coolant system Among the demonstrations performed were:

instruments aligned and a. To verify that water can be charged by the Chemical and Volume Control operational. Associated System at rated flow against normal reactor coolant pressures.

auxiliary systems were to be operational.)

b. To check letdown design flow rate for each operating mode.
c. To check response of system to change in pressurizer level.
d. To check response procedures and components used in boric acid batching and transfer operations.
e. To check operation of the excess letdown and seal-water flow paths.
f. To check steam generator level instrumentation response to level NAPS UFSAR changes.
g. To check thermal expansion of system components and piping.
h. To perform isothermal calibration of resistance temperature detectors and incore thermocouples.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-11

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

i. To operationally check out the residual heat removal system.

Revision 5209/29/2016

j. Visual and surface examination of the upper and lower core structures after the heatup and cooldown were completed (see item 6 below.)
4. Component tests
a. Pressurizer At operating temperature During the hot functional testing, the pressure-controlling capability of the pressurizer was demonstrated to be within the controlling band. After core loading, with the reactor coolant pumps operating and with full spray, the pressure-reducing capability of the pressurizer was verified. With the spray secured and all heaters energized, the pressure-increasing capability of the pressurizer was verified. Expected rates of pressure decrease/increase with tolerances were specified in the test procedures.
b. Reactor coolant system At ambient conditions, As the pumps and motors were placed in operation they were checked for:

pumps and motors during heatup, and at a. Direction of rotation.

temperature

b. Vibration.
c. Power requirements.

NAPS UFSAR

d. Lubrication
e. Cooling.
f. Recirculation flow.
g. Flow and pressure characteristics.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-12

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

h. Megger and hi-pot tests (as applicable)

Revision 5209/29/2016

i. Overload protection.
j. Correct power supply voltage During the reactor coolant system cold hydrostatic and hot functional tests, the pumps were operated to verify proper installation. Following core loading, measurements were made to determine flow and input power relationships.
c. Steam generators At ambient conditions, The proper operation of instrumentation and control systems for steam during heatup, and at generators was checked during heatup and at temperature. The heat transfer temperature. (The capability of the steam generators was demonstrated. The functioning of the secondary system had blowdown system was also checked.

been satisfactorily hydrostatically tested.)

d. Pressurizer relief and Pressure conditions The setpoints of the relief and safety valves were verified from vendor safety valves certification data, by bench tests, or by in-plant tests. When verified by in-plant tests, setpoints were checked by using a pressure assist device that adds to the force due to pressure. NAPS UFSAR Once the valve started to lift, this assist device was vented, allowing the valve to reseat immediately. Following lifting and blowdown of any valve, the reseating of the valve was verified.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-13

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

e. Main steam stop valves At operating temperature At hot conditions and with pressure equalized across the valve, the operation of Revision 5209/29/2016 (steam flow no required) the main steam stop valves was verified. The operating times were verified to be within expected values as specified by the test procedure.
f. Reactor coolant system At ambient conditions and At ambient and at hot conditions, the operation of the loop isolation valves was (RCS) loop isolation at operating temperature checked.

valves and pressure conditions

g. Main steam stop valve Before core loading Main steam stop valve piping was checked for excessive vibration while piping closing the main steam stop valves with steam available from the heatup of the reactor coolant by the reactor coolant pumps.
h. Pressurizer relief valve Pressure conditions The discharge piping associated with pressurizer relief valves was checked for discharge piping excessive vibration during the operation (opening and closing) of the pressurizer relief valves. Following lifting and blowdown of any valve, the re-seating of the valve was verified. (Note that this test may be done in conjunction with item d of this section.)
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with NAPS UFSAR clarifications noted in Section 3A.40.

14.1-14

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

5. Pressure boundary integrity tests Revision 5209/29/2016
a. Hydrostatic tests Below 200°F (after Cold hydrostatic testing of the reactor coolant system pressure boundary was verification of cleanliness, performed at test pressures as specified by ASME standards for the system.

and fill of system) Prior to pressurization, the system was heated above the minimum temperature for pressurization. The pressure was then increased in increments and at each increment inspections were made for leakage. Leaky valves or mechanical joints were not a basis for rejecting the test. Relief valves were provided to prevent inadvertent over-pressurization of the system.

b. Baseline data for During preoperational Systems and components that require inspections in accordance with inservice inspection testing Section XI of the ASME Code were examined for baseline data either following the cold hydrostatic test or following hot functional testing, depending on the system and component and its availability and accessibility.

Data from these inspections provided baseline data for inservice inspections

c. Nondestructive testing of Before hydrostatic test All reactor coolant system weld joints were nondestructively tested using liquid stainless steel safe ends penetrant and/or radiographic tests as required by Section III of the ASME and critical components Code. NAPS UFSAR
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-15

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Reactor Coolant System (continued)

6. Vibration monitoring on During and after hot Comprehensive vibration measurements had been made during hot functional Revision 5209/29/2016 reactor internals functional testing testing before core loading for Carolina Power & Light Companys H. B.

Robinson Unit 2. The results of these tests had been documented and submitted to the Directorate of Reactor Licensing. These data were the basis for acceptance of following plants, such as North Anna Units 1 and 2, without repeating these tests. During hot functional testing, the plant was operated with full flow for a minimum of 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br /> in order to achieve approximately 20 million cycles on the internal components. Following hot functional testing, the internals were removed and inspected for vibration effects before core loading.

III. Reactivity Control System

1. Chemical and volume At ambient and/or at Makeup and letdown operations were conducted with the Chemical and control system operating conditions. Volume Control System to check out the difference modes of dilution and System components were boration and verify flows in the different modes.

operationally checked out The adequacy of heat tracing to maintain the highest concentration in solution before fuel loading. was verified. The ability to adequately sample and the sampling techniques were demonstrated. NAPS UFSAR

2. Emergency boron shutdown During hot functional The pressure/flow characteristics of the emergency boration system were system testing verified by pumping into the reactor coolant system.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-16

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Reactivity Control System (continued)

3. Automatic reactor power Preoperational conditions The system alignment was verified at preoperational conditions to demonstrate Revision 5209/29/2016 control system (installation checks had the response of the system to simulated inputs. These tests were performed to been made) verify that the systems would operate satisfactorily at power. The alignment of the system was verified at power by programmed step changes and under actual test transient conditions to verify that controlled parameters were within tolerances specified by test procedures.
4. Incore monitor system
a. Incore thermocouples During heatup and at During heatup and at temperature, the incore thermocouples were calibrated to temperature the average of the reactor coolant system resistance temperature detectors. All readout and temperature-compensating equipment was checked during the calibration, and isothermal corrections for the operative thermocouples were determined.
b. Movable detector system At ambient conditions, Before core loading, the installation checkout of the movable detector system before core loading, and was completed. The response of each channel was verified using simulated after core loading and detector inputs. After core loading and insertion of the thimbles in the core, a critical testing dummy cable was used to check indexing and to ensure free passage to all NAPS UFSAR positions and set the limit switches based on data obtained during critical testing. During flux mapping at power, the detector responses to neutron flux were verified.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-17

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Reactivity Control System (continued)

5. Control rod system Revision 5209/29/2016
a. Rod control system Ambient conditions, During the installation check of this system, it was energized and operationally before core loading, and checked out with mechanisms connected to each power supply. The ability of hot conditions after core the system to step the mechanism was verified, the alarm and inhibit functions loading checked out, and correct values of system parameters adjusted to specified values. After core loading, the operation of each rod over its full range of travel was demonstrated.
b. Rod drop tests Cold and hot plant At cold and hot plant conditions after core loading, the drop times of the conditions after core full-length rods were measured. The drop time was measured from the release loading of the rod until the rod enters the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications.
c. Rod position indication At ambient conditions and During rod control system tests, the rod position indication system was aligned at temperature after core to provide rod movement indication. Rod setpoints were also adjusted during loading these tests. After plant heatup, individual rod positions were calibrated to within tolerances specified by the test procedure.

