ML18066A314: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 1: | Line 1: | ||
{{Adams | |||
| number = ML18066A314 | |||
| issue date = 10/01/1998 | |||
| title = Provides Update to Design Insp Action Items Re Insp Rept 50-255/97-201 Conducted on 970916-1114.Util Recommends That NRC Consider Scheduling Efforts Early in 1999 to Review Insp Items for Closure Based on Completion Dates for Items | |||
| author name = Haskell N | |||
| author affiliation = CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.), | |||
| addressee name = | |||
| addressee affiliation = NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) | |||
| docket = 05000255 | |||
| license number = | |||
| contact person = | |||
| document report number = 50-255-97-201, NUDOCS 9810070265 | |||
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE | |||
| page count = 55 | |||
}} | |||
See also: [[see also::IR 05000255/1997201]] | |||
=Text= | |||
{{#Wiki_filter:A CMS Energy Company October 1, 1998 U.S. Nuclear Regulatory | |||
Commission | |||
Attn: Document Control Desk Washington | |||
D.C. 20555 Palisades | |||
Nuclear Plant 27780 Blue Star Memorial Highway Covert. Ml 49043 DOCKET 50-255 -LICENSE DPR-20 -PALISADES | |||
PLANT * Tel. 616 764 2276 Fax.* 616 764 2490 Nathan L. Ha.ks/I Director. | |||
Licensing | |||
OCTOBER 1, 1998 UPDATE TO DESIGN INSPECTION | |||
ACTION ITEMS During the period from September | |||
16 through November 14, 1997, the NRC conducted | |||
a design inspection | |||
at the Palisades | |||
Nuclear Plant. By letter dated December 30, 1997, the NRC issued Inspection | |||
Report No. 50-255/97-201, and requested | |||
a response within 60 days detailing | |||
our plans to complete the corrective | |||
actions required to resolve the open items listed in Attachment | |||
A of the inspection | |||
report. Contained | |||
within our March 2, 1998 response was a single commitment | |||
to provide the NRC a status of our progress in completing | |||
actions associated | |||
with each open inspection | |||
item. The purpose of this commitment, in part, was to assist the NRC in planning for follow-up | |||
review and closeout of these items. Attachment | |||
A of this letter contains the text of each open inspection | |||
item from the December 30, 1997 inspection | |||
report, followed by our 60 day response as submitted | |||
in our March 2, 1998 letter, followed by the status of associated | |||
action as of October 1, 1998. This status includes the results of our investigations | |||
and corrective | |||
actions, along with planned completion | |||
dates for ongoing actions. Attachment | |||
B contains similar information | |||
for programmatic | |||
issues related to inspection | |||
findings. | |||
_J Based on completion | |||
dates for the remaining | |||
open items, we recommend | |||
that NRC consider scheduling | |||
efforts early in 1999 to review inspection | |||
items for closure. A review of completion | |||
dates for open items indicates | |||
that a majority of actions will be completed | |||
by the end of 1998. 9810070265 | |||
981001 PDR ADOCK 05000255 G PDR | |||
-. . .:.; * * -.. -Sl:JMMAR¥-'-8F | |||
COMMITMENTS | |||
This letter closes the March 2, 1998 commitment | |||
as .restated | |||
below, and contains no new commitments. "By October 1, 1998, Consumers | |||
Energy will provide NRC with a status of our progress in completing | |||
all actions identified | |||
in the attachments | |||
to this letter.'' | |||
* Nathan L. Haskell . Director, Licensing | |||
CC Administrator, Region Ill, USNRC Project Manager, NRR, USNRC NRC Resident Inspector | |||
-Palisades | |||
Attachments | |||
2 | |||
ATTACHMENT | |||
A CONSUMERS | |||
ENERGY COMPANY PALISADES | |||
PLANT DOCKET 50-255 STATUS OF PLANS FOR CORRECTIVE | |||
ACTIONS TO RESOLVE NRC DESIGN INSPECTION | |||
OPEN ITEMS 45 Pages | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Unresolved | |||
Item 50-255/97-201-01 | |||
The team questioned | |||
whether the CCW system design met the vendor-recommended | |||
minimum flow of 2000 gpm for the CCW pumps under all operating | |||
conditions. | |||
The team was concerned | |||
that small differences | |||
in the pump operating | |||
characteristics | |||
could cause significant | |||
differences | |||
in flow through each pump during parallel pump operation | |||
due to the flatness of the pump operating | |||
* curves at low flows. The licensee had no analysis available | |||
to demonstrate | |||
that the CCW pumps met the minimum flow requirements. | |||
During the inspection, the licensee developed | |||
a preliminary | |||
system flow model, which showed that, when all three pumps were started upon receiving | |||
a safety injection | |||
system (SIS) signal, the minimum pump flow was through CCW pump P-52A at 1768 gpm. The licensee received a revised minimum flow requirement | |||
of 1600 gpm from the pump manufacturer. | |||
The team's review of the licensee's | |||
completed | |||
flow model calculation | |||
will be an Inspection | |||
Fol/owup Item 50-255197-201-01. | |||
* Palisades | |||
60 Day Response: | |||
As a result of CCW system balancing, scheduled | |||
for the 1998 refueling | |||
outage, a reanalysis | |||
of minimum predicted | |||
CCW system flow rates will be performed. | |||
This reanalysis | |||
will verify that minimum flow rate requirements | |||
will be met under a worst case scenario with appropriate | |||
pump IST degradation | |||
input. This action will be completed | |||
by September | |||
1, 1998. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-01) | |||
was identified | |||
as open. Pump performance | |||
data was obtained during the 98 refueling | |||
outage. The completion | |||
for the reanalysis | |||
has been rescheduled | |||
for August 1, 1999 to accommodate | |||
emerging higher priority analytical | |||
work. Unresolved | |||
Item 50-255/97-201-02 | |||
The team verified the heat removal capability | |||
of the CCW heat exchangers | |||
by reviewing | |||
the results of various accident analyses. | |||
The licensee had performed | |||
the following | |||
LOCA analyses: | |||
* EA-D-PAL-93-207-01, "LOCA Containment | |||
Response Analysis With Reduced LPSI Flow Using CONTEMPT El-28 Code," Revision 0, * EA-D-PAL-93-272-03, "LOCA Containment | |||
Response Analysis With Degraded Heat Removal System Using CONTEMPT El-28A Computer Code," Revision 0, *and * EA-GEJ-96-01, "A-PAL-94-324 | |||
Containment | |||
Spray System (CSS) Sensitivity | |||
on the Containment | |||
Heat Removal During Recirculation (Post-RAS)," Revision 1. The team verified that the input assumptions | |||
relating to the CCW system for the above analyses were correct. The above LOCA analyses demonstrated | |||
that the heat exchangers | |||
could remove sufficient | |||
heat from containment | |||
following | |||
a LOCA to keep the containment | |||
pressure and 1 | |||
* ---------------------- | |||
-----ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS temperature | |||
within the design limits. In each case, the analysis documented | |||
a CCW temperature | |||
exiting the shutdown coolers exceeding | |||
the system design temperature | |||
of 140 degrees Fahrenheit | |||
(140 °F) as stated in FSAR table 9-6 and DBD 1.01, "Component | |||
Cooling Water," Revision 3. The team noted that the licensee accepted the maximum CCW temperature | |||
that resulted from the scenarios | |||
analyzed in EA-D-PAL-207-01 | |||
and EA-D-PAL-93-272-03 | |||
by Corrective | |||
Action D-PAL-93-272G, based primarily | |||
on an evaluation | |||
of the effects on pipe stress. However, the licensee had not considered | |||
the other negative effects, such as any detrimental | |||
effects from elevated CCW temperature | |||
on pump seals. Also, the licensee had not determined | |||
the maximum possible CCW temperature | |||
under worst case conditions | |||
and had not identified | |||
that a change to the FSAR could be required. | |||
The team reviewed the latest LOCA analysis, EA-GEJ-96-01, and determined | |||
that it documented | |||
a CCW temperature | |||
exiting the shutdown cooling heat exchanger | |||
was 184 °F. The licensee determined | |||
the system was operable under this condition | |||
and issued Condition | |||
Report (CR) C-PAL-97-1363F | |||
to determine | |||
the most limiting CCWtemperature | |||
for any condition | |||
and to evaluate all the effects resulting | |||
from that limiting temperature | |||
on the CCW system. ' It appeared that the requirements | |||
of 10 CFR 50, Appendix B, Criterion | |||
111, "Design Control," were not met in this case in that the design basis for the CCW system, as defined in 10 CFR 50.2, did not encompass | |||
the entire range of bounding temperatures. | |||
The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-02. | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design lnspection;.we | |||
determined | |||
that the CCW system is operable at a predicted | |||
maximum system temperature | |||
of 184°F. The CCW system will be analyzed to confirm the most limiting temperature | |||
for any design basis condition, and to determine | |||
the effects of this temperature | |||
on system components | |||
by October 1; 1998. The FSAR will be updated as appropriate. | |||
The programmatic | |||
design control aspects related to this issue will be addressed | |||
as identified | |||
in Attachment | |||
B, Item 1. 10/1/98 Update: In June of 1998, Engineering | |||
Analysis EA-LOCA-98-01 | |||
was performed | |||
to determine | |||
the limiting condition | |||
CCW temperature. | |||
The results show a maximum 180°F CCW temperature | |||
out of the CCW heat exchanger. | |||
The effects of this temperature | |||
on system components | |||
was then evaluated. | |||
It was determined | |||
that the CCW heat exchanger | |||
outlet temperature | |||
indication | |||
range was too narrow and needed to be expanded to meet RG 1.91 requirements. | |||
By December 15, 1998, these temperature | |||
indicators | |||
will be replaced and full compliance | |||
with RG 1.97 requirements | |||
will be achieved. | |||
All other evaluated | |||
CCW system component | |||
peak temperature | |||
ratings fall within the predicted | |||
180°F temperature. | |||
The FSAR was changed to clarify CCW system design temperature | |||
and LOCA maximum temperatures. | |||
The temperature | |||
indicator | |||
range issue (50-255/97201-02) | |||
was identified | |||
as open, and was the subject of a NOTICE OF DEVIATION | |||
(50-255/98003-02), in NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION." Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." 2 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Refer to Attachment | |||
B, Item 1 for the programmatic "design control" aspects associated | |||
with this issue. Unresolved | |||
Item 50-255/97-201-03 | |||
The team reviewed C-PAL-96-1-63-01, "120 day response to GL 96-06, Assurance | |||
of Equipment | |||
Operability | |||
and Containment | |||
Integrity | |||
during Design Basis Accident Condition," Revision 0, which was the licensee's | |||
response to Nuclear Regulatory | |||
Commission (NRG) Generic Letter 96-06, "Assurance | |||
of Containment | |||
Operability | |||
and Containment | |||
Integrity | |||
During Design-Basis | |||
Accident Conditions," and observed that the licensee took credit for relief valve RV-0939 to protect the CCW piping inside containment | |||
from overpressurization | |||
in the event of a LOCA. RV-0939 was not included in the /ST program. The team questioned | |||
whether RV-0939 performed | |||
a safety function and if it should have been included in the /ST program. The licensee issued CR C-PAL-97-1686 | |||
to evaluate this | |||
discrepancy. | |||
10 CFR 50.55a requires /ST in accordance | |||
with ASME Section XI of valves that perform a safety function. | |||
It appeared that the licensee did not fully implement | |||
these requirements | |||
for RV-0939. The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-03. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, it was determined | |||
that sufficient | |||
overpressure | |||
protection | |||
is provided for the CCW system without taking credit for relief valve RV-0939, and the CCW system is therefore | |||
operable. | |||
The CCW piping in containment | |||
is not required during an accident and is classified | |||
non-Q, safety related. As a result, the ISl/IST programs have classified | |||
the CCW piping and related components, including | |||
RV-0939, as non-class | |||
and excluded the same from inspection/test | |||
requirements | |||
of the Code. The Palisades | |||
response to GL 96-06 determined | |||
acceptability | |||
of systems by generally | |||
taking credit for 1) steam/gas | |||
service, 2) available | |||
expansion | |||
paths, or 3) relief valves as a means to provide *sufficient | |||
protection | |||
against thermally | |||
induced over pressurization. | |||
In the case of the CCW system, "available | |||
relief valves" serves as the basis for acceptability. | |||
Relief valve operation | |||
is considered | |||
important | |||
but not a safety related function, and therefore, the classification | |||
of the CCW system and its components | |||
such as RV-0939 were not changed. Although RV-0939 is not in the IST program, it, along with RV-2108 and RV-0956, is inspected, maintained | |||
and set point verified via | |||
maintenance | |||
activity PPAC CCS043 on a 10-year interval. | |||
These are essentially | |||
the same as the requirements | |||
of the Code (ASME/ANSI | |||
OM-1987, Part 1 ). Based on this evaluation, no further action is required. | |||
RV-0939 is appropriately | |||
classified, maintained | |||
and tested. Our existing GL 96-06 submittal | |||
is accurate. | |||
3 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS 10/1/98 Update: This response has not changed since the submittal | |||
of our original 60-day inspection | |||
report response. | |||
Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-03) | |||
was identified | |||
as closed. No further actions on this item are planned. Unresolved | |||
Item 50-255/97-201-04 | |||
FSAR Section 9.3.2.3 stated that the CCW pipingwithin | |||
containment | |||
was not vulnerable | |||
to failure caused by a high energy line break (HELB) and referred to Deviation | |||
Report (DR) D-PAL-89-061, "Post Accident Operation | |||
of CCW System, 11 dated March 23, 1989, for the evaluation. | |||
This DR referred to Engineering | |||
Analysis (EA) EA GW0-7793-01, "CCW Piping Inside Containment | |||
HELBA," Revision 0. This EA was reviewed by the team, and it concluded | |||
that the CCW piping inside containment | |||
was not affected by HELBs, but did not contain the analysis performed | |||
or a reference | |||
to the analysis. | |||
The EA contained | |||
an outline of the methodology, listed the drawings and walkdowns | |||
used, and referenced | |||
the source of the postulated | |||
HELBs. Palisades | |||
Administrative | |||
Procedure | |||
No. 9.11, "Engineering | |||
Analysis, 11 Revision 9, stated that an EA shall present an argument which substantiates | |||
the conclusion | |||
of the EA. The EA also contained | |||
an error in the identification | |||
of the Systematic | |||
Evaluation | |||
Program (SEP) topic number for evaluation | |||
of the effects of internally | |||
generated | |||
missiles. | |||
The licensee initiated | |||
Engineering | |||
Assistance | |||
Request (EAR) EAR-97-0632 | |||
to revise EA-GW0-7793-01. | |||
During the inspection, the licensee issued Revision 1 of EA-GW0-7793-01, which included a discussion | |||
of the walkdown analysis used and corrected | |||
the SEP references. | |||
This revised EA was acceptable | |||
to the team. It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion . Ill, "Design Control," regarding | |||
verifying | |||
the adequacy of designs were not adhered to in this case. Also, the requirements | |||
of the licensee's | |||
Administrative | |||
Procedure | |||
9. 11 were not fully met in that EA-GW0-7793-01, Revision 0, did not contain full substantiation | |||
of the conclusion. | |||
The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-04. | |||
Palisades | |||
60 Day Response: | |||
As a remedial action, EA-GW0-7793-01 | |||
was revised to provide justification | |||
for its conclusion | |||
and to correct references | |||
to related NRC corresponqence. | |||
The related programmatic | |||
design control and calculation | |||
control aspects will be addressed | |||
as identified | |||
in Attachment | |||
B, Items 1 and 2. 10/1/98 Update: This response has not changed since the submittal | |||
of our original 60-day inspection | |||
report response. | |||
Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-04) | |||
was identified | |||
as closed. No further actions are planned for this item . Refer to Attachment | |||
B, Item 1 for the programmatic "design control" aspects associated | |||
with this issu.e. 4 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Unresolved | |||
Item 50-255/97-201-05 | |||
The team reviewed the implementation | |||
of the licensee's | |||
commitment | |||
to NRG Regulatory | |||
Guide (RG) 1.97, "Instrumentation | |||
for Light-Water-Cooled | |||
Nuclear Power Plants To Assess Plant and Environs Conditions | |||
During and Following | |||
an Accident," Revision 3, as described | |||
in FSAR Appendix 7C. The RG stated a range for CCW flow instrumentation | |||
of 0-110 percent. Since | |||
there was no instrument | |||
to directly measure CCW flow, the licensee used a combination | |||
of instruments, including | |||
TE-0912 and TE-0913, which measure shutdown cooling heat exchanger | |||
outlet temperature, to indicate flow. Use of instruments (other than flow indicators) | |||
to monitor for CCW flow was determined | |||
as acceptable | |||
by the NRG (a letter from NRG to Consumers | |||
Power Company, dated July 19, 1988, entitled "Palisades | |||
Plant-Response to Generic Letter 82-33 Conformance | |||
to Regulatory | |||
Guide 1.97 "Instrumentation | |||
for Light-Water-Cooled | |||
Nuclear Power Plants To Assess Plant and Environs Conditions | |||
During and Following | |||
an Accident''). | |||
The required range for these TEs in FSAR Appendix 7C was 0-180 °F. This range did not encompass | |||
the temperature | |||
determined | |||
in EA-GEJ-96-01, "A-PAL-94-324 | |||
Containment | |||
Spray System (CSS) Sensitivity | |||
on Containment | |||
Heat Removal During Recirculation (Post-RAS)," Revision 1. This analysis determined | |||
an outlet temperature | |||
of the CCW from the shutdown cooling heat exchanger | |||
of 184 °F. The licensee issued CR C-PAL-97-1363E | |||
to evaluate the process instrumentation | |||
and controls associated | |||
with the CCW system for the effects of the higher temperature | |||
predicted | |||
by the analysis. | |||
The licensee did not appear to meet their commitment | |||
to NRG RG 1.97, "Instrumentation | |||
for Light-Water-Cooled | |||
Nuclear Power Plants To Assess Plant and Environs Conditions | |||
During and Following | |||
an Accident," in that the installed | |||
CCW temperature | |||
indicators | |||
were not capable of monitoring | |||
the full temperature | |||
range expected to be observed in the CCW system. The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-05. | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design Inspection, we determined | |||
that the COW system is operable at a predicted | |||
maximum system temperature | |||
of 184°F. The CCW system will be analyzed to confirm the most limiting temperature | |||
for any design basis condition, and the effects of this temperature | |||
on system components. | |||
In response to this specific issue, process instrumentation | |||
and controls associated | |||
with the CCW system will be reviewed to identify the impact of the maximum predicted | |||
temperature. | |||
This action will be completed | |||
by October 1, 1998. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-05) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF DEVIATION | |||
(50-255/98003-02) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." In summary, the range of the CCW heat exchanger | |||
outlet temperature | |||
indicators | |||
will be changed to meet RG 1.97 requirements | |||
by December 15, 1998. 5 | |||
* ** * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Unresolved | |||
Item 50-255/97-201-06 | |||
The team identified | |||
a lack of closure verification | |||
testing on SI system check valves that could potentially | |||
result in an overpressure | |||
condition | |||
affecting | |||
the low-pressure | |||
piping on the suction of the HPSI pumps. The minimum flow recirculation | |||
lines associated | |||
with the two HPSI pumps and the two LPSI 'pumps were interconnected | |||
upstream of the air-operated | |||
minimum flow recirculation | |||
isolation | |||
valves. In the event that only one HPSI pump was operating | |||
under post-accident | |||
conditions | |||
with the minimum flow recirculation | |||
isolation | |||
valves closed, back leakage through the minimum flow piping associated | |||
with the idle HPS/ pump could over pressurize | |||
the idle HPS/pump suction piping. Backflow between the HPS/ minimum flow lines should be prevented | |||
by check valves CK-ES3339 | |||
or CK-ES3331, and CK-ES3340 | |||
or CK-ES3332. | |||
However, EGAD-EP-01, "lnservice | |||
Testing Program-Valve | |||
Test Program," Revision 10 indicated | |||
that closure verification | |||
testing of these check valves was not included in the /ST program. *The team asked the licensee if closure of these check valves was considered | |||
a safety function requiring | |||
/ST. The licensee initiated | |||
CR C-PAL-97-1660 | |||
to evaluate the testing requirements | |||
of these check valves. On November 10, 1997, the operability | |||
determination | |||
concluded | |||
that these system check valves had not been subject to closure verification | |||
testing as required, and both HPSI pumps were declared inoperable. | |||
In accordance | |||
with TS Section 3.0.3, 3.3, and 4.0.3, the licensee entered a Limiting Condition | |||
for Operation (LCO) action statement, performed | |||
closure verification | |||
testing of check valves CK-ES3339 | |||
and CK-ES3340, and verified the operability | |||
of these valves. The licensee stated that closure verification | |||
testing of these check valves would be added to the /ST program. The team also identified | |||
a lack of closure verification | |||
testing on SI system valves that could potentially | |||
result in a Safety Injection | |||
Tank (SIT) being degraded under post-accident | |||
conditions. | |||
The normally closed SIT vent valves, CV-3051, 3063, 3065, and 3067, could be opened in accordance | |||
with SOP-3, "Safety Injection | |||
and Shutdown Cooling System," Revision 28, to reduce SIT pressure. | |||
SOP-3 did not require the affected SIT to be declared inoperable | |||
when a vent was opened. When a vent valve was opened the SIT pressure boundary (250 psig design pressure) | |||
was exposed to the SIT vent header piping (100 psig design pressure). | |||
SOP-3 did not include d(rections | |||
to isolate an open vent valve in the event of an accident. | |||
EGAD-EP-01, lnservice | |||
Testing Program -Valve Test Program," Revision 10, indicated | |||
that closure verification | |||
testing of these valves was not included in the /ST program. The team asked the licensee if the failure of a valve to close could result in a SIT being degraded under accident conditions, and if closure of these valves was considered | |||
a safety function requiring | |||
/ST testing. The licensee initiated | |||
CR C-PAL-97-1592 | |||
to evaluate this item and placed caution tags on the control room switches for vent valves CV-3051, 3063, 3065, and 3067 to prevent the valves from being opened without entering an LCO for the SITs. The licensee also stated that these valves had been opened rarely during plant operation. | |||
1 O CFR 50. 55a requires in-service | |||
inspection | |||
in accordance | |||
with Section XI of the ASME Boiler and Pressure Vessel Code. This code requires testing of valves which perform a safety function. | |||
It appeared that the licensee did not implement | |||
these requirements | |||
with regard to valves CK-ES3339, CK-ES3340, CV-3051, CV-3063, CV-3065, and CV-3067. The team identified | |||
this item as part of Unresolved | |||
Item 50-=255197-201-06. | |||
6 | |||
-------ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
During the Design Inspection, high pressure safety injection | |||
pump minimum flow recirculation | |||
line check valves CK-ES3339 | |||
and CK-ES3340 | |||
were tested and the HPSI system was declared operable. | |||
Action to include check valves CK-ES3339 | |||
and CK-ES3340 | |||
in the IST Program will be completed | |||
by July 15, 1998. lri the interim, the check valves are tested to meet quarterly | |||
testing requirements. | |||
During the Design Inspection, the Safety Injection | |||
Tank (SIT) vent valves CV-3051, CV-3063, CV-3065 and CV-3067 were closed and cautioned | |||
tagged with the tanks declared operable. | |||
Action to revise operating | |||
procedures | |||
to address opening the SIT vent valves will be completed | |||
prior to removal of the caution tags. Prior to March 15, 1998, a representative | |||
sample of check valves, AOVs and MOVs will be reviewed and verified to be incorporated | |||
in the IST program as required. | |||
10/1/98 Update: Check valves CK-ES3339 | |||
and CK-ES3340 | |||
have been included in the IST Program. Operating | |||
procedures | |||
have been revised to address opening of the SIT vent valves CV-3051, CV-3063, CV-3065 and CV-3067 and caution tags have been removed. A representative | |||
sample of check valves, AOVs and MOVs have been sampled to determine | |||
if they are included in the IST Program as required. | |||
The sampling identified | |||
additional | |||
AOVs and one check valve that required inclusion | |||
into the IST Program. These valves have been incorporated | |||
into the IST Program and have been tested to confirm their safety related function. | |||
In addition, several other actions associated | |||
with the IST Program are underway to enhance databases, review ISi Program bases for IST Program impact, and revise IST Program and bases to enhance purpose, scope and program descriptions. | |||
These actions are projected | |||
to be complete by . May 1, 1999. Presently, Palisades | |||
is in full c_ompliance | |||
with the ISi and IST program requirements. | |||
Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-06) | |||
was identified | |||
as closed. .This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-03) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REP.ORT 50-255/98003." Unresolved | |||
Item 50-255/97-201-07 | |||
The team reviewed the HVAC system serving the cable spreading | |||
room. The team observed that DR F-CG-91-072 | |||
was prepared in May 1991 when it was discovered | |||
that the assumptions | |||
in calculation | |||
EA-FC-573-2, "Calculated | |||
Required Air Flow for Inverter/Charger | |||
Cabinet Cooling Fan," dated October 3, 1982, used an ambient temperature | |||
of 94 °F instead of the correct design basis temperature | |||
of 104 °F. The Safety System Design Confirmation (SSDC) Team that found this discrepancy | |||
recommended | |||
that the EA be updated. Procedure*9.11, "Engineering | |||
Analysis," Revision 9, required all EAs to be revised if analytical | |||
inputs or major assumptions | |||
change. The 7 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS licensee aec1dedtiotl6 | |||
reVisetfie | |||
EA-; and ffie alscrepaiicy | |||
was recorded in DBD 4.02 (125-V de system) and DBD 4.03 (preferred | |||
ac system). The fans were installed | |||
in 1983 and were not safety related. DR F-CG-91-072 | |||
was closed in October 1994, when the decision was made not to revise the calculation. | |||
The licensee stated that specifications | |||
were being developed | |||
for replacing | |||
the inverters | |||
and chargers during the time the discrepancy | |||
was being evaluated | |||
and that this knowledge | |||
contributed | |||
to the decision not to update the EA. The inverters | |||
and chargers were scheduled | |||
to be replaced in the near future by Specification | |||
Change (SC) SC-96-033. | |||
The new equipment | |||
would have internal cooling fans designed for a 104 °F maximum ambient and SC-96-033 | |||
would supersede | |||
EA-FC-573-2 | |||
upon installation. | |||
The team had no other concerns about the cable spreading | |||
room HVAC system. It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion/I, "Quality Assurance | |||
Program," were not followed in this case in that the requirements | |||
of Procedure | |||
9. 11 regarding | |||
revising EAs were not fully implemented. | |||
The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-07. | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design Inspection, Design Basis Documents | |||
were revised to address this discrepancy. | |||
Analysis EA-FC-573-2 | |||
will be revised or superseded | |||
by December 1, 1998. The calculation | |||
control aspects related to this issue (in this case, the revision of all analyses whenever analytical | |||
inputs or major assumptions | |||
change) will be addressed | |||
by the action described | |||
in Attachment | |||
B, Item 2. 10/1/98 Update: The schedule for resolving | |||
remains as stated above. Per NRG correspondence | |||
dated May 18, 1998, titled "NRG INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-07) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-04) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." Unresolved | |||
Item 50-255/97-201-08 | |||
The team identified | |||
the following | |||
discrepancies | |||
in SJ system mechanical | |||
calculations: | |||
* EA-DBD-2.01-004, "Electrical | |||
and Mechanical | |||
Failure Analysis for the Low Pressure Safety Injection | |||
System," Revision 0, pages 10 and 25, identified | |||
a situation | |||
in which a Joss of an emergency | |||
diesel generator (EOG) during a large-break | |||
LOCA would result in only one LPSI pump and two LPS/ injection | |||
valves being operable. | |||
The EA stated: "The acceptability | |||
of this situation | |||
could not be verified." The team asked if this statement | |||
was correct. The licensee replied that the statement | |||
was not current, and that the statement | |||
appeared to be based on superseded | |||
calculation | |||
ANF-88-107, "Palisades | |||
Large Break LOCA/ECCS | |||
Analysis With Increased | |||
Radial Peaking," Revision 1. Calculation | |||
ANF-88-107 | |||
was superseded | |||
by Seimens calculation | |||
EMF-96-172, "Palisades | |||
Large Break LOCA/ECCS | |||
Analysis," Revision 0. The licensee initiated | |||
Engineering | |||
Assistance | |||
Request (EAR) 97-0635 to revise EA-DBD-2.01-004. | |||
8 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS * EA-A-NL-92-185-01, "Worst Case Operating | |||
Conditions | |||
for the LPSllSDC System MOVs," Revision 1, addressed | |||
the most limiting conditions | |||
under which the system motor-operated | |||
valves (MOVs) were required to open and close. This analysis included MOVs M0-3015 and M0-3016. These valves were the isolation | |||
valves installed | |||
in the shutdown cooling inlet . piping from primary coolant system (PCS) loop 2. For all normal operations | |||
-other than shutdown cooling being in service, -the valves were electrically | |||
locked closed. Page 19 of EA-A-NL-92-185-01 | |||
stated that the scenario that could produce the most limiting differential | |||
pressure was that these valves would be required to close in the event of a downstream | |||
pipe break. The EA addressed | |||
a potential | |||
12-in. downstream | |||
pipe break and determined | |||
that complete depressurization | |||
and blowdown of the PCS to the hot-leg elevation | |||
would occur before operators | |||
could enter the EOPs and attempt to isolate the break. Therefore, the analysis then established | |||
a maximum flow rate of 4120 gpm through valves M0-3015 and M0-3016, based on a normal system flow rate of 3000 gpm and a calculated | |||
leakage of 1120 gpm through a break of a 1-112-inch | |||
branch line downstream | |||
of the valves. The team asked the licensee to provide the basis of the postulated | |||
1-112-inch | |||
branch line failure, since it did not appear to be consistent | |||
with the postulated | |||
pipe crack used in the internal flooding analysis of the safeguards | |||
areas (EA-C-PAL-95-1526-01, "Internal | |||
Flooding Evaluation | |||
for Plant Areas Outside of Containment," Revision 0). The licensee verified that the flooding analysis break flow was different | |||
and that this difference | |||
would not affect the conclusions | |||
of EA-A-NL-92-185-01. | |||
Assumptions | |||
5.9 and 5.10 of EA-A-NL-92-185-01 | |||
stated that the HPS/ and LPSI injection | |||
flows to the loops were approximately | |||
equal under post-accident | |||
conditions. | |||
These assumptions | |||
did not appear consistent | |||
with the flow values calculated | |||
in EA-SDW-95-001, "Generation | |||
of Minimum and Maximum HPSllLPSI | |||
System Performance | |||
Curves Using Pipe-Flo," Revision 2. The team asked the licensee to provide the bases of these values. The licensee stated that the values were not current and verified that the difference | |||
between these values and the current values would not affect the EA results. The licensee initiated | |||
CR C-PAL-97-1670 | |||
to resolve the discrepancies | |||
in EA-A-NL-92-185-01. | |||
* EA-E-PAL-93-004E-01, "/ST Check Valve Minimum Flow Rate Requirements | |||
to Support Chapter 14 Events," Revision 0, identified | |||
1601 gpm as the required test flow for the LPS/ injection | |||
check valves. The team observed that this value appeared to be less limiting than the values calculated | |||
in EA-SDW-95-001, "Generation | |||
of Minimum and Maximum HPS/ILPSI | |||
System Performance | |||
Curves Using Pipe-Flo," Revision 2. The licensee initiated | |||
CR C-PAL-97-1603 | |||
to address this discrepancy. | |||
The licensee determined | |||
that the LPSI test flow presented | |||
in EA-E-PAL-93-004E-01 | |||
was less than the current calculated | |||
requirement. | |||
However, the actual LPSI check valve flow acceptance | |||
criterion | |||
in /ST Procedure | |||
Q0-88, "ESS Check Valve Operability | |||
Test (Cold Shutdown)," Revision 17, was verified to be 1690 gpm, which was greater than the current calculated | |||
requirement. | |||
The licensee stated that the affected documentation | |||
will be corrected. | |||
Administrative | |||
Procedure | |||
9. 11, "Engineering | |||
Analysis," Revision 9, Section 6. 1. 5. c stated that an analysis shall be revised if analytical | |||
inputs changed. In the above instances, engineering | |||
analyses were not updated to reflect analytical | |||
input change. The licensee initiated | |||
C-PAL-97-1636 | |||
to evaluate the overall issue of calculation | |||
control. The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-08. | |||
9 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
During the Design Inspection, it was determined | |||
that the LPSI check valves are operable since IST acceptance | |||
criteria and actual test flow rates exceeded the minimum required flow rates in analysis EMF-96-72 | |||
which had superseded | |||
EA-E-PAL-93-004E-01. | |||
By June 1, 1998, engineering | |||
guideline | |||
EGAD-EP-09 | |||
and IST procedure | |||
Q0-8B basis document will be revised to assure that the increased | |||
