North Anna Power Station Updated Final Safety Analysis Report Chapter 17
Intentionally Blank Intentionally Blank
Revision 54--09/27/18 NAPS UFSAR 17-1 CHAPTER 17 QUALITY ASSURANCE PROGRAM The Quality Assurance Program is described in Topical Report DOM-QA-1, Dominion Nuclear Facility Quality Assurance Program Description (QAPD). This topical report provides the QAPD for Dominions nuclear power stations and independent spent fuel storage installations.
The Dominion QAPD conforms to applicable regulatory requirements, such as 10CFR50, AppendixB, and approved industry standards, including equivalent alternatives, where identified.
This program applies to activities during design, construction, operation, and decommissioning as well as siting.