NAPS UFSAR

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-18

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Reactivity Control System (continued)

6. Auxiliary start-up Before core loading Three separate temporary source range instruments were installed in the core Revision 5209/29/2016 instrumentation test during core-loading operations. One of these channels served as a spare to the other two channels. During the core loading operations, these detectors were relocated at specific loading steps to provide the most meaningful neutron count rate within minimum acceptable levels, as specified by the core-loading procedures. The response of each channel to a neutron source was verified before core loading.

IV. Protection System

1. Reactor protection system Before core loading Before core loading, the reactor trip system was tested to demonstrate (installation checks had operability, proper logic, redundancy, coincidence, independence, and safe been performed) failure on power loss. The protection channels were verified through to tripping of the reactor trip breakers. The trip time of each reactor protection signal was also measured from the output of the sensor to tripping of the reactor trip breaker. These times were verified to be less than the values identified in the safety analysis report.

NAPS UFSAR

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-19

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing IV. Protection System (continued)

2. Engineered safety features Before core loading Before core loading, the engineered safety features logic systems were tested to Revision 5209/29/2016 (installation checks had demonstrate operability, proper logic, redundancy, coincidence, and been performed) independence. The protection channels were verified through to actuation of the output relays. The response time of each protection signal was also measured from the output of the sensor to actuation of the output relay. Their times were verified to be less than the values identified in the safety analysis report. Operation of the engineered safety features components (i.e., motors, valves, diesel generators) was checked in other tests.

V. Power Conversion System

1. System tests
a. Vibration frequency and Hot functional testing and When the main turbine was rolled, vibration readings were monitored. (Turbine amplitude or plant heatup after initial vibrations were also monitored throughout the power escalation program.)

criticality Major equipment (e.g., feedwater pumps and condensate pumps) was operated as it became available and was observed for indications of excessive vibration.

b. Expansion and restraint During heatup, at During heatup to operating temperature, selected points on the components and NAPS UFSAR temperature, and piping of the systems were checked at various temperatures to verify that they cooldown before core could expand unrestricted. After cooldown, these components were verified to loading have returned to their approximate cold position.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-20

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing V. Power Conversion System (continued)

2. Components and individual systems Revision 5209/29/2016
a. Steam generator pressure Pressure conditions The setpoints of safety valves were verified from vendor certification data, by relief and safety valves bench tests, or by in-plant tests, setpoints were checked by using a pressure assist device that adds to the force due to pressure. Once the valve left the seated position, the assist device was vented, allowing the valve to re-seat immediately. Steam relief valve setpoints were made during instrument alignment and verified by plant transient tests.
b. Emergency feedwater Before initial criticality During hot functional testing before initial criticality, the emergency feedwater (auxiliary) system system was checked out to verify its ability to feed the steam generators.

Automatic starting was verified during testing of the safeguards logic system tests. The auxiliary feedwater piping was checked for excessive vibration while starting and stopping the auxiliary feedwater pumps with normal operation of the associated motor-operated and hand-control discharge valves in the auxiliary feedwater system.

c. Turbine control and Hot functional testing During hot functional testing, the turbine control system was demonstrated in bypass valves and/or power operation turbine operation up to and including a period of operation at synchronous NAPS UFSAR after initial criticality speed. The turbine bypass valves to the condenser and their associated control systems were operationally checked out before and during hot functional testing. Other testing on the turbine bypass valves was completed after initial criticality.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-21

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing V. Power Conversion System (continued)

d. Feedwater and feedwater Before hot functional The feedwater and condensate pumps were operationally checked out before Revision 5209/29/2016 control system testing and at power hot functional testing. During power escalation, the power was slowly increased and the ability of the feedwater pumps and control system to maintain level in the steam generators was verified. Steam generator level indicators were aligned before filling the system, and during fill the system was used to monitor the level in the steam generator. Before start-up, the feedwater-regulating valve control system was calibrated using simulated signals. During start-up when at power the ability of the system to control level within specified tolerances under transient conditions was also verified
e. Condenser circulating Before initial core loading Before core loading, the main circulating water pumps and circulating water water and at power system valves were tested to verify operability. During unit start-up, acceptable condenser operation was verified in accordance with operating procedures.
f. Makeup water and During steam generator The makeup system to the steam generators was checked out during fill of the chemical treatment fill, hot functional testing, steam generators during hot functional testing and at power. The chemical systems and at power treatment system was checked out when chemicals were added to the steam generators at heatup and at operating conditions. NAPS UFSAR
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-22

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VI. Auxiliary Systems

1. Reactor coolant system See III, item 1.

Revision 5209/29/2016 makeup (Chemical and Volume Control System (CVCS))

2. Seal and pump cooling Before heatup and at Before reactor coolant pump operation and with the system pressurized, flow to water (CVCS) temperature the pump seals and cooling water flow was adjusted to specified values using installed instruments. During hot functional testing when at operating temperature and pressure, seal and cooling flows and temperatures were checked.
3. Vent and drain system During initial primary fill Venting of the reactor coolant system was done during initial filling by venting and pressurization and the reactor vessel head and pressurizer. During hot functional testing and after during hot functional core loading, the secondary system was vented while pressurizing the testing secondary system. Secondary drains were tested for unrestricted flow in accordance with operating procedures.
4. Component cooling system Ambient and/or hot plant Component cooling flow to the various components in the system was adjusted, conditions the system operationally checked out, and setpoints adjusted. Data were taken NAPS UFSAR to verify that adequate cooling was provided to each cooled component and, when load was available, that temperature limits were being maintained.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-23

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VI. Auxiliary Systems (continued)

5. Residual heat removal Before and during hot This system was tested by verifying pressure and flow characteristics of the Revision 5209/29/2016 system functional testing pumps and operation of the isolation valves. During cooldown after hot functional testing, the heat removal capability and cooldown rate of the system was demonstrated. The residual heat removal system piping was checked for excessive vibration while starting and stopping the residual heat removal pumps with normal operation of the valve used to control flow.
6. Purification system (CVCS) Operating temperature During hot functional testing with the demineralizers charged with resin, before core loading operation of the purification system was demonstrated by verification of flow, pressure drops, temperatures, and conditioning of ion-exchange resins (see III, item 1).
7. Fire protection system Before initial core loading The water fire protection system motor and diesel-driven pumps and pressure maintenance equipment were tested to verify proper operation in conformance with fire insurance requirements. The carbon dioxide fire protection system was tested by individual component checks and by puff tests in various fire-protected areas by simulating system initiating conditions. The Halon 1301 fire protection system was checked for operability and proper installation. NAPS UFSAR
8. Service water system Before initial core loading The system was operationally checked out to verify pressure and flow. Service water flow was verified to components in the system.
9. Auxiliary building Before initial core loading The system was operated to test for leaks and air flows to the areas supplied ventilation from the system and to verify motor currents and speeds, verify setpoints, and check alarms (see also IX.)
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-24

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VI. Auxiliary Systems (continued)

10. Compressed gas system Before initial core loading The instrument air system, including air receivers and compressors, was tested Revision 5209/29/2016 (used for safety-related to verify proper operation. A loss-of-instrument-air test was conducted by functions) securing the makeup air to each dedicated air accumulator supplying each safety-related component that is required to operate following a loss of instrument air. The capacity of each dedicated air accumulator was verified by operating the safety-related component a specified number of times over a specified time interval. Air-operated components were tested to ensure that they fail in the safe mode upon loss of operating pressure. Other compressed gas systems were verified for proper operation.
11. Control-rod drive Before and/or during hot The system was operationally checked out to verify air flow, temperatures, mechanism and rod position functional testing motor current and speed.

indication coil cooling system

12. Neutron shield tank cooling Before initial core loading The system was operationally checked out to verify pump and heat exchanger system operability.
13. Leak detection system Before and during Temperature detectors and their alarm functions in the drain lines from (sensitivity and accuracy to preoperational tests pressurizer safety valves and the reactor vessel head seal were checked.