minimum design flow requirement | |||
is met, and that design bases agree with IST acceptance | |||
criteria. | |||
Remedial actions to revise EA-DBD-2.01-004 | |||
to accurately | |||
reflect electrical | |||
system response to events will be completed | |||
by August 15, 1998. EA-A-NL-92-185-01 | |||
and EA-SDW-95-001 | |||
are bounding analyses which will not be required to be revised or superseded. | |||
Specifically, * the calculation | |||
control process will be revised to allow bounding analyses to remain unchanged | |||
when revisions | |||
to inputs or assumptions | |||
do not affect the analysis conclusions. | |||
The calculation | |||
control aspects related to this issue will be addressed | |||
by the action described | |||
in Attachment | |||
B, Item 2. 10/1/98 Update: Engineering | |||
guideline | |||
EGAD-EP-09, IST procedure | |||
Q0-8B Basis Document, and engineering | |||
analysis EA-DBD-2.01-004 | |||
were revised as stated above. Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-08) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-04) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." Unresolved | |||
Item 50-255/97-201-09 | |||
During an SI system walkdown on October 6, 1997, the team observed scaffolding | |||
installed | |||
adjacent to the SIRWT on the roof of the auxiliary | |||
building. | |||
The team questioned | |||
how the installation | |||
of scaffolding | |||
in the vicinity of safety-related | |||
equipment | |||
was controlled | |||
to prevent damage to the safety-related | |||
equipment | |||
during a seismic event. The licensee provided Procedure | |||
MSM-M-43, "Scaffolding," Revision 2, for the team's review. Section 5. 3 of this procedure | |||
required an engineering | |||
review of scaffolding | |||
installed | |||
in the vicinity of safety related equipment. | |||
However, the licensee determined | |||
that the scaffolding | |||
observed during the walkdown had not received engineering | |||
review in accordance | |||
with the procedure. | |||
The licensee initiated | |||
CR C-PAL-97-1417 | |||
to address the scaffolding | |||
installation, and the scaffolding | |||
was removed on October 8, 1997. EA-C-PAL-97-1417A-01, "Operability | |||
Reassessment | |||
of SIRWT Scaffolding," Revision 0, was completed | |||
during the inspection. | |||
Based on a structural | |||
analysis of the maximum loading on the SIRWT due to seismic interaction | |||
with the scaffolding | |||
during a safe shutdown earthquake, this analysis concluded | |||
that the SIRWT was not inoperable | |||
due to this nonconforming | |||
condition. | |||
10 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS During another SI system walkdown on October 30, 1997, the team observed additional | |||
scaffolding | |||
installed | |||
in the east ESG room adjacent to safety-related | |||
piping. An evaluation | |||
by the licensee determined | |||
that this scaffolding | |||
had not been installed | |||
in accordance | |||
with Procedure | |||
MSM-M-43, "Scaffolding," Revision 2. The licensee initiated | |||
CR C-PAL-97-1585 | |||
to address this scaffolding | |||
installation | |||
and, based on a visual inspection, concluded | |||
that this nonconforming | |||
scaffolding | |||
would not render any safety-related | |||
piping or components | |||
inoperable. | |||
The licensee removed the scaffolding. | |||
In addition, the licensee performed | |||
a walkdown of all plant scaffolding | |||
during the inspection | |||
and verified that there were no additional | |||
nonconforming | |||
conditions. | |||
The licensee stated that all scaffolding | |||
erections | |||
would cease until appropriate | |||
personnel | |||
underwent | |||
remedial training. | |||
The team observed the following | |||
three separate conditions | |||
in the west ESG room involving | |||
potential | |||
seismic interactions | |||
with safety-related | |||
equipment. | |||
The team noted that, during a seismic event, unrestrained | |||
items could potentially | |||
damage safety-related | |||
piping and equipment. | |||
The safety-related | |||
piping and equipment | |||
in the west ESG room were required for operation | |||
of the HPSI, LPSI, and containment | |||
spray systems in the event of an accident. | |||
* The team observed an unsecured | |||
operations | |||
storage cabinet located adjacent to safety-related | |||
piping and valves. The team asked the licensee if the condition | |||
was in accordance | |||
with plant procedures. | |||
The licensee initiated | |||
CR C-PAL-97-1587, which determined | |||
that the cabinet was not placed in accordance | |||
with the spacing requirements | |||
of Administrative | |||
Procedure | |||
1.01, "Material | |||
Condition | |||
Standards | |||
and Housekeeping | |||
Responsibilities," Revision 11. The operability | |||
evaluation | |||
concluded | |||
that the nonconforming | |||
condition | |||
did not result in any safety-related | |||
equipment | |||
being inoperable. | |||
The cabinet was laid on its side to eliminate | |||
the toppling concern. The licensee stated that the cabinet would be removed from the area. * The team observed an* unsecured | |||
chainfall | |||
located adjacent to and above the shutdown cooling heat exchangers. | |||
A similar chainfall | |||
in the east ESG room was secured. The team asked the licensee if the condition | |||
was in accordance | |||
with plant procedures. | |||
The licensee determined | |||
that the chainfall | |||
location was not in accordance | |||
with Administrative | |||
Procedure | |||
1.01, and initiated | |||
CR C-PAL 97-1586. The operability | |||
evaluation | |||
concluded | |||
that the nonconforming | |||
condition | |||
did not result in any safety-related | |||
equipment | |||
being inoperable. | |||
The licensee stated that the chainfall | |||
chains would be moved away from the heat exchanger. | |||
* The team observed a ladder in the west ESG room that appeared to be improperly | |||
stored. The ladder was lying on the floor under the installed | |||
ladder rack. The team asked the licensee if the condition | |||
was in accordance | |||
with plant procedures. | |||
The licensee initiated | |||
CR C-PAL-97-1601 | |||
and determined | |||
that the ladder location was not in accordance | |||
with the "Palisades | |||
Ladder Control Policy for Operating | |||
Spaces," dated May 14, 1997. The CR concluded | |||
that, although the ladder storage did not meet the ladder control policy, the nonconforming | |||
condition | |||
did not result in any safety-related | |||
equipment | |||
being inoperable. | |||
The licensee stated that the ladder was removed from the area. Procedure | |||
MSM-M-43 required an engineering | |||
review of scaffolding | |||
installed | |||
in the vicinity of safety-related | |||
equipment. | |||
Procedure | |||
1. 01 and the "Palisades | |||
Ladder Control Policy for Operating | |||
Spaces," dated May 14, 1997, contain requirements | |||
for storing items in the vicinity of safety-related | |||
equipment. | |||
In these cases, the licensee did not comply with the procedural | |||
requirements | |||
for activities | |||
affecting | |||
quality as required by 1 O CFR Part 50, Appendix B, Criterion | |||
V, "Instructions, 11 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Procedures, and Drawings." The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-09. | |||
Palisades | |||
60 Day Response: | |||
Remedial actions consisted | |||
of dispositioning | |||
all scaffolding | |||
and unrestrained | |||
items near the SIRW Tank and in the East and West Safeguards | |||
Rooms to assure operability | |||
of safety-related | |||
equipment.* | |||
Subsequently, walkdowns | |||
were conducted | |||
in other areas containing | |||
safety-related | |||
equipment | |||
and no conditions | |||
similar to the scaffolding | |||
conditions | |||
identified | |||
in this open item were observed. | |||
Maintenance | |||
and construction | |||
crews were briefed on the lessons learned pertaining | |||
to scaffolding | |||
erection. | |||
By July 15, 1998, we will revise procedures, provide training and reinforce | |||
management | |||
expectations | |||
as necessary | |||
to maintain compliance | |||
with seismic interaction | |||
requirements | |||
for related equipment. | |||
10/1/98 Update: Specific actions to revise procedures, provide training and reinforce | |||
management | |||
expectations | |||
as necessary | |||
to maintain compliance | |||
with seismic interaction | |||
requirements | |||
for safety-related | |||
equipment | |||
have been completed. | |||
Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 | |||
* (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-09) | |||
was identified | |||
as closed. This item was also the subject of NOTICES OF VIOLATION | |||
(50-255/98003-05 | |||
and 50-255/98003-06) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRG under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." This response is associated | |||
with plans to enhance maintenance | |||
personnel | |||
scaffolding | |||
training, and provide training for Auxiliary | |||
Operators | |||
to recognize | |||
unrestrained | |||
items for prompt identification. | |||
Training will be completed | |||
by March 1, 1999. Unresolved | |||
Item 50-255/97-201-10 | |||
During the surrogate | |||
tour, the team obseNed the ends of two vent pipes that connected | |||
the containment | |||
sump to the 590-ft elevation | |||
of the containment. | |||
The team asked the licensee to explain the design of these vent lines. During a review of the vent lines, the licensee determined | |||
that the top of the vents were located inside the containment | |||
at an elevation | |||
of approximately | |||
595-ft. The maximum calculated | |||
post-accident | |||
water elevation | |||
was at elevation | |||
597-ft. The vent pipes did not have screens on their inlets. The licensee also determined | |||
that the two vent lines entered the containment | |||
sump inside the sump screens, creating a potential | |||
path for debris to enter the EGGS pump suction piping under post-accident | |||
conditions. | |||
The licensee initiated | |||
CR C-PAL-97-1571, on October 29, 1997, to evaluate this condition | |||
and determined | |||
that the postulated | |||
type and quantity of debris that could enter the vent pipes under post-accident | |||
conditions | |||
would not prevent the SI and containment | |||
spray systems from performing | |||
their safety function, and that these systems were operable under this condition. | |||
The licensee also installed | |||
Temporary | |||
Modification | |||
TM-97-046, on October 29, 1997, to add screens to the top of the vent pipes during the inspection. | |||
These screens would prevent debris from entering the EGGS pump suctions in the event of an accident. | |||
12 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control," were not met in this instance in that the design basis of the containment | |||
sump to exclude debris from the EGGS pump suction piping was not fully implemented. | |||
The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-10. | |||
Palisades | |||
60 Day Response: | |||
As stated above, an operability | |||
determination | |||
concluded | |||
the Engineered | |||
Safeguards | |||
Systems were operable in the as-found condition. | |||
As additional | |||
assurance | |||
for continued | |||
operability, temporary | |||
screens were placed over the vent pipes. These screens will be permanently | |||
installed | |||
in the 1998 refueling | |||
outage. The programmatic | |||
design control aspects related to this issue will be addressed | |||
as identified | |||
in Attachment | |||
B, Item 1. 10/1/98 Update: Containment | |||
sump vent screens were permanently | |||
installed | |||
during the 1998 refueling | |||
outage. Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-10) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-0?a) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND.NOTICE | |||
OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." As part of our annual design basis document update projected | |||
for June 1999, the Containment | |||
Spray Design Basis Document DBD-2.03 will be revised to address issues vital to the function of the Engineering | |||
Safety Features following | |||
a LOCA. Refer to Attachment | |||
B, Item 1 for the programmatic "design control" aspects associated | |||
with this issue. Inspection | |||
Followup Item 50-255/97-201-11 | |||
The team also observed several piping penetrations | |||
between the east and west ESG rooms which included rubber piping expansion | |||
joints used as penetration | |||
seals. The team questioned | |||
the design of these piping penetration | |||
seals. The licensee stated that the engineering | |||
analyses that demonstrated | |||
that these penetrations | |||
met the design basis did not-specifically | |||
address the use of rubber piping expansion | |||
joints in the penetration | |||
seals. The team reviewed EA-RJC-92-0508, * ''Analysis | |||
of the Effect of a Fire on the Fire Barrier Penetration | |||
Seal Number FZ-0508," Revision 0, and verified that the rubber piping expansion | |||
joints were not addressed. | |||
The licensee initiated | |||
CR C-PAL-97-1627 | |||
and determined | |||
that the failure to specifically | |||
justify the presence of rubber expansion | |||
joints did not invalidate | |||
the conclusions | |||
of the original engineering | |||
analyses and that the penetration | |||
seals were adequate. | |||
The licensee also stated that the affected documentation | |||
would be corrected, and that an "extent of condition" review would be performed. | |||
The team identified | |||
this item as Inspection | |||
Fo/lowup Item 50-255197-201-11. | |||
13 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
An operability | |||
determination | |||
during the Design Inspection | |||
concluded | |||
that the safety function provided by the fire barriers separating | |||
the East and West Safeguards | |||
Rooms is not affected by the use of rubber expansion | |||
pipe joints. By August 1, 1998, we will revise the design basis engineering | |||
analysis to formally justify the installed | |||
rubber expansion | |||
pipe joints, and perform an investigation | |||
of other area fire barriers for potential | |||
unanalyzed | |||
designs. 1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-11) | |||
was identified | |||
as closed. The revision to the design basis engineering | |||
analysis for rubber expansion | |||
pipe joints is complete along with investigations | |||
for other fire barriers for potential | |||
unanalyzed | |||
designs. No other unanalyzed | |||
fire barrier design issues were discovered. | |||
No further actions are planned for this inspection | |||
item. Inspection | |||
Followup Item 50-255197-201-12 | |||
The team reviewed 10 SI system calculations | |||
and 1 pressurizer | |||
pressure uncertainty | |||
calculation; | |||
these were identified | |||
as "basis documents." Basis Document Rl-38, "SIRW Tank Level Instrument | |||
Calibration," Revision 6, was reviewed for adequacy. | |||
It provided the basis for calibration | |||
of SIRWT level indicators | |||
LT-0332A *and LT-0332B to enable their use to monitor the TS requirement | |||
that the tank contain at least 250, 000 gallons of borated water. Rl-38 used a tank boron concentration | |||
of 1720 parts per million (ppm) and did not consider the range of 1720 to 2500 ppm allowed by TS Section 3.3. Rl-38 was the basis document for the calibration | |||
of the level indicator | |||
that supported | |||
manual actuation | |||
of post-accident | |||
recirculation | |||
operation. | |||
The team was concerned | |||
that the increased | |||
density of the tank water at higher boron concentrations | |||
would increase the instrument | |||
uncertainty. | |||
The calculation | |||
also did not account for variation | |||
in boron concentration | |||
density caused by temperature | |||
changes; an effect which could also affect the total uncertainty. | |||
The licensee recalculated | |||
the total instrument | |||
uncertainty | |||
using the most conservative | |||
boron concentrations | |||
and temperature, and the *resulting | |||
change to the total uncertainty | |||
remained bounded by the original uncertainty | |||
value. Bases Document Rl-69, "Subcooled | |||
Margin Monitor Surveillance," Revision 6, was reviewed for adequacy. | |||
The subcooled | |||
margin monitor (SMM) provided the operator indication | |||
of the PCS margin to .saturation | |||
conditions. | |||
Rl-69 evaluated | |||
possible errors induced in the SMM. The team found that Rl-69 did not account for seismic uncertainty. | |||
This was inconsistent | |||
with RG 1.97 "Instrumentation | |||
for Light-Water-Cooled | |||
Nuclear Power Plants To Assess Plant and Environs Conditions | |||
During and Following | |||
an Accident," May 1983. This RG identifies | |||
subcooled | |||
margin as a Category/, Type A variable, which must continue to read within the required accuracy following, but not necessarily | |||
during, a safe-shutdown | |||
earthquake | |||
event. The team was concerned | |||
that the calculated | |||
error was nonconservative | |||
because it did not consider seismic uncertainty, and could provide misleading | |||
information | |||
to the operators. | |||
The licensee reanalyzed | |||
the potential | |||
error in the SMM, including | |||
seismic uncertainty, and the resulting | |||
total uncertainty | |||
remained bounded by the original uncertainty | |||
value. The licensee assigned Procedure | |||
Change Request (PCR) 5569 to revise Rl-69. 14 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS EA-RSW-94-001, "F/-0404 Instrumentation | |||
Uncertainty | |||
Calculation," Revision 2, was also reviewed for adequacy. | |||
The analysis established | |||
the recommended | |||
uncertainties | |||
of Fl-0404, which was used in flow testing of the SJ pumps. The instrument | |||
was installed | |||
in 1989, and has been calibrated | |||
five times since then. Drift error was determined | |||
using historical | |||
calibration | |||
data. For the first 4 years, the instrument | |||
was calibrated | |||
once a year. The team found that 24 months had transpired | |||
between the fourth and fifth calibrations. | |||
The licensee stated that the interval was | |||
in 1993 from 11 months to 24 months. The team asked if the drift analysis was revised to account for this change in the calibration | |||
interval. | |||
The* team was concerned | |||
that increasing | |||
the calibration | |||
interval to 24 months would increase the drift error and consequently | |||
increase the total uncertainty | |||
of the instrument. | |||
The licensee reanalyzed | |||
the Fl-0404 uncertainty | |||
using appropriate | |||
drift performance | |||
data for the longer calibration | |||
interval, and the resulting | |||
change to the total uncertainty | |||
remained bounded by the original uncertainty | |||
value. The licensee issued EAR-97-0658 | |||
to revise EA-RSW-94-001. | |||
The team also reviewed Basis Document Rl-15A, "Safety Injection | |||
Tank Pressure Channel Calibration," Revision 7, for adequacy. | |||
Rl-15A formed the bases for the pressure channel setpoints | |||
for PIA-0363, 0367, 0369, and 0371, which defined low-and high-pressure | |||
alarms for the S/Ts. The /ow-pressure | |||
alarms warned the operators | |||
of decreasing | |||
nitrogen pressure in the tanks. The channel alarms were set to annunciate | |||
earlier than the pressure limits of TS Section 3.3. 1 (b) so appropriate | |||
action could be taken before pressure reached the setpoints | |||
of pressure switches PS-03408, 03448, 03738, and 30508, which were set to alarm at the TS limits. The team was concerned | |||
that Rl-15A did not consider uncertainties | |||
such as stability | |||
and temperature | |||
effects and that the current total uncertainty | |||
was not adequate. | |||
Considering | |||
the low alarm point of 207 psig, the calculated | |||
uncertainty | |||
allowance | |||
of +/-6.85 psig could result in an alarm at close to 200 psig, which was the TS limit. If additional | |||
uncertainties | |||
were added, the channel pressure switches could alarm after the TS pressure switches. | |||
The licensee reanalyzed | |||
the setpoint for P/A-0363, 0367, 0369, and 0371 using additional | |||
appropriate | |||
uncertainty | |||
inputs and determined | |||
that the resulting | |||
instrument | |||
uncertainty | |||
was bounded by Rl-15A. The team observed that the results of these basis documents | |||
were determined | |||
to encompass | |||
specific additional | |||
uncertainties | |||
due to the assumed margins used in the documents | |||
to account for unquantified | |||
effects. The licensee had a guide entitled "Design & Maintenance | |||
Guide on Instrument | |||
Setpoint Methodology," EGAD-PROJ-16, Revision 0, and the team concluded | |||
that it provided a satisfactory | |||
methodology | |||
for setpoint calculations | |||
and was consistent | |||
with industry standard S67-04, Part I, "Setpoints | |||
for Nuclear Safety-Related | |||
Instrumentation." The licensee stated that EGAD-PROJ-16 | |||
provided identical | |||
guidance as EGAD-PROJ-08, Revision 0, of the same title, which was the current designation | |||
of the guide. The instruments | |||
that were re-analyzed | |||
during the inspection | |||
used the guidance of EGAD-PROJ-08. | |||
This methodology | |||
affirmed that margins remained bounded. The licensee stated that use of this guide was not required by plant procedures. | |||
However, the licensee has previously | |||
recognized | |||
from past assessments | |||
that its basis documents | |||
were not as rigorous as required by the current /SA standards. | |||
The licensee stated that EGAD-PROJ-08 | |||
was being revised and that the appropriate | |||
procedures | |||
would be revised to require its use. The team identified | |||
this item as Inspection | |||
Fol/owup Item 50-255197-201-12. | |||
Palisades | |||
60 Day Response: | |||
None of the above calculational deficiencies | |||
identified | |||
during the Design Inspection | |||
affected the operability | |||
of any safety-related | |||
equipment. | |||
During the inspection, EGAD-ELEC-08 | |||
Rev 1 was approved and issued to provide | |||
for instrument | |||
setpoint methodology. | |||
Our engineering | |||
staff 15 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS has been briefed as to the need to utilize this guidance. | |||
Plant procedures | |||
will be revised by August 15, 1998, to incorporate | |||
EGAD-ELEC-08 | |||
for use when setpoint calculations | |||
are required. | |||
10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-12) | |||
was identified | |||
as closed. Applicable | |||
plant administrative | |||
procedures | |||
have been changed to reference | |||
guidance document EGAD-ELEC-08 | |||
for use when performing | |||
setpoint calculations, and enhanced to more clearly . describe the applicability | |||
of EGAD-ELEC-08. | |||
No further actions are planned | |||
for this inspection | |||
item. Unresolved | |||
Item 50-255/97-201-13 | |||
During a walkdown of the SI system, the team observed that transmitters | |||
for containment | |||
spray flow, FT-0301 and FT-0302, and shutdown cooling heat exchanger | |||
flow, FT-0306, were properly mounted below their flow elements, but the process tubing was observed to be inadequately | |||
sloped back to the transmitters. | |||
Additionally, a walkdown performed | |||
by the licensee at the team's request during an * in-containment | |||
inspection | |||
revealed that the process lines to the HPSI cold-leg flow transmitters | |||
FT-0308, FT-0310, FT-0312, and FT-0313, and the LPSI flow transmitters, FT-0307, FT-0309, FT-0311, and FT-0314, were also installed | |||
with inadequate | |||
slope. The team was concerned | |||
that inadequate | |||
slope in instrument | |||
tubing could contribute | |||
to significant | |||
instrument | |||
uncertainty | |||
by entraining | |||
unequal amounts of air in either leg of the transmitter, causing erroneous | |||
readings. | |||
This was shown to be a valid concern when an operator observed an erroneous | |||
reading in the left channel containment | |||
spray loop indicator, Fl-0301A. | |||
The "below zero" reading was caused by air trapped in one of the process iines. The licensee issued CR C-PAL-97-1561 | |||
to vent the line. The lack of tubing slope was inconsistent | |||
with original plant installation | |||
specification | |||
J-F020, Revision 0. This specification | |||
stated: "Flow instruments (differential | |||
tyP.e) in liquid and condensable | |||
vapor service shall preferably | |||
be mounted below the main line connection | |||
so that the impulse lines will slope down to the instrument." The specification | |||
also stated: "Impulse lines to flow instruments | |||
shall slope (up or down) a minimum of one inch per foot." Plant drawings J-F133, Revision 1; * J-F134, Revision O; J-F140, Revision O; and J-F141, Revision 0, depict various acceptable | |||
installation | |||
configurations | |||
for a differential | |||
transmitter. | |||
The current installations | |||
of the flow instruments | |||
identified | |||
above were not consistent | |||
with these drawings. | |||
A later specification, J-465 (Q), "The Technical | |||
Specification | |||
for Installation | |||
of Instrumentation | |||
For Nuclear Service for CPCo Palisades," Revision 0, dated 1981 stated: "The installation | |||
shall be neat in appearance, properly supported, and shall provide for proper slope for adequate drainage or venting of the instrument | |||
lines." This specification | |||
has since been incorporated | |||
into specification | |||
20557-J-59 (Q) under the same title, which requires that a "horizontal | |||
tubing run is continually | |||
sloped in accordance | |||
with design drawings." The licensee issued CR C-PAL-97-1561 | |||
to evaluate these instrument | |||
tubing sloping discrepancies. | |||
According | |||
to the operability | |||
determination | |||
of the CR, the instruments | |||
have never shown any adverse effects of trapped air during the last 20 years of operation. | |||
The HPSI and LPSI flow transmitters | |||
were mounted as much as 8 ft above their flow elements. | |||
To accommodate | |||
instruments | |||
mounted above flow elements, specification | |||
J-F020 stated: "5 foot minimum "drop legs (equivalent | |||
of a loop seal)" may be required before the tubing is sloped up the I 16 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS meter." Plant drawings J-F152, Revision 1, and J-F153, Revision 0, depict these mounting configurations. | |||
The licensee stated that the bottom and side tap locations | |||
for the tubing would tend to limit the amount of air getting into the transmitters | |||
and that air entrainment | |||
would be minimal due to the ratio of the volume of the HPSI and LPSI pump suction piping to the tubing volume. EA-C-PAL-95-0877D, "Evaluation | |||
of the Potential | |||
for Excessive | |||
Air Entrainment | |||
Caused by Vortexing | |||
SIRWT During a LOCA," Revision 0, evaluated | |||
the potential | |||
for excessive | |||
air entrainment | |||
in the lines of the pumps caused by vortexing | |||
in the SIRWT during a LOCA, and determined | |||
that the air f]ntrainment | |||
would be a small percentage | |||
of the flow volume. The licensee also stated that technicians | |||
are required to vent the transmitters | |||
during every 18 month surveillance. | |||
However, the team was concerned | |||
that, since the transmitters | |||
sense low static pressure during normal standby operation, air may accumulate | |||
between calibration | |||
intervals | |||
and between system tests. Additionally, the water circulated | |||
through the SI lines from the containment | |||
sump could contain significant | |||
amounts of dissolved | |||
gasses, which could enter the tubing up to the flow transmitters. | |||
The team was concerned | |||
that the effect of air entrapped | |||
in the instrument | |||
tubing could cause large and unquantifiable | |||
errors in the flow indications. | |||
EOP Supplement | |||
4, "Loss of Coolant Accident Recovery Safety Function Status Check Sheet," contained | |||
curves presenting | |||
total SI flow ranges intended to help ensure that the minimum values utilized in the accident analyses (LOCA, MSLB, Steam Generator | |||
Tube Rupture (SGTR)) were met. There was also a minimum total flow criterion | |||
for the operators | |||
to meet, which ensured the containment | |||
sump check valves remained in a stable condition | |||
in EOP-4. 0, "Loss of Coolant Accident Recovery," Revision 9. The operators | |||
would use the HPSI and LPSI flow indication | |||
from FT-0308, 0310, 0312, 0313, 0307, 0309, 0311, and 0314 to compare SI system performance | |||
against the EOP requirements. | |||
The team was concerned | |||
that the potentially | |||
large errors could confuse the operator and impair decision making. The licensee stated that the opetators | |||
are trained to use all available | |||
indications | |||
and that alternate/additional | |||
instrumentation | |||
could be used to confirm trending of PCS conditions | |||
such as that for pressurizer | |||
level, subcooling | |||
margin, reactor vessel level, and charging pump flows. The licensee issued EAR-97-0699 | |||
to evaluate this item. It appeared that the design basis for instrument | |||
tubing installation | |||
was not implemented | |||
in the plant installation | |||
as required by 10 CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control." The team identified | |||
this item as Unresolved | |||
Item 50-255197-0201-13. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
the HPSI and LPSI flow indication | |||
is operable based on plant operating | |||
experience. | |||
Since the inspection, a plant walkdown was conducted | |||
which revealed that the HPSI and LPSI tubing configuration | |||
met design requirements | |||
but did not conform to associated | |||
design drawings. | |||
The existing tubing configurations | |||
*were observed, and the tubing was determined | |||
not to be susceptible | |||
to air entrainment. | |||
The * conclusions | |||
reached from this walkdown review further justify the reliability | |||
of the HPSI and LPSI flow indication, although configuration | |||
discrepancies | |||
exist. By August 15, 1998, we will resolve the HPSl/LPSI | |||
flow indication | |||
tubing discrepancies | |||
and compare our design requirements | |||
to additional | |||
samples of safety related instrument | |||
tubing to identify any additional | |||
nonconformances | |||
with design criteria. | |||
The programmatic | |||
design control aspects related to this issue will be addressed | |||
as identified | |||
in Attachment | |||
8, Item 1. 17 | |||
* * * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-13) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-07b) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." Subsequent | |||
to the Design Inspection, Palisades | |||
walked down these installations | |||
during the 98 refueling | |||
outage and confirmed | |||
that the sensing lines for HPSI and LPSI flow transmitters | |||
FT-0308, 0310, 0312, 0313, 0307, 0309, 0311 , and 0314 are appropriately | |||
sloped -thus no deviations | |||
from design requirements | |||
exist. A sampling of other sensing lines associated | |||
with safety-related | |||
equipment | |||
were also walked down and confirmed | |||
to meet design requirements | |||
for sensing line slope. NRC correspondence | |||
dated August 3, 1998 rescinded | |||
this cited potential | |||
violation. | |||
No further actions are planned for this inspection | |||
item. Unresolved | |||
Item 50-255/97-201-14 | |||
The team reviewed EA-ELEC-LDTAB-005, "Emergency | |||
Diesel Generator | |||
1-1 & 1-2 Steady State Loading," Revision 4, and verified that the analysis was consistent | |||
with the design basis information | |||
in the FSAR. All required accident loads for a LOCA and a LOOP were identified | |||
and tabulated. | |||
The electrical | |||
loads exceeded the continuous | |||
rating of the EOG during the first 32 minutes of operation | |||
but were below the EOG maximum 2-hour rating. One of the inputs to this analysis was the electrical | |||
toad estimate for LPSI pumps P-67 A and P-678. These electrical | |||
load estimates | |||
were based on the minimum hydraulic | |||
LPS/ pump performance | |||
used in EA-A-PAL-92-037, "Emergency | |||
Diesel Generator | |||
Loadings-First | |||
Two.Hours," Revision 1, which determined | |||
that LPSI pump flow would be* 3600 gpm. Although the LPS/ pump flow was conservative | |||
for evaluating | |||
LOCA mitigation, it was not conservative | |||
for determining | |||
the maximum load the EOG could experience | |||
during a LOCA. The team determined | |||
that the LPS/ pumps could pump 4500 gpm with one LPS/ pump discharging | |||
into all four injection | |||
loops as identified | |||
in EA-SDW-95-001, "Generation | |||
of Minimum and Maximum HPSllLPSI | |||
System Performance | |||
Curves Using Pipe-Flo," Revision | |||
2. The team was concerned | |||
that the licensee had not analyzed for the worst-case | |||
electrical | |||
load demand on the EDGs. Preliminary | |||
evaluations | |||
by the_ licensee using the correct maximum loads indicated | |||
that the electrical | |||
loading on one EOG could be higher than that determined | |||
in EA-ELEC-LDTAB-005. | |||
The licensee issued CR C-. PAL-97-1650 | |||
to review and correct all necessary | |||
electrical | |||
analyses and determined | |||
the EDGs to be operable. | |||
The team reviewed EA-ELEC-VOL | |||
T-13, "Palisades | |||
Loss of Coolant Accident With Off$ite Power Available," Revision 0, which evaluated | |||
the ac voltage available | |||
during normal operating, refueling, and accident conditions. | |||
The team noted that the calculation | |||
had not been revised since 1993 and . that the load magnitudes | |||
identified | |||
in EA-ELEC-LDTAB-005, Revision 4, and EA-SDW-95-001, Revision 2, had not been included. | |||
The licensee reviewed the impact of the revised loads on EA-ELEC-VOL | |||
T-13 and determined | |||
that the changes had minimal effect on the analysis. | |||
The team also noted that FSAR Section 8.3 stated that backfeeding | |||
via the main and station power transformers | |||
could be utilized; | |||
however, EA-ELEC-VOL | |||
T-13 had not analyzed this particular | |||
operating | |||
mode. The licensee stated that it had recognized | |||
that an analysis for backfeeding | |||
needed to be performed | |||
in 1994 and had issued AIR A-PAL-94-223 | |||
to create an analysis in order to bound 18 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS this condition | |||
of operation. | |||
The licensee initiated | |||
C-PAL-97-1619 | |||
to review and update EA-ELEC-VOLT-13 | |||
for load changes. It appeared that the requirements | |||
of10 CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control," had not been met for EA-ELEC-LDTAB-005 | |||
an*d EA-ELEC-VOLT-13 | |||
in that the design basis had not been updated to document the actual plant parameters. | |||
The team identified | |||
this item as part of Unresolved | |||
Item 50-255197-201-14. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made which concluded, based on an evaluation | |||
which bounded recent load changes, that the electrical | |||
system is operable. | |||
Mechanical | |||
flow model analyses, which serve as input to the electrical | |||
load flow analyses, will be completed | |||
by December 15, 1998. The electrical | |||
load flow analyses, which will assure plant loads are accounted | |||
for and applicable | |||
operating | |||
scenarios | |||
are addressed, will be completed | |||
by August 15, 1999. A specific backfeed analysis will be completed | |||
by Januar}t 15, 1999. The programmatic | |||
design control aspects related to this issue will be addressed | |||
as identified | |||
in Attachment | |||
8, Item 1. 1011/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", th.is item (50-255/97201-14) | |||
was identified | |||
as closed. The mechanical | |||
and subsequent | |||
electrical | |||
flow model analyses are on target for completion | |||
by December 15, 1998 and August 15, 1999, respectively, as stated above. Backfeed analysis EA-ELEC-FL | |||
T-009, "GSU Short Circuit Analysis" was completed | |||
with design attributes | |||
captured in the applicable | |||
Design Basis Document. | |||
Refer to Attachment | |||
8, Item 1 for the programmatic "design control" aspects associated | |||
with this issue. * Inspection | |||
Followup Item 50-255/97-201-15 | |||
FSAR Section 8.5.2 stated that cables would be sized in accordance | |||
with the National Electric Code (NEC) or Insulated | |||
Power Cable Engineers | |||
Association | |||
(/PCEAllCEA) | |||
ampacity values and the cable ampacities | |||
would be adjusted on the basis of actual field conditions | |||
when possible. | |||
The adjustments | |||
included conductor | |||
operating | |||
temperature, ambient temperature, cable overall diameter, raceway fill, and fire stops. The licensee had recently initiated | |||
a program to verify the adequacy of its cable ampacity sizing. EA-ELEC-AMP-032, "Ampacity | |||
Evaluation | |||
for Open Air Cable Trays With a Percent Fill Greater Than 30% of the Usable Cross Sectional | |||
Area," Revision 1, was issued in 1997 to address cable sizing. While reviewing | |||
the EA, the team noted the absence of fire stop derating and increased | |||
cable temperatures | |||
due to thermal radiation | |||
from hot pipes. The licensee had initiated | |||
AIR A-PAL-97-062 | |||
to evaluate the effects of local heat sources on fire stops; however, evaluation | |||
of the effects on cable degradation | |||
due to the close proximity | |||
of hot piping systems had not been included. | |||
The licensee stated that evaluation | |||
of the effects of hot piping would be included under A-PAL-97-062. | |||
The team identified | |||
this item as Inspection | |||
Followup Item 50-255197-201-15 . 19 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
We will complete our Cable Ampacity Sizing Program by September | |||
15, 1998 which will identify any cable degradation | |||
due to the close proximity | |||
of hot piping, and any degradation | |||
of fire stops due to local heat sources. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-15) | |||
was identified | |||
as open. Cable * degradation | |||
due to the close proximity | |||
of hot piping, and any degradation | |||
of fire stops due to local heat sources has been evaluated. | |||
Results confirm that the cable design is acceptable. | |||
No further actions are planned for this inspection | |||
item. Unresolved | |||
Item 50-255/97-201-16 | |||
The 120-V ac safety-related | |||
and non-safety-related | |||
loads were powered from instrument | |||
ac bus Y-01. Bus Y-01 was powered from either motor control center (MCC) 1or2 via automatic | |||
transfer switch Y-50. MCCs 1 and 2 were redundant | |||
safety-related | |||
busses. The licensee stated in a January 24, 1978, letter to the NRG that it would. implement | |||
the recommendation | |||
of RG 1. 6 in that no . provision | |||
would exist for automatically | |||
transferring | |||
loads between redundant | |||
power sources. The NRG issued a safety evaluation | |||
report, dated April 7, 1978, confirming | |||
the licensee's | |||
commitment. | |||
FC-364, "Feeder Change for Instrument | |||
Bus Y-01," Revision 0, implemented | |||
this commitment | |||
and powered bus Y-01 from MCC 1 and non-safety-related | |||
MCC 3. However, FC-854, "Y-01 Power Supply Feed Modification," Re.vision | |||
0, moved the backup power source from MCC 3 to the safety-related | |||
MCC 2, and resulted in a departure | |||
from the plant's licensing | |||
basis. The modification | |||
installed | |||
fuses in series with the existing breakers, which provided an additional | |||
level of protection | |||
for the two safety-related | |||
busses. The team observed that the safety evaluation | |||
performed | |||
for FC-854 did not identify that prior NRC approval was required. | |||
The licensee issued CR C-PAL-97-1678 | |||
to document this deviation | |||
from the licensing | |||
basis. It appeared that this modification | |||
was a USO in that the possibility | |||
of a common-mode | |||
failure of the redundant | |||
safety-related | |||
busses was created, which was not previously | |||
evaluated | |||
in the FSAR and, thus, the criterion | |||
of 10 CFR 50.59(a)(2)(ii) | |||
was satisfied. | |||
The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-16. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was completed | |||
which concluded | |||
that the implemented | |||
design meets the intent of RG 1.6 and provides a single failure proof method of preventir:ig | |||
the transfer of a fault between redundant | |||
load sources. The current configuration | |||
was implemented | |||
under FC-854 with the modification | |||
safety evaluation | |||
concluding | |||
that an unreviewed | |||
safety question does not exist. Prior NRC approval of the change was not required. | |||
A description | |||
of the implemented | |||
modification | |||
was transmitted | |||
to the NRC in our Annual Report of Facility Changes, Tests and Experiments | |||
dated April 2, 1991. This 1989 modification | |||
resulted in a change to a prior NRC commitment. | |||
In accordance | |||
with NEI guidelines, we will submit by November 1, 1998, a revised commitment | |||
which reflects the existing plant configuration | |||
and governing | |||
design basis. 20 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN iNSPECTION | |||
OPEN ITEMS 10/1/98 Update: Per NRG correspondence | |||
dated May 18, 1998, titled "NRG INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-16) | |||
was identified | |||
as closed. This item was also the subject of a NOTICE OF DEVIATION | |||
(50-255/98003-08) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRG \ . .mder correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." In summary, Palisades | |||
concludes | |||
that our commitment | |||
to assure that redundant | |||
safety related power sources cannot be both affected by a fault on the instrument | |||
bus has been maintained. | |||
NRG correspondence | |||
dated August 3, 1998 concluded | |||
that a USQ does not exist, and that Consumers | |||
appropriately | |||
notified the NRG of past design changes, and rescinded | |||
this cited potential | |||
deviation. | |||
No further actions are planned for this inspection | |||
item. Inspection | |||
Followup Item 50-255/97-201-17 | |||
The team observed that no system analysis existed to show that all the Class 1 E 120-V ac loads had *adequate | |||
voltages. | |||
The licensee demonstrated | |||
during the inspection | |||
that adequate voltages did exist for selected loads. For example, EA-ELEC-VOLT-24, "Voltage Drop From Preferred | |||
AC Power Source Y10 Breaker 2 and Y40 Breaker 2 Out to the 5U12 Relays," Revision 0, showed that adequate ac voltage for those selected components | |||
was available | |||
at the minimum.inverter | |||
voltage. The licensee initiated | |||
CR C-PAL-97-1621 | |||
to evaluate and resolve this concern. The team identified | |||
this item as part of Inspection | |||
Fol/owup Item 50-255197-201-17. | |||
Palisades | |||
60 Day Response:. | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
the Class 1 E 120 V * ac loads are operable based on past plant operating | |||
experience | |||
and the expected minimal change in supplied voltage between normal and accident plant conditions. | |||
By August 15, 1998,. we will perform a bounding analysis to confirm that Class 1 E 120 V ac loads have adequate voltage during accident conditions. | |||
10/1/98 Update: Per NRG correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-17) | |||
is identified | |||
as open. A bounding calculation | |||
was performed | |||
under EA-C-PAL-97-1621A-01 | |||
that developed | |||
worst case voltage levels for the Preferred | |||
AC System and confirmed | |||
adequate available | |||
voltage during accident conditions . These analysis results will be incorporated | |||
into Design Basis Document DBD-4.03, "Preferred | |||
AC System" and tracked under change request number 4.03-12-R3-0728. | |||
No further actions are planned for this inspection | |||
item . 21 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Unresolved | |||
Item 50-255/97-201-18 | |||
The team reviewed relay settings for protective | |||
relays associated | |||
with LPSI pump P-67 A, HPSI pump P-66A, SW pump P-7A, CCW pump P-52A, EOG 1-1 differential | |||
protection, bus 1C undervoltage | |||
protection, and Bus 1 C second-level | |||
undervoltage | |||
protection. | |||
The settings were consistent | |||
with the design parameters | |||
of the devices being protected. | |||
However, during the review, the licensee determined | |||
that the overcurrent | |||
relays for supply breakers 152-105 and 152-106 to bus 1C had not been calibration | |||
tested during the last refueling | |||
outage (1995) as required by Periodic and Predetermined | |||
Activity (PPAC) SPS025, "Bus 1 C Relay Testing." The licensee stated that these relays would be calibrated | |||
during the 1998 refueling | |||
outage. The licensee reviewed past calibration | |||
data for this type of relay and determined | |||
that negligible | |||
drift had previously | |||
been documented. | |||
The licensee initiated | |||
CR C-PAL-97-1568 | |||
to resolve this discrepancy. | |||
It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion | |||
XI, "Test Control," had not been implemented | |||
in this case in that certain relays had not been tested as required by the test program. The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-18. | |||
* Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that past calibrations | |||
of overcurrent | |||
relays for breakers 152-105 and 152-106 revealed insignificant | |||
drift and the relays are operable. | |||
We will perform maintenance | |||
activity PPAC SPS025 to calibrate | |||
the overcurrent | |||
relays during the 1998 refueling | |||
outage. Our corrective | |||
action history identified | |||
no other examples of failure to perform scheduled | |||
relay testing. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-18) | |||
was identified-as | |||
closed. This item was also the subject of a NOTICE OF VIOLATION | |||
(50-255/98003-09) | |||
from the same letter. Palisades | |||
responded | |||
with additional | |||
information | |||
to the NRC under correspondence | |||
dated June 24, 1998, entitled "RESPONSE | |||
TO NOTICE OF VIOLATION | |||
AND NOTICE OF DEVIATION | |||
FROM INSPECTION | |||
REPORT 50-255/98003." In summary, the overcurrent | |||
relays for breakers 152-105 and 152-106 will be tested/calibrated | |||
by December 31, 1998. The requirements | |||
for PPAC SPS025 have been revised to allow performance | |||
of the testing and calibration | |||
while the plant is at power operation. | |||
Unresolved | |||
Item 50-255/97-201-19 | |||
The team questioned | |||
the replacement | |||
schedule for Agastat E7000 series relays. The team was aware that the manufacturer, in correspondence | |||
to other utilities, had recommended | |||
a 10-year replacement | |||
schedule for these relays. The licensee stated that 52 E7000 series relays were installed | |||
and that 7000 series Agastats were also installed | |||
in Class 1 E applications. | |||
Some circuits containing | |||
7000 series relays included the 2400-V bus 1C and*1D supply breakers, time delay relays associated | |||
with charging pumps. P-55A, B, and C, and auto transfer failure alarms for 2400-V busses 1C and 10. The manufacturer's | |||
stated qualified | |||
life forthe E7000 relays was 10 years. The licensee stated that the | |||
qualified | |||
life applied if the relays were located in a harsh environment | |||
and, 22 | |||
* * * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS since the E7000 relays were located in a mild environment, no qualified | |||
life determination | |||
was required. | |||
Based upon this justification, the licensee issued PPAC Deletion Form MSE 034, dated March 3, 1995, which stated that the relays would not require replacement | |||
at 10-year intervals. | |||
The team believed that the qualified | |||
life stated by the manufacturer | |||
applied to any environment. | |||
The team verified with the manufacturer | |||
that the projected | |||
qualified | |||
life of 10 years was the operating | |||
life of the E7000 series relay as long as the device did not exceed the equipment | |||
ratings, and that the life of 10 years was applicable | |||
to either a mild or harsh environment. | |||
The licensee had not evaluated | |||
the qualified | |||
life ofthe 7000 series relays. The manufacturer | |||
of Agastat relays issued a 10 CFR Part 21 notification | |||
concerning | |||
the inability | |||
of the E7000 series relays to switch a 1-amp load at rated voltage. The licensee evaluated | |||
the installed | |||
E7000 series relays and identified | |||
no concerns. | |||
The team observed that this evaluation | |||
did not review those 7000 series relays dedicated | |||
by the licensee to safety-related | |||
use. The licensee issued CR C-PAL-97-1663 | |||
to resolve the issues concerning | |||
Agastat relays and determined | |||
that all the relays were operable. | |||
It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control," had not been met in this instance in that the design basis lifetime for Agastat relays as stated by the manufacturer | |||
had not been correctly | |||
implemented | |||
in the facility. | |||
The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-19. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the 7000 series relays are operable based on their similarity | |||
in application | |||
and design to E7000 relays. By July 15, 1998, we will complete our analysis of both 7000 and E7000 series relays dedicated | |||
for safety related use to confirm their ability to perform safety-related | |||
functions | |||
during their installed | |||
life and their conformance | |||
with applicable | |||
design requirements. | |||
10/1/98 Update: Per NRG correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-19) | |||
was identified | |||
as open. A review of both 7000 and E7000 relay age-sensitive | |||
components | |||
was performed | |||
that indicates | |||
that all relay materials | |||
will last for greater than 40 years without significant | |||
degradation | |||
when installed | |||
in mild environments. | |||
Based on this review, a 10 year replacement | |||
interval is not justified | |||
and the relays can be expected to perform their design function for greater than 40 years. No further | |||
actions are planned for this inspection | |||
item. Unresolved | |||
Item 50-255/97-201-20 | |||
The 125-V de system was divided into two independent | |||
systems. Each system consisted | |||
of a battery, switchgear, distribution | |||
panel, and two chargers. | |||
Station battery 1, battery charger 1, and battery charger 3 supplied 125-V de bus 1. Battery charger 1 was supplied from MCC 1 and battery charger 3 was supplied from MCC 2. Administrative | |||
controls limited the operation | |||
so that only one charger per battery was in service. This prevented | |||
a common-mode | |||
failure from affecting | |||
both * 23 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS emergency | |||
busses. The supply to 125-V de bus 2 was similar, with battery charger 2 fed from MCC 2 and battery charger 4 fed from MCC 1. Operating | |||
Procedure | |||
SOP-30, "Station Power," Revision 20, required the battery chargers to be operated in pairs (1 and 2 or 3 and 4). The licensee stated that the battery chargers were swapped monthly to provide equal operating | |||
time for each battery charger. During swapping of the battery chargers in accordance | |||
with Section 7. 7. 2 of SOP-30, the 125-V de breaker on the in-service | |||
battery charger was opened and then the 125-V de breaker for the battery charger to be placed in service was closed. During this evolution, both battery chargers were disconnected | |||
from the station battery and 125-V de switchgear | |||
bus. Although temporary | |||
disconnecting | |||
the battery charger from the de bus had minimal safety impact on the plant, the team observed that TS 3. 7. 1 h required two station batteries | |||
and the de systems (including | |||
at least one battery charger on each bus) to be operable when the PCS was above 300 °F. The licensee stated that an LCO was not entered when no battery chargers were connected | |||
to the de busses. The licensee initiated | |||
CR C-PAL-97-1537 | |||
to resolve this discrepancy. | |||
The team identified | |||
the licensee's | |||
failure to enter an LCO during battery charger switching | |||
evolution | |||
as Unresolved | |||
Item 50-255197-201-20. | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design Inspection, we concluded | |||
that our design bases were met and an LCO would not entered when realigning | |||
battery chargers. | |||
This conclusion | |||
was based on no appreciable | |||
battery discharge | |||
occurring | |||
during the short realignment | |||
period when neither | |||
charger was connected | |||
to the 125 Vdc bus. In response to this Design Inspection | |||
item, however, operating | |||
procedure | |||
SOP-30 was revised in anticipation | |||
of an amendment | |||
approving | |||
our December 27, 1995 technical | |||
specifications | |||
change request. Although the requested | |||
change does not require a connected | |||
charger, the change defines 125 Vdc bus operability | |||
in terms of applied bus voltage. SOP-30 now requires entry into an LCO whenever performing | |||
charger realignment. | |||
On January 26, 1998, a technical | |||
specification | |||
change request was resubmitted | |||
as part of the Improved Technical | |||
Specifications | |||
Program. An amendment | |||
in response to this latest change request will resolve this open item. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-20) | |||
was identified | |||
as closed. In July 1998, Amendment | |||
180 of the Palisades | |||
Electrical | |||
Technical | |||
Specifications | |||
was implemented | |||
that clarifies | |||
the 125 Vdc system operational | |||
requirements. | |||
With the issuance and implementation | |||
of Amendment | |||
180, no further actions are planned for this inspection | |||
item. Inspection | |||
Followi.Jp | |||
Item 50-255197-201-21 | |||
The team reviewed the 125-V de battery loading during the normal and alternate | |||
battery charger alignment. | |||
During the normal battery charger alignment, battery charger 1 was powered from EOG 1-1 and battery charger 2 was powered from EOG 1-2. During a LOCA combined with a LOOP in this normal alignment, the batteries | |||
would be without ac power for approximately | |||
1 O seconds until the EDGs restored power. The team reviewed EA-ELEC-LDTAB-009, "Battery Sizing for the Palisades | |||
Class 1 E Station Batteries | |||
ED-01 and ED-02," Revision 2, which verified that the battery was sized to provide adequate power during the 10 second interval until the EDGs provided ac power to battery 24 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGNINSPECTION | |||
OPEN ITEMS chargers 1 and 2. During the alternate | |||
battery charger alignment | |||
with battery charger 3 powered from EOG 1-2 and battery charger 4 powered from EOG 1-1, the station batteries | |||
would be required to carry the de loads for more than 10 seconds in the event of a LOCA combined with a LOOP and a single failure of ac power. EA-ELEC-LDTAB-009 | |||
did not analyze the battery loading for station batteries | |||
ED-01 and ED-02 during this condition. | |||
When questioned | |||
by the team the licensee stated that the de loading during this scenario would be greater than the worst-case | |||
loading assumed in ELEC-LDTAB-009. | |||
The licensee issued CR C-PAL-97-1596 | |||
to resolve this discrepancy. | |||
Additionally | |||
the team had concerns on whether the licensee met the single failure criterion | |||
when the alternate | |||
battery charger alignment | |||
was in effect. The team identified | |||
the question with respect to the single failure criterion | |||
and the additional | |||
loading on the battery as an Inspection | |||
Followup Item 50-255197-201-21. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the station batteries | |||
are operable. | |||
Operability | |||
was based on a preliminary | |||
analysis where additional | |||
* conservative | |||
loads were included in the battery load analysis showing that the battery terminal voltage would be greater than the required minimum output of 105 Vdc throughout | |||
the exp.ected | |||
load duration until an operable charger would be connected | |||
to the bus. Operating | |||
procedures | |||
control alternate | |||
charger alignment | |||
but do not restrict this practice which is allowed by technical | |||
specifications. | |||
By January 15; 1999, we will complete a formal analysis of battery loading considering | |||
the battery chargers are in their alternate | |||
alignment, and a combined event of a LOCA, LOOP and single failure of ac power occurs. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-21) | |||
was identified | |||
as open. As stated above, by January 15, 1999, the formal battery loading analysis will be completed. | |||
Inspection | |||
Followup Item 50-255/97-201-22 | |||
The team identified | |||
that TS Section 4. 7.2c required that each station battery be demonstrated | |||
operable by verifying | |||
that the battery capacity was adequate to supply and maintain in an operable status all of the actual emergency | |||
loads for 2 hours when the battery was subjected | |||
to a battery service test. The battery service tests performed | |||
on station batteries | |||
ED-01 and ED-02 were performed | |||
for a duration of 4 hours. The 4-hour duration and loading was based on the design basis station blackout (SBO) coping time. The team noted that the 2-hour requirement | |||
of TS 4. 7.2c was non-conservative | |||
with respect to the design basis, which required the station batteries | |||
to be available | |||
for4 hours. The design basis duration of 4 hours was included in FSAR Section 8.4.2; DBD 4.01, "Station Batteries," Revision 3; RE-83A, "Service/Modified | |||
Performance | |||
Test-Battery | |||
No. ED-01," Revision 9, and RE-838, "Service/Modified | |||
Performance | |||
Test-Battery | |||
No. ED-02," Revision 9. Testing the batteries | |||
in accordance | |||
with RE-83A and B has ensured that batteries | |||
ED-01and02 | |||
have met the 4-hour design basis requirement. | |||
The licensee has submitted | |||
TS changes to correct the non-conservative | |||
TS Section 4. 7.2c and issued CR C-PAL-97-1551 | |||
to resolve this discrepancy. | |||
The team identified | |||
this item as Inspection | |||
Followup Item 50-255197-201-22. | |||
25 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the 4-hour SBO station battery load profile envelops the 2-hour OBA load profile. By January 15, 1999, we will complete a formal analysis of battery loading considering | |||
the battery chargers are in their allowed alignment | |||
configurations | |||
with a combined event of a LOCA, LOOP and.single | |||
failure of ac power. We submitted | |||
a technical | |||
specification | |||
change request on December 27, 1995 to describe the test profile as the design basis profile without stipulating | |||
a specific period for the profile. On January 26, 1998, a technical | |||
specification | |||
change request was resubmitted | |||
as part of the Improved Technical | |||
Specifications | |||
Program which identifies | |||
a four hour load profile for the service test. An amendment | |||
in response to this latest technical | |||
specifications | |||
request will resolve this open item. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-22) | |||
was identified | |||
as open. As identified | |||
above, by January 15, 1999, the formal battery loading analysis will be completed. | |||
In July 1998, Amendment | |||
180 of the Palisades | |||
Electrical.Technical | |||
Specifications | |||
was implemented. | |||
Amendment | |||
180 does not specify a duty cycle (profile) | |||
duration in units of time. Therefore, the design basis requirements | |||
found in the FSAR can be used. Inspection | |||
Followup Item 50-255/97-201-23 | |||
EA-ELEC-FL | |||
T-005, "Short-Circuit | |||
for the Palisades | |||
Class 1 E Station Batteries | |||
ED-01 and ED-02," . Revision 0, was submitted | |||
to the team as the short-circuit | |||
analysis for the Class 1E 125-V de system. The following | |||
discrepancies | |||
with the assumptions, methodology, and conclusions | |||
were identified: | |||
* Section 4. 4 and 4. 5 assumed various breaker and fuse impedances, which had not been verified against the installed | |||
facility. | |||
* Section 5. 2 utilized the battery charger current limit of 220 amps as the maximum short-circuit | |||
contribution | |||
without supporting | |||
documentation. | |||
* Section 5.2 stated that the open-circuit | |||
voltage was 2.06 V per cell, whereas the EA utilized an open-circuit | |||
voltage of 2. 0 V per cell. * Section 8. 0 stated that the results were to be further reviewed by the licensee; | |||
however, the team found no evidence of this review. Section 8. O also contained | |||
no conclusion | |||
about the de system acceptability. | |||
The licensee issued A/Rs A-PAL-97-108, 109, and 110 to resolve these discrepancies. | |||
The licensee stated that the* analyses would be reviewed and the conclusions | |||
revised. During the 1995 refueling | |||
outage, FES-95-206 | |||
replaced existing batteries | |||
ED-01 and ED-02. The team questioned | |||
if the sh9rt-circuit | |||
current provided by the new battery was analyzed and if there were any effects on the de distribution | |||
panel breakers, since the team noted that EA-ELEC-FL | |||
T-005 26 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS . had not been updated since 1994. The team also noted that the design basis for the evaluation | |||
of fault current contributions | |||
on de circuits was in FSAR Section 8.5.2, which stated "The 125 volt de protection | |||
design considers | |||
the fault current available | |||
at the source side of the feeder protective | |||
device." However, the licensee stated that the short-circuit | |||
contribution | |||
value for de circuits was taken at the electrical | |||
load terminals | |||
and not at the breaker load terminals (de short-circuit | |||
current value would be less when calculated | |||
at the load terminal vice the source side of the feeder protection | |||
device because voltage available | |||
at the load terminal would be less than at the source breaker). | |||
The licensee determined | |||
that the short-circuit | |||
contribution | |||
at 8 breakers (breakers | |||
72-101, 72-105, 72-106, 72-121, 72-127, 72-133, and 72-135) on distribution | |||
panels 011-1and011-2 | |||
could exceed the short-circuit | |||
interrupting | |||
ratings when evaluated | |||
in accordance | |||
with the design basis method in the FSAR. Also, when the team questioned | |||
the assumed breaker fault ratings on de busses 010, 020, 011-1, and 011-2of13,000 | |||
amps in EA-ELEC-FLT-005, the licensee was unable to show manufacturer | |||
or testing documentation | |||
to support this assumption. | |||
The team believed that this assumption | |||
was inconsistent | |||
with its experience. | |||
The licensee performed | |||
an operability | |||
review and issued CR C-PAL-97-1652 | |||
to resolve these discrepancies. | |||
The maximum short-circuit | |||
current of the battery installed | |||
by FES-95-:206, as provided by the manufacturer, was 17094 amps. Calculation | |||
EA-ELEC-FL | |||
T-005 did not reflect this new short:..circuit | |||
current. Upon questioning | |||
by th.e team, the licensee stated that an evaluation | |||
was performed | |||
to ensure that the system short-circuits | |||
were acceptable. | |||
During the team's review of this evaluation | |||
it was determined | |||
that the maximum battery short-circuit | |||
current was not utilized. | |||
The.licensee | |||
stated that the short-circuit | |||
current utilized, 12,821 amps, was provided by the manufacturer | |||
as a more realistic | |||
value than 17,094 amps. However, the licensee could not document a basis for the 12,821 amps and stated that they would verify it with the manufacturer. | |||
The team identified | |||
these discrepancies | |||
concerning | |||
EA-ELEC-FL | |||
T-005 as part of Inspection | |||
Followup Item 50-255197-201-23. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that a fault would more likely occur at the load rather than at the breaker terminals. | |||
A fault at the load (esults in a reduced value of fault current which falls within the breaker interrupting | |||
rating. We have since obtained vendor specifications | |||
which envelop our calculated | |||
peak short circuit currents assumed to occur at the breaker terminals. | |||
These specifications | |||
confirm our earlier conclusion | |||
that the breakers are suitable for their intended service, and resolve any concerns with respect to breaker short circuit interrupting | |||
capability. | |||
Revisions | |||
to analysis EA-ELEC-FL | |||
T-005, to correct the plant-identified | |||
deficiencies | |||
described | |||
in the Design Inspection | |||
report, will be complete by January 15, 1999. 10/1/98 Update: Per NRG correspondence | |||
dated May 18, 1998, titled "NRG INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-23) | |||
was identified | |||
as open. Revisions | |||
to analysis EA-ELEC-FL | |||
T-005, to correct the plant-identified | |||
deficiencies | |||
described | |||
in the Design Inspection | |||
report, remains scheduled | |||
for completion | |||
by January 15, 1999 . 27 | |||
* ** * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Inspection | |||
Followup Item 50-255197-201-24 | |||
FSAR Section 8.4.3.3 stated that the batteries | |||
were designed to furnish their maximum load down to an operating | |||
temperature | |||
of 70 °F without dropping below 105 V de, and that the equipment | |||
supplied by the batteries | |||
was capable of operating | |||
satisfactorily | |||
at this voltage rating. EA-ELEC-VOL | |||
T-026, "Voltage Drop Model of the Palisades | |||
Class 1 E Station Batteries | |||
D01 and D02," Revision 0, evaluated | |||
the de voltages at the distribution | |||
panels based upon a battery voltage of 105 V de, but did not evaluate the voltages that would be available | |||
at the load device terminals. | |||
The team was concerned | |||
that the additional | |||
voltage drop from the distribution | |||
panel to the loads could result in voltages less than the design basis of the loads, and that no analysis was performed | |||
to evaluate this situation. | |||
For example, the deign-basis | |||
minimum input voltage for the inverters | |||
was 105 V de and the licensee could not show any vendor documentation | |||
to support operating | |||
at a value Jess than 105 V de. The team noted that the inverters | |||
could be subjected | |||
to an input voltage of approximately | |||
102 V de if the battery voltage were 105 V de. The licensee stated that battery surveillance | |||
testing has shown that battery voltage, when subjected | |||
to an SBO duty cycle, did not decrease below 108 V de. During the inspection, the licensee evaluated | |||
several safety-related | |||
loads and verified that adequate voltages would exist at 105 V de battery voltage. The licensee issued CR C-PAL-97-1620 | |||
to evaluate the lack of an EA to ensure that adequate voltages would exist at the load terminals. | |||
The team identified | |||
this item as part of Inspection | |||
Followup Item 50-255197-201-24. | |||
Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the 125 Vdc system is operable based on an evaluation | |||
of several safety related loads, in which adequate load voltage was found to exist with a 105 Vdc battery terminal voltage. By November 15, 1998, we will perform a bounding analysis to identify the worst-case | |||
minimum voltage levels at the load assuring that minimum load voltage req.uirements | |||
are met. * 1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-24) | |||
was identified | |||
as open. As stated above, this issue is scheduled | |||
for completion | |||
by November 15, 1998. Unresolved | |||
Item 50-255197-201-25 | |||
The team also questioned | |||
the capability | |||
of solenoid valves to operate at voltages of 87 V de as stated in DBD 1. 01, | |||
Cooling Water System," Revision 4. The licensee determined | |||
that the DBD was incorrectly | |||
worded and that the correct solenoid capability | |||
was 90-140 V de. Upon further review, the licensee identified | |||
that improperly | |||
rated coils, rated 102-126 V de, were installed | |||
in solenoid valves SV-0918 and SV-09778. | |||
The licensee initiated | |||
Engineering | |||
Assistance | |||
Request (EAR) 97-0652 to replace the coils. It appeared that the requirements | |||
of 10 CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control," were not followed in that the design basis for the solenoid valve coils was not implemented | |||
in the plant. The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-25 . 28 | |||
** ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
Since the design inspection, further evaluation | |||
identified | |||
that there is no impact on the mitigation | |||
of an accident if solenoid valves SV-0918 and SV-09778 fail to open due to low voltage since the close position is both the failed position and the required safety position. | |||
Based on this review, the design basis is met by the existing solenoid valve installation. | |||
The actions in response to Inspection | |||
Followup Item 50-255/97-201-24 | |||
will identify any other minimum voltage problems. | |||
10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-25) | |||
was identified | |||
as closed. No further actions are planned for this inspection | |||
item. Inspection | |||
Followup Item 50-255/97-201-26 | |||
The team identified | |||
other discrepancies | |||
in calculations | |||
as follows: * Assumptions | |||
4. 6 and 4. 7 of EA-ELEC-VOL | |||
T-26, Revision 0, and assumptions | |||
4. 8 and 4. 9 of EA-ELEC-M/SC-022, "Electrical | |||
Systems Model of the Palisades | |||
Class 1 E Safety Re/a.fed 125 V de System," Revision 1, assumed various fuse and breaker impedances | |||
which had not been verified against the installed | |||
equipment. | |||
* Section 7. 0 of EA-ELEC-VOL | |||
T-26, Revision 0, "Conclusion," stated that the results were to be further reviewed by the licensee; | |||
however, the team found no indication | |||
that this review had been performed. | |||
The "Conclusion" section also contained | |||
no statement | |||
concerning | |||
the de system acceptability. | |||
* EA-ELEC-VOL | |||
T-26, Revision 0, utilized a correction | |||
factor for battery temperature | |||
of 77 °F instead of the correction | |||