NAPS UFSAR detect leaks) Pressurizer relief tank level and temperature sensors were calibrated and their associated alarms checked.

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-25

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VI. Auxiliary Systems (continued)

14. Primary sampling system Before and/or during hot Operations were performed to:

Revision 5209/29/2016 functional testing a. Established purge times.

b. Demonstrate that liquid and gas samples can be obtained from sample points.
c. Demonstrate that valves, instruments and controls function properly.
d. Verify proper functioning of the sample cooler.
e. Demonstrate that sample vessels can be removed and replaced without problems.
15. Primary pressure relief Before hot functional The pressurizer relief tank, associated valves, and instrumentation were system testing and at pressure checked out to verify performance of design functions. (See II, item 4.3, for conditions testing of pressurizer relief and safety valves.)

VII. Electrical Systems

1. Normal distribution test Throughout plant start-up The integrity and operation of these components were verified before being (transformers, motor, relay and before applicable energized by meggering, hi-pot testing, continuity checks, and operational switches, power supplies equipment operation verification of controlling devices as applicable. After being energized, phasing NAPS UFSAR etc.; phasing and meggering and voltage regulation tests were performed and channel and train separation where applicable) and redundancy features were verified as applicable.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-26

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VII. Electrical Systems (continued)

2. Vital bus test (full-load test Before initial core loading Verification that the vital bus load could be supplied under normal and Revision 5209/29/2016 using all power sources) power-failure conditions was made. In particular, transfers that take place under loss of power and redundant features function per design were verified.
3. Direct current systems Before core loading The redundant features of the battery, battery charger, and inverters were (full-load and duration test) checked out. The capacity of the battery and voltage regulation was verified.

The recharging of a discharged battery within a specified period was also verified, The ability of each inverter to maintain design output under varying direct current input was also verified.

4. Communications systems Before fuel loading and To verify proper communications between all onsite stations and (telephone, public address, during power operation interconnection to commercial telephone service. To balance and adjust intercoms, and evacuation amplifiers and speakers and verify that evacuation alarms could be heard at all signals) stations throughout the plant. Also, to verify that all temporary communications at the fuel-loading stations and control stations were functioning properly.
5. Emergency power systems Before initial core loading The automatic starting and loading of the diesel generators was demonstrated (manual start and under loss of emergency bus alternating current power. The operation of the synchronization, full NAPS UFSAR logic and sequencing of circuit breakers were demonstrated along with the automatic loading tests, proper safety-related bus stripping and separation of non-vital loads. Load under loss of all alternating current voltage) duration tests were demonstrated over several hours of operation along with voltage and frequency regulation tests under transient and steady-state conditions.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-27

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing VIII. Containment Systems

1. Reactor containment Before core loading A containment structural test was performed. Containment Type A, B, and C Revision 5209/29/2016 leakage tests were performed in accordance with Appendix J to 10 CFR 50.
2. Ventilation system Before and/or during hot The system was operated to balance air flows and to verify ability to maintain functional testing temperatures below maximum allowable limits.
3. Post-accident heat removal Before initial criticality Tests were performed to verify pump operating characteristics and response to system (containment sprays) control signals, sequencing of the pumps, valves, and controllers, and to ensure that spray nozzles were unobstructed. The time required to actuate the system after a containment high-pressure signal is received was verified.
4. Containment isolation Before core loading The operation of actuation systems and components used for containment isolation was verified.
5. Hydrogen removal system Before initial criticality Operability of flow paths and heaters associated with the recombiners were verified.

IX. Gaseous Radioactivity Removal Systems Filtration system (testing Before core loading Testing was performed to verify flows, pressure drops, and effectiveness of performed on particulate filter these systems in performing their function. NAPS UFSAR system in containment and auxiliary structures for post-accident and routine release of gaseous effluent)

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-28

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing X. Emergency Core Cooling Systema

1. System tests (expansion and Before and/or during hot Movement of piping that connects to the reactor coolant system was checked Revision 5209/29/2016 restraints, vibration) functional testing by the test described in II, item 2. Pumps, motors, and piping were observed for excessive vibration.
2. High-pressure safety Before core loading This system was operationally tested to adjust pressure/flow values. Tests were injection also conducted to check pump operating characteristics and to verify operation from normal and emergency power sources. More specifically that:
a. Valves installed for redundant flow paths operated as designed.
b. Pump operating characteristics were verified and the capability of the high-head safety injection pumps to take suction from the low-head pumps was demonstrated with the reactor coolant systems at ambient conditions.
c. Valves and pumps operated on operator initiation and/or automatically on initiation of a safety injection signal.
d. The fail position on loss of power for each remotely operated valve was as specified.
e. Level and pressure instruments were properly calibrated. NAPS UFSAR
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-29

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing X. Emergency Core Cooling Systema (continued)

3. Low-pressure safety Before core loading The low-head safety injection system was checked to verify design flow, flow Revision 5209/29/2016 injection paths, and pump operating characteristics. Tests were conducted to verify operation from the normal power source. More specifically, that:
a. Valves installed for redundant flow paths operated as designed.
b. Pump operating characteristics were verified with the reactor coolant system at ambient conditions.
c. Valves and motors operated on operator initiation and/or automatically on initiation of a safety injection signal.
d. The fail position on loss of power for each remotely operated valve was as specified.
e. Level and pressure instruments were properly calibrated.
4. Accumulator Before core loading Flow through the accumulator discharge lines was initiated to demonstrate that the motor-operated valves stroked properly and the check valves were free to open. Tests were also made to verify that accumulator pressure could be maintained.