factor for 70 °F, which was the minimum design basis temperature | |||
for the battery. The number utilized is less conservative | |||
and the licensee evaluated | |||
that the overall effect on voltages in the calculation | |||
would be less than 0. 5 percent. * EA-ELEC-LDTAB-029, Revision 2, stated the type of battery constant as 1.0 in Attachment | |||
A and 1.4 on Sheet 4. The constant to be utilized depended on the type of battery. 1. 0 referred to a lead acid battery; 1.4 referred to a nickel-cadmium | |||
battery. The licensee reviewed the EA and determined | |||
that the correct constant was utilized in the EA and that the reference | |||
to 1. 4 was an editorial | |||
error. The licensee issued CR C-PAL-97-1656 | |||
to address the battery temperature | |||
correction | |||
factor and stated that the other discrepancies | |||
would be corrected | |||
in future revisions | |||
to the calculations. | |||
The team identified | |||
this item as part of Inspection | |||
Fo//owup Item 50-255197-201-26. | |||
29 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the calculation | |||
deficiencies | |||
identified | |||
had no affect on the analyses conclusions; | |||
ie, supplied voltages remain within equipment | |||
ratings and the station batteries | |||
are not affected. | |||
By January 15, 1999, EA-ELEC-VOLT-26, EA-ELEC-MISC-022 | |||
and EA-ELEC-LDTAB-029 | |||
will be revised to resolve the deficiencies | |||
noted above. 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-26) | |||
was identified | |||
a:s closed. Analyses EA-ELEC-VOLT-26, EA-ELEC-MISC-022 | |||
and EA-ELEC-LDTAB-029 | |||
will be revised by January 15, 1999 as projected | |||
above. Inspection | |||
Followup Item 50-255/97-201-27 | |||
The team noted that TS Section 4. 7.1.b required testing to be performed | |||
at every. refueling | |||
to demonstrate | |||
the overall automatic | |||
operation | |||
of the emergency | |||
power system. Proper operation | |||
was verified by bus load shedding and automatic | |||
starting of selected motors and equipment | |||
to establish | |||
that emergency | |||
power had been restored within 30 seconds. FSAR Tables 8-6 and 8-:-7 stated that sequencing | |||
would occur in 65 seconds. Technical | |||
Surveillance | |||
Procedure | |||
RT-BC, "Engineered | |||
Safeguards | |||
System -Left Channel," Revision 8, and RT-8D, "Engineered | |||
Safeguards | |||
System -Right Channel," Revision 8, required performance | |||
testing to be within the 65-second | |||
requirement. | |||
The team questioned | |||
the use of a 30-second | |||
test duration in the TS instead of a 65-second | |||
duration, which would demonstrate | |||
that all required equipment | |||
would start. The licensee stated that the TS did not specifically | |||
require full testing of the entire diesel load sequence but only required testing of selected loads. The team noted that the licensee was testing the diesel loading to the full accident loading sequence and has submitted | |||
a proposed TS change which would be more consistent | |||
with the current design. The team reviewed Test Procedures | |||
R0-128-1, "Diesel Generator | |||
1-1 24 Hour Load Run," Revision 2, and R0-128-2, "Diesel GeneratOr | |||
1-2 24 Hour Load Run," Revision 2. The team noted that Section 3. O of the Acceptance | |||
Criteria and Operability | |||
Sheet for Procedure | |||
R0-128-2 referred to TS Section 3. 7. 1 and 4. 7. 1. 11, and that these references | |||
would only be correct when the proposed improved TS, which have been submitted | |||
to NRG for approval, became effective. | |||
The licensee issued CR C-PAL-97-1566 | |||
to resolve these discrepancies. | |||
The team identified | |||
this item as Inspection | |||
Followup Item 50-255197-201-27. | |||
Palisades | |||
60 Day Response: | |||
Several issues identified | |||
in the Design Inspection | |||
are associated | |||
with interpretation | |||
of existing Technical | |||
Specifications. | |||
On December 27, 1995 we submitted | |||
an electrical | |||
technical | |||
specifications | |||
change* request which served to resolve the discrepancy | |||
noted above pertaining | |||
to the Emergency | |||
Diesel Generator (EOG) load sequence test. On January 26, 1998, we submitted | |||
a request for improved technical | |||
specifications | |||
which specifies | |||
testing the EOG to the load 30 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS intervals | |||
programmed | |||
by the sequencer; | |||
eliminating | |||
any specific reference | |||
to the sequence time. It is expected that the amendment | |||
resulting | |||
from the most recent .technical | |||
specification | |||
change request will serve to resolve this and other technical | |||
specification | |||
related open items. 1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item | |||
(50-255/97201-27) | |||
was identified | |||
as closed. In July 1998, Amendment | |||
180 of the Palisades | |||
Electrical | |||
Technical | |||
Specifications | |||
was implemented. | |||
Amendment | |||
180 specifies | |||
testing the EOG to the load intervals | |||
programmed | |||
by the sequencer; | |||
eliminating | |||
specific reference | |||
to the sequence time. No further actions are planned for this item. Inspection | |||
Followup Item 50-255197-201-28 | |||
The team identified | |||
the following | |||
discrepancies | |||
when reviewing | |||
station battery Test Procedures | |||
RE-83A, "Service/Modified | |||
Performance | |||
Test-Battery | |||
No. ED-01," Revision 9, and RE-83B, "Service/Modified | |||
Performance | |||
Test-Battery | |||
No. ED-02," Revision 9: * The tests evaluated | |||
whether the final discharge | |||
voltage (105 V de) of station batteries | |||
ED-01and02 was met at the end of the test (4 hours). Load parameters (amps) at 1 and 239 minutes were not verified during the test. These load parameters | |||
were design requirements | |||
of EA-ELEC-LDTAB-009, Revision 2. The licensee demonstrated | |||
that the 1-and 239-minute data were recorded elsewhere | |||
and that the duty cycle was* tested in accordance | |||
with the design requirements. | |||
The licensee stated that the battery testing procedures | |||
would be revised to include verification | |||
of these design parameters. | |||
* The procedures | |||
did not require any calibration | |||
tolerances | |||
for the discharge | |||
testing shunt and control unit. The licensee stated that the tolerance | |||
was removed from the procedure | |||
before testing during the 1996 refueling | |||
outage and issued PCRs 5422 and 5423 to change the | |||
procedures | |||
to include these tolerances. | |||
* The battery charging data in Procedure | |||
RE-83B for the 1996 refueling | |||
outage did not meet Step 5. 2. 2, which required the battery charging rate to be decreasing | |||
and to remain within 5 percent over the last 8 hours before stopping the equalization | |||
process, in that the process was stopped before the end of the 8-hour period. The licensee stated that the nearly steady state voltage operation | |||
of the charger gave adequate assurance | |||
that the battery was operable before exiting the test and issued CR C-PAL-97-1460 | |||
to resolve this discrepancy. | |||
* During the performance | |||
of procedure | |||
RE-83B at the 1996 refueling | |||
outage, the elapsed time recorded manually did not agree with the testing control unit time. The licensee stated that because the testing unit did not have the capability | |||
to record the time, the test start and stop times were recorded manually. | |||
The inconsistencies | |||
were minor and had no effect on the test results. The licensee issued C-PAL-97-1460 | |||
to evaluated | |||
this discrepancy. | |||
The team identified | |||
this item as Inspection | |||
Followup Item 50-255197-201-28. | |||
31 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
Note: Inspection | |||
Followup Item 50-255/97-201-28, Unresolved | |||
Item 97-201-30 | |||
bullets 7, 8, 9, 10, 11 and 12, and Unresolved | |||
Item 97-201-31 | |||
bullets 6 and 13 are completed | |||
under this action due to their subject similarity. | |||
Surveillance | |||
tests RE-83A and RE-838 will be revised as appropriate | |||
to eliminate | |||
the identified | |||
deficiencies | |||
to support 1998 refueling | |||
outage performance. | |||
By December 15, 1998, we will review DC system requirements, FSAR Chapter 8 and surveillance | |||
tests RE-83A and RE-838 for consistency, and resolve the deficiencies | |||
identified | |||
in this open item and the following: | |||
* Reconcile | |||
FSAR section 8.2.3 concerning | |||
the battery supplying | |||
safe shutdown loads for 4 hours with the requirement | |||
to strip loads. (Inspection | |||
report item #30-7.) * * Disposition | |||
battery shunt and de tie breakers which are not consistent | |||
with FSAR section 8.3.5.2. (Inspection | |||
report item #30-8.) * Reconcile | |||
one battery charger capability | |||
to supply normal loads and recharge battery in less than 9 hours with FSAR section 8.3.5.3. (Inspection | |||
report item #30-9.) * Reconcile | |||
alternate | |||
alignment | |||
of battery chargers with FSAR section 8.4 .. 2.2. (Inspection | |||
report item #30-10.) * Reconcile | |||
battery chargers cross connection | |||
with FSAR section 8.5.2. (Inspection | |||
report item #30-11.) * Reconcile | |||
design of system 1, 2, 3, 4 circuits and their separation requirements | |||
with FSAR section 8.5.3.2. (Inspection | |||
report item #30-12.) * Add battery discharge | |||
restriction | |||
to the D8D. (Inspection | |||
report item #31-6.) * Disposition | |||
battery cell specific gravities. (Inspection | |||
report item #31-13.) 10/1/98 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION'', this item (50-255/97201-28) | |||
was identified | |||
as open. Surveillance | |||
tests RE-83A and RE-838 were revised and satisfactorily | |||
performed | |||
during the 1998 refueling | |||
outage. The June 30, 1998 FSAR revision resolved inspection | |||
report items #30-8, #30-9, and #30-12. The above remaining | |||
items are scheduled | |||
to be complete by December 15, 1998 .. Inspection | |||
Followup Item 50-255/97-201-29 | |||
The team reviewed the following | |||
electrical | |||
modification | |||
packages and found them consistent | |||
with the plant design basis: 32 | |||
* * * * * * * * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Temporary | |||
Modification | |||
TM-96-027, "lnsta/1152-Spare | |||
#5 Breaker in 152-113 Cubicle," dated April 10, 1996 FES-95-206, "ED-01 and ED-02 Station Battery Replacement," Revision O FC-364, "Feeder Change for Instrument | |||
Bus Y-01," Revision O FC-854, "Y-01 Power Supply Feed Modification," Revision 0 FC-638, ''Add Component | |||
Cooling Water Pumps to the Normal Shutdown Sequencer," Revision 0 FC-798, "Battery Room Temperature | |||
Indication | |||
and Alarm," Revision O FC-683, "Removal of Pressurizer | |||
Heaters from SIS Trip," Revision O Except as previously | |||
discussed, all these modifications | |||
were adequately | |||
prepared, provided the necessary | |||
technical | |||
basis for the changes, and contained | |||
adequate installation | |||
instructions | |||
and testing requirements. | |||
The 10 CFR 50. 59 safety evaluations | |||
were adequate, except for the two listed below: = Safety Reviews 95-1431and95-1432, dated July 7, 1995, for FES-95-206 | |||
stated that the battery duty cycle service test duration for station .batteries | |||
ED-01 and ED-02 was changed from 2 hours to 4 hours. The licensee noted that TS Section 4. 7.2.c was affected by this design change. However, the USQ evaluation, Question 2 of Section II, was not checked "Yes" for a TS change. TS 4. 7.2.c required that a 2-hour battery test be performed; | |||
while design analysis ELEC-LDTAB-009 | |||
and FSAR Section 8.4.2 required a 4-hour battery duty cycle. The licensee has submitted | |||
a proposed TS change to reflect the proper battery test duration and issued CR C-PAL-97-1551 | |||
to address this discrepancy. | |||
* The safety review documentation | |||
for TM-96-027 | |||
stated that the FSAR was not reviewed. | |||
Administrative | |||
Procedure | |||
3. 07, "Safety Evaluations," page 12, required that the FSAR be reviewed and that thos*e sections reviewed be noted on the safety review sheet. The licensee initiated .C-PAL-97-1493 | |||
to evaluate this discrepancy. | |||
The team identified | |||
these safety review discrepancies | |||
as Inspection | |||
Fol/owup Item 50-255197- | |||
201-29. Palisades | |||
60 Day Response: | |||
It was not documented | |||
in the safety evaluation | |||
for FES-95-206 | |||
that a technical | |||
specification | |||
change would be required to change the battery duty cycle service test duration from 2 to 4 hours. An FES-95-206-specific | |||
technical | |||
specifications | |||
change was not considered | |||
necessary | |||
by the preparer of the safety evaluation | |||
since a technical | |||
specifications | |||
change request eliminating | |||
reference | |||
to a specific duty cycle time was to be submitted | |||
under the Improved Technical | |||
Specifications | |||
Program in the near term. Since completion | |||
of the FES-95-206 | |||
safety evaluation, Palisades | |||
has implemented | |||
a Safety & Design Review Group which reviews and approves all design changes and safety evaluations. | |||
The purpose for forming and employing | |||
this group is to provide consistent | |||
oversight | |||
The quality of safety evaluations | |||
and their reviews has significantly | |||
improved over the recent years. It is unlikely that a safety evaluation | |||
deficiency, similar to that associated | |||
with FES-95-206, would have occurred | |||
since deployment | |||
of the Safety & Design Review Group. 33 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS The original safety review for TM-96-027 | |||
inappropriately | |||
indicated | |||
that FSAR sections had not been reviewed. | |||
In reality, the FSAR was reviewed during safety review preparation | |||
and the FSAR was found to contain description | |||
at a level of detail that the TM would not affect. The review of the TM-96-027 safety review was performed | |||
by telecon (an infrequent | |||
practice) | |||
with no follow-up | |||
review performed | |||
by the Safety & Design Review telecon reviewer. | |||
By April 15, 1998, design control procedures | |||
will be revised to require a follow-up | |||
review whenever a review is performed | |||
by telecon. 1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND.NOTICE | |||
OF VIOLATION", this item (50-255/97201-29) | |||
was identified | |||
as closed. Administrative | |||
Procedure | |||
AP 3.07, "SAFETY EVALUATIONS" was revised to require follow-up | |||
reviews as stated above. No further actions are planned for this inspection | |||
item. Note: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-30) | |||
was identified | |||
as open. FSAR changes identified | |||
in Unresolved | |||
Item 50-255/97201-30 | |||
are identified | |||
below. Some of these bullets are grouped and evaluated | |||
with other URl's or IFl's. For clarity, each bullet's actions will be separately | |||
addressed. | |||
Unresolved | |||
Item 50-255197-201-30 | |||
The team identified | |||
the following | |||
discrepancies | |||
in the FSAR: * Page 6. 7-4 stated that 'containment | |||
isolation | |||
valves fail closed with loss of voltage or control air except for the CCW return isolation | |||
valves. However, the CCW supply isolation | |||
valve (CV-0910) | |||
is also a fail-open | |||
valve and should have *been noted as an exception | |||
to fail-closed | |||
containment | |||
isolation | |||
valves. The licensee issued FSAR Change Request 6-142-R20-1426 | |||
to correct the FSAR. Palisades | |||
60 Day Response: | |||
The next FSAR annual update revision will incorporate | |||
this change. 1011198 Update: Annual FSAR update issued June 30, 1998, included this change. * Section 6. 7 classified | |||
the CCW penetrations | |||
as Class C-2, which was defined as penetrations | |||
with lines not missile protected. | |||
However, EA-GW0-7793-01 | |||
stated that the entire CCW system (both inside and outside containment) | |||
was missile protected. | |||
The licensee issued FSAR Change Request 6-143-R20-1427 | |||
to state that the CCW penetrations | |||
were not vulnerable | |||
to internally | |||
generated | |||
missiles . 34 | |||
* * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
The next FSAR annual update revision will incorporate | |||
this change. 10/1/98 Update: Annual FSAR update issued June 30, 1998, included this change. * Table 9-10 stated that valves 3029 and 3030, containment | |||
sump suction valves, failed closed upon loss of air and were equipped with an accumulator. | |||
The valves actually failed as is and had no accumulator. | |||
The licensee issued FSAR Change Request 9-293-R20-1431 | |||
to correct *the FSAR and CR C-PAL-97-1559 | |||
to evaluate and trend the FSAR discrepancies | |||
being identified | |||
at the plant. Palisades | |||
60 Day Response: | |||
The next FSAR annual update revision will incorporate | |||
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * Table 9-9 correctly | |||
stated that the high-pressure | |||
air piping was seismic Class I from the receivers | |||
to the valve operators. | |||
However, FSAR Table 5.2-3 stated that the entire system was seismic Class I. The licensee issued FSAR Change Request 5-155-R20-1432 | |||
to correct the FSAR 5. 2-3. Palisades | |||
60 Day Response: | |||
The next FSAR annual update revision will incorporate | |||
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * Section 8.4.2.2 stated that the station batteries | |||
would be tested to Institute | |||
of Electrical | |||
and Electronics | |||
Engineers (IEEE) 450-1975. | |||
However, battery testing procedures | |||
RE-83A, Revision 9, and RE-838, Revision 9, referred to IEEE 450-1995. | |||
FSAR Change Request 8-126-R20-1249 | |||
had been initiated, but the licensee did not intend to act on this change until approval was received from NRG of a related proposed TS change. Palisades | |||
60 Day Response: | |||
This FSAR change is on hold until the license amendment | |||
responding | |||
to our improved electrical | |||
technical | |||
speeification | |||
change request, submitted | |||
January 26, 1998, is received. | |||
This change cites IEEE 450-1995 for the battery testing . 35 | |||
* ** ATTACHMENT | |||
A * STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS 1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-30) | |||
was identified | |||
as open. In July 1998, Amendment | |||
180 of the Palisades | |||
Electrical | |||
Technical | |||
Specifications | |||
was implemented | |||
with IEEE 450-1995 as a reference. | |||
FSAR change 8-126-R21-1249 | |||
will be implemented | |||
as part of the next annual FSAR update. to reflect the use of this IEEE standard. | |||
* Table 5. 7-8 listed the seismic design value for the station batteries | |||
and racks as "later" instead of including | |||
the actual values of the batteries | |||
installed | |||
by FES-95-206. | |||
The licensee issued EAR-97-0636 | |||
to evaluate this discrepancy | |||
and revise the FSAR. Palisades | |||
60 Day Response: | |||
The table in the FSAR is designated | |||
as containing | |||
the original seismic design values for the plant. The term "later" was an original FSAR description | |||
which acknowledged | |||
that an impending | |||
upgrade to install a second redundant | |||
electrical | |||
train would be made and the applicable | |||
seismic criteria would not be available | |||
until then. Since we have chosen to keep this table for historical | |||
record, the word "later" will be removed and the table maintained | |||
as original seismic criteria. | |||
The next FSAR annual update will incorporate | |||
this change requested | |||
by FSAR Change Request 5-157-R20-1456. | |||
1011198 Update: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this portion of unresolved | |||
item 50-255/97201-30 | |||
was identified | |||
as closed. The annual FSAR update issued June 30, 1998, included this change. No further actions are planned for this inspection | |||
item. * Section 8.2.3 stated the "The de battery system is designed to supply the required shutdown loads, with a total loss of ac power, for at ieast 4 hours." This statement | |||
did not reflect the fact that load stripping | |||
was required during the 4 hours for the battery to perform its intended function during a loss of ac power. * Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
1011198 Update: The resolution | |||
of this issue is addressed | |||
in Inspection | |||
Followup Item 50-255/97201-28 | |||
due to subject similarity. | |||
This item is projected | |||
to be complete by December 15, 1998. Section 8. 3. 5. 2 stated that "Operation | |||
of all circuit breakers in the de and the preferred | |||
ac systems is manual with automatic | |||
trip for fault isolation." The battery shunt trip breakers and the de bus tie breakers do not comply with this statement. | |||
36 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: Revision 20 of FSAR Chapter 8 incorporates | |||
the exclusion | |||
of the battery isolation | |||
shunt trip breakers and tie breakers between the left and right sections of each switchgear | |||
bus that do not have an automatic | |||
trip for fault isolation. | |||
Our June 30, 1998, annual FSAR update includes this change. * Section 8. 3. 5. 3 stated that "Each of the two battery chargers provided on the. de bus is capable of supplying | |||
the normal de loads on the bus and simultaneously | |||
recharging | |||
the battery in a reasonable | |||
time. A fully discharged | |||
battery can be recharged | |||
in less than nine hours." Contrary to the statement, one battery charger could not supply the normal loads and recharge a fully discharged | |||
battery in less than 9 hours. Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: Revision 20 of FSAR Chapter 8 now states that two battery chargers are needed to recharge a fully discharged | |||
battery in less than nine hours. Our June 30, 1998, annual FSAR update includes this change. * Section 8.4.2.2 stated that "Emergencv | |||
Operation | |||
-.On loss of normal and standby ac power, the batteries | |||
will supply power to all preferred | |||
ac and de loads, until one of the (diesel generators) | |||
DGs has started and can supply power for the chargers." This statement | |||
was not correct if the battery chargers were in their alternate | |||
alignment | |||
and did not reflect load shedding during the 4-hour duration. | |||
Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: The resolution | |||
of this issue is addressed | |||
in Inspection | |||
Followup Item 50-255/97201- | |||
28 due to subject similarity. | |||
We plan to complete this item by December 15, 1998. * Section 8.5.2 stated that ''The power source for the driven equipment | |||
and the control power for that system are supplied from the sources in one channel." This statement | |||
would not be correct if the battery chargers were cross-connected . 37 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: The resolution | |||
of this issue is addressed | |||
in Inspection | |||
Followup Item 50-255/97201- | |||
28 due to subject similarity. | |||
We plan to complete this item | |||
by December 15, 1998. * * Section 8.5.3.2 referred to "System 1, 2, 3, 4 Circuits" and separation | |||
requirements | |||
for those circuits. | |||
The licensee was not able to identify these circuits. | |||
* Palisades | |||
60 Day Response: | |||
Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: Revision 20 of FSAR Chapter 8 expands the definition | |||
along with providing | |||
routing and isolation | |||
requirements | |||
for 'left', 'right' and channel '1 ', '2', '3', and '4' circuits. | |||
Our June 30, 1998, annual FSAR update includes this change. * Section 8.4.1.3 required clarification | |||
as to whether the reserve capability | |||
margin referred to the capability | |||
of the overall EDG and engine or if it referred to the capability | |||
of the EOG to handle an increase loading due to a control circuit ma/function | |||
during the loading sequence. | |||
The licensee issued C-PAL-97-1309 | |||
to resolve this discrepancy. | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design Inspection, an operability | |||
determination | |||
was made concluding | |||
that the EDGs are operable. | |||
This conclusion | |||
was reached based on the capability | |||
of the EDGs to provide the required design function | |||
in the event of a control. circuit malfunction | |||
or delayed containment | |||
high pressure signal; but not both concurrently. | |||
The design basis accident analysis does not require that these two events occur simultaneously. | |||
Due to the change being descriptive | |||
in nature, rather than licensing | |||
basis information, we have elected to use the Design Basis Documents | |||
rather than the FSAR to make the clarification. | |||
Design Basis Document Change 5.03-11-R3- | |||
0617 was initiated | |||
and the revision will be made by December 15, 1998. 10/1/98 Update: Revision 4 of DBD 5.03 incorporates | |||
the requested | |||
change which evaluated | |||
the system functional | |||
requirements | |||
of the EOG starting and carrying the largest load due to a control circuit malfunction. | |||
Revision 4 also includes discussion | |||
regarding | |||
the EOG control circuit malfunction | |||
and starting a containment | |||
spray pump during a delayed containment | |||
high pressure scenario; | |||
*concluding | |||
that the malfunction | |||
and the pump start are mutually | |||
exclusive. | |||
No further actions are planned for this item. 38 | |||
* .ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS * Section 6.1.2.3 stated that ''The RAS ... provides a permissive | |||
to manually close the valves in the pump minimum flow lines." EOP-4. 0, "Loss of Coolant Accident Recovery," Revision 9, Step 23, directed the operators | |||
to place the hand switches for these valves in the pump minimum flow lines (CV-3027 and CV-3056) to CLOSE when SIRWT level lowered to between 25 percent and 15 percent. Per EOP-4.0, Step 51, the RAS occurred when the SIRWT level reached 2 percent. The FSAR appeared to conflict with EOP-4.0. The licensee initiated | |||
FSAR Change Request 6-141-R20-1425 | |||
to update the FSAR. Palisades | |||
60 Day Response: | |||
The next FSAR annual update revision will incorporate | |||
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * The footnote for Table 14.17.1-1 | |||
implied that a containment | |||
building temperature | |||
of 90 °F was used as input to the large-break | |||
LOCA analysis because it is the limiting temperature | |||
during normal operation. | |||
The 90 °F value did not appear to be limiting. | |||
The licensee stated that the 90 °F value was the nominal containment | |||
building temperature, not the limiting temperature, and was used in the accident analysis in accordance | |||
with Seimens Power Corporation's | |||
large-break | |||
LOCA methodology | |||
guidelines. | |||
The licensee initiated | |||
FSAR Change Request 14-95-R20-1441 | |||
to update the FSAR. * Palisades | |||
60 Day Response: | |||
The next. FSAR annual update revision will incorporate | |||
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. The above discrepancies | |||
had not been corrected | |||
and the FSAR had not been updated to ensure that the material in the FSAR contained | |||
the latest material | |||
as required by 10 CFR 50. 71(e). The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-30. | |||
Palisades | |||
60 Day Response: | |||
10 CFR 50.71(e) requires that the FSAR be updated to contain the latest material developed | |||
and that it includes the effects of all changes made in the facility or procedures | |||
described | |||
in the FSAR. Although several of the identified | |||
FSAR discrepancies | |||
were clear errors, most were cases where statements | |||
in the FSAR were misleading | |||
or unclear and not cases where the FSAR was not updated per 10 CFR 50.71 (e). Our ongoing FSAR verification | |||
and validation | |||
effort should provide identification | |||
and correction | |||
of similar conditions | |||
which may exist in the FSAR. Our processes | |||
were also changed a few years ago to require a safety review (1 O CFR 50.59 screening) | |||
for 39 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS all analyses, modifications, etc which have the potential | |||
to affect the design basis of the facility. | |||
This widespread | |||
10 CFR 50.59 screening | |||
will prevent failures to update the FSAR in accordance | |||
with 10 CFR 50.71(e). | |||
In addition, a license basis self assessment | |||
performed | |||
in accordance | |||
with NEI 96-05, "Guidelines | |||
for Assessing | |||
Programs for Maintaining | |||
the Licensing | |||
Basis," found few discrepancies | |||
in the FSAR sections sampled which | |||
had not been previously | |||
identified | |||
for correction | |||
by other plant processes. | |||
Therefore, we feel that the current efforts underway will correct other errors which may exist in the FSAR and the current plant processes | |||
will ensure that the FSAR is updated properly. | |||
10/1/98 Update: The above response remains unchanged | |||
from our 60-day response. | |||
Note: Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-31) | |||
was identified | |||
as open. DBD changes identified | |||
in Unresolved | |||
Item 50-255/97-201-31 | |||
are identified | |||
below. Some of these bullets are grouped and evaluated | |||
with other UR l's or IFl's. For clarity, each bullet's actions will be separately | |||
addressed. | |||
Unresolved | |||
Item 50-255/97-201-31 | |||
The team identified | |||
the following | |||
discrepancies | |||
in the DBDs: * DBD 1.07, ''Auxiliary | |||
Building HVAC Systems," Revision 1, Table 3.2.1, incorrectly | |||
stated that the design basis temperature | |||
for Room 123, which contains the CCW pumps, was 125 °F. The correct temperature | |||
was 104 °F as stated in 080 7.01, "Electrical | |||
Equipment | |||
Qualification | |||
Program," Revision 1, Appendix A. The 125 °F temperature | |||
was a conservative | |||
assumption | |||
used to size the outside air supply fans. Table 3.2.1 also contained | |||
a typographical | |||
error in a reference | |||
number. The licensee issued 080 Change Requests 1.07-71-R1-0512 | |||
and 1.07-72-R1-0532 | |||
to correct the 080. Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Revision 2 of DBD 1.07, "Auxiliary | |||
Building HVAC Systems" incorporated | |||
the above changes. The basis for the 125 ° F CCW room temperature | |||
was clarified | |||
and references | |||
were corrected. | |||
* 080 1.07, Revision 1, Section 3.2.1.3, listed maximum room temperatures | |||
for the west ESF room from an outdated analysis. | |||
The latest analysis, EA-O-PAL-93-272F-01, "Engineering | |||
40 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Safeguards | |||
Room Heatup Following | |||
LOCA in Conjunction | |||
With a Loop," Revision 0, determined | |||
lower maximum room temperatures | |||
for various SW flows through the air coolers. The 080 also required clarification | |||
of the normal design temperature | |||
of the ESG room. The licensee issued 080 Change Request 1.07-73-R1-0543 | |||
to correct the 080. Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Revision 2 of DBD 1.07, "Auxiliary | |||
Building HVAC Systems" incorporated | |||
the above change. The basis for the 135°F Engineering | |||
Safeguards | |||
Room temperature | |||
was clarified. | |||
* 080 7. 08, "Plant Protection | |||
Against Flooding, 77 Revision 1, incorrectly | |||
stated that the EOG would be inoperable | |||
before a flood reached the EOG windings because the lube oil heaters were located below the windings at 7 inches above the floor. EA-C-PAL-95-1526-01, "Internal | |||
Flooding Evaluation | |||
for Plant Areas Outside of Containment, 77 Revision 0, stated that the minimum flood level at which the EOG could become inoperable | |||
was 10 inches due to the exciter cubicle bus bars and that the lube oil heaters were not needed for EOG * operability. | |||
The licensee issued CR C-PAL-97-1557 | |||
to initiate a 080 change and evaluate the item. Palisades | |||
60 Day Response: | |||
During the Design Inspection, an operability | |||
determination | |||
concluded | |||
that the EDGs * are operable based on other indications | |||
available | |||
to inform operations | |||
that water level in the rooms is increasing. | |||
DBD change request 7.08-40-R1-0561 | |||
was initiated | |||
to state that the limiting component | |||
is not lube oil heaters but the exciter cubicle bus bars located ten inches above the EOG room floor. The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by December 15, 1998. 10/1/98 Update: This DBD change is on target for completion | |||
by December 15, 1998 as identified | |||
above. * 080 2. 03, "Containment | |||
Spray System, 77 Revision 2, stated that the air supply to the sump outlet valves, CV-3029 and 3030, was backed by an accumulator. | |||
There were no accumulators | |||
for these valves. The licensee identified | |||
this error while evaluating | |||
an FSAR statement | |||
that these valves had an accumulator | |||
backup that was questioned | |||
by the team, and issued 080 Change Request 2.03-22-R2-0531 | |||
to correct the 080 . 41 | |||
* ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Revision 3 of DBD 2.03, "Containment | |||
Spray System" corrected | |||
the terminology | |||
from "accumulator" to "high pressure air receivers". | |||
No further action is planned. * DBD 1.01, "Component | |||
Cooling Water System," Revision 3, Section 3.3. 7, incorrectly | |||
indicated | |||
that Class 1 E and non-Class 1 E breakers were installed | |||
in the same distribution | |||
panels. The licensee initiated | |||
DBD Change Request 1.01-14-R3-0518 | |||
to correct the DBD. Section 3. 3. 7 of this DBD also stated that solenoid valves had been tested to operate at 87 V de instead of 90 V de. The licensee stated that the DBD would be corrected. | |||
Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Due to competing | |||
priorities, this DBD change has been rescheduled | |||
to be completed | |||
by December 15, 1998. * * * During the teain's review of FES-95-206, it was noted that the battery manufacturer | |||
had imposed a limit of 40 battery discharges | |||
for the 20-year life of the battery. This restriction | |||
had not been identified | |||
in any DBD. The licensee stated that the requirement | |||
would be added to DBD4.01. . Palisades | |||
60 Day Response: | |||
A Design Basis Document Request will be incorporated | |||
into the DBD by December 15, 1998. Refer to our response to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: This DBD change is on target for completion | |||
by December 15, 1998, as | |||
above. * Appendix A of DBD 7. 02, "Palisades | |||
Design Basis Document EQ Master Equipment | |||
List," Revision 2, incorrectly listed | |||
the location for L T-0383; referred to EIP 0343 instead of E/P 0346; and did not include SV-32138 in Table A-1. The licensee issued DBD Change Requests 7. 02-4-R2-0522, 7. 02-6-R2-0527, and 7.D2-4-R2-0523 | |||
to correct the DBD . 42 | |||
* * * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by December 15, 1998. 10/1/98 Update: These DBD changes are on target for completion | |||
by December 15, 1998. * DBD 2.01, "Low Pressure Safety Injection | |||
System," Revision 3, and DBD 2.02, "High Pressure Safety Injection | |||
System," Revision 3, both contained | |||
references | |||
to ANF-88-107, "Palisades | |||
Large Break LOCNECCS Analysis With Increased | |||
Radial Peaking," Revision 1. ANF-88-107 | |||
was superseded | |||
by Seimens Calculation | |||
EMF-96-172, "Palisades | |||
Large Break LOCNECCS Analysis," Revision 0. The licensee Initiated | |||
DBD Change Requests 2. 01-30-R3-0519 and 2.02-27-R3-0520 | |||
to update the DBDs. * Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request will be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Revision 4 of DBD 2.01, "Low Pressure Safety Injection | |||
System," and Revision 4 of DBD 2.02, "High Pressure Safety Injection | |||
System," incorporated | |||
reference | |||
to the most current LOCA analysis. | |||
No further action is planned for this item. DBD 2.01, "Low Pressure Safety Injection | |||
System," Revision 3, Section 3.3.1.3, stated that the SIRWT must maintain a minimum of 20,000 gallons at the time of a RAS to limit the radiological | |||
consequences | |||
of an accident. | |||
The DBD reference | |||
for this statement | |||
was TAM-95-05, "Radiological | |||
Consequences | |||
for the Palisades | |||
Maximum Hypothetical | |||
Accident & Loss of Coolant Accident," Revision 0. A review of EA-TAM-95-05 | |||
indicated | |||
that this analysis did not take credit for the 20,000 gallons at the time of RAS to limit the radiological | |||
consequences | |||
of an accident. | |||
The licensee issued DBD Change Request 2.01-31-R3-0524 | |||
to update the DBD. Palisades | |||
60 Day Response: | |||
The identified | |||
Design Basis Document Change Request wlll be incorporated | |||
into the DBD by July 1, 1998. 10/1/98 Update: Revision 4 of DBD 2.01, "Low Pressure Safety Injection | |||
System," clarifies | |||
the SIRW tank minimum volume design requirements. | |||
No further action is planned for this item . 43 | |||
* * * ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS The team also identified | |||
the following | |||
discrepancies | |||
in other documentation: | |||
* P&ID M-232, Sheet 2A, incorrectly | |||
identified | |||
L T-0383 as connected | |||
to penetration | |||
#54 instead of#56. The licensee issued Document Change Request (OCR) 97-0856lo | |||
correct the drawing. | |||
Palisades | |||
60 Day Response: | |||
P&ID M-232, Sheet 2A has been reviseo to incorporate | |||
OCR 97-0856. 10/1/98 Update: No further update necessary. | |||
* Documents | |||
E-33, Revision 46, and E-37, Revision 46, were not revised to reflect the installed | |||
condi(ion | |||
of the battery charger cabling that was rerouted by SC-89-284. | |||
The licensee issued CR C-PAL-97-1495 | |||
to resolve this discrepancy. | |||
Palisades | |||
60 Day Response: | |||
E-33, Rev 46 and E-37, Rev 46 have been revised to reflect the correct battery charger cable routing installed | |||
by SC-89-284 . 10/1/98 Update: * No further | |||
necessary. | |||
* * P&ID M-209, Sheet 3 (Revision | |||
34), incorrectly | |||
depicted valves SV-0918 and SV-09778 as normally deenergized. | |||
The licensee issued EAR 97-0652 to revise the drawing. * Palisades | |||
60 Day Response: | |||
P&ID M-209, Sheet 3, Revision 35 has been issued to depict SV-09778 as normally energized. | |||
Further evaluation | |||
of SV-0918 identified | |||
that the normally deenergized | |||
state as depicted on M-209 Sheet 3 is appropriate | |||
per FSAR Table 9-10. 10/1/98 Update: No further update necessary. | |||
* Vendor drawing E-12A, Sheet 39, Revision 0, indicated | |||
that the battery discharge | |||
characteristics | |||
were based upon battery cell specific gravities | |||
of 1.215 +/- 0.005. However, the batteries | |||
were being maintained | |||
to a criterion | |||
of 1.215 +/- 0.010. The licensee issued EAR 97-0669 to update the drawing. Palisades | |||
60 Day Response: | |||
E-12 A, Sheet 39, Rev O will be updated by December 15, 1998. Refer to our response 44 | |||
ATTACHMENT | |||
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION | |||
OPEN ITEMS to Inspector | |||
Followup Item 50-255/97-201-28. | |||
10/1/98 Update: This item is on target for completion | |||
by December 15, 1998. These documentation | |||
discrepancies | |||
were not consistent | |||
with 1 O CFR Part 50, Appendix B, Criterion | |||
Ill, "Design Control," which requires that the design basis be correctly | |||
translated | |||
into drawings. | |||
The team identified | |||
this item as Unresolved | |||
Item 50-255197-201-31. | |||
The programmatic | |||
design control aspects related to this issue will be addressed | |||
as identified | |||
in Attachment | |||
B, Item 1. 'i 45 | |||
----* * ATTACHMENT | |||
B CONSUMERS | |||
ENERGY COMPANY PALISADES | |||
PLANT DOCKET 50-255 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE 6 Pages | |||
* * ATTACHMENT | |||
8 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE Per NRC correspondence | |||
dated May 18, 1998, titled "NRC INSPECTION | |||
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", inspection | |||
item 50-255/98003-01 | |||
was identified | |||
as open. As stated in the report, this item | |||
will remain open | |||
pending NRC review of the results of the collective | |||
significance | |||
of individual | |||
inspection | |||
items and planned programmatic | |||
improvements. | |||
The following | |||
summarizes | |||
of our programmatic | |||
improvements. | |||
1. DESIGN CONTROL ISSUES: The following | |||
issues were identified | |||
in the Design Inspection | |||
report as potentially | |||
not meeting requirements | |||
of 10 CFR 50, Appendix B, Criterion | |||
Ill, "Design Control." Our design control program provides assurance | |||
that the plant as-built configuration | |||
conforms to design requirements, and the configuration | |||
is operated, tested and maintained | |||
within required design parameters. | |||
The deficiencies | |||
identified | |||
during the Design Inspection | |||
relate to these design control program objectives. | |||
Design Objective | |||
For Operating | |||
Systems Within Design Parameters: | |||
* Loss-Of-Coolant | |||
Accident analysis identified | |||
the maximum CCW temperature | |||
of 184°F yet the effects of this temperature | |||
on CCW system components | |||
was not performed. (Unresolved | |||
Item 50-255/97-201-02.) | |||
* Incomplete | |||
analysis (inadequate | |||
justification | |||
for conclusion | |||
and incorrect | |||
references | |||
to related NRC correspondence) | |||
for CCW piping for High Energy Line Break. (Unresolved | |||
Item 50-255/97-201-04.) | |||
* Some AC Load calculations | |||
have not been updated to reflect current design. (Unresolved | |||
Item 50-255/97-201-14.) | |||
Design Objective | |||
For As-Built Conditions | |||
Conforming | |||
To Design Requirements: | |||
* * * Unscreened | |||
Emergency | |||
Core Cooling System Suction piping vent. (Unresolved | |||
Item 50-255/97-201-10.) | |||
Some instrument | |||
tubing is not sloped consistent | |||
with design requirements . (Unresolved | |||
Item 50-255/97-201-13.) | |||
Design Basis Document I design documentation | |||
discrepancies. (Unresolved | |||
Item 50-255/97-201-31.) | |||
1 | |||
* ATTACHMENT | |||
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE Palisades | |||
60 Day Response: | |||
Elements comprising | |||
and supporting | |||
our.design | |||
control program consist of our calculation | |||
control program, instrument | |||
setpoint program, FSAR verification | |||
and validation (V&V), design basis documents (DBDs) with associated | |||
safety system design confirmations, and as-built confirmation | |||
through drawing review or field walkdown. | |||
These elements will be revised as appropriate | |||
by December 15, 1998 to prevent the recurrence | |||
of conditions | |||
similar to those identified | |||
in the Design Inspection | |||
and cited above. Resolution | |||
of any nonconforming | |||
conditions | |||
identified | |||
will be implemented | |||
through our corrective | |||
action program. 10/1/98 Update: Programs exist at Palisades | |||
that ensure proper station design attributes | |||
are considered, evaluated, changed and documented. | |||
These programs makeup our overall "Design Control" program. In past months, several programs have been reviewed in various inspections | |||
and routine assessments | |||
such as: * NRC INFORMATION | |||
NOTICE 98-22:"DEFICIENCIES | |||
IDENTIFIED | |||
DURING NRC DESIGN INSPECTIONS" was evaluated | |||
by comparing | |||
the adequacy of our program design controls against other station Design Inspection | |||
identified | |||
concerns. | |||
* Self assessments | |||
were performed | |||
in areas such as design document control and modification | |||
programs. | |||
* NRC inspections | |||
and internal NPAD audits in the areas of Engineering | |||
and Technical | |||
Support were performed | |||
in mid 1998 that evaluated | |||
several Palisades | |||
design and configuration | |||
program attributes. | |||
As a result of these and other efforts, "Design Control" Program enhancements | |||
have been identified | |||
and incorporated | |||
into the appropriate | |||
programs. | |||
For example, several changes have been made to design change processes | |||
to better define the applicability | |||
of each distinct process, and to ensure that design change inpuUoutput | |||
requirements | |||
are adequately | |||
addressed. | |||
2 | |||
* ATTACHMENT | |||
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE No major programmatic | |||
weaknesses | |||
were identified | |||
in these reviews and program enhancements | |||
are now complete. | |||
To conclude, the Palisades "Design Control" Program is considered | |||
effective. | |||
2. CALCULATION | |||
CONTROL ISSUES: The Design Inspection | |||
issues identified | |||
below reflect weaknesses | |||
in our calculation | |||
control program. Improvements | |||
in our calculation | |||
control program will serve to prevent recurrence | |||
of these conditions. | |||
Inspection | |||
Report Issues: * Required justification | |||
for conclusion | |||
and correct references | |||
to related NRC correspondence | |||
not provided in analysis. (Unresolved | |||
Item 50-255/97-201-04.) | |||
* Not all analyses revised whenever analytical | |||
inputs or major assumptions | |||
change. (Unresolved | |||
Item 50-255/97-201-07.) | |||
* Analyses not reflecting | |||
accurate as-built configuration | |||
and system operation, not all interdependent | |||
analyses have been revised together in response to changes, and analytical | |||
design bases do nofagreewith | |||
test acceptance | |||
criteria. (Unresolved | |||
Item 50-255/97-201-08.) | |||
Palisades | |||
60 Day Response: | |||
Prior to the Design Inspection, calculation | |||
control weaknesses | |||
were recognized | |||
and an improvement | |||
plan was implemented. | |||
Over 19,000 calculations | |||
have .been indexed to provide for improved retrievability. | |||
A cross-index | |||
between selected calculations | |||
of record and the documents | |||
that use the results of the calculations | |||
is being developed. | |||
These and other improvements | |||
to our calculation | |||
program serving to prevent recurrence | |||
of the deficiencies | |||
cited above will be made by December 15, 1998. 10/1/98 Update: The identification | |||
of calculations | |||
referenced | |||
in the major design documents | |||
has been completed. | |||
The Calculation | |||
Control Improvement | |||
Project is on target for 3 | |||
* * * ATTACHMENT | |||
8 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE completion | |||
of the detailed calculation | |||
cross-index | |||
by December 15, 1998. Development | |||
of the computerized | |||
calculation | |||
retrieval | |||
application | |||
and completion | |||
of associated | |||
engineer training will follow in early 1999. 3. SETPOINT CONTROL ISSUES: Station procedures | |||
and guidance to require the use of established | |||
uncertainty | |||
methodology | |||
need to be implemented. | |||
The plan for implementation | |||
should be validated | |||
against weaknesses | |||
identified | |||
in* Unresolved | |||
Item 50-255/97-201-12. | |||
Palisades | |||
60 Day Response: | |||
An instrument | |||
uncertainty | |||
evaluation | |||
methodology | |||
manual has been developed. | |||
Uncertainty | |||
calculations | |||
for Reactor Protection | |||
System and Engineered | |||
Safety Features Actuation | |||
System setpoints | |||
have been performed | |||
Ul?ing .the methodology | |||
manual. Incorporation | |||
of instrument | |||
uncertainty | |||
evaluation | |||
requirements | |||
in procedures, and training select engineers | |||
to perform uncertainty | |||
calculations, will be completed | |||
by December 15, 1998. 10/1/98 Update: As stated in Inspector | |||
Follow-up | |||
Item 50-255/97201-12, station procedures | |||
have been revised to consider use of established | |||
instrument | |||
uncertainty | |||
guidance when developing | |||
test acceptance | |||
criteria and determining | |||
errors for operating | |||
instrument | |||
loops. In addition, a self assessment | |||
of the Setpoint Control Process was performed | |||
with potential | |||
areas for improvement | |||
being evaluated. | |||
4. 10 CFR 50.54(F} RESPONSE: | |||
Evaluate inspection | |||
findings, both specific and programmatic, against the Palisades | |||
response to NRC's October 9, 1996 request for information | |||
pursuant to 1 O CFR 50.54(f) regarding | |||
adequacy and availability | |||
of design bases information. | |||
Palisades | |||
60 Day Response: | |||
After review of the inspection | |||
findings and comparison | |||
to our response to the 1 O CFR 50.54(f) letter regarding | |||
the adequacy and availability | |||
of design basis .4 | |||
.. * ATTACHMENT | |||
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE information, we have determined | |||
that our response to the 10 CFR 50.54 (f) letter remains complete and accurate. | |||
Improvements | |||
to our design programs, initiated | |||
through our response, will be directly responsible | |||
for resolution | |||
of issues * identified | |||
within the Design Inspection | |||
report. The programs and projects being improved include our Calculation | |||
Control Program, Setpoint Methodology | |||
and Control Program, FSAR Verification | |||
and. Validation | |||
Project, and our Fuse Control Program. * Beyond programmatic | |||
improvements, design basis knowledge | |||
will be further enhanced by the development | |||
of 1 O additional | |||
DB Os and the performance | |||
of. three safety system design confirmations | |||
similar to the NRC's safety system functional | |||
inspections. | |||
To date, four of the new DBDs have been issued and one design confirmation | |||
has been completed. | |||
No additional | |||
programmatic | |||
improvement | |||
efforts have initiated | |||
as a result of actions being taken | |||
to satisfy our 10 CFR 50.54(f) response. | |||
A final review of the adequacy of our response will be completed | |||
by December 15, 1998. 10/1/98 Update: Some of the initiatives | |||
noted in our 60-day response to the Des_ign Inspection | |||
were not part of Palisades | |||
formal response to the NRC's October 9, 1996 request for information | |||
pursuant to 10 CFR 50.54(f) regarding | |||
adequacy and availability | |||
of design bases information. | |||
Our February 6, 1997, 50.54(f) response coneluded | |||
that the Palisades' | |||
design bases information | |||
was adequate, and reasonabie | |||
assurance | |||
exists that: 1) design bases information | |||
has been translated | |||
into operating, maintenance, and testing procedures, and 2) system, structures, and component | |||
configuration | |||
and performance | |||
are consistent | |||
with the design bases. Our 50.54(f) response also referred to specific initiatives | |||
to further strengthen | |||
plant processes | |||
and design basis documentation. | |||
Specifically | |||
noted as * commitments | |||
in the 50.54(f) response were: 1) performing | |||
an FSAR Verification | |||
Project, 2) completing | |||
ten new Design Basis Documents, 3) conducting | |||
one Safety System Functional | |||
Type inspection | |||
per fuel cycle, and 4) updating and re-instituting | |||
use of a Quality Assurance | |||
Requirements | |||
Matrix database. | |||
Other initiatives | |||
to strengthen | |||
plant processes | |||
and design basis documentation | |||
were also undertaken | |||
that were not specifically | |||
included ln the 50.54(f) response 5 | |||
* ATTACHMENT | |||
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC | |||
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE such as: 1) implementing | |||
a calculation | |||
control improvement | |||
project, 2) implementing | |||
improvements | |||
in instrument | |||
setpoint uncertainty | |||
methodology, 3) performing | |||
an assessment | |||
of instrument | |||
setpoint control, and 4) performing | |||
an assessment | |||
of the fuse control program. The 50.54(f) response remains complete and accurate. | |||
The response to Attachment | |||
B Item 1 relates to and supports this position. | |||
It should be noted, however, that the 50.54(f) response and its committed | |||
programmatic | |||
initiatives, along with other initiatives | |||
noted above, will not resolve all issues identified | |||
within the Design Inspection | |||
since it is more effective | |||
to resolve certain issues on an individual, | |||
basis. A formal review that evaluates | |||
the Design Inspection | |||
findings against the 50.54(f) response is on target for completion | |||
by December 15, 1998. 6 | |||
}} |
Revision as of 19:21, 17 June 2019
ML18066A314 | |
Person / Time | |
---|---|
Site: | Palisades |
Issue date: | 10/01/1998 |
From: | Haskell N CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.) |
To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
References | |
50-255-97-201, NUDOCS 9810070265 | |
Download: ML18066A314 (55) | |
See also: IR 05000255/1997201
Text
A CMS Energy Company October 1, 1998 U.S. Nuclear Regulatory
Commission
Attn: Document Control Desk Washington
D.C. 20555 Palisades
Nuclear Plant 27780 Blue Star Memorial Highway Covert. Ml 49043 DOCKET 50-255 -LICENSE DPR-20 -PALISADES
PLANT * Tel. 616 764 2276 Fax.* 616 764 2490 Nathan L. Ha.ks/I Director.
Licensing
OCTOBER 1, 1998 UPDATE TO DESIGN INSPECTION
ACTION ITEMS During the period from September
16 through November 14, 1997, the NRC conducted
a design inspection
at the Palisades
Nuclear Plant. By letter dated December 30, 1997, the NRC issued Inspection
Report No. 50-255/97-201, and requested
a response within 60 days detailing
our plans to complete the corrective
actions required to resolve the open items listed in Attachment
A of the inspection
report. Contained
within our March 2, 1998 response was a single commitment
to provide the NRC a status of our progress in completing
actions associated
with each open inspection
item. The purpose of this commitment, in part, was to assist the NRC in planning for follow-up
review and closeout of these items. Attachment
A of this letter contains the text of each open inspection
item from the December 30, 1997 inspection
report, followed by our 60 day response as submitted
in our March 2, 1998 letter, followed by the status of associated
action as of October 1, 1998. This status includes the results of our investigations
and corrective
actions, along with planned completion
dates for ongoing actions. Attachment
B contains similar information
for programmatic
issues related to inspection
findings.
_J Based on completion
dates for the remaining
open items, we recommend
that NRC consider scheduling
efforts early in 1999 to review inspection
items for closure. A review of completion
dates for open items indicates
that a majority of actions will be completed
by the end of 1998. 9810070265
981001 PDR ADOCK 05000255 G PDR
-. . .:.; * * -.. -Sl:JMMAR¥-'-8F
COMMITMENTS
This letter closes the March 2, 1998 commitment
as .restated
below, and contains no new commitments. "By October 1, 1998, Consumers
Energy will provide NRC with a status of our progress in completing
all actions identified
in the attachments
to this letter.
- Nathan L. Haskell . Director, Licensing
CC Administrator, Region Ill, USNRC Project Manager, NRR, USNRC NRC Resident Inspector
-Palisades
Attachments
2
ATTACHMENT
A CONSUMERS
ENERGY COMPANY PALISADES
PLANT DOCKET 50-255 STATUS OF PLANS FOR CORRECTIVE
ACTIONS TO RESOLVE NRC DESIGN INSPECTION
OPEN ITEMS 45 Pages
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Unresolved
Item 50-255/97-201-01
The team questioned
whether the CCW system design met the vendor-recommended
minimum flow of 2000 gpm for the CCW pumps under all operating
conditions.
The team was concerned
that small differences
in the pump operating
characteristics
could cause significant
differences
in flow through each pump during parallel pump operation
due to the flatness of the pump operating
- curves at low flows. The licensee had no analysis available
to demonstrate
that the CCW pumps met the minimum flow requirements.
During the inspection, the licensee developed
a preliminary
system flow model, which showed that, when all three pumps were started upon receiving
a safety injection
system (SIS) signal, the minimum pump flow was through CCW pump P-52A at 1768 gpm. The licensee received a revised minimum flow requirement
of 1600 gpm from the pump manufacturer.
The team's review of the licensee's
completed
flow model calculation
will be an Inspection
Fol/owup Item 50-255197-201-01.
- Palisades
60 Day Response:
As a result of CCW system balancing, scheduled
for the 1998 refueling
outage, a reanalysis
of minimum predicted
CCW system flow rates will be performed.
This reanalysis
will verify that minimum flow rate requirements
will be met under a worst case scenario with appropriate
pump IST degradation
input. This action will be completed
by September
1, 1998. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-01)
was identified
as open. Pump performance
data was obtained during the 98 refueling
outage. The completion
for the reanalysis
has been rescheduled
for August 1, 1999 to accommodate
emerging higher priority analytical
work. Unresolved
Item 50-255/97-201-02
The team verified the heat removal capability
of the CCW heat exchangers
by reviewing
the results of various accident analyses.
The licensee had performed
the following
LOCA analyses:
- EA-D-PAL-93-207-01, "LOCA Containment
Response Analysis With Reduced LPSI Flow Using CONTEMPT El-28 Code," Revision 0, * EA-D-PAL-93-272-03, "LOCA Containment
Response Analysis With Degraded Heat Removal System Using CONTEMPT El-28A Computer Code," Revision 0, *and * EA-GEJ-96-01, "A-PAL-94-324
Containment
Spray System (CSS) Sensitivity
on the Containment
Heat Removal During Recirculation (Post-RAS)," Revision 1. The team verified that the input assumptions
relating to the CCW system for the above analyses were correct. The above LOCA analyses demonstrated
that the heat exchangers
could remove sufficient
heat from containment
following
a LOCA to keep the containment
pressure and 1
- ----------------------
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS temperature
within the design limits. In each case, the analysis documented
a CCW temperature
exiting the shutdown coolers exceeding
the system design temperature
of 140 degrees Fahrenheit
(140 °F) as stated in FSAR table 9-6 and DBD 1.01, "Component
Cooling Water," Revision 3. The team noted that the licensee accepted the maximum CCW temperature
that resulted from the scenarios
analyzed in EA-D-PAL-207-01
and EA-D-PAL-93-272-03
by Corrective
Action D-PAL-93-272G, based primarily
on an evaluation
of the effects on pipe stress. However, the licensee had not considered
the other negative effects, such as any detrimental
effects from elevated CCW temperature
on pump seals. Also, the licensee had not determined
the maximum possible CCW temperature
under worst case conditions
and had not identified
that a change to the FSAR could be required.
The team reviewed the latest LOCA analysis, EA-GEJ-96-01, and determined
that it documented
a CCW temperature
exiting the shutdown cooling heat exchanger
was 184 °F. The licensee determined
the system was operable under this condition
and issued Condition
Report (CR) C-PAL-97-1363F
to determine
the most limiting CCWtemperature
for any condition
and to evaluate all the effects resulting
from that limiting temperature
on the CCW system. ' It appeared that the requirements
of 10 CFR 50, Appendix B, Criterion
111, "Design Control," were not met in this case in that the design basis for the CCW system, as defined in 10 CFR 50.2, did not encompass
the entire range of bounding temperatures.
The team identified
this item as Unresolved
Item 50-255197-201-02.
Palisades
60 Day Response:
Prior to the Design lnspection;.we
determined
that the CCW system is operable at a predicted
maximum system temperature
of 184°F. The CCW system will be analyzed to confirm the most limiting temperature
for any design basis condition, and to determine
the effects of this temperature
on system components
by October 1; 1998. The FSAR will be updated as appropriate.
The programmatic
design control aspects related to this issue will be addressed
as identified
in Attachment
B, Item 1. 10/1/98 Update: In June of 1998, Engineering
Analysis EA-LOCA-98-01
was performed
to determine
the limiting condition
CCW temperature.
The results show a maximum 180°F CCW temperature
out of the CCW heat exchanger.
The effects of this temperature
on system components
was then evaluated.
It was determined
that the CCW heat exchanger
outlet temperature
indication
range was too narrow and needed to be expanded to meet RG 1.91 requirements.
By December 15, 1998, these temperature
indicators
will be replaced and full compliance
with RG 1.97 requirements
will be achieved.
All other evaluated
CCW system component
peak temperature
ratings fall within the predicted
180°F temperature.
The FSAR was changed to clarify CCW system design temperature
and LOCA maximum temperatures.
The temperature
indicator
range issue (50-255/97201-02)
was identified
as open, and was the subject of a NOTICE OF DEVIATION
(50-255/98003-02), in NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION." Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." 2
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Refer to Attachment
B, Item 1 for the programmatic "design control" aspects associated
with this issue. Unresolved
Item 50-255/97-201-03
The team reviewed C-PAL-96-1-63-01, "120 day response to GL 96-06, Assurance
of Equipment
Operability
and Containment
Integrity
during Design Basis Accident Condition," Revision 0, which was the licensee's
response to Nuclear Regulatory
Commission (NRG) Generic Letter 96-06, "Assurance
of Containment
Operability
and Containment
Integrity
During Design-Basis
Accident Conditions," and observed that the licensee took credit for relief valve RV-0939 to protect the CCW piping inside containment
from overpressurization
in the event of a LOCA. RV-0939 was not included in the /ST program. The team questioned
whether RV-0939 performed
a safety function and if it should have been included in the /ST program. The licensee issued CR C-PAL-97-1686
to evaluate this
discrepancy.
10 CFR 50.55a requires /ST in accordance
with ASME Section XI of valves that perform a safety function.
It appeared that the licensee did not fully implement
these requirements
for RV-0939. The team identified
this item as part of Unresolved
Item 50-255197-201-03.
Palisades
60 Day Response:
During the Design Inspection, it was determined
that sufficient
overpressure
protection
is provided for the CCW system without taking credit for relief valve RV-0939, and the CCW system is therefore
The CCW piping in containment
is not required during an accident and is classified
non-Q, safety related. As a result, the ISl/IST programs have classified
the CCW piping and related components, including
RV-0939, as non-class
and excluded the same from inspection/test
requirements
of the Code. The Palisades
response to GL 96-06 determined
acceptability
of systems by generally
taking credit for 1) steam/gas
service, 2) available
expansion
paths, or 3) relief valves as a means to provide *sufficient
protection
against thermally
induced over pressurization.
In the case of the CCW system, "available
relief valves" serves as the basis for acceptability.
Relief valve operation
is considered
important
but not a safety related function, and therefore, the classification
of the CCW system and its components
such as RV-0939 were not changed. Although RV-0939 is not in the IST program, it, along with RV-2108 and RV-0956, is inspected, maintained
and set point verified via
maintenance
activity PPAC CCS043 on a 10-year interval.
These are essentially
the same as the requirements
of the Code (ASME/ANSI
OM-1987, Part 1 ). Based on this evaluation, no further action is required.
RV-0939 is appropriately
classified, maintained
and tested. Our existing GL 96-06 submittal
is accurate.
3
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS 10/1/98 Update: This response has not changed since the submittal
of our original 60-day inspection
report response.
Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-03)
was identified
as closed. No further actions on this item are planned. Unresolved
Item 50-255/97-201-04
FSAR Section 9.3.2.3 stated that the CCW pipingwithin
containment
was not vulnerable
to failure caused by a high energy line break (HELB) and referred to Deviation
Report (DR) D-PAL-89-061, "Post Accident Operation
of CCW System, 11 dated March 23, 1989, for the evaluation.
This DR referred to Engineering
Analysis (EA) EA GW0-7793-01, "CCW Piping Inside Containment
HELBA," Revision 0. This EA was reviewed by the team, and it concluded
that the CCW piping inside containment
was not affected by HELBs, but did not contain the analysis performed
or a reference
to the analysis.
The EA contained
an outline of the methodology, listed the drawings and walkdowns
used, and referenced
the source of the postulated
HELBs. Palisades
Administrative
Procedure
No. 9.11, "Engineering
Analysis, 11 Revision 9, stated that an EA shall present an argument which substantiates
the conclusion
of the EA. The EA also contained
an error in the identification
of the Systematic
Evaluation
Program (SEP) topic number for evaluation
of the effects of internally
generated
missiles.
The licensee initiated
Engineering
Assistance
Request (EAR) EAR-97-0632
to revise EA-GW0-7793-01.
During the inspection, the licensee issued Revision 1 of EA-GW0-7793-01, which included a discussion
of the walkdown analysis used and corrected
the SEP references.
This revised EA was acceptable
to the team. It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion . Ill, "Design Control," regarding
verifying
the adequacy of designs were not adhered to in this case. Also, the requirements
of the licensee's
Administrative
Procedure
9. 11 were not fully met in that EA-GW0-7793-01, Revision 0, did not contain full substantiation
of the conclusion.
The team identified
this item as Unresolved
Item 50-255197-201-04.
Palisades
60 Day Response:
As a remedial action, EA-GW0-7793-01
was revised to provide justification
for its conclusion
and to correct references
to related NRC corresponqence.
The related programmatic
design control and calculation
control aspects will be addressed
as identified
in Attachment
B, Items 1 and 2. 10/1/98 Update: This response has not changed since the submittal
of our original 60-day inspection
report response.
Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-04)
was identified
as closed. No further actions are planned for this item . Refer to Attachment
B, Item 1 for the programmatic "design control" aspects associated
with this issu.e. 4
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Unresolved
Item 50-255/97-201-05
The team reviewed the implementation
of the licensee's
commitment
to NRG Regulatory
Guide (RG) 1.97, "Instrumentation
for Light-Water-Cooled
Nuclear Power Plants To Assess Plant and Environs Conditions
During and Following
an Accident," Revision 3, as described
in FSAR Appendix 7C. The RG stated a range for CCW flow instrumentation
of 0-110 percent. Since
there was no instrument
to directly measure CCW flow, the licensee used a combination
of instruments, including
TE-0912 and TE-0913, which measure shutdown cooling heat exchanger
outlet temperature, to indicate flow. Use of instruments (other than flow indicators)
to monitor for CCW flow was determined
as acceptable
by the NRG (a letter from NRG to Consumers
Power Company, dated July 19, 1988, entitled "Palisades
Plant-Response to Generic Letter 82-33 Conformance
to Regulatory
Guide 1.97 "Instrumentation
for Light-Water-Cooled
Nuclear Power Plants To Assess Plant and Environs Conditions
During and Following
an Accident).
The required range for these TEs in FSAR Appendix 7C was 0-180 °F. This range did not encompass
the temperature
determined
in EA-GEJ-96-01, "A-PAL-94-324
Containment
Spray System (CSS) Sensitivity
on Containment
Heat Removal During Recirculation (Post-RAS)," Revision 1. This analysis determined
an outlet temperature
of the CCW from the shutdown cooling heat exchanger
of 184 °F. The licensee issued CR C-PAL-97-1363E
to evaluate the process instrumentation
and controls associated
with the CCW system for the effects of the higher temperature
predicted
by the analysis.
The licensee did not appear to meet their commitment
to NRG RG 1.97, "Instrumentation
for Light-Water-Cooled
Nuclear Power Plants To Assess Plant and Environs Conditions
During and Following
an Accident," in that the installed
CCW temperature
indicators
were not capable of monitoring
the full temperature
range expected to be observed in the CCW system. The team identified
this item as part of Unresolved
Item 50-255197-201-05.
Palisades
60 Day Response:
Prior to the Design Inspection, we determined
that the COW system is operable at a predicted
maximum system temperature
of 184°F. The CCW system will be analyzed to confirm the most limiting temperature
for any design basis condition, and the effects of this temperature
on system components.
In response to this specific issue, process instrumentation
and controls associated
with the CCW system will be reviewed to identify the impact of the maximum predicted
temperature.
This action will be completed
by October 1, 1998. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-05)
was identified
as closed. This item was also the subject of a NOTICE OF DEVIATION
(50-255/98003-02)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." In summary, the range of the CCW heat exchanger
outlet temperature
indicators
will be changed to meet RG 1.97 requirements
by December 15, 1998. 5
- ** * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Unresolved
Item 50-255/97-201-06
The team identified
a lack of closure verification
testing on SI system check valves that could potentially
result in an overpressure
condition
affecting
the low-pressure
piping on the suction of the HPSI pumps. The minimum flow recirculation
lines associated
with the two HPSI pumps and the two LPSI 'pumps were interconnected
upstream of the air-operated
minimum flow recirculation
isolation
valves. In the event that only one HPSI pump was operating
under post-accident
conditions
with the minimum flow recirculation
isolation
valves closed, back leakage through the minimum flow piping associated
with the idle HPS/ pump could over pressurize
the idle HPS/pump suction piping. Backflow between the HPS/ minimum flow lines should be prevented
by check valves CK-ES3339
or CK-ES3331, and CK-ES3340
or CK-ES3332.