NAPS UFSAR

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-30

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing XI. Fuel Storage and Handling System

1. Spent-fuel pit cooling and Before core loading Tests were performed to verify operability of the spent-fuel pit cooling pumps; Revision 5209/29/2016 refueling purification operability of the refueling purification pumps; flow through the spent-fuel pit system heat exchange loops; operation of the skimmer loops; flows through the refueling purification filters and ion exchanger; alarm setpoints; and correct functioning of valves, instruments, and controls.
2. Refueling equipment (hand Before storage of new fuel Tests were performed before core loading to demonstrate the functioning of the tools and power equipment, and initial core loading fuel transfer system and the fuel handling equipment using a dummy assembly, including protective in accordance with design drawings and instruction manuals. The sections that interlocks) involve the spent-fuel facility were checked before the storage of new fuel in the spent-fuel storage pool.
3. Operability and leak tests of Before initial core loading During the initial filling of the spent-fuel storage pool, operability and leaking sectionalizing devices in testing of the sectionalizing devices was performed.

fuel storage pool and refueling canal

4. Spent fuel storage building Before plant start-up This is part of the auxiliary building ventilation system (refer to VI, item 1).

ventilation system

5. Spent-fuel storage radiation Before plant start-up Refer to XIII, item 1.

NAPS UFSAR monitoring equipment

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-31

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing XII. Reactors Components Handling System Reactor components handling Before use for installation Testing was conducted on the polar crane in accordance with standard crane Revision 5209/29/2016 system (polar crane) of components within the testing procedures during the construction of the station.

containment XIII. Radiation Protection System

1. Process, criticality, and area Before core loading and Before core loading, the radiation alarms associated with core loading were monitors plant operation checked out and alarm setpoints were verified. Process and area monitor sensors and channels were calibrated and alarm setpoints made.
2. Personnel monitor and Before core loading and/or Before core loading and required equipment use, instruments were calibrated.

survey instruments initial criticality After this initial calibration, the instruments are periodically checked for recalibration.

3. Laboratory equipment Before core loading and Laboratory equipment was checked to verify equipment performance and initial criticality calibration. Chemical analyses performed on standard samples. During start-up the equipment received additional verification by normal usage.
a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

NAPS UFSAR 14.1-32

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-1 (continued)

LIST OF PREOPERATIONAL TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing XIV. Radioactive Waste System Radioactive waste system Before initial criticality Tests were performed to establish the satisfactorily performance of pumps and Revision 5209/29/2016 instruments, leaktightness of piping and equipment, and the operation of packaging and waste reduction equipment; and to verify proper operation of alarms and controls. More specifically, to ensure that:

a. Manual and automatic valves were operable
b. Instrument controllers operated properly.
c. Alarms were operable.
d. Pumps performed their system function satisfactorily.
e. The waste gas compressors operated properly.
f. The gas analyzers operated properly.
g. The waste evaporator was operational.
h. The hydrogen and nitrogen supply packages were sufficient for operation of the system.

NAPS UFSAR

a. The preoperational test program for the emergency core cooling system (ECCS) meets the requirements set forth in Regulatory Guide 1.79, June 1974, with clarifications noted in Section 3A.40.

14.1-33

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading

1. Mechanical and instrument Before initial criticality Operational testing of the rod control systems was conducted to check the Revision 5209/29/2016 tests on control rod drive and controlling features, adjusts setpoints, and verify rod speeds and sequencing rod position indicators of power to the rod drives. After core loading and installation of the rod mechanisms, tests were conducted to verify operation of the rod drive mechanisms, over their full travel, the latching and releasing features were demonstrated, and calibration of the position indicators was performed over the rod full-range travel per tolerances specified in the test procedure.
2. Reactor trip circuit and Before initial criticality Operational testing was conducted to verify the reactor protection circuits in manual trip tests the various modes of tripping, including manual reactor trip up to the tripping of the reactor trip breakers. After core loading, the release and insertion of each full-length mechanism was demonstrated.
3. Rod drop measurement cold Before initial criticality At cold and hot plant conditions after core loading, the drop times of the and hot at rated flow and no full-length rods were measured. The drop time was measured from the flow beginning decay of the stationary gripper coil voltage until the rod entered the top of the dashpot. This time was verified to be less than the maximum value specified in the Technical Specifications. Ten additional measurements were made for the fastest and slowest rods.

NAPS UFSAR

4. Pressure test of reactor Before initial criticality After core loading and installation of the reactor vessel head and torquing of coolant system the reactor vessel head studs, pressure testing was performed at 100 psi above operating pressure to verify that no leakage occurred past the head and vessel seal.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-34

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading (continued)

5. Chemical tests (to establish Before heatup Water for reactor coolant system fill and makeup was analyzed for chloride Revision 5209/29/2016 water quality) content, conductivity, total suspended solids, pH, clarity, and fluorides to requirements specified by the chemistry manual for NSSS. During pre-operational testing, hydrazine was added to scavenge oxygen. After core loading and before exceeding 250°F, hydrogen was added to scavenge oxygen during critical operation. After initially establishing chemistry, analysis was performed to verify requirements.
6. Nuclear instrumentation Before core loading Before core loading, the source range channels were aligned and operational calibration and neutron based on data derived from using a neutron source. After a power history had response been established on the core, the detector anode and discriminator voltages were reset based on obtained data.
7. Mechanical and electrical Before initial criticality The movable detector systems were checked out in accordance with the tests of incore movable and during physics operating procedures and ICPs. After core loading and insertion of the detectors testing detector thimbles, the system was again operationally checked out by ensuring the free passage of detectors into all inserted thimbles. Electrical tests were performed using simulated signals to check out the recorders.

During physics measurements the system was operationally checked and NAPS UFSAR limit switches set based on flux mapping data. Incore thermocouples were checked out during hot functional testing (see Table 14.1-1, III, item 4.a).

a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-35

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing I. Precritical Tests After Fuel Loading (continued)

8. Reactor coolant flow Before initial criticality After core loading, measurements were made of elbow tap differential Revision 5209/29/2016 measurement pressures to make relative comparison. At hot shutdown conditions after core loading, measurements of loop elbow differential pressure drops were made.

Using these data with the reactor coolant pump performance curve, the calculated flow was verified to the design flow. Flow coastdown and transients after reactor coolant pump trips were also determined at shutdown conditions after core loading.

9. Pressurizer effectiveness test At hot shutdown after At hot no-load temperature and pressure the effectiveness of the pressurizer core loading heaters in maintaining and increasing system was demonstrated. The heaters were energized and the pressure was compared with an expected pressure rise given in the procedure. The ability of the spray system to reduce pressure was also demonstrated. The spray valves were opened and the pressure decrease compared with the expected pressure decrease given in the procedure.
10. Vibration monitoring on -- No vibration monitoring was done after core loading (refer to test identified reactor internals in Table 14.1-1, II. item 6)
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for NAPS UFSAR a listing of symbols used in these figures.

14.1-36

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests

1. Initial criticality Plant at hot shutdown The objective was to bring the reactor critical for the first time from the plant Revision 5209/29/2016 conditions specified. Before the start of rod withdrawal, the nuclear instrumentation had been aligned and checked, and conservative reactor trip setpoints made per the test procedures. All rods were withdrawn except the last controlling bank, which was left partially inserted for control once criticality was achieved by boron dilution. At preselected points in rod withdrawal and boron dilution, data were taken and inverse count rate ratio pots were made to enable extrapolation to the expected critical point.
2. Radiation surveys At steady-state Radiation surveys were made during the power escalation to determine dose conditions during power rate levels at preselected points inside containment due to neutron and escalation gamma radiation. Instruments used were calibrated to known sources, and the calibration rechecked following the survey.
3. Calibration of nuclear After start-up and during After initial criticality and during escalation into the intermediate and power instruments with thermal escalation ranges, data were taken to verify overlap between the source, intermediate, power and determination of and power range channels and to verify the alarm and protective functions.

overlap These data were collected until the overlaps were firmly established. During low power escalation, the power range detector currents were monitored and NAPS UFSAR compared with the intermediate range currents to verify response of the power range detectors. The power range nuclear channels were calibrated to reactor thermal output based on measurement of secondary plant feedwater flow, feedwater temperature, and steam pressure.

a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-37

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests (continued)

4. Effluent radiation monitors Before plant start-up These instruments were calibrated to a known radiation source or to analog Revision 5209/29/2016 (calibration against known signals which had been calibrated to known radiation sources.