However, EGAD-EP-01, "lnservice
Testing Program-Valve
Test Program," Revision 10 indicated
that closure verification
testing of these check valves was not included in the /ST program. *The team asked the licensee if closure of these check valves was considered
a safety function requiring
/ST. The licensee initiated
CR C-PAL-97-1660
to evaluate the testing requirements
of these check valves. On November 10, 1997, the operability
determination
concluded
that these system check valves had not been subject to closure verification
testing as required, and both HPSI pumps were declared inoperable.
In accordance
with TS Section 3.0.3, 3.3, and 4.0.3, the licensee entered a Limiting Condition
for Operation (LCO) action statement, performed
closure verification
testing of check valves CK-ES3339
and CK-ES3340, and verified the operability
of these valves. The licensee stated that closure verification
testing of these check valves would be added to the /ST program. The team also identified
a lack of closure verification
testing on SI system valves that could potentially
result in a Safety Injection
Tank (SIT) being degraded under post-accident
conditions.
The normally closed SIT vent valves, CV-3051, 3063, 3065, and 3067, could be opened in accordance
with SOP-3, "Safety Injection
and Shutdown Cooling System," Revision 28, to reduce SIT pressure.
SOP-3 did not require the affected SIT to be declared inoperable
when a vent was opened. When a vent valve was opened the SIT pressure boundary (250 psig design pressure)
was exposed to the SIT vent header piping (100 psig design pressure).
SOP-3 did not include d(rections
to isolate an open vent valve in the event of an accident.
EGAD-EP-01, lnservice
Testing Program -Valve Test Program," Revision 10, indicated
that closure verification
testing of these valves was not included in the /ST program. The team asked the licensee if the failure of a valve to close could result in a SIT being degraded under accident conditions, and if closure of these valves was considered
a safety function requiring
/ST testing. The licensee initiated
CR C-PAL-97-1592
to evaluate this item and placed caution tags on the control room switches for vent valves CV-3051, 3063, 3065, and 3067 to prevent the valves from being opened without entering an LCO for the SITs. The licensee also stated that these valves had been opened rarely during plant operation.
1 O CFR 50. 55a requires in-service
inspection
in accordance
with Section XI of the ASME Boiler and Pressure Vessel Code. This code requires testing of valves which perform a safety function.
It appeared that the licensee did not implement
these requirements
with regard to valves CK-ES3339, CK-ES3340, CV-3051, CV-3063, CV-3065, and CV-3067. The team identified
this item as part of Unresolved
Item 50-=255197-201-06.
6
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
During the Design Inspection, high pressure safety injection
pump minimum flow recirculation
line check valves CK-ES3339
and CK-ES3340
were tested and the HPSI system was declared operable.
Action to include check valves CK-ES3339
and CK-ES3340
in the IST Program will be completed
by July 15, 1998. lri the interim, the check valves are tested to meet quarterly
testing requirements.
During the Design Inspection, the Safety Injection
Tank (SIT) vent valves CV-3051, CV-3063, CV-3065 and CV-3067 were closed and cautioned
tagged with the tanks declared operable.
Action to revise operating
procedures
to address opening the SIT vent valves will be completed
prior to removal of the caution tags. Prior to March 15, 1998, a representative
sample of check valves, AOVs and MOVs will be reviewed and verified to be incorporated
in the IST program as required.
10/1/98 Update: Check valves CK-ES3339
and CK-ES3340
have been included in the IST Program. Operating
procedures
have been revised to address opening of the SIT vent valves CV-3051, CV-3063, CV-3065 and CV-3067 and caution tags have been removed. A representative
sample of check valves, AOVs and MOVs have been sampled to determine
if they are included in the IST Program as required.
The sampling identified
additional
AOVs and one check valve that required inclusion
into the IST Program. These valves have been incorporated
into the IST Program and have been tested to confirm their safety related function.
In addition, several other actions associated
with the IST Program are underway to enhance databases, review ISi Program bases for IST Program impact, and revise IST Program and bases to enhance purpose, scope and program descriptions.
These actions are projected
to be complete by . May 1, 1999. Presently, Palisades
is in full c_ompliance
with the ISi and IST program requirements.
Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-06)
was identified
as closed. .This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-03)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REP.ORT 50-255/98003." Unresolved
Item 50-255/97-201-07
The team reviewed the HVAC system serving the cable spreading
room. The team observed that DR F-CG-91-072
was prepared in May 1991 when it was discovered
that the assumptions
in calculation
EA-FC-573-2, "Calculated
Required Air Flow for Inverter/Charger
Cabinet Cooling Fan," dated October 3, 1982, used an ambient temperature
of 94 °F instead of the correct design basis temperature
of 104 °F. The Safety System Design Confirmation (SSDC) Team that found this discrepancy
recommended
that the EA be updated. Procedure*9.11, "Engineering
Analysis," Revision 9, required all EAs to be revised if analytical
inputs or major assumptions
change. The 7
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS licensee aec1dedtiotl6
reVisetfie
EA-; and ffie alscrepaiicy
was recorded in DBD 4.02 (125-V de system) and DBD 4.03 (preferred
ac system). The fans were installed
in 1983 and were not safety related. DR F-CG-91-072
was closed in October 1994, when the decision was made not to revise the calculation.
The licensee stated that specifications
were being developed
for replacing
the inverters
and chargers during the time the discrepancy
was being evaluated
and that this knowledge
contributed
to the decision not to update the EA. The inverters
and chargers were scheduled
to be replaced in the near future by Specification
Change (SC) SC-96-033.
The new equipment
would have internal cooling fans designed for a 104 °F maximum ambient and SC-96-033
would supersede
EA-FC-573-2
upon installation.
The team had no other concerns about the cable spreading
room HVAC system. It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion/I, "Quality Assurance
Program," were not followed in this case in that the requirements
of Procedure
9. 11 regarding
revising EAs were not fully implemented.
The team identified
this item as part of Unresolved
Item 50-255197-201-07.
Palisades
60 Day Response:
Prior to the Design Inspection, Design Basis Documents
were revised to address this discrepancy.
Analysis EA-FC-573-2
will be revised or superseded
by December 1, 1998. The calculation
control aspects related to this issue (in this case, the revision of all analyses whenever analytical
inputs or major assumptions
change) will be addressed
by the action described
in Attachment
B, Item 2. 10/1/98 Update: The schedule for resolving
remains as stated above. Per NRG correspondence
dated May 18, 1998, titled "NRG INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-07)
was identified
as closed. This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-04)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." Unresolved
Item 50-255/97-201-08
The team identified
the following
discrepancies
in SJ system mechanical
calculations:
- EA-DBD-2.01-004, "Electrical
and Mechanical
Failure Analysis for the Low Pressure Safety Injection
System," Revision 0, pages 10 and 25, identified
a situation
in which a Joss of an emergency
diesel generator (EOG) during a large-break
LOCA would result in only one LPSI pump and two LPS/ injection
valves being operable.
The EA stated: "The acceptability
of this situation
could not be verified." The team asked if this statement
was correct. The licensee replied that the statement
was not current, and that the statement
appeared to be based on superseded
calculation
ANF-88-107, "Palisades
Large Break LOCA/ECCS
Analysis With Increased
Radial Peaking," Revision 1. Calculation
ANF-88-107
was superseded
by Seimens calculation
EMF-96-172, "Palisades
Large Break LOCA/ECCS
Analysis," Revision 0. The licensee initiated
Engineering
Assistance
Request (EAR) 97-0635 to revise EA-DBD-2.01-004.
8
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS * EA-A-NL-92-185-01, "Worst Case Operating
Conditions
for the LPSllSDC System MOVs," Revision 1, addressed
the most limiting conditions
under which the system motor-operated
valves (MOVs) were required to open and close. This analysis included MOVs M0-3015 and M0-3016. These valves were the isolation
valves installed
in the shutdown cooling inlet . piping from primary coolant system (PCS) loop 2. For all normal operations
-other than shutdown cooling being in service, -the valves were electrically
locked closed. Page 19 of EA-A-NL-92-185-01
stated that the scenario that could produce the most limiting differential
pressure was that these valves would be required to close in the event of a downstream
pipe break. The EA addressed
a potential
12-in. downstream
pipe break and determined
that complete depressurization
and blowdown of the PCS to the hot-leg elevation
would occur before operators
could enter the EOPs and attempt to isolate the break. Therefore, the analysis then established
a maximum flow rate of 4120 gpm through valves M0-3015 and M0-3016, based on a normal system flow rate of 3000 gpm and a calculated
leakage of 1120 gpm through a break of a 1-112-inch
branch line downstream
of the valves. The team asked the licensee to provide the basis of the postulated
1-112-inch
branch line failure, since it did not appear to be consistent
with the postulated
pipe crack used in the internal flooding analysis of the safeguards
areas (EA-C-PAL-95-1526-01, "Internal
Flooding Evaluation
for Plant Areas Outside of Containment," Revision 0). The licensee verified that the flooding analysis break flow was different
and that this difference
would not affect the conclusions
of EA-A-NL-92-185-01.
Assumptions
5.9 and 5.10 of EA-A-NL-92-185-01
stated that the HPS/ and LPSI injection
flows to the loops were approximately
equal under post-accident
conditions.
These assumptions
did not appear consistent
with the flow values calculated
in EA-SDW-95-001, "Generation
of Minimum and Maximum HPSllLPSI
System Performance
Curves Using Pipe-Flo," Revision 2. The team asked the licensee to provide the bases of these values. The licensee stated that the values were not current and verified that the difference
between these values and the current values would not affect the EA results. The licensee initiated
CR C-PAL-97-1670
to resolve the discrepancies
in EA-A-NL-92-185-01.
- EA-E-PAL-93-004E-01, "/ST Check Valve Minimum Flow Rate Requirements
to Support Chapter 14 Events," Revision 0, identified
1601 gpm as the required test flow for the LPS/ injection
check valves. The team observed that this value appeared to be less limiting than the values calculated
in EA-SDW-95-001, "Generation
of Minimum and Maximum HPS/ILPSI
System Performance
Curves Using Pipe-Flo," Revision 2. The licensee initiated
CR C-PAL-97-1603
to address this discrepancy.
The licensee determined
that the LPSI test flow presented
in EA-E-PAL-93-004E-01
was less than the current calculated
requirement.
However, the actual LPSI check valve flow acceptance
criterion
in /ST Procedure
Q0-88, "ESS Check Valve Operability
Test (Cold Shutdown)," Revision 17, was verified to be 1690 gpm, which was greater than the current calculated
requirement.
The licensee stated that the affected documentation
will be corrected.
Administrative
Procedure
9. 11, "Engineering
Analysis," Revision 9, Section 6. 1. 5. c stated that an analysis shall be revised if analytical
inputs changed. In the above instances, engineering
analyses were not updated to reflect analytical
input change. The licensee initiated
C-PAL-97-1636
to evaluate the overall issue of calculation
control. The team identified
this item as part of Unresolved
Item 50-255197-201-08.
9
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
During the Design Inspection, it was determined
that the LPSI check valves are operable since IST acceptance
criteria and actual test flow rates exceeded the minimum required flow rates in analysis EMF-96-72
which had superseded
EA-E-PAL-93-004E-01.
By June 1, 1998, engineering
guideline
EGAD-EP-09
and IST procedure
Q0-8B basis document will be revised to assure that the increased
minimum design flow requirement
is met, and that design bases agree with IST acceptance
criteria.
Remedial actions to revise EA-DBD-2.01-004
to accurately
reflect electrical
system response to events will be completed
by August 15, 1998. EA-A-NL-92-185-01
and EA-SDW-95-001
are bounding analyses which will not be required to be revised or superseded.
Specifically, * the calculation
control process will be revised to allow bounding analyses to remain unchanged
when revisions
to inputs or assumptions
do not affect the analysis conclusions.
The calculation
control aspects related to this issue will be addressed
by the action described
in Attachment
B, Item 2. 10/1/98 Update: Engineering
guideline
EGAD-EP-09, IST procedure
Q0-8B Basis Document, and engineering
analysis EA-DBD-2.01-004
were revised as stated above. Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-08)
was identified
as closed. This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-04)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." Unresolved
Item 50-255/97-201-09
During an SI system walkdown on October 6, 1997, the team observed scaffolding
installed
adjacent to the SIRWT on the roof of the auxiliary
building.
The team questioned
how the installation
of scaffolding
in the vicinity of safety-related
equipment
was controlled
to prevent damage to the safety-related
equipment
during a seismic event. The licensee provided Procedure
MSM-M-43, "Scaffolding," Revision 2, for the team's review. Section 5. 3 of this procedure
required an engineering
review of scaffolding
installed
in the vicinity of safety related equipment.
However, the licensee determined
that the scaffolding
observed during the walkdown had not received engineering
review in accordance
with the procedure.
The licensee initiated
CR C-PAL-97-1417
to address the scaffolding
installation, and the scaffolding
was removed on October 8, 1997. EA-C-PAL-97-1417A-01, "Operability
Reassessment
of SIRWT Scaffolding," Revision 0, was completed
during the inspection.
Based on a structural
analysis of the maximum loading on the SIRWT due to seismic interaction
with the scaffolding
during a safe shutdown earthquake, this analysis concluded
that the SIRWT was not inoperable
due to this nonconforming
condition.
10
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS During another SI system walkdown on October 30, 1997, the team observed additional
installed
in the east ESG room adjacent to safety-related
piping. An evaluation
by the licensee determined
that this scaffolding
had not been installed
in accordance
with Procedure
MSM-M-43, "Scaffolding," Revision 2. The licensee initiated
CR C-PAL-97-1585
to address this scaffolding
installation
and, based on a visual inspection, concluded
that this nonconforming
would not render any safety-related
piping or components
The licensee removed the scaffolding.
In addition, the licensee performed
a walkdown of all plant scaffolding
during the inspection
and verified that there were no additional
nonconforming
conditions.
The licensee stated that all scaffolding
erections
would cease until appropriate
personnel
underwent
remedial training.
The team observed the following
three separate conditions
in the west ESG room involving
potential
seismic interactions
with safety-related
equipment.
The team noted that, during a seismic event, unrestrained
items could potentially
damage safety-related
piping and equipment.
The safety-related
piping and equipment
in the west ESG room were required for operation
of the HPSI, LPSI, and containment
spray systems in the event of an accident.
- The team observed an unsecured
operations
storage cabinet located adjacent to safety-related
piping and valves. The team asked the licensee if the condition
was in accordance
with plant procedures.
The licensee initiated
CR C-PAL-97-1587, which determined
that the cabinet was not placed in accordance
with the spacing requirements
of Administrative
Procedure
1.01, "Material
Condition
Standards
and Housekeeping
Responsibilities," Revision 11. The operability
evaluation
concluded
that the nonconforming
condition
did not result in any safety-related
equipment
being inoperable.
The cabinet was laid on its side to eliminate
the toppling concern. The licensee stated that the cabinet would be removed from the area. * The team observed an* unsecured
chainfall
located adjacent to and above the shutdown cooling heat exchangers.
A similar chainfall
in the east ESG room was secured. The team asked the licensee if the condition
was in accordance
with plant procedures.
The licensee determined
that the chainfall
location was not in accordance
with Administrative
Procedure
1.01, and initiated
CR C-PAL 97-1586. The operability
evaluation
concluded
that the nonconforming
condition
did not result in any safety-related
equipment
being inoperable.
The licensee stated that the chainfall
chains would be moved away from the heat exchanger.
- The team observed a ladder in the west ESG room that appeared to be improperly
stored. The ladder was lying on the floor under the installed
ladder rack. The team asked the licensee if the condition
was in accordance
with plant procedures.
The licensee initiated
CR C-PAL-97-1601
and determined
that the ladder location was not in accordance
with the "Palisades
Ladder Control Policy for Operating
Spaces," dated May 14, 1997. The CR concluded
that, although the ladder storage did not meet the ladder control policy, the nonconforming
condition
did not result in any safety-related
equipment
being inoperable.
The licensee stated that the ladder was removed from the area. Procedure
MSM-M-43 required an engineering
review of scaffolding
installed
in the vicinity of safety-related
equipment.
Procedure
1. 01 and the "Palisades
Ladder Control Policy for Operating
Spaces," dated May 14, 1997, contain requirements
for storing items in the vicinity of safety-related
equipment.
In these cases, the licensee did not comply with the procedural
requirements
for activities
affecting
quality as required by 1 O CFR Part 50, Appendix B, Criterion
V, "Instructions, 11
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Procedures, and Drawings." The team identified
this item as Unresolved
Item 50-255197-201-09.
Palisades
60 Day Response:
Remedial actions consisted
of dispositioning
all scaffolding
and unrestrained
items near the SIRW Tank and in the East and West Safeguards
Rooms to assure operability
of safety-related
equipment.*
Subsequently, walkdowns
were conducted
in other areas containing
safety-related
equipment
and no conditions
similar to the scaffolding
conditions
identified
in this open item were observed.
Maintenance
and construction
crews were briefed on the lessons learned pertaining
to scaffolding
erection.
By July 15, 1998, we will revise procedures, provide training and reinforce
management
expectations
as necessary
to maintain compliance
with seismic interaction
requirements
for related equipment.
10/1/98 Update: Specific actions to revise procedures, provide training and reinforce
management
expectations
as necessary
to maintain compliance
with seismic interaction
requirements
for safety-related
equipment
have been completed.
Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003
- (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-09)
was identified
as closed. This item was also the subject of NOTICES OF VIOLATION
(50-255/98003-05
and 50-255/98003-06)
from the same letter. Palisades
responded
with additional
information
to the NRG under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." This response is associated
with plans to enhance maintenance
personnel
training, and provide training for Auxiliary
Operators
to recognize
unrestrained
items for prompt identification.
Training will be completed
by March 1, 1999. Unresolved
Item 50-255/97-201-10
During the surrogate
tour, the team obseNed the ends of two vent pipes that connected
the containment
sump to the 590-ft elevation
of the containment.
The team asked the licensee to explain the design of these vent lines. During a review of the vent lines, the licensee determined
that the top of the vents were located inside the containment
at an elevation
of approximately
595-ft. The maximum calculated
post-accident
water elevation
was at elevation
597-ft. The vent pipes did not have screens on their inlets. The licensee also determined
that the two vent lines entered the containment
sump inside the sump screens, creating a potential
path for debris to enter the EGGS pump suction piping under post-accident
conditions.
The licensee initiated
CR C-PAL-97-1571, on October 29, 1997, to evaluate this condition
and determined
that the postulated
type and quantity of debris that could enter the vent pipes under post-accident
conditions
would not prevent the SI and containment
spray systems from performing
their safety function, and that these systems were operable under this condition.
The licensee also installed
Temporary
Modification
TM-97-046, on October 29, 1997, to add screens to the top of the vent pipes during the inspection.
These screens would prevent debris from entering the EGGS pump suctions in the event of an accident.
12
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion
Ill, "Design Control," were not met in this instance in that the design basis of the containment
sump to exclude debris from the EGGS pump suction piping was not fully implemented.
The team identified
this item as part of Unresolved
Item 50-255197-201-10.
Palisades
60 Day Response:
As stated above, an operability
determination
concluded
the Engineered
Safeguards
Systems were operable in the as-found condition.
As additional
assurance
for continued
operability, temporary
screens were placed over the vent pipes. These screens will be permanently
installed
in the 1998 refueling
outage. The programmatic
design control aspects related to this issue will be addressed
as identified
in Attachment
B, Item 1. 10/1/98 Update: Containment
sump vent screens were permanently
installed
during the 1998 refueling
outage. Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-10)
was identified
as closed. This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-0?a)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND.NOTICE
OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." As part of our annual design basis document update projected
for June 1999, the Containment
Spray Design Basis Document DBD-2.03 will be revised to address issues vital to the function of the Engineering
Safety Features following
a LOCA. Refer to Attachment
B, Item 1 for the programmatic "design control" aspects associated
with this issue. Inspection
Followup Item 50-255/97-201-11
The team also observed several piping penetrations
between the east and west ESG rooms which included rubber piping expansion
joints used as penetration
seals. The team questioned
the design of these piping penetration
seals. The licensee stated that the engineering
analyses that demonstrated
that these penetrations
met the design basis did not-specifically
address the use of rubber piping expansion
joints in the penetration
seals. The team reviewed EA-RJC-92-0508, * Analysis
of the Effect of a Fire on the Fire Barrier Penetration
Seal Number FZ-0508," Revision 0, and verified that the rubber piping expansion
joints were not addressed.
The licensee initiated
CR C-PAL-97-1627
and determined
that the failure to specifically
justify the presence of rubber expansion
joints did not invalidate
the conclusions
of the original engineering
analyses and that the penetration
seals were adequate.
The licensee also stated that the affected documentation
would be corrected, and that an "extent of condition" review would be performed.
The team identified
this item as Inspection
Fo/lowup Item 50-255197-201-11.
13
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
An operability
determination
during the Design Inspection
concluded
that the safety function provided by the fire barriers separating
the East and West Safeguards
Rooms is not affected by the use of rubber expansion
pipe joints. By August 1, 1998, we will revise the design basis engineering
analysis to formally justify the installed
rubber expansion
pipe joints, and perform an investigation
of other area fire barriers for potential
unanalyzed
designs. 1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-11)
was identified
as closed. The revision to the design basis engineering
analysis for rubber expansion
pipe joints is complete along with investigations
for other fire barriers for potential
unanalyzed
designs. No other unanalyzed
fire barrier design issues were discovered.
No further actions are planned for this inspection
item. Inspection
Followup Item 50-255197-201-12
The team reviewed 10 SI system calculations
and 1 pressurizer
pressure uncertainty
calculation;
these were identified
as "basis documents." Basis Document Rl-38, "SIRW Tank Level Instrument
Calibration," Revision 6, was reviewed for adequacy.
It provided the basis for calibration
of SIRWT level indicators
LT-0332A *and LT-0332B to enable their use to monitor the TS requirement
that the tank contain at least 250, 000 gallons of borated water. Rl-38 used a tank boron concentration
of 1720 parts per million (ppm) and did not consider the range of 1720 to 2500 ppm allowed by TS Section 3.3. Rl-38 was the basis document for the calibration
of the level indicator
that supported
manual actuation
of post-accident
recirculation
operation.
The team was concerned
that the increased
density of the tank water at higher boron concentrations
would increase the instrument
uncertainty.
The calculation
also did not account for variation
in boron concentration
density caused by temperature
changes; an effect which could also affect the total uncertainty.
The licensee recalculated
the total instrument
uncertainty
using the most conservative
boron concentrations
and temperature, and the *resulting
change to the total uncertainty
remained bounded by the original uncertainty
value. Bases Document Rl-69, "Subcooled
Margin Monitor Surveillance," Revision 6, was reviewed for adequacy.
The subcooled
margin monitor (SMM) provided the operator indication
of the PCS margin to .saturation
conditions.
Rl-69 evaluated
possible errors induced in the SMM. The team found that Rl-69 did not account for seismic uncertainty.
This was inconsistent
with RG 1.97 "Instrumentation
for Light-Water-Cooled
Nuclear Power Plants To Assess Plant and Environs Conditions
During and Following
an Accident," May 1983. This RG identifies
subcooled
margin as a Category/, Type A variable, which must continue to read within the required accuracy following, but not necessarily
during, a safe-shutdown
event. The team was concerned
that the calculated
error was nonconservative
because it did not consider seismic uncertainty, and could provide misleading
information
to the operators.
The licensee reanalyzed
the potential
error in the SMM, including
seismic uncertainty, and the resulting
total uncertainty
remained bounded by the original uncertainty
value. The licensee assigned Procedure
Change Request (PCR) 5569 to revise Rl-69. 14
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS EA-RSW-94-001, "F/-0404 Instrumentation
Uncertainty
Calculation," Revision 2, was also reviewed for adequacy.
The analysis established
the recommended
uncertainties
of Fl-0404, which was used in flow testing of the SJ pumps. The instrument
was installed
in 1989, and has been calibrated
five times since then. Drift error was determined
using historical
calibration
data. For the first 4 years, the instrument
was calibrated
once a year. The team found that 24 months had transpired
between the fourth and fifth calibrations.
The licensee stated that the interval was
in 1993 from 11 months to 24 months. The team asked if the drift analysis was revised to account for this change in the calibration
interval.
The* team was concerned
that increasing
the calibration
interval to 24 months would increase the drift error and consequently
increase the total uncertainty
of the instrument.
The licensee reanalyzed
the Fl-0404 uncertainty
using appropriate
drift performance
data for the longer calibration
interval, and the resulting
change to the total uncertainty
remained bounded by the original uncertainty
value. The licensee issued EAR-97-0658
to revise EA-RSW-94-001.
The team also reviewed Basis Document Rl-15A, "Safety Injection
Tank Pressure Channel Calibration," Revision 7, for adequacy.
Rl-15A formed the bases for the pressure channel setpoints
for PIA-0363, 0367, 0369, and 0371, which defined low-and high-pressure
alarms for the S/Ts. The /ow-pressure
alarms warned the operators
of decreasing
nitrogen pressure in the tanks. The channel alarms were set to annunciate
earlier than the pressure limits of TS Section 3.3. 1 (b) so appropriate
action could be taken before pressure reached the setpoints
of pressure switches PS-03408, 03448, 03738, and 30508, which were set to alarm at the TS limits. The team was concerned
that Rl-15A did not consider uncertainties
such as stability
and temperature
effects and that the current total uncertainty
was not adequate.
Considering
the low alarm point of 207 psig, the calculated
uncertainty
allowance
of +/-6.85 psig could result in an alarm at close to 200 psig, which was the TS limit. If additional
uncertainties
were added, the channel pressure switches could alarm after the TS pressure switches.
The licensee reanalyzed
the setpoint for P/A-0363, 0367, 0369, and 0371 using additional
appropriate
uncertainty
inputs and determined
that the resulting
instrument
uncertainty
was bounded by Rl-15A. The team observed that the results of these basis documents
were determined
to encompass
specific additional
uncertainties
due to the assumed margins used in the documents
to account for unquantified
effects. The licensee had a guide entitled "Design & Maintenance
Guide on Instrument
Setpoint Methodology," EGAD-PROJ-16, Revision 0, and the team concluded
that it provided a satisfactory
methodology
for setpoint calculations
and was consistent
with industry standard S67-04, Part I, "Setpoints
for Nuclear Safety-Related
Instrumentation." The licensee stated that EGAD-PROJ-16
provided identical
guidance as EGAD-PROJ-08, Revision 0, of the same title, which was the current designation
of the guide. The instruments
that were re-analyzed
during the inspection
used the guidance of EGAD-PROJ-08.
This methodology
affirmed that margins remained bounded. The licensee stated that use of this guide was not required by plant procedures.
However, the licensee has previously
recognized
from past assessments
that its basis documents
were not as rigorous as required by the current /SA standards.
The licensee stated that EGAD-PROJ-08
was being revised and that the appropriate
procedures
would be revised to require its use. The team identified
this item as Inspection
Fol/owup Item 50-255197-201-12.
Palisades
60 Day Response:
None of the above calculational deficiencies
identified
during the Design Inspection
affected the operability
of any safety-related
equipment.
During the inspection, EGAD-ELEC-08
Rev 1 was approved and issued to provide
for instrument
setpoint methodology.
Our engineering
staff 15
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS has been briefed as to the need to utilize this guidance.
Plant procedures
will be revised by August 15, 1998, to incorporate
EGAD-ELEC-08
for use when setpoint calculations
are required.
10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-12)
was identified
as closed. Applicable
plant administrative
procedures
have been changed to reference
guidance document EGAD-ELEC-08
for use when performing
setpoint calculations, and enhanced to more clearly . describe the applicability
of EGAD-ELEC-08.
No further actions are planned
for this inspection
item. Unresolved
Item 50-255/97-201-13
During a walkdown of the SI system, the team observed that transmitters
for containment
spray flow, FT-0301 and FT-0302, and shutdown cooling heat exchanger
flow, FT-0306, were properly mounted below their flow elements, but the process tubing was observed to be inadequately
sloped back to the transmitters.
Additionally, a walkdown performed
by the licensee at the team's request during an * in-containment
inspection
revealed that the process lines to the HPSI cold-leg flow transmitters
FT-0308, FT-0310, FT-0312, and FT-0313, and the LPSI flow transmitters, FT-0307, FT-0309, FT-0311, and FT-0314, were also installed
with inadequate
slope. The team was concerned
that inadequate
slope in instrument
tubing could contribute
to significant
instrument
uncertainty
by entraining
unequal amounts of air in either leg of the transmitter, causing erroneous
readings.
This was shown to be a valid concern when an operator observed an erroneous
reading in the left channel containment
spray loop indicator, Fl-0301A.
The "below zero" reading was caused by air trapped in one of the process iines. The licensee issued CR C-PAL-97-1561
to vent the line. The lack of tubing slope was inconsistent
with original plant installation
specification
J-F020, Revision 0. This specification
stated: "Flow instruments (differential
tyP.e) in liquid and condensable
vapor service shall preferably
be mounted below the main line connection
so that the impulse lines will slope down to the instrument." The specification
also stated: "Impulse lines to flow instruments
shall slope (up or down) a minimum of one inch per foot." Plant drawings J-F133, Revision 1; * J-F134, Revision O; J-F140, Revision O; and J-F141, Revision 0, depict various acceptable
installation
configurations
for a differential
transmitter.
The current installations
of the flow instruments
identified
above were not consistent
with these drawings.
A later specification, J-465 (Q), "The Technical
Specification
for Installation
of Instrumentation
For Nuclear Service for CPCo Palisades," Revision 0, dated 1981 stated: "The installation
shall be neat in appearance, properly supported, and shall provide for proper slope for adequate drainage or venting of the instrument
lines." This specification
has since been incorporated
into specification
20557-J-59 (Q) under the same title, which requires that a "horizontal
tubing run is continually
sloped in accordance
with design drawings." The licensee issued CR C-PAL-97-1561
to evaluate these instrument
tubing sloping discrepancies.
According
to the operability
determination
of the CR, the instruments
have never shown any adverse effects of trapped air during the last 20 years of operation.
The HPSI and LPSI flow transmitters
were mounted as much as 8 ft above their flow elements.
To accommodate
instruments
mounted above flow elements, specification
J-F020 stated: "5 foot minimum "drop legs (equivalent
of a loop seal)" may be required before the tubing is sloped up the I 16
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS meter." Plant drawings J-F152, Revision 1, and J-F153, Revision 0, depict these mounting configurations.
The licensee stated that the bottom and side tap locations
for the tubing would tend to limit the amount of air getting into the transmitters
and that air entrainment
would be minimal due to the ratio of the volume of the HPSI and LPSI pump suction piping to the tubing volume. EA-C-PAL-95-0877D, "Evaluation
of the Potential
for Excessive
Air Entrainment
Caused by Vortexing
SIRWT During a LOCA," Revision 0, evaluated
the potential
for excessive
air entrainment
in the lines of the pumps caused by vortexing
in the SIRWT during a LOCA, and determined
that the air f]ntrainment
would be a small percentage
of the flow volume. The licensee also stated that technicians
are required to vent the transmitters
during every 18 month surveillance.
However, the team was concerned
that, since the transmitters
sense low static pressure during normal standby operation, air may accumulate
between calibration
intervals
and between system tests. Additionally, the water circulated
through the SI lines from the containment
sump could contain significant
amounts of dissolved
gasses, which could enter the tubing up to the flow transmitters.
The team was concerned
that the effect of air entrapped
in the instrument
tubing could cause large and unquantifiable
errors in the flow indications.
EOP Supplement
4, "Loss of Coolant Accident Recovery Safety Function Status Check Sheet," contained
curves presenting
total SI flow ranges intended to help ensure that the minimum values utilized in the accident analyses (LOCA, MSLB, Steam Generator
Tube Rupture (SGTR)) were met. There was also a minimum total flow criterion
for the operators
to meet, which ensured the containment
sump check valves remained in a stable condition
in EOP-4. 0, "Loss of Coolant Accident Recovery," Revision 9. The operators
would use the HPSI and LPSI flow indication
from FT-0308, 0310, 0312, 0313, 0307, 0309, 0311, and 0314 to compare SI system performance
against the EOP requirements.
The team was concerned
that the potentially
large errors could confuse the operator and impair decision making. The licensee stated that the opetators
are trained to use all available
indications
and that alternate/additional
instrumentation
could be used to confirm trending of PCS conditions
such as that for pressurizer
level, subcooling
margin, reactor vessel level, and charging pump flows. The licensee issued EAR-97-0699
to evaluate this item. It appeared that the design basis for instrument
tubing installation
was not implemented
in the plant installation
as required by 10 CFR Part 50, Appendix B, Criterion
Ill, "Design Control." The team identified
this item as Unresolved
Item 50-255197-0201-13.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
the HPSI and LPSI flow indication
is operable based on plant operating
experience.
Since the inspection, a plant walkdown was conducted
which revealed that the HPSI and LPSI tubing configuration
met design requirements
but did not conform to associated
design drawings.
The existing tubing configurations
- were observed, and the tubing was determined
not to be susceptible
to air entrainment.
The * conclusions
reached from this walkdown review further justify the reliability
of the HPSI and LPSI flow indication, although configuration
discrepancies
exist. By August 15, 1998, we will resolve the HPSl/LPSI
flow indication
tubing discrepancies
and compare our design requirements
to additional
samples of safety related instrument
tubing to identify any additional
nonconformances
with design criteria.
The programmatic
design control aspects related to this issue will be addressed
as identified
in Attachment
8, Item 1. 17
- * * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-13)
was identified
as closed. This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-07b)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." Subsequent
to the Design Inspection, Palisades
walked down these installations
during the 98 refueling
outage and confirmed
that the sensing lines for HPSI and LPSI flow transmitters
FT-0308, 0310, 0312, 0313, 0307, 0309, 0311 , and 0314 are appropriately
sloped -thus no deviations
from design requirements
exist. A sampling of other sensing lines associated
with safety-related
equipment
were also walked down and confirmed
to meet design requirements
for sensing line slope. NRC correspondence
dated August 3, 1998 rescinded
this cited potential
violation.
No further actions are planned for this inspection
item. Unresolved
Item 50-255/97-201-14
The team reviewed EA-ELEC-LDTAB-005, "Emergency
Diesel Generator
1-1 & 1-2 Steady State Loading," Revision 4, and verified that the analysis was consistent
with the design basis information
in the FSAR. All required accident loads for a LOCA and a LOOP were identified
and tabulated.
The electrical
loads exceeded the continuous
rating of the EOG during the first 32 minutes of operation
but were below the EOG maximum 2-hour rating. One of the inputs to this analysis was the electrical
toad estimate for LPSI pumps P-67 A and P-678. These electrical
load estimates
were based on the minimum hydraulic
LPS/ pump performance
used in EA-A-PAL-92-037, "Emergency
Diesel Generator
Loadings-First
Two.Hours," Revision 1, which determined
that LPSI pump flow would be* 3600 gpm. Although the LPS/ pump flow was conservative
for evaluating
LOCA mitigation, it was not conservative
for determining
the maximum load the EOG could experience
during a LOCA. The team determined
that the LPS/ pumps could pump 4500 gpm with one LPS/ pump discharging
into all four injection
loops as identified
in EA-SDW-95-001, "Generation
of Minimum and Maximum HPSllLPSI
System Performance
Curves Using Pipe-Flo," Revision
2. The team was concerned
that the licensee had not analyzed for the worst-case
electrical
load demand on the EDGs. Preliminary
evaluations
by the_ licensee using the correct maximum loads indicated
that the electrical
loading on one EOG could be higher than that determined
in EA-ELEC-LDTAB-005.
The licensee issued CR C-. PAL-97-1650
to review and correct all necessary
electrical
analyses and determined
The team reviewed EA-ELEC-VOL
T-13, "Palisades
Loss of Coolant Accident With Off$ite Power Available," Revision 0, which evaluated
the ac voltage available
during normal operating, refueling, and accident conditions.
The team noted that the calculation
had not been revised since 1993 and . that the load magnitudes
identified
in EA-ELEC-LDTAB-005, Revision 4, and EA-SDW-95-001, Revision 2, had not been included.
The licensee reviewed the impact of the revised loads on EA-ELEC-VOL
T-13 and determined
that the changes had minimal effect on the analysis.
The team also noted that FSAR Section 8.3 stated that backfeeding
via the main and station power transformers
could be utilized;
however, EA-ELEC-VOL
T-13 had not analyzed this particular
operating
mode. The licensee stated that it had recognized
that an analysis for backfeeding
needed to be performed
in 1994 and had issued AIR A-PAL-94-223
to create an analysis in order to bound 18
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS this condition
of operation.
The licensee initiated
C-PAL-97-1619
to review and update EA-ELEC-VOLT-13
for load changes. It appeared that the requirements
of10 CFR Part 50, Appendix B, Criterion
Ill, "Design Control," had not been met for EA-ELEC-LDTAB-005
an*d EA-ELEC-VOLT-13
in that the design basis had not been updated to document the actual plant parameters.
The team identified
this item as part of Unresolved
Item 50-255197-201-14.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made which concluded, based on an evaluation
which bounded recent load changes, that the electrical
system is operable.
Mechanical
flow model analyses, which serve as input to the electrical
load flow analyses, will be completed
by December 15, 1998. The electrical
load flow analyses, which will assure plant loads are accounted
for and applicable
operating
scenarios
are addressed, will be completed
by August 15, 1999. A specific backfeed analysis will be completed
by Januar}t 15, 1999. The programmatic
design control aspects related to this issue will be addressed
as identified
in Attachment
8, Item 1. 1011/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", th.is item (50-255/97201-14)
was identified
as closed. The mechanical
and subsequent
electrical
flow model analyses are on target for completion
by December 15, 1998 and August 15, 1999, respectively, as stated above. Backfeed analysis EA-ELEC-FL
T-009, "GSU Short Circuit Analysis" was completed
with design attributes
captured in the applicable
Design Basis Document.
Refer to Attachment
8, Item 1 for the programmatic "design control" aspects associated
with this issue. * Inspection
Followup Item 50-255/97-201-15
FSAR Section 8.5.2 stated that cables would be sized in accordance
with the National Electric Code (NEC) or Insulated
Power Cable Engineers
Association
(/PCEAllCEA)
ampacity values and the cable ampacities
would be adjusted on the basis of actual field conditions
when possible.
The adjustments
included conductor
operating
temperature, ambient temperature, cable overall diameter, raceway fill, and fire stops. The licensee had recently initiated
a program to verify the adequacy of its cable ampacity sizing. EA-ELEC-AMP-032, "Ampacity
Evaluation
for Open Air Cable Trays With a Percent Fill Greater Than 30% of the Usable Cross Sectional
Area," Revision 1, was issued in 1997 to address cable sizing. While reviewing
the EA, the team noted the absence of fire stop derating and increased
cable temperatures
due to thermal radiation
from hot pipes. The licensee had initiated
AIR A-PAL-97-062
to evaluate the effects of local heat sources on fire stops; however, evaluation
of the effects on cable degradation
due to the close proximity
of hot piping systems had not been included.
The licensee stated that evaluation
of the effects of hot piping would be included under A-PAL-97-062.
The team identified
this item as Inspection
Followup Item 50-255197-201-15 . 19
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
We will complete our Cable Ampacity Sizing Program by September
15, 1998 which will identify any cable degradation
due to the close proximity
of hot piping, and any degradation
of fire stops due to local heat sources. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-15)
was identified
as open. Cable * degradation
due to the close proximity
of hot piping, and any degradation
of fire stops due to local heat sources has been evaluated.
Results confirm that the cable design is acceptable.
No further actions are planned for this inspection
item. Unresolved
Item 50-255/97-201-16
The 120-V ac safety-related
and non-safety-related
loads were powered from instrument
ac bus Y-01. Bus Y-01 was powered from either motor control center (MCC) 1or2 via automatic
transfer switch Y-50. MCCs 1 and 2 were redundant
safety-related
busses. The licensee stated in a January 24, 1978, letter to the NRG that it would. implement
the recommendation
of RG 1. 6 in that no . provision
would exist for automatically
transferring
loads between redundant
power sources. The NRG issued a safety evaluation
report, dated April 7, 1978, confirming
the licensee's
commitment.
FC-364, "Feeder Change for Instrument
Bus Y-01," Revision 0, implemented
this commitment
and powered bus Y-01 from MCC 1 and non-safety-related
MCC 3. However, FC-854, "Y-01 Power Supply Feed Modification," Re.vision
0, moved the backup power source from MCC 3 to the safety-related
MCC 2, and resulted in a departure
from the plant's licensing
basis. The modification
installed
fuses in series with the existing breakers, which provided an additional
level of protection
for the two safety-related
busses. The team observed that the safety evaluation
performed
for FC-854 did not identify that prior NRC approval was required.
The licensee issued CR C-PAL-97-1678
to document this deviation
from the licensing
basis. It appeared that this modification
was a USO in that the possibility
of a common-mode
failure of the redundant
safety-related
busses was created, which was not previously
evaluated
in the FSAR and, thus, the criterion
was satisfied.
The team identified
this item as Unresolved
Item 50-255197-201-16.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was completed
which concluded
that the implemented
design meets the intent of RG 1.6 and provides a single failure proof method of preventir:ig
the transfer of a fault between redundant
load sources. The current configuration
was implemented
under FC-854 with the modification
safety evaluation
concluding
that an unreviewed
safety question does not exist. Prior NRC approval of the change was not required.
A description
of the implemented
modification
was transmitted
to the NRC in our Annual Report of Facility Changes, Tests and Experiments
dated April 2, 1991. This 1989 modification
resulted in a change to a prior NRC commitment.
In accordance
with NEI guidelines, we will submit by November 1, 1998, a revised commitment
which reflects the existing plant configuration
and governing
design basis. 20
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN iNSPECTION
OPEN ITEMS 10/1/98 Update: Per NRG correspondence
dated May 18, 1998, titled "NRG INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-16)
was identified
as closed. This item was also the subject of a NOTICE OF DEVIATION
(50-255/98003-08)
from the same letter. Palisades
responded
with additional
information
to the NRG \ . .mder correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." In summary, Palisades
concludes
that our commitment
to assure that redundant
safety related power sources cannot be both affected by a fault on the instrument
bus has been maintained.
NRG correspondence
dated August 3, 1998 concluded
that a USQ does not exist, and that Consumers
appropriately
notified the NRG of past design changes, and rescinded
this cited potential
deviation.
No further actions are planned for this inspection
item. Inspection
Followup Item 50-255/97-201-17
The team observed that no system analysis existed to show that all the Class 1 E 120-V ac loads had *adequate
voltages.
The licensee demonstrated
during the inspection
that adequate voltages did exist for selected loads. For example, EA-ELEC-VOLT-24, "Voltage Drop From Preferred
AC Power Source Y10 Breaker 2 and Y40 Breaker 2 Out to the 5U12 Relays," Revision 0, showed that adequate ac voltage for those selected components
was available
at the minimum.inverter
voltage. The licensee initiated
CR C-PAL-97-1621
to evaluate and resolve this concern. The team identified
this item as part of Inspection
Fol/owup Item 50-255197-201-17.
Palisades
60 Day Response:.
During the Design Inspection, an operability
determination
was made concluding
the Class 1 E 120 V * ac loads are operable based on past plant operating
experience
and the expected minimal change in supplied voltage between normal and accident plant conditions.
By August 15, 1998,. we will perform a bounding analysis to confirm that Class 1 E 120 V ac loads have adequate voltage during accident conditions.
10/1/98 Update: Per NRG correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-17)
is identified
as open. A bounding calculation
was performed
under EA-C-PAL-97-1621A-01
that developed
worst case voltage levels for the Preferred
AC System and confirmed
adequate available
voltage during accident conditions . These analysis results will be incorporated
into Design Basis Document DBD-4.03, "Preferred
AC System" and tracked under change request number 4.03-12-R3-0728.
No further actions are planned for this inspection
item . 21
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Unresolved
Item 50-255/97-201-18
The team reviewed relay settings for protective
relays associated
with LPSI pump P-67 A, HPSI pump P-66A, SW pump P-7A, CCW pump P-52A, EOG 1-1 differential
protection, bus 1C undervoltage
protection, and Bus 1 C second-level
undervoltage
protection.
The settings were consistent
with the design parameters
of the devices being protected.
However, during the review, the licensee determined
that the overcurrent
relays for supply breakers 152-105 and 152-106 to bus 1C had not been calibration
tested during the last refueling
outage (1995) as required by Periodic and Predetermined
Activity (PPAC) SPS025, "Bus 1 C Relay Testing." The licensee stated that these relays would be calibrated
during the 1998 refueling
outage. The licensee reviewed past calibration
data for this type of relay and determined
that negligible
drift had previously
been documented.
The licensee initiated
CR C-PAL-97-1568
to resolve this discrepancy.
It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion
XI, "Test Control," had not been implemented
in this case in that certain relays had not been tested as required by the test program. The team identified
this item as Unresolved
Item 50-255197-201-18.
- Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that past calibrations
of overcurrent
relays for breakers 152-105 and 152-106 revealed insignificant
drift and the relays are operable.
We will perform maintenance
activity PPAC SPS025 to calibrate
the overcurrent
relays during the 1998 refueling
outage. Our corrective
action history identified
no other examples of failure to perform scheduled
relay testing. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-18)
was identified-as
closed. This item was also the subject of a NOTICE OF VIOLATION
(50-255/98003-09)
from the same letter. Palisades
responded
with additional
information
to the NRC under correspondence
dated June 24, 1998, entitled "RESPONSE
TO NOTICE OF VIOLATION
AND NOTICE OF DEVIATION
FROM INSPECTION
REPORT 50-255/98003." In summary, the overcurrent
relays for breakers 152-105 and 152-106 will be tested/calibrated
by December 31, 1998. The requirements
for PPAC SPS025 have been revised to allow performance
of the testing and calibration
while the plant is at power operation.
Unresolved
Item 50-255/97-201-19
The team questioned
the replacement
schedule for Agastat E7000 series relays. The team was aware that the manufacturer, in correspondence
to other utilities, had recommended
a 10-year replacement
schedule for these relays. The licensee stated that 52 E7000 series relays were installed
and that 7000 series Agastats were also installed
in Class 1 E applications.
Some circuits containing
7000 series relays included the 2400-V bus 1C and*1D supply breakers, time delay relays associated
with charging pumps. P-55A, B, and C, and auto transfer failure alarms for 2400-V busses 1C and 10. The manufacturer's
stated qualified
life forthe E7000 relays was 10 years. The licensee stated that the
qualified
life applied if the relays were located in a harsh environment
and, 22
- * * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS since the E7000 relays were located in a mild environment, no qualified
life determination
was required.
Based upon this justification, the licensee issued PPAC Deletion Form MSE 034, dated March 3, 1995, which stated that the relays would not require replacement
at 10-year intervals.
The team believed that the qualified
life stated by the manufacturer
applied to any environment.
The team verified with the manufacturer
that the projected
qualified
life of 10 years was the operating
life of the E7000 series relay as long as the device did not exceed the equipment
ratings, and that the life of 10 years was applicable
to either a mild or harsh environment.
The licensee had not evaluated
the qualified
life ofthe 7000 series relays. The manufacturer
of Agastat relays issued a 10 CFR Part 21 notification
concerning
the inability
of the E7000 series relays to switch a 1-amp load at rated voltage. The licensee evaluated
the installed
E7000 series relays and identified
no concerns.
The team observed that this evaluation
did not review those 7000 series relays dedicated
by the licensee to safety-related
use. The licensee issued CR C-PAL-97-1663
to resolve the issues concerning
Agastat relays and determined
that all the relays were operable.
It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion
Ill, "Design Control," had not been met in this instance in that the design basis lifetime for Agastat relays as stated by the manufacturer
had not been correctly
implemented
in the facility.
The team identified
this item as Unresolved
Item 50-255197-201-19.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that the 7000 series relays are operable based on their similarity
in application
and design to E7000 relays. By July 15, 1998, we will complete our analysis of both 7000 and E7000 series relays dedicated
for safety related use to confirm their ability to perform safety-related
functions
during their installed
life and their conformance
with applicable
design requirements.
10/1/98 Update: Per NRG correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-19)
was identified
as open. A review of both 7000 and E7000 relay age-sensitive
components
was performed
that indicates
that all relay materials
will last for greater than 40 years without significant
degradation
when installed
in mild environments.
Based on this review, a 10 year replacement
interval is not justified
and the relays can be expected to perform their design function for greater than 40 years. No further
actions are planned for this inspection
item. Unresolved
Item 50-255/97-201-20
The 125-V de system was divided into two independent
systems. Each system consisted
of a battery, switchgear, distribution
panel, and two chargers.
Station battery 1, battery charger 1, and battery charger 3 supplied 125-V de bus 1. Battery charger 1 was supplied from MCC 1 and battery charger 3 was supplied from MCC 2. Administrative
controls limited the operation
so that only one charger per battery was in service. This prevented
a common-mode
failure from affecting
both * 23
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS emergency
busses. The supply to 125-V de bus 2 was similar, with battery charger 2 fed from MCC 2 and battery charger 4 fed from MCC 1. Operating
Procedure
SOP-30, "Station Power," Revision 20, required the battery chargers to be operated in pairs (1 and 2 or 3 and 4). The licensee stated that the battery chargers were swapped monthly to provide equal operating
time for each battery charger. During swapping of the battery chargers in accordance
with Section 7. 7. 2 of SOP-30, the 125-V de breaker on the in-service
battery charger was opened and then the 125-V de breaker for the battery charger to be placed in service was closed. During this evolution, both battery chargers were disconnected
from the station battery and 125-V de switchgear
bus. Although temporary
disconnecting
the battery charger from the de bus had minimal safety impact on the plant, the team observed that TS 3. 7. 1 h required two station batteries
and the de systems (including
at least one battery charger on each bus) to be operable when the PCS was above 300 °F. The licensee stated that an LCO was not entered when no battery chargers were connected
to the de busses. The licensee initiated
CR C-PAL-97-1537
to resolve this discrepancy.
The team identified
the licensee's
failure to enter an LCO during battery charger switching
evolution
as Unresolved
Item 50-255197-201-20.
Palisades
60 Day Response:
Prior to the Design Inspection, we concluded
that our design bases were met and an LCO would not entered when realigning
battery chargers.
This conclusion
was based on no appreciable
battery discharge
occurring
during the short realignment
period when neither
charger was connected
to the 125 Vdc bus. In response to this Design Inspection
item, however, operating
procedure
SOP-30 was revised in anticipation
of an amendment
approving
our December 27, 1995 technical
specifications
change request. Although the requested
change does not require a connected
charger, the change defines 125 Vdc bus operability
in terms of applied bus voltage. SOP-30 now requires entry into an LCO whenever performing
charger realignment.
On January 26, 1998, a technical
specification
change request was resubmitted
as part of the Improved Technical
Specifications
Program. An amendment
in response to this latest change request will resolve this open item. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-20)
was identified
as closed. In July 1998, Amendment
180 of the Palisades
Electrical
Technical
Specifications
was implemented
that clarifies
the 125 Vdc system operational
requirements.
With the issuance and implementation
of Amendment
180, no further actions are planned for this inspection
item. Inspection
Followi.Jp
Item 50-255197-201-21
The team reviewed the 125-V de battery loading during the normal and alternate
battery charger alignment.
During the normal battery charger alignment, battery charger 1 was powered from EOG 1-1 and battery charger 2 was powered from EOG 1-2. During a LOCA combined with a LOOP in this normal alignment, the batteries
would be without ac power for approximately
1 O seconds until the EDGs restored power. The team reviewed EA-ELEC-LDTAB-009, "Battery Sizing for the Palisades
Class 1 E Station Batteries
ED-01 and ED-02," Revision 2, which verified that the battery was sized to provide adequate power during the 10 second interval until the EDGs provided ac power to battery 24
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGNINSPECTION
OPEN ITEMS chargers 1 and 2. During the alternate
battery charger alignment
with battery charger 3 powered from EOG 1-2 and battery charger 4 powered from EOG 1-1, the station batteries
would be required to carry the de loads for more than 10 seconds in the event of a LOCA combined with a LOOP and a single failure of ac power. EA-ELEC-LDTAB-009
did not analyze the battery loading for station batteries
ED-01 and ED-02 during this condition.
When questioned
by the team the licensee stated that the de loading during this scenario would be greater than the worst-case
loading assumed in ELEC-LDTAB-009.
The licensee issued CR C-PAL-97-1596
to resolve this discrepancy.
Additionally
the team had concerns on whether the licensee met the single failure criterion
when the alternate
battery charger alignment
was in effect. The team identified
the question with respect to the single failure criterion
and the additional
loading on the battery as an Inspection
Followup Item 50-255197-201-21.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that the station batteries
are operable.
Operability
was based on a preliminary
analysis where additional
- conservative
loads were included in the battery load analysis showing that the battery terminal voltage would be greater than the required minimum output of 105 Vdc throughout
the exp.ected
load duration until an operable charger would be connected
to the bus. Operating
procedures
control alternate
charger alignment
but do not restrict this practice which is allowed by technical
specifications.
By January 15; 1999, we will complete a formal analysis of battery loading considering
the battery chargers are in their alternate
alignment, and a combined event of a LOCA, LOOP and single failure of ac power occurs. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-21)
was identified
as open. As stated above, by January 15, 1999, the formal battery loading analysis will be completed.
Inspection
Followup Item 50-255/97-201-22
The team identified
that TS Section 4. 7.2c required that each station battery be demonstrated
operable by verifying
that the battery capacity was adequate to supply and maintain in an operable status all of the actual emergency
loads for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> when the battery was subjected
to a battery service test. The battery service tests performed
on station batteries
ED-01 and ED-02 were performed
for a duration of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The 4-hour duration and loading was based on the design basis station blackout (SBO) coping time. The team noted that the 2-hour requirement
of TS 4. 7.2c was non-conservative
with respect to the design basis, which required the station batteries
to be available
for4 hours. The design basis duration of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> was included in FSAR Section 8.4.2; DBD 4.01, "Station Batteries," Revision 3; RE-83A, "Service/Modified
Performance
Test-Battery
No. ED-01," Revision 9, and RE-838, "Service/Modified
Performance
Test-Battery
No. ED-02," Revision 9. Testing the batteries
in accordance
with RE-83A and B has ensured that batteries
ED-01and02
have met the 4-hour design basis requirement.
The licensee has submitted
TS changes to correct the non-conservative
TS Section 4. 7.2c and issued CR C-PAL-97-1551
to resolve this discrepancy.
The team identified
this item as Inspection
Followup Item 50-255197-201-22.
25
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that the 4-hour SBO station battery load profile envelops the 2-hour OBA load profile. By January 15, 1999, we will complete a formal analysis of battery loading considering
the battery chargers are in their allowed alignment
configurations
with a combined event of a LOCA, LOOP and.single
failure of ac power. We submitted
a technical
specification
change request on December 27, 1995 to describe the test profile as the design basis profile without stipulating
a specific period for the profile. On January 26, 1998, a technical
specification
change request was resubmitted
as part of the Improved Technical
Specifications
Program which identifies
a four hour load profile for the service test. An amendment
in response to this latest technical
specifications
request will resolve this open item. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-22)
was identified
as open. As identified
above, by January 15, 1999, the formal battery loading analysis will be completed.
In July 1998, Amendment
180 of the Palisades
Electrical.Technical
Specifications
was implemented.
Amendment
180 does not specify a duty cycle (profile)
duration in units of time. Therefore, the design basis requirements
found in the FSAR can be used. Inspection
Followup Item 50-255/97-201-23
EA-ELEC-FL
T-005, "Short-Circuit
for the Palisades
Class 1 E Station Batteries
ED-01 and ED-02," . Revision 0, was submitted
to the team as the short-circuit
analysis for the Class 1E 125-V de system. The following
discrepancies
with the assumptions, methodology, and conclusions
were identified:
- Section 4. 4 and 4. 5 assumed various breaker and fuse impedances, which had not been verified against the installed
facility.
- Section 5. 2 utilized the battery charger current limit of 220 amps as the maximum short-circuit
contribution
without supporting
documentation.
- Section 5.2 stated that the open-circuit
voltage was 2.06 V per cell, whereas the EA utilized an open-circuit
voltage of 2. 0 V per cell. * Section 8. 0 stated that the results were to be further reviewed by the licensee;
however, the team found no evidence of this review. Section 8. O also contained
no conclusion
about the de system acceptability.
The licensee issued A/Rs A-PAL-97-108, 109, and 110 to resolve these discrepancies.
The licensee stated that the* analyses would be reviewed and the conclusions
revised. During the 1995 refueling
outage, FES-95-206
replaced existing batteries
ED-01 and ED-02. The team questioned
if the sh9rt-circuit
current provided by the new battery was analyzed and if there were any effects on the de distribution
panel breakers, since the team noted that EA-ELEC-FL
T-005 26
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS . had not been updated since 1994. The team also noted that the design basis for the evaluation
of fault current contributions
on de circuits was in FSAR Section 8.5.2, which stated "The 125 volt de protection
design considers
the fault current available
at the source side of the feeder protective
device." However, the licensee stated that the short-circuit
contribution
value for de circuits was taken at the electrical
load terminals
and not at the breaker load terminals (de short-circuit
current value would be less when calculated
at the load terminal vice the source side of the feeder protection
device because voltage available
at the load terminal would be less than at the source breaker).
The licensee determined
that the short-circuit
contribution
at 8 breakers (breakers
72-101, 72-105, 72-106, 72-121, 72-127, 72-133, and 72-135) on distribution
panels 011-1and011-2
could exceed the short-circuit
interrupting
ratings when evaluated
in accordance
with the design basis method in the FSAR. Also, when the team questioned
the assumed breaker fault ratings on de busses 010, 020, 011-1, and 011-2of13,000
amps in EA-ELEC-FLT-005, the licensee was unable to show manufacturer
or testing documentation
to support this assumption.
The team believed that this assumption
was inconsistent
with its experience.
The licensee performed
an operability
review and issued CR C-PAL-97-1652
to resolve these discrepancies.
The maximum short-circuit
current of the battery installed
by FES-95-:206, as provided by the manufacturer, was 17094 amps. Calculation
EA-ELEC-FL
T-005 did not reflect this new short:..circuit
current. Upon questioning
by th.e team, the licensee stated that an evaluation
was performed
to ensure that the system short-circuits
were acceptable.
During the team's review of this evaluation
it was determined
that the maximum battery short-circuit
current was not utilized.
The.licensee
stated that the short-circuit
current utilized, 12,821 amps, was provided by the manufacturer
as a more realistic
value than 17,094 amps. However, the licensee could not document a basis for the 12,821 amps and stated that they would verify it with the manufacturer.
The team identified
these discrepancies
concerning
EA-ELEC-FL
T-005 as part of Inspection
Followup Item 50-255197-201-23.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that a fault would more likely occur at the load rather than at the breaker terminals.
A fault at the load (esults in a reduced value of fault current which falls within the breaker interrupting
rating. We have since obtained vendor specifications
which envelop our calculated
peak short circuit currents assumed to occur at the breaker terminals.
These specifications
confirm our earlier conclusion
that the breakers are suitable for their intended service, and resolve any concerns with respect to breaker short circuit interrupting
capability.
Revisions
to analysis EA-ELEC-FL
T-005, to correct the plant-identified
deficiencies
described
in the Design Inspection
report, will be complete by January 15, 1999. 10/1/98 Update: Per NRG correspondence
dated May 18, 1998, titled "NRG INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-23)
was identified
as open. Revisions
to analysis EA-ELEC-FL
T-005, to correct the plant-identified
deficiencies
described
in the Design Inspection
report, remains scheduled
for completion
by January 15, 1999 . 27
- ** * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Inspection
Followup Item 50-255197-201-24
FSAR Section 8.4.3.3 stated that the batteries
were designed to furnish their maximum load down to an operating
temperature
of 70 °F without dropping below 105 V de, and that the equipment
supplied by the batteries
was capable of operating
satisfactorily
at this voltage rating. EA-ELEC-VOL
T-026, "Voltage Drop Model of the Palisades
Class 1 E Station Batteries
D01 and D02," Revision 0, evaluated
the de voltages at the distribution
panels based upon a battery voltage of 105 V de, but did not evaluate the voltages that would be available
at the load device terminals.
The team was concerned
that the additional
voltage drop from the distribution
panel to the loads could result in voltages less than the design basis of the loads, and that no analysis was performed
to evaluate this situation.
For example, the deign-basis
minimum input voltage for the inverters
was 105 V de and the licensee could not show any vendor documentation
to support operating
at a value Jess than 105 V de. The team noted that the inverters
could be subjected
to an input voltage of approximately
102 V de if the battery voltage were 105 V de. The licensee stated that battery surveillance
testing has shown that battery voltage, when subjected
to an SBO duty cycle, did not decrease below 108 V de. During the inspection, the licensee evaluated
several safety-related
loads and verified that adequate voltages would exist at 105 V de battery voltage. The licensee issued CR C-PAL-97-1620
to evaluate the lack of an EA to ensure that adequate voltages would exist at the load terminals.
The team identified
this item as part of Inspection
Followup Item 50-255197-201-24.
Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that the 125 Vdc system is operable based on an evaluation
of several safety related loads, in which adequate load voltage was found to exist with a 105 Vdc battery terminal voltage. By November 15, 1998, we will perform a bounding analysis to identify the worst-case
minimum voltage levels at the load assuring that minimum load voltage req.uirements
are met. * 1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-24)
was identified
as open. As stated above, this issue is scheduled
for completion
by November 15, 1998. Unresolved
Item 50-255197-201-25
The team also questioned
the capability
of solenoid valves to operate at voltages of 87 V de as stated in DBD 1. 01,
Cooling Water System," Revision 4. The licensee determined
that the DBD was incorrectly
worded and that the correct solenoid capability
was90-140 V de. Upon further review, the licensee identified
that improperly
rated coils, rated 102-126 V de, were installed
in solenoid valves SV-0918 and SV-09778.
The licensee initiated
Engineering
Assistance
Request (EAR) 97-0652 to replace the coils. It appeared that the requirements
of 10 CFR Part 50, Appendix B, Criterion
Ill, "Design Control," were not followed in that the design basis for the solenoid valve coils was not implemented
in the plant. The team identified
this item as Unresolved
Item 50-255197-201-25 . 28
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
Since the design inspection, further evaluation
identified
that there is no impact on the mitigation
of an accident if solenoid valves SV-0918 and SV-09778 fail to open due to low voltage since the close position is both the failed position and the required safety position.
Based on this review, the design basis is met by the existing solenoid valve installation.
The actions in response to Inspection
Followup Item 50-255/97-201-24
will identify any other minimum voltage problems.
10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-25)
was identified
as closed. No further actions are planned for this inspection
item. Inspection
Followup Item 50-255/97-201-26
The team identified
other discrepancies
in calculations
as follows: * Assumptions
4. 6 and 4. 7 of EA-ELEC-VOL
T-26, Revision 0, and assumptions
4. 8 and 4. 9 of EA-ELEC-M/SC-022, "Electrical
Systems Model of the Palisades
Class 1 E Safety Re/a.fed 125 V de System," Revision 1, assumed various fuse and breaker impedances
which had not been verified against the installed
equipment.
- Section 7. 0 of EA-ELEC-VOL
T-26, Revision 0, "Conclusion," stated that the results were to be further reviewed by the licensee;
however, the team found no indication
that this review had been performed.
The "Conclusion" section also contained
no statement
concerning
the de system acceptability.
- EA-ELEC-VOL
T-26, Revision 0, utilized a correction
factor for battery temperature
of 77 °F instead of the correction
factor for 70 °F, which was the minimum design basis temperature
for the battery. The number utilized is less conservative
and the licensee evaluated
that the overall effect on voltages in the calculation
would be less than 0. 5 percent. * EA-ELEC-LDTAB-029, Revision 2, stated the type of battery constant as 1.0 in Attachment
A and 1.4 on Sheet 4. The constant to be utilized depended on the type of battery. 1. 0 referred to a lead acid battery; 1.4 referred to a nickel-cadmium
battery. The licensee reviewed the EA and determined
that the correct constant was utilized in the EA and that the reference
to 1. 4 was an editorial
error. The licensee issued CR C-PAL-97-1656
to address the battery temperature
correction
factor and stated that the other discrepancies
would be corrected
in future revisions
to the calculations.
The team identified
this item as part of Inspection
Fo//owup Item 50-255197-201-26.
29
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
During the Design Inspection, an operability
determination
was made concluding
that the calculation
deficiencies
identified
had no affect on the analyses conclusions;
ie, supplied voltages remain within equipment
ratings and the station batteries
are not affected.