concentration)

5. Moderator temperature Hot zero power At normal no-load temperature and no nuclear heating, reactor coolant reactivity coefficient system cooldown and heatup were accomplished using the steam dump and reactor coolant pumps operation as required. An approximate 5°F change in temperature was initiated, and during these changes the average temperature and reactivity were recorded on an X-Y plotter. From these data the moderator temperature coefficient was determined.
6. Pressure reactivity coefficient -- Direct measurements of the pressure coefficient of reactivity were not made, measurements since the effects of pressure on reactivity are of second order when compared with other effects.
7. Control rod reactivity worth Hot zero power Under zero-power conditions at near operating temperature and pressure, the determination of differential nuclear design predictions for rod cluster control assembly (RCCA) group and integral worth and differential worths were validated. These validations were made from boron verification of worth for concentration sampling data, RCCA bank positions, and recorder traces of shutdown capability reactivity. From this data the integral RCCA group worths were determined, NAPS UFSAR including verification of rod insertion limits to ensure adequate shutdown margin. The minimum boron concentration for maintaining the reactor shutdown with the most reactive rod cluster control assembly stuck in the full-out position was determined for Unit 1. The determination was made from analysis of boron concentration and RCCS worths.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-38

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing II. Initial Criticality and Low-Power Tests (continued)

8. Boron reactivity worth Zero power Differential boron worth measurements were made by monotonically Revision 5209/29/2016 measurement increasing or decreasing reactor coolant boron concentration. Compensation for the reactivity effect of the boron concentration change was made by withdrawing or inserting respective control rods to maintain moderator average temperature and power level constant and observing the resultant accumulated change in core reactivity corresponding to these successive rod movements.
9. Determination of boron Zero power These determinations are described under II, item 1 above.

concentration of initial criticality and reactivity allocation

10. Flux distribution Zero power Flux distribution measurements with normal rod patterns were taken during measurement with normal rod the zero-power physics tests.

patterns

11. Chemical tests to demonstrate Before criticality and Before criticality, the procedures and equipment for performing chemical ability to control water quality during power escalation analyses of primary and secondary systems were demonstrated. During power escalation, sampling was performed and analysis done to verify that NAPS UFSAR plant chemistry was within specifications.
12. Pseudo-rod-ejection test, to Zero power Incore measurements were made for Unit 1 under pseudo-ejected-rod verify safety analysis (hot) conditions simulating the zero-power accident to determine the hot-channel factors and verify that they were within assumptions made in the accident analysis.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-39

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Power Ascension Tests

1. Natural circulation test to -- The ability of natural circulation to remove decay heat has been demonstrated Revision 5209/29/2016 confirm sufficient cooling at the Carolina Power & Light Companys H. B. Robinson Unit 2. Tests have capacity shown natural circulation flow to be more than adequate to remove decay heat, and such a test was not repeated on North Anna Unit 1. However, special tests were conducted for Unit 2, as described in Section 14.1.4.
2. Power reactivity coefficient During power escalation During each power escalation for Unit 1, recorder traces were made of evaluation and power defect reactor power and reactivity changes. From these traces, the power measurements (30, 50, 75 and coefficient of reactivity and power defects were determined.

100%)

3. Plant response to load swings, During power escalation Plant response to the following load changes was demonstrated:

including automatic control a. +/-10% step load change from 30, 75 and 100% power.

system checkout (30, 50, 75 and 100%) b. 50% load reduction from 75 and 100% power.

c. Plant trip from 100% power level.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

NAPS UFSAR 14.1-40

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Power Ascension Tests (continued)

The data collected from the performance of these tests were analyzed for Revision 5209/29/2016 control system behavior and requirements for realignment. Acceptance criteria, such as the plant not tripping (where applicable), relief and safety valves not lifting, and steam dump operating correctly, were identified in the individual procedures. At approximately 30% power, the automatic control systems were checked by initiating a perturbation and observing controller response. During the transient tests these systems were operationally checked under actual design load changing conditions.

4. Chemical analysis (30, 50, 75, During power escalation During low-power physics tests and at 30, 50, 75, and 100% power, samples 100%) of reactor coolant were taken and analysis performed to verify that coolant chemistry requirements could be maintained.
5. Effluents and effluent During power escalation Installed effluent monitors were operated continuously at selected locations monitoring systems (30, 50, in the plant to monitor for radioactive constituents in the effluents.

75, 100%) Instruments detected any changes in activity and alerted the operator when radiochemical analysis should be performed

6. Evaluation of core During power escalation At steady-state power points, incore data were obtained and analysis performance (30, 50, 75, performed to verify that the core performance margins were within design NAPS UFSAR 100%) predictions, for expected normal and abnormal rod configurations.
7. Loss of flow Before criticality Reactor coolant system response to loss of flow for various combinations of pump trips was determined from hot shutdown conditions.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-41

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Power Ascension Tests (continued)

8. Turbine trip (100%)a At power This test verified that the pressurizer safety valves did not lift and that the Revision 5209/29/2016 plant could be maintained in a hot shutdown condition. The turbine trip from 100% power was conducted as an integral part of the generator trip from 100% power.
9. Generator trip (100%)a At power Generator trip was performed at 100% power to verify the plants capability of withstanding an instantaneous reduction in load from 100 to 0%. A generator trip was initiated by manually opening the main generator breakers.

This would be automatically initiate a turbine trip.

10. Shutdown from outside the Greater than or equal to The ability to bring the plant to and maintain the plant in hot shutdown control room 10% generator power conditions after a trip from greater than or equal to 10% power was demonstrated using instrumentation and controls outside the control room.
11. Loss of offsite power Greater than or equal to Tests were performed in which loss of voltage was simulated. Starting of the 10% generator power diesels and connecting of the emergency loads on the emergency bus was demonstrated.
12. Radiation surveys and At power The surveys to determine the effectiveness of the shielding have been shielding effectiveness (50 discussed under Radiation Survey (Item II.2). These surveys were conducted and 100%) up to and including 100% power.

NAPS UFSAR

13. Part-length rod Approximately 75% Technical Specifications required part-length rods for Unit 1 to remain fully insertion/withdrawal (75%) power withdrawn; therefore no testing was performed. No part-length rods were installed in Unit 2.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-42

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Power Ascension Tests (continued)

14. Dropped rod-effectiveness of Greater than or equal to Automatic turbine runback and rod withdrawal stop is not necessary as a Revision 5209/29/2016 instruments to detect dropped 50% reactor power result of a dropped rod, and the circuitry required for such action does not rod and verification of exist in this plant. Rod drop tests based on common failure criteria were associated automatic action performed dynamically to demonstrate the negative rate trip function from greater than or equal to 50% reactor power.
15. Vibration measurements on -- These measurements were not performed at power. Refer to II, item 6, above reactor internals (30, 50, 75, for measurements before operation.

and 100%)

16. Pseudo-rod-ejection test to 30% power Incore measurements were made for Unit 1 with individual rods withdrawn verify safety analysis out of bank position to determine the resulting hot-channel factors and verify that they are within expected limits. These determinations were made from movable detector and thermocouple data. This measurement was not performed on Unit 2 because of the negligible worth of a control rod withdrawn from its full-power insertion limit, and the large magnitude of margin remaining to hot-channel factor limits in the ejected-rod configuration (see Section 14.1.3). This was verified by the test performed for Unit 1.
17. Evaluation of flux asymmetry 50% power Incore flux measurements were made with a single rod assembly moving NAPS UFSAR partially below bank position and fully inserted to demonstrate that core limits are not exceeded.
a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

14.1-43

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-2 (continued)

LISTS OF START-UP TESTS Plant Test or Measurement Condition/Prerequisite Test Objective and Summary of Testing III. Power Ascension Tests (continued)

18. Process computer (30, 50, During power escalation When available during power escalation, the process computer was checked Revision 5209/29/2016 100%) out and comparisons made between process signals and those assessed by the process computer. (No safety-related functions are performed by the computer.)
19. Moisture carryover At power Radioactive tracer of sodium-24 was injected into the steam generators.

measurement Samples obtained from the steam generator upper shell, main steam line taps, and the feedwater system were analyzed.

a. Reference Drawings 1 through 15 show the logics for initiation of turbine and generator trips. The logics show the sensed variables and all available setpoints. See Figure 7.2-1 for a listing of symbols used in these figures.

NAPS UFSAR 14.1-44

Revision 5209/29/2016 NAPS UFSAR 14.1-45 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-3 UNIT 2 START-UP PHYSICS TESTS I. Hot Zero Power Tests

1. Reactivity computer checkout.
2. Isothermal temperature coefficient at ARO and D bank in (also D, C banks in if MTC for D bank in is greater than or equal to 0 pcm/°F).
3. Boron endpoints at ARO; D bank in; D, C banks in; D, C, B banks in; D, C, B, A banks in; shutdown bank B in with all other rods out; and shutdown bank A in with all other rods out.
4. Reactivity worths of all control and shutdown rod banks.
5. Boron worth over the range of control banks A through D moving during rod insertion and withdrawal.
6. Power distribution measurements for ARO and D bank in.

II. Power Ascension Tests

1. 30% power flux map.
2. 50% power flux map.
3. Pseudo-dropped-rod test (RCCA D-10) and associated power distribution measurements at 50% power.
4. Incore/ex-core detector calibration flux maps at 75% power.
5. APDMS flux maps at or below 95% power.
6. Flux maps at 90% and 100% power (equilibrium conditions).

Revision 5209/29/2016 NAPS UFSAR 14.1-46 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-4 PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 I. Hot Zero Power Tests

1. Isothermal temperature coefficient at D, C banks in; D, C, B banks in; and D, C, B, A banks in.
2. Boron endpoint for the N-1 rods-in configuration.
3. Reactivity worth of N-1 rods.
4. Pseudo-rod-ejection and associated power distribution measurements.

II. Power Ascension

1. Pseudo-rod-ejection and associated power distribution measurement at 30% power.
2. Pseudo-dropped-rod test (RCCA H-6) and associated power distribution measurement.
3. Power coefficients.
4. Integral power defect.
5. Doppler-only power coefficients.

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-5

SUMMARY

OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured life (BOL), Design Accident Analysis Revision 5209/29/2016 Test Description Core Condition Parameter Value Best Estimate) Tolerance Criterion

1. Isothermal Banks D, C in T -7.86 pcm/°F -8.9 pcm/°F +/-3 pcm/°F -2.107 pcm/°F temperature Banks D, C, B in T -13.48 pcm/°F -14.1 pcm/°F +/-3 pcm/°F -2.134 pcm/°F coefficient Banks D, C, B, T -14.07 pcm/°F -13.8 pcm/°F +/-3 pcm/°F -2.135 pcm/°F A in
2. Boron N-1 rods inserted CB 601 ppm 580 ppm +/-50 ppm x CB 24000 endpoint pcm where =

11.08 pcm/ppm

3. Rod worth N-1 rods IN-1 a 8015 7893 pcm +/-789 pcm (IN-1)/1.04 5780 pcm
4. Pseudo- hot zero power FQ 6.85 10.8 NA 13.0 ejected (HZP), Bank C at control rod 120 steps, Bank D IB-8 a 443 pcm 464 pcm +/-46 pcm (IB-8) x 1.04 at 0 steps, RCCA 785 pcm B-8 at 228 steps. NAPS UFSAR 30% power, Bank FQ 2.1 2.1 NA 7.07 D at 194 steps, RCCA B-8 at 228 IB-8 3 pcm 7 pcm +/-1 pcm b (IB-8) x 1.04 steps. 200 pcm N
5. Pseudo- 50% power, F 1.62 1.70 NA 1.69 c dropped H RCCA H-6 control rod IH-6 a 138 pcm 146 pcm +/-22 pcm (IH-6) x 1.04 250 pcm 14.1-47

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-5 (continued)

SUMMARY

OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured life (BOL), Design Accident Analysis Revision 5209/29/2016 Test Description Core Condition Parameter Value Best Estimate) Tolerance Criterion

6. Power 30% power ( Q ) power -15.24 pcm/% -14.02 pcm/% +/-4.57 pcm/% NA coefficient power power power 50% power ( Q ) power -12.74 pcm/% -13.75 pcm/% +/-3.82 pcm/% NA power power power 75% power ( Q ) power -13.57 pcm/% -13.39 pcm/% +/-4.07 pcm/% NA power power power 90% power ( Q ) power -10.70 pcm/% -13.31 pcm/% +/-3.21 pcm/% NA power power power
7. Power defect 0 - 100% power Reactivity worth 1270 pcm 1299 pcm +/-191 pcm NA
8. Doppler-only 30% power -13.62 pcm/% -11.35 pcm/% +/-4.09 pcm/% Inferred value power ( Q ) inferred Doppler power power power +/-30% uncertainty coefficient must overlap allowance range of Figure 15.1-3 NAPS UFSAR 50% power ( Q ) inferred Doppler

-10.77 pcm/% -10.75 pcm/% +/-3.23 pcm/% Inferred value power power power +/-30% uncertainty must overlap allowance range of Figure 15.1-3 14.1-48

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Table 14.1-5 (continued)

SUMMARY

OF UNIT 1 MEASURED VALUES, DESIGN VALUES, DESIGN TOLERANCE, AND ACCIDENT ANALYSIS CRITERIA FOR PHYSICS TESTS THAT HAVE BEEN DELETED FOR UNIT 2 Design Value (beginning of Unit 1 Measured life (BOL), Design Accident Analysis Revision 5209/29/2016 Test Description Core Condition Parameter Value Best Estimate) Tolerance Criterion

8. Doppler-only 75% power ( Q ) inferred Doppler

-11.08 pcm/% -9.96 pcm/% +/-3.32 pcm/% Inferred value power power power power +/-30% uncertainty coefficient must overlap (continued) allowance range of Figure 15.1-3 90% power ( Q ) inferred Doppler

-7.59 pcm/% -9.38 pcm/% +/-2.28 pcm/% All inferred values power power power fell within range of Figure 15.1-3, as shown on Figure 14.1-3

a. IN-1 = integrated reactivity worth of all control rods except the most reactive rod (N-1).

IB-8 = integrated reactivity worth of rod cluster control assembly (RCCA) B-8.

IH-6 = integrated reactivity worth of RCCA H-6.

b. Violation of design tolerance was evaluated to be insignificant due to low value of reactivity worth.

NAPS UFSAR

c. Accident analysis referenced to hot full power.

14.1-49

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Figure 14.1-1 TYPICAL PRE-OPERATIONAL TEST SEQUENCE Revision 5209/29/2016 NAPS UFSAR 14.1-50

The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Figure 14.1-2 TYPICAL START-UP TEST SEQUENCE Revision 5209/29/2016 NAPS UFSAR 14.1-51

Revision 5209/29/2016 NAPS UFSAR 14.1-52 The following information is HISTORICAL and is not intended or expected to be updated for the life of the plant.

Figure 14.1-3 CYCLE 1 BOL PHYSICS TEST DOPPLER POWER COEFFICIENT USED IN ACCIDENT ANALYSIS UNIT 1

Revision 5209/29/2016 NAPS UFSAR 14.2-1 14.2 AUGMENTATION OF VEPCOS STAFF FOR INITIAL TEST AND OPERATION The start-up organization used during the period of initial operation consisted of all personnel in the Station Operations Department, with additional support provided by the Engineering Services Department and the Chemistry and Health Physics Department.

In operations, there were, for one-unit operation, five senior licensed shift supervisors, five licensed control room operators, and a combined group of 14 assistant control room operators and auxiliary operators with a minimum of two licensed assistant control room operators. For two-unit operations, there were five senior licensed shift supervisors, five senior licensed assistant shift supervisors, 10 licensed control room operators, and a combined group of 18 assistant control room operators and auxiliary operators with a minimum of six licensed assistant control room operators. Shifts were scheduled to ensure that a minimum of three licensed reactor operators and two licensed senior reactor operators are on duty at all times during two-unit operations.

Technical support was provided during start-up using the services of graduate-level engineers. A trained power engineer was assigned through the architect-engineer to assist in preliminary operations for both units. In addition, engineering representatives were assigned at the station by the supplier of the nuclear steam supply system to render start-up support.

VEPCO had overall responsibility during plant start-up, including precriticality tests, approach to criticality, and postcriticality operations. The station staff was assisted by the architect-engineer and the supplier of the nuclear steam supply system. The Stone & Webster start-up engineer was assigned to the station from the start of flushing operations through commercial operation. The start-up engineer reported directly to the Station Manager and received instructions from him.

Experienced Westinghouse reactor engineers were also assigned to the station for fuel loading, initial criticality, and physics testing. These reactor engineers were qualified and knowledgeable in reactor operations.

They reported directly to the VEPCO reactor engineers and received instructions from them. The Westinghouse reactor engineers acted in an advisory capacity only; VEPCO retained responsibility for, and control of, the unit. Reactor specialists (e.g., control engineers) were available and utilized as required.

Revision 5209/29/2016 NAPS UFSAR 14.2-2 Intentionally Blank

Revision 5209/29/2016 NAPS UFSAR 14A-i Appendix 14A NRC Questions and VEPCOs Responses Regarding the North Anna Power Station Unit 2 Modified Startup Physics Testing Program

Revision 5209/29/2016 NAPS UFSAR 14A-ii Intentionally Blank

Revision 5209/29/2016 NAPS UFSAR 14A-1 APPENDIX 14A NRC QUESTIONS AND VEPCOS RESPONSES REGARDING THE NORTH ANNA POWER STATION UNIT 2 MODIFIED STARTUP PHYSICS TESTING PROGRAM Question 1 With respect to Item B.3 on Table 14.1-3 and Item B.2 on Table 14.1-4, what is the reason for performing the pseudo-dropped-rod test with RCCA D-10 instead of RCCA H-6?

Response

This test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. The evaluation of the results associated with these tests indicated that of the two rods, RCCA D-10 resulted in the more limiting radial power distribution and consequently had the minimum margin to departure from nucleate boiling. This was the basis for choosing RCCA D-10 for the Unit 2 test.

Question 2 Describe any known differences between the fuel and core of North Anna Unit 1 and the fuel and core of North Anna Unit 2.

Response

Three differences have been identified between the Unit 1 and Unit 2 fuel and core. They are:

1. The location of the secondary sources within the core.
2. The part-length control rods have been removed.
3. The fuel rods have been prepressurized to a different pressure.

The core locations of the secondary sources for Unit 1 and Unit 2 are shown in Figure 14A-1. It is not expected that this change will lead to a measurable difference in the physics characteristics between the Unit 1 and Unit 2 cores.

The core location of the part-length control rods for Unit 1 is shown in Figure 14A-2. This change will not lead to a measurable difference in the physics characteristics between the Unit 1 and Unit 2 cores because the use of the part-length control rods is not permitted during Unit 1 core operation. It is planned that these rods will be removed from Unit 1 following the end of Cycle 1 operation.

Unit 2 fuel has a prepressurization value that is approximately 50 psi lower than that used for Unit 1 fuel. This difference will have no perceptible effect on the physics characteristics of the

Revision 5209/29/2016 NAPS UFSAR 14A-2 core. In addition, an evaluation has shown that there will be no adverse impact on fuel or core performance.

Question 3 Describe any differences between the physics test methods that were used for Unit 1 and the physics test methods that will be used for Unit 2.

Response

For Unit 1, the reactivity worth of shutdown bank B was determined with control banks A through D fully inserted into the core, using the dilution-boration technique. The worth of shutdown bank A was determined with control banks A through D and shutdown bank B fully inserted into the core. Shutdown bank A underwent an exchange with the most reactive rod (RCCA B-8) followed by a dilution of the reactor coolant system in order to fully insert shutdown bank A.

For Unit 2, the reactivity worths of shutdown banks A and B will be determined individually with all other control rod banks out of the core. The worth of shutdown bank B will be determined using the conventional dilution/boration technique. A boron endpoint determination will be made for this control rod configuration. The worth of shutdown bank A will be determined by using rod exchange with one of the rod banks, and if necessary, dilution/boration of the reactor coolant system in order to reach the desired state point, i.e.,

shutdown bank A fully inserted with all other rods out. A boron endpoint determination will be made for this control rod configuration.

Question 4 For each of the start-up physics tests that were performed for Unit 1 but are not going to be performed for Unit 2, give the technical basis for not performing those tests.

Response

The tests that are not going to be performed for Unit 2 are listed in Table 14.1-4. Deletion of these physics tests from the start-up program is justified for the following reasons:

1. The successful performance of the abbreviated program is sufficient to
a. Verify that the core was correctly loaded and that there are no anomalies present that could cause problems later in the cycle.
b. Verify that the calculational model that has been used will correctly predict core behavior during the cycle.
c. Verify the reactivity worth of the control rod banks.

Revision 5209/29/2016 NAPS UFSAR 14A-3

d. Provide data for nuclear instrumentation calibration.
e. Demonstrate the sensitivity of this instrumentation to abnormal core conditions.
2. The calculation model was verified as a result of the Unit 1 start-up.
3. The fuel and core characteristics of Unit 2 are virtually identical to those of Unit 1, and the results obtained for these tests during the Unit 1 start-up demonstrated that a large margin exists between the measured parameter values and the design values used in the safety analyses.

Each of the tests that are not going to be performed for Unit 2 is listed below, together with the specific technical basis for not performing these tests as part of the Unit 2 start-up physics testing program.

A1. Isothermal Temperature coefficient at D, C banks in, D, C, B banks in, and D, C, B, A banks in The Core Operating Limits Report will require that a nonpositive value for the moderator temperature coefficient be maintained during normal operation. Based on the results of design calculations and the Unit 1 moderator temperature coefficient test results, it is expected that performance of the moderator temperature coefficient tests with all rods out and with control bank D in will be adequate to demonstrate a nonpositive moderator temperature coefficient value and also provide enough data to establish control rod withdrawal limits, should they be necessary. The successful completion of these tests will verify the design model used to predict the isothermal temperature coefficient values. Additionally, review criteria have been developed for the Unit 2 isothermal temperature coefficient tests that are based on the Unit 1 test results (Table 14A-1).

The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All of the Unit 1 measured temperature coefficient values were acceptable. The Unit 1 test results and review criteria for the isothermal temperature coefficients at D, C banks in, D, C, B banks in, and D, C, B, A banks in are listed in Table 14.1-5, Item 1.

A2. Boron Endpoint for the N-1 rods-in configuration Boron endpoint measurements will be made following each of the rod worth tests. The successful completion of these tests will verify the design model used to predict the boron endpoint values. Additionally, review criteria have been developed for the Unit 2 boron endpoint measurements that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured endpoint values were acceptable. The Unit 1 test results and review criterion for the boron endpoint for the N-1 rods-in configuration are listed in Table 14.1-5, Item 2.

Revision 5209/29/2016 NAPS UFSAR 14A-4 A3. Reactivity worth of N-1 rods As described in the response to Question 3, the reactivity worth of the control and shutdown rod banks will be measured as part of the physics testing program. The successful completion of these measurements will verify the design models used to predict the reactivity worth of the rod banks. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. All Unit 1 measured rod worth values (including the reactivity worth of N-1 rods) were acceptable, and demonstrated that a large margin existed with respect to the shutdown margin limit. The Unit 1 test results and review criterion for the reactivity worth of N-1 rods are listed in Table 14.1-5, Item 3.

A4. Pseudo-rod-ejection and associated power distribution measurements (HZP)

The successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Since the same design model is used to predict all rod worths, including the worth of an ejected rod, additional verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurements (HZP) are listed in Table 14.1-5, Item 4. These results indicated that the measured rod worth value and the heat flux hot-channel factor value were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.

B1. Pseudo-rod-ejection and associated power distribution measurement at 30% power The successful completion of the rod bank reactivity worth measurements for the four control banks and the two shutdown banks for Unit 2 will verify the design model used to calculate rod worths. Since the same design model is used to predict all rod worths, including the worth of an ejected rod, additional verification of the design model is not required. Additionally, review criteria have been developed for the Unit 2 rod bank reactivity worth tests that are based on the Unit 1 test results (Table 14A-1). The acceptability of the Unit 2 tests with respect to these review criteria will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 test results and review criteria for the pseudo-rod-ejection and associated power distribution measurement at 30% power are listed in Table 14.1-5, Item 4. These results indicated that the measured rod worth value and the heat flux hot-channel factor value were acceptable, and demonstrated a large margin with respect to the values used in the safety analysis.

Revision 5209/29/2016 NAPS UFSAR 14A-5 B2. Pseudo-dropped-rod test (RCCA H-6) and associated power distribution measurement As described in the response to Question 1, this test was performed twice for Unit 1, once using RCCA D-10 and once using RCCA H-6. For Unit 2, this test will be performed using the limiting rod, RCCA D-10. The successful completion of this test will verify the design models and demonstrate margin to the values used in the safety analysis. Additionally, the use of review criteria that are based on Unit 1 test results for other Unit 2 tests (Table 14A-1) will further demonstrate the similarity between the Unit 1 and Unit 2 cores. The Unit 1 results for both dropped rod tests were acceptable and demonstrated margin with respect to the values used in the safety analysis. The Unit 1 test results and review criteria for the pseudo-dropped-rod test and associated power distribution measurement using RCCA H-6 are listed in Table 14.1-5, Item 5.

B3. Power coefficient tests B4. Integral power defect B5. Doppler-only power coefficients The successful completion of the isothermal temperature coefficient tests, the boron endpoint measurements, and the rod bank reactivity tests, together with the acceptability of these tests with respect to their respective review criteria, will service to further demonstrate the similarity between the Unit 1 and Unit 2 cores. As indicated in Table 14.1-5, Items 6, 7, and 8, the Unit 1 measured values for the total power coefficient, the integral power defect, and the Doppler-only power coefficient verified the design models used to predict the values of these parameters and were acceptable with respect to the values used in the safety analyses. An additional description of the Unit 1 test results and their evaluation has been provided in a letter from Mr. C. M. Stallings, VEPCO, to Mr. H. R. Denton, USNRC, Ser. No. 169, dated March 20, 1979.

In summary, this information provides a sufficient technical basis for the deletion of these tests from the Unit 2 physics testing program.

Question 5 It is suggested that review criteria be established, where appropriate, to compare the Unit 2 test results with the Unit 1 test results for the isothermal temperature coefficient measurements, the boron endpoint measurements, the rod bank reactivity worth measurements, and the boron worth measurement. For each of these tests, list the specific review criteria that will be used. Also, indicate the action that will be taken if the review criteria are not met.

Response

The tests and the specific test review criteria that will be used are listed on Table 14A-1. As described in the response to Question 3, the reactivity worth and boron endpoint measurements associated with shutdown banks A and B that will be performed for Unit 2 are not direct

Revision 5209/29/2016 NAPS UFSAR 14A-6 duplicates of the tests that were performed during the Unit 1 testing program. Therefore, review criteria based on Unit 1 test results would be inappropriate. The results of these tests will be reviewed, instead, with respect to design values (best-estimate predictions) and the standard design tolerances.

As stated in the main body of the FSAR and as required by the VEPCO Nuclear Power Station Quality Assurance Manual, test results will be reviewed and evaluated by the Station Nuclear Safety and Operating Committee. Should the results of any of these tests fail to meet the review criteria, the Committee may decide to perform additional testing. This additional testing may be a repeat of the original test or may be the performance of a test that had been deleted from the Unit 2 physics testing program. In addition, the NRC Region II Resident Inspector will be notified verbally in a timely manner, and a report will be sent to Nuclear Reactor Regulation (NRR).

Revision 5209/29/2016 NAPS UFSAR 14A-7 Table 14A-1 UNIT 2 ISOTHERMAL TEMPERATURE COEFFICIENT, BORON ENDPOINT, ROD WORTH REACTIVITY, AND BORON WORTH TESTS AND REVIEW CRITERIA Review Criteria Test Description Unit 1 Measured Value Tolerance Isothermal temperature coefficient ARO 0.98 pcm/°F +/-2 pcm/°F D bank in -4.29 pcm/°F +/-2 pcm/°F Boron endpoint ARO 1322 ppm +/-24 ppm D bank in 1193 ppm +/-24 ppm D, C banks in 1075 ppm +/-24 ppm D, C, B banks in 884 ppm +/-24 ppm D, C, B, A banks in 781 ppm +/-24 ppm Shutdown bank A in 1220 ppm (design) +/-21 ppm Shutdown bank B in 1224 ppm (design) +/-20 ppm Control rod worth D bank 1463 pcm +/-100 pcm C bank 1303 pcm +/-98 pcm B bank 2036 pcm +/-153 pcm A bank 1309 pcm +/-98 pcm Total D through A 6111 pcm +/-306 pcm Shutdown bank A 1114 pcm (design) +/-111 pcm Shutdown bank B 1043 pcm (design) +/-104 pcm Boron worth pcm pcm ARO through A bank 11.08 ----------- +/-0.55 -----------

ppm ppm

Revision 5209/29/2016 NAPS UFSAR 14A-8 Figure 14A-1 SECONDARY SOURCE LOCATIONS

Revision 5209/29/2016 NAPS UFSAR 14A-9 Figure 14A-2 PART LENGTH CONTROL ROD LOCATIONS (UNIT 1)

Revision 5209/29/2016 NAPS UFSAR 14A-10 Intentionally Blank