By January 15, 1999, EA-ELEC-VOLT-26, EA-ELEC-MISC-022
and EA-ELEC-LDTAB-029
will be revised to resolve the deficiencies
noted above. 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-26)
was identified
a:s closed. Analyses EA-ELEC-VOLT-26, EA-ELEC-MISC-022
and EA-ELEC-LDTAB-029
will be revised by January 15, 1999 as projected
above. Inspection
Followup Item 50-255/97-201-27
The team noted that TS Section 4. 7.1.b required testing to be performed
at every. refueling
to demonstrate
the overall automatic
operation
of the emergency
power system. Proper operation
was verified by bus load shedding and automatic
starting of selected motors and equipment
to establish
that emergency
power had been restored within 30 seconds. FSAR Tables 8-6 and 8-:-7 stated that sequencing
would occur in 65 seconds. Technical
Surveillance
Procedure
RT-BC, "Engineered
Safeguards
System -Left Channel," Revision 8, and RT-8D, "Engineered
Safeguards
System -Right Channel," Revision 8, required performance
testing to be within the 65-second
requirement.
The team questioned
the use of a 30-second
test duration in the TS instead of a 65-second
duration, which would demonstrate
that all required equipment
would start. The licensee stated that the TS did not specifically
require full testing of the entire diesel load sequence but only required testing of selected loads. The team noted that the licensee was testing the diesel loading to the full accident loading sequence and has submitted
a proposed TS change which would be more consistent
with the current design. The team reviewed Test Procedures
R0-128-1, "Diesel Generator
1-1 24 Hour Load Run," Revision 2, and R0-128-2, "Diesel GeneratOr
1-2 24 Hour Load Run," Revision 2. The team noted that Section 3. O of the Acceptance
Criteria and Operability
Sheet for Procedure
R0-128-2 referred to TS Section 3. 7. 1 and 4. 7. 1. 11, and that these references
would only be correct when the proposed improved TS, which have been submitted
to NRG for approval, became effective.
The licensee issued CR C-PAL-97-1566
to resolve these discrepancies.
The team identified
this item as Inspection
Followup Item 50-255197-201-27.
Palisades
60 Day Response:
Several issues identified
in the Design Inspection
are associated
with interpretation
of existing Technical
Specifications.
On December 27, 1995 we submitted
an electrical
technical
specifications
change* request which served to resolve the discrepancy
noted above pertaining
to the Emergency
Diesel Generator (EOG) load sequence test. On January 26, 1998, we submitted
a request for improved technical
specifications
which specifies
testing the EOG to the load 30
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS intervals
programmed
by the sequencer;
eliminating
any specific reference
to the sequence time. It is expected that the amendment
resulting
from the most recent .technical
specification
change request will serve to resolve this and other technical
specification
related open items. 1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item
(50-255/97201-27)
was identified
as closed. In July 1998, Amendment
180 of the Palisades
Electrical
Technical
Specifications
was implemented.
Amendment
180 specifies
testing the EOG to the load intervals
programmed
by the sequencer;
eliminating
specific reference
to the sequence time. No further actions are planned for this item. Inspection
Followup Item 50-255197-201-28
The team identified
the following
discrepancies
when reviewing
station battery Test Procedures
RE-83A, "Service/Modified
Performance
Test-Battery
No. ED-01," Revision 9, and RE-83B, "Service/Modified
Performance
Test-Battery
No. ED-02," Revision 9: * The tests evaluated
whether the final discharge
voltage (105 V de) of station batteries
ED-01and02 was met at the end of the test (4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />). Load parameters (amps) at 1 and 239 minutes were not verified during the test. These load parameters
were design requirements
of EA-ELEC-LDTAB-009, Revision 2. The licensee demonstrated
that the 1-and 239-minute data were recorded elsewhere
and that the duty cycle was* tested in accordance
with the design requirements.
The licensee stated that the battery testing procedures
would be revised to include verification
of these design parameters.
- The procedures
did not require any calibration
tolerances
for the discharge
testing shunt and control unit. The licensee stated that the tolerance
was removed from the procedure
before testing during the 1996 refueling
outage and issued PCRs 5422 and 5423 to change the
procedures
to include these tolerances.
- The battery charging data in Procedure
RE-83B for the 1996 refueling
outage did not meet Step 5. 2. 2, which required the battery charging rate to be decreasing
and to remain within 5 percent over the last 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> before stopping the equalization
process, in that the process was stopped before the end of the 8-hour period. The licensee stated that the nearly steady state voltage operation
of the charger gave adequate assurance
that the battery was operable before exiting the test and issued CR C-PAL-97-1460
to resolve this discrepancy.
- During the performance
of procedure
RE-83B at the 1996 refueling
outage, the elapsed time recorded manually did not agree with the testing control unit time. The licensee stated that because the testing unit did not have the capability
to record the time, the test start and stop times were recorded manually.
The inconsistencies
were minor and had no effect on the test results. The licensee issued C-PAL-97-1460
to evaluated
this discrepancy.
The team identified
this item as Inspection
Followup Item 50-255197-201-28.
31
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
Note: Inspection
Followup Item 50-255/97-201-28, Unresolved
Item 97-201-30
bullets 7, 8, 9, 10, 11 and 12, and Unresolved
Item 97-201-31
bullets 6 and 13 are completed
under this action due to their subject similarity.
Surveillance
tests RE-83A and RE-838 will be revised as appropriate
to eliminate
the identified
deficiencies
to support 1998 refueling
outage performance.
By December 15, 1998, we will review DC system requirements, FSAR Chapter 8 and surveillance
tests RE-83A and RE-838 for consistency, and resolve the deficiencies
identified
in this open item and the following:
- Reconcile
FSAR section 8.2.3 concerning
the battery supplying
safe shutdown loads for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> with the requirement
to strip loads. (Inspection
report item #30-7.) * * Disposition
battery shunt and de tie breakers which are not consistent
with FSAR section 8.3.5.2. (Inspection
report item #30-8.) * Reconcile
one battery charger capability
to supply normal loads and recharge battery in less than 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> with FSAR section 8.3.5.3. (Inspection
report item #30-9.) * Reconcile
alternate
alignment
of battery chargers with FSAR section 8.4 .. 2.2. (Inspection
report item #30-10.) * Reconcile
battery chargers cross connection
with FSAR section 8.5.2. (Inspection
report item #30-11.) * Reconcile
design of system 1, 2, 3, 4 circuits and their separation requirements
with FSAR section 8.5.3.2. (Inspection
report item #30-12.) * Add battery discharge
restriction
to the D8D. (Inspection
report item #31-6.) * Disposition
battery cell specific gravities. (Inspection
report item #31-13.) 10/1/98 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION, this item (50-255/97201-28)
was identified
as open. Surveillance
tests RE-83A and RE-838 were revised and satisfactorily
performed
during the 1998 refueling
outage. The June 30, 1998 FSAR revision resolved inspection
report items #30-8, #30-9, and #30-12. The above remaining
items are scheduled
to be complete by December 15, 1998 .. Inspection
Followup Item 50-255/97-201-29
The team reviewed the following
electrical
modification
packages and found them consistent
with the plant design basis: 32
- * * * * * * * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Temporary
Modification
TM-96-027, "lnsta/1152-Spare
- 5 Breaker in 152-113 Cubicle," dated April 10, 1996 FES-95-206, "ED-01 and ED-02 Station Battery Replacement," Revision O FC-364, "Feeder Change for Instrument
Bus Y-01," Revision O FC-854, "Y-01 Power Supply Feed Modification," Revision 0 FC-638, Add Component
Cooling Water Pumps to the Normal Shutdown Sequencer," Revision 0 FC-798, "Battery Room Temperature
Indication
and Alarm," Revision O FC-683, "Removal of Pressurizer
Heaters from SIS Trip," Revision O Except as previously
discussed, all these modifications
were adequately
prepared, provided the necessary
technical
basis for the changes, and contained
adequate installation
instructions
and testing requirements.
The 10 CFR 50. 59 safety evaluations
were adequate, except for the two listed below: = Safety Reviews 95-1431and95-1432, dated July 7, 1995, for FES-95-206
stated that the battery duty cycle service test duration for station .batteries
ED-01 and ED-02 was changed from 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The licensee noted that TS Section 4. 7.2.c was affected by this design change. However, the USQ evaluation, Question 2 of Section II, was not checked "Yes" for a TS change. TS 4. 7.2.c required that a 2-hour battery test be performed;
while design analysis ELEC-LDTAB-009
and FSAR Section 8.4.2 required a 4-hour battery duty cycle. The licensee has submitted
a proposed TS change to reflect the proper battery test duration and issued CR C-PAL-97-1551
to address this discrepancy.
- The safety review documentation
for TM-96-027
stated that the FSAR was not reviewed.
Administrative
Procedure
3. 07, "Safety Evaluations," page 12, required that the FSAR be reviewed and that thos*e sections reviewed be noted on the safety review sheet. The licensee initiated .C-PAL-97-1493
to evaluate this discrepancy.
The team identified
these safety review discrepancies
as Inspection
Fol/owup Item 50-255197-
201-29. Palisades
60 Day Response:
It was not documented
in the safety evaluation
for FES-95-206
that a technical
specification
change would be required to change the battery duty cycle service test duration from 2 to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. An FES-95-206-specific
technical
specifications
change was not considered
necessary
by the preparer of the safety evaluation
since a technical
specifications
change request eliminating
reference
to a specific duty cycle time was to be submitted
under the Improved Technical
Specifications
Program in the near term. Since completion
of the FES-95-206
safety evaluation, Palisades
has implemented
a Safety & Design Review Group which reviews and approves all design changes and safety evaluations.
The purpose for forming and employing
this group is to provide consistent
oversight
The quality of safety evaluations
and their reviews has significantly
improved over the recent years. It is unlikely that a safety evaluation
deficiency, similar to that associated
with FES-95-206, would have occurred
since deployment
of the Safety & Design Review Group. 33
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS The original safety review for TM-96-027
inappropriately
indicated
that FSAR sections had not been reviewed.
In reality, the FSAR was reviewed during safety review preparation
and the FSAR was found to contain description
at a level of detail that the TM would not affect. The review of the TM-96-027 safety review was performed
by telecon (an infrequent
practice)
with no follow-up
review performed
by the Safety & Design Review telecon reviewer.
By April 15, 1998, design control procedures
will be revised to require a follow-up
review whenever a review is performed
by telecon. 1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND.NOTICE
OF VIOLATION", this item (50-255/97201-29)
was identified
as closed. Administrative
Procedure
AP 3.07, "SAFETY EVALUATIONS" was revised to require follow-up
reviews as stated above. No further actions are planned for this inspection
item. Note: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-30)
was identified
as open. FSAR changes identified
in Unresolved
Item 50-255/97201-30
are identified
below. Some of these bullets are grouped and evaluated
with other URl's or IFl's. For clarity, each bullet's actions will be separately
addressed.
Unresolved
Item 50-255197-201-30
The team identified
the following
discrepancies
in the FSAR: * Page 6. 7-4 stated that 'containment
isolation
valves fail closed with loss of voltage or control air except for the CCW return isolation
valves. However, the CCW supply isolation
valve (CV-0910)
is also a fail-open
valve and should have *been noted as an exception
to fail-closed
containment
isolation
valves. The licensee issued FSAR Change Request 6-142-R20-1426
to correct the FSAR. Palisades
60 Day Response:
The next FSAR annual update revision will incorporate
this change. 1011198 Update: Annual FSAR update issued June 30, 1998, included this change. * Section 6. 7 classified
the CCW penetrations
as Class C-2, which was defined as penetrations
with lines not missile protected.
However, EA-GW0-7793-01
stated that the entire CCW system (both inside and outside containment)
was missile protected.
The licensee issued FSAR Change Request 6-143-R20-1427
to state that the CCW penetrations
were not vulnerable
to internally
generated
missiles . 34
- * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
The next FSAR annual update revision will incorporate
this change. 10/1/98 Update: Annual FSAR update issued June 30, 1998, included this change. * Table 9-10 stated that valves 3029 and 3030, containment
sump suction valves, failed closed upon loss of air and were equipped with an accumulator.
The valves actually failed as is and had no accumulator.
The licensee issued FSAR Change Request 9-293-R20-1431
to correct *the FSAR and CR C-PAL-97-1559
to evaluate and trend the FSAR discrepancies
being identified
at the plant. Palisades
60 Day Response:
The next FSAR annual update revision will incorporate
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * Table 9-9 correctly
stated that the high-pressure
air piping was seismic Class I from the receivers
to the valve operators.
However, FSAR Table 5.2-3 stated that the entire system was seismic Class I. The licensee issued FSAR Change Request 5-155-R20-1432
to correct the FSAR 5. 2-3. Palisades
60 Day Response:
The next FSAR annual update revision will incorporate
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * Section 8.4.2.2 stated that the station batteries
would be tested to Institute
of Electrical
and Electronics
Engineers (IEEE) 450-1975.
However, battery testing procedures
RE-83A, Revision 9, and RE-838, Revision 9, referred to IEEE 450-1995.
FSAR Change Request 8-126-R20-1249
had been initiated, but the licensee did not intend to act on this change until approval was received from NRG of a related proposed TS change. Palisades
60 Day Response:
This FSAR change is on hold until the license amendment
responding
to our improved electrical
technical
speeification
change request, submitted
January 26, 1998, is received.
This change cites IEEE 450-1995 for the battery testing . 35
- ** ATTACHMENT
A * STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS 1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-30)
was identified
as open. In July 1998, Amendment
180 of the Palisades
Electrical
Technical
Specifications
was implemented
with IEEE 450-1995 as a reference.
FSAR change 8-126-R21-1249
will be implemented
as part of the next annual FSAR update. to reflect the use of this IEEE standard.
- Table 5. 7-8 listed the seismic design value for the station batteries
and racks as "later" instead of including
the actual values of the batteries
installed
by FES-95-206.
The licensee issued EAR-97-0636
to evaluate this discrepancy
and revise the FSAR. Palisades
60 Day Response:
The table in the FSAR is designated
as containing
the original seismic design values for the plant. The term "later" was an original FSAR description
which acknowledged
that an impending
upgrade to install a second redundant
electrical
train would be made and the applicable
seismic criteria would not be available
until then. Since we have chosen to keep this table for historical
record, the word "later" will be removed and the table maintained
as original seismic criteria.
The next FSAR annual update will incorporate
this change requested
by FSAR Change Request 5-157-R20-1456.
1011198 Update: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this portion of unresolved
item 50-255/97201-30
was identified
as closed. The annual FSAR update issued June 30, 1998, included this change. No further actions are planned for this inspection
item. * Section 8.2.3 stated the "The de battery system is designed to supply the required shutdown loads, with a total loss of ac power, for at ieast 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />." This statement
did not reflect the fact that load stripping
was required during the 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for the battery to perform its intended function during a loss of ac power. * Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
1011198 Update: The resolution
of this issue is addressed
in Inspection
Followup Item 50-255/97201-28
due to subject similarity.
This item is projected
to be complete by December 15, 1998. Section 8. 3. 5. 2 stated that "Operation
of all circuit breakers in the de and the preferred
ac systems is manual with automatic trip for fault isolation." The battery shunt trip breakers and the de bus tie breakers do not comply with this statement.
36
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: Revision 20 of FSAR Chapter 8 incorporates
the exclusion
of the battery isolation
shunt trip breakers and tie breakers between the left and right sections of each switchgear
bus that do not have an automatic trip for fault isolation.
Our June 30, 1998, annual FSAR update includes this change. * Section 8. 3. 5. 3 stated that "Each of the two battery chargers provided on the. de bus is capable of supplying
the normal de loads on the bus and simultaneously
recharging
the battery in a reasonable
time. A fully discharged
battery can be recharged
in less than nine hours." Contrary to the statement, one battery charger could not supply the normal loads and recharge a fully discharged
battery in less than 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />. Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: Revision 20 of FSAR Chapter 8 now states that two battery chargers are needed to recharge a fully discharged
battery in less than nine hours. Our June 30, 1998, annual FSAR update includes this change. * Section 8.4.2.2 stated that "Emergencv
Operation
-.On loss of normal and standby ac power, the batteries
will supply power to all preferred
ac and de loads, until one of the (diesel generators)
DGs has started and can supply power for the chargers." This statement
was not correct if the battery chargers were in their alternate
alignment
and did not reflect load shedding during the 4-hour duration.
Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: The resolution
of this issue is addressed
in Inspection
Followup Item 50-255/97201-
28 due to subject similarity.
We plan to complete this item by December 15, 1998. * Section 8.5.2 stated that The power source for the driven equipment
and the control power for that system are supplied from the sources in one channel." This statement
would not be correct if the battery chargers were cross-connected . 37
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: The resolution
of this issue is addressed
in Inspection
Followup Item 50-255/97201-
28 due to subject similarity.
We plan to complete this item
by December 15, 1998. * * Section 8.5.3.2 referred to "System 1, 2, 3, 4 Circuits" and separation
requirements
for those circuits.
The licensee was not able to identify these circuits.
- Palisades
60 Day Response:
Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: Revision 20 of FSAR Chapter 8 expands the definition
along with providing
routing and isolation
requirements
for 'left', 'right' and channel '1 ', '2', '3', and '4' circuits.
Our June 30, 1998, annual FSAR update includes this change. * Section 8.4.1.3 required clarification
as to whether the reserve capability
margin referred to the capability
of the overall EDG and engine or if it referred to the capability
of the EOG to handle an increase loading due to a control circuit ma/function
during the loading sequence.
The licensee issued C-PAL-97-1309
to resolve this discrepancy.
Palisades
60 Day Response:
Prior to the Design Inspection, an operability
determination
was made concluding
This conclusion
was reached based on the capability
of the EDGs to provide the required design function
in the event of a control. circuit malfunction
or delayed containment
high pressure signal; but not both concurrently.
The design basis accident analysis does not require that these two events occur simultaneously.
Due to the change being descriptive
in nature, rather than licensing
basis information, we have elected to use the Design Basis Documents
rather than the FSAR to make the clarification.
Design Basis Document Change 5.03-11-R3-
0617 was initiated
and the revision will be made by December 15, 1998. 10/1/98 Update: Revision 4 of DBD 5.03 incorporates
the requested
change which evaluated
the system functional
requirements
of the EOG starting and carrying the largest load due to a control circuit malfunction.
Revision 4 also includes discussion
regarding
the EOG control circuit malfunction
and starting a containment
spray pump during a delayed containment
high pressure scenario;
- concluding
that the malfunction
and the pump start are mutually
exclusive.
No further actions are planned for this item. 38
- .ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS * Section 6.1.2.3 stated that The RAS ... provides a permissive
to manually close the valves in the pump minimum flow lines." EOP-4. 0, "Loss of Coolant Accident Recovery," Revision 9, Step 23, directed the operators
to place the hand switches for these valves in the pump minimum flow lines (CV-3027 and CV-3056) to CLOSE when SIRWT level lowered to between 25 percent and 15 percent. Per EOP-4.0, Step 51, the RAS occurred when the SIRWT level reached 2 percent. The FSAR appeared to conflict with EOP-4.0. The licensee initiated
FSAR Change Request 6-141-R20-1425
to update the FSAR. Palisades
60 Day Response:
The next FSAR annual update revision will incorporate
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. * The footnote for Table 14.17.1-1
implied that a containment
building temperature
of 90 °F was used as input to the large-break
LOCA analysis because it is the limiting temperature
during normal operation.
The 90 °F value did not appear to be limiting.
The licensee stated that the 90 °F value was the nominal containment
building temperature, not the limiting temperature, and was used in the accident analysis in accordance
with Seimens Power Corporation's
large-break
LOCA methodology
guidelines.
The licensee initiated
FSAR Change Request 14-95-R20-1441
to update the FSAR. * Palisades
60 Day Response:
The next. FSAR annual update revision will incorporate
this change. 10/1/98 Update: Annual FSAR update issued in June 30, 1998, included this change. The above discrepancies
had not been corrected
and the FSAR had not been updated to ensure that the material in the FSAR contained
the latest material
as required by 10 CFR 50. 71(e). The team identified
this item as Unresolved
Item 50-255197-201-30.
Palisades
60 Day Response:
10 CFR 50.71(e) requires that the FSAR be updated to contain the latest material developed
and that it includes the effects of all changes made in the facility or procedures
described
in the FSAR. Although several of the identified
FSAR discrepancies
were clear errors, most were cases where statements
in the FSAR were misleading
or unclear and not cases where the FSAR was not updated per 10 CFR 50.71 (e). Our ongoing FSAR verification
and validation
effort should provide identification
and correction
of similar conditions
which may exist in the FSAR. Our processes
were also changed a few years ago to require a safety review (1 O CFR 50.59 screening)
for 39
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS all analyses, modifications, etc which have the potential
to affect the design basis of the facility.
This widespread
10 CFR 50.59 screening
will prevent failures to update the FSAR in accordance
with 10 CFR 50.71(e).
In addition, a license basis self assessment
performed
in accordance
with NEI 96-05, "Guidelines
for Assessing
Programs for Maintaining
the Licensing
Basis," found few discrepancies
in the FSAR sections sampled which
had not been previously
identified
for correction
by other plant processes.
Therefore, we feel that the current efforts underway will correct other errors which may exist in the FSAR and the current plant processes
will ensure that the FSAR is updated properly.
10/1/98 Update: The above response remains unchanged
from our 60-day response.
Note: Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", this item (50-255/97201-31)
was identified
as open. DBD changes identified
in Unresolved
Item 50-255/97-201-31
are identified
below. Some of these bullets are grouped and evaluated
with other UR l's or IFl's. For clarity, each bullet's actions will be separately
addressed.
Unresolved
Item 50-255/97-201-31
The team identified
the following
discrepancies
in the DBDs: * DBD 1.07, Auxiliary
Building HVAC Systems," Revision 1, Table 3.2.1, incorrectly
stated that the design basis temperature
for Room 123, which contains the CCW pumps, was 125 °F. The correct temperature
was 104 °F as stated in 080 7.01, "Electrical
Equipment
Qualification
Program," Revision 1, Appendix A. The 125 °F temperature
was a conservative
assumption
used to size the outside air supply fans. Table 3.2.1 also contained
a typographical
error in a reference
number. The licensee issued 080 Change Requests 1.07-71-R1-0512
and 1.07-72-R1-0532
to correct the 080. Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Revision 2 of DBD 1.07, "Auxiliary
Building HVAC Systems" incorporated
the above changes. The basis for the 125 ° F CCW room temperature
was clarified
and references
were corrected.
- 080 1.07, Revision 1, Section 3.2.1.3, listed maximum room temperatures
for the west ESF room from an outdated analysis.
The latest analysis, EA-O-PAL-93-272F-01, "Engineering
40
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Safeguards
Room Heatup Following
LOCA in Conjunction
With a Loop," Revision 0, determined
lower maximum room temperatures
for various SW flows through the air coolers. The 080 also required clarification
of the normal design temperature
of the ESG room. The licensee issued 080 Change Request 1.07-73-R1-0543
to correct the 080. Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Revision 2 of DBD 1.07, "Auxiliary
Building HVAC Systems" incorporated
the above change. The basis for the 135°F Engineering
Safeguards
Room temperature
was clarified.
- 080 7. 08, "Plant Protection
Against Flooding, 77 Revision 1, incorrectly
stated that the EOG would be inoperable
before a flood reached the EOG windings because the lube oil heaters were located below the windings at 7 inches above the floor. EA-C-PAL-95-1526-01, "Internal
Flooding Evaluation
for Plant Areas Outside of Containment, 77 Revision 0, stated that the minimum flood level at which the EOG could become inoperable
was 10 inches due to the exciter cubicle bus bars and that the lube oil heaters were not needed for EOG * operability.
The licensee issued CR C-PAL-97-1557
to initiate a 080 change and evaluate the item. Palisades
60 Day Response:
During the Design Inspection, an operability
determination
concluded
that the EDGs * are operable based on other indications
available
to inform operations
that water level in the rooms is increasing.
DBD change request 7.08-40-R1-0561
was initiated
to state that the limiting component
is not lube oil heaters but the exciter cubicle bus bars located ten inches above the EOG room floor. The identified
Design Basis Document Change Request will be incorporated
into the DBD by December 15, 1998. 10/1/98 Update: This DBD change is on target for completion
by December 15, 1998 as identified
above. * 080 2. 03, "Containment
Spray System, 77 Revision 2, stated that the air supply to the sump outlet valves, CV-3029 and 3030, was backed by an accumulator.
There were no accumulators
for these valves. The licensee identified
this error while evaluating
an FSAR statement
that these valves had an accumulator
backup that was questioned
by the team, and issued 080 Change Request 2.03-22-R2-0531
to correct the 080 . 41
- ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Revision 3 of DBD 2.03, "Containment
Spray System" corrected
the terminology
from "accumulator" to "high pressure air receivers".
No further action is planned. * DBD 1.01, "Component
Cooling Water System," Revision 3, Section 3.3. 7, incorrectly
indicated
that Class 1 E and non-Class 1 E breakers were installed
in the same distribution
panels. The licensee initiated
DBD Change Request 1.01-14-R3-0518
to correct the DBD. Section 3. 3. 7 of this DBD also stated that solenoid valves had been tested to operate at 87 V de instead of 90 V de. The licensee stated that the DBD would be corrected.
Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Due to competing
priorities, this DBD change has been rescheduled
to be completed
by December 15, 1998. * * * During the teain's review of FES-95-206, it was noted that the battery manufacturer
had imposed a limit of 40 battery discharges
for the 20-year life of the battery. This restriction
had not been identified
in any DBD. The licensee stated that the requirement
would be added to DBD4.01. . Palisades
60 Day Response:
A Design Basis Document Request will be incorporated
into the DBD by December 15, 1998. Refer to our response to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: This DBD change is on target for completion
by December 15, 1998, as
above. * Appendix A of DBD 7. 02, "Palisades
Design Basis Document EQ Master Equipment
List," Revision 2, incorrectly listed
the location for L T-0383; referred to EIP 0343 instead of E/P 0346; and did not include SV-32138 in Table A-1. The licensee issued DBD Change Requests 7. 02-4-R2-0522, 7. 02-6-R2-0527, and 7.D2-4-R2-0523
to correct the DBD . 42
- * * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by December 15, 1998. 10/1/98 Update: These DBD changes are on target for completion
by December 15, 1998. * DBD 2.01, "Low Pressure Safety Injection
System," Revision 3, and DBD 2.02, "High Pressure Safety Injection
System," Revision 3, both contained
references
to ANF-88-107, "Palisades
Large Break LOCNECCS Analysis With Increased
Radial Peaking," Revision 1. ANF-88-107
was superseded
by Seimens Calculation
EMF-96-172, "Palisades
Large Break LOCNECCS Analysis," Revision 0. The licensee Initiated
DBD Change Requests 2. 01-30-R3-0519 and 2.02-27-R3-0520
to update the DBDs. * Palisades
60 Day Response:
The identified
Design Basis Document Change Request will be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Revision 4 of DBD 2.01, "Low Pressure Safety Injection
System," and Revision 4 of DBD 2.02, "High Pressure Safety Injection
System," incorporated
reference
to the most current LOCA analysis.
No further action is planned for this item. DBD 2.01, "Low Pressure Safety Injection
System," Revision 3, Section 3.3.1.3, stated that the SIRWT must maintain a minimum of 20,000 gallons at the time of a RAS to limit the radiological
consequences
of an accident.
The DBD reference
for this statement
was TAM-95-05, "Radiological
Consequences
for the Palisades
Maximum Hypothetical
Accident & Loss of Coolant Accident," Revision 0. A review of EA-TAM-95-05
indicated
that this analysis did not take credit for the 20,000 gallons at the time of RAS to limit the radiological
consequences
of an accident.
The licensee issued DBD Change Request 2.01-31-R3-0524
to update the DBD. Palisades
60 Day Response:
The identified
Design Basis Document Change Request wlll be incorporated
into the DBD by July 1, 1998. 10/1/98 Update: Revision 4 of DBD 2.01, "Low Pressure Safety Injection
System," clarifies
the SIRW tank minimum volume design requirements.
No further action is planned for this item . 43
- * * ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS The team also identified
the following
discrepancies
in other documentation:
- P&ID M-232, Sheet 2A, incorrectly
identified
L T-0383 as connected
to penetration
- 54 instead of#56. The licensee issued Document Change Request (OCR) 97-0856lo
correct the drawing.
Palisades
60 Day Response:
P&ID M-232, Sheet 2A has been reviseo to incorporate
OCR 97-0856. 10/1/98 Update: No further update necessary.
- Documents
E-33, Revision 46, and E-37, Revision 46, were not revised to reflect the installed
condi(ion
of the battery charger cabling that was rerouted by SC-89-284.
The licensee issued CR C-PAL-97-1495
to resolve this discrepancy.
Palisades
60 Day Response:
E-33, Rev 46 and E-37, Rev 46 have been revised to reflect the correct battery charger cable routing installed
by SC-89-284 . 10/1/98 Update: * No further
necessary.
- * P&ID M-209, Sheet 3 (Revision
34), incorrectly
depicted valves SV-0918 and SV-09778 as normally deenergized.
The licensee issued EAR 97-0652 to revise the drawing. * Palisades
60 Day Response:
P&ID M-209, Sheet 3, Revision 35 has been issued to depict SV-09778 as normally energized.
Further evaluation
of SV-0918 identified
that the normally deenergized
state as depicted on M-209 Sheet 3 is appropriate
per FSAR Table 9-10. 10/1/98 Update: No further update necessary.
- Vendor drawing E-12A, Sheet 39, Revision 0, indicated
that the battery discharge
characteristics
were based upon battery cell specific gravities
of 1.215 +/- 0.005. However, the batteries
were being maintained
to a criterion
of 1.215 +/- 0.010. The licensee issued EAR 97-0669 to update the drawing. Palisades
60 Day Response:
E-12 A, Sheet 39, Rev O will be updated by December 15, 1998. Refer to our response 44
ATTACHMENT
A STATUS OF ACTION PLANS TO RESOLVE DESIGN INSPECTION
OPEN ITEMS to Inspector
Followup Item 50-255/97-201-28.
10/1/98 Update: This item is on target for completion
by December 15, 1998. These documentation
discrepancies
were not consistent
with 1 O CFR Part 50, Appendix B, Criterion
Ill, "Design Control," which requires that the design basis be correctly
translated
into drawings.
The team identified
this item as Unresolved
Item 50-255197-201-31.
The programmatic
design control aspects related to this issue will be addressed
as identified
in Attachment
B, Item 1. 'i 45
* * ATTACHMENT
B CONSUMERS
ENERGY COMPANY PALISADES
PLANT DOCKET 50-255 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE 6 Pages
- * ATTACHMENT
8 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE Per NRC correspondence
dated May 18, 1998, titled "NRC INSPECTION
REPORT 50-255/98003 (DRS) AND NOTICE OF VIOLATION", inspection
item 50-255/98003-01
was identified
as open. As stated in the report, this item
will remain open
pending NRC review of the results of the collective
significance
of individual
inspection
items and planned programmatic
improvements.
The following
summarizes
of our programmatic
improvements.
1. DESIGN CONTROL ISSUES: The following
issues were identified
in the Design Inspection
report as potentially
not meeting requirements
of 10 CFR 50, Appendix B, Criterion
Ill, "Design Control." Our design control program provides assurance
that the plant as-built configuration
conforms to design requirements, and the configuration
is operated, tested and maintained
within required design parameters.
The deficiencies
identified
during the Design Inspection
relate to these design control program objectives.
Design Objective
For Operating
Systems Within Design Parameters:
- Loss-Of-Coolant
Accident analysis identified
the maximum CCW temperature
of 184°F yet the effects of this temperature
on CCW system components
was not performed. (Unresolved
Item 50-255/97-201-02.)
- Incomplete
analysis (inadequate
justification
for conclusion
and incorrect
references
to related NRC correspondence)
for CCW piping for High Energy Line Break. (Unresolved
Item 50-255/97-201-04.)
- Some AC Load calculations
have not been updated to reflect current design. (Unresolved
Item 50-255/97-201-14.)
Design Objective
For As-Built Conditions
Conforming
To Design Requirements:
- * * Unscreened
Emergency
Core Cooling System Suction piping vent. (Unresolved
Item 50-255/97-201-10.)
Some instrument
tubing is not sloped consistent
with design requirements . (Unresolved
Item 50-255/97-201-13.)
Design Basis Document I design documentation
discrepancies. (Unresolved
Item 50-255/97-201-31.)
1
- ATTACHMENT
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE Palisades
60 Day Response:
Elements comprising
and supporting
our.design
control program consist of our calculation
control program, instrument
setpoint program, FSAR verification
and validation (V&V), design basis documents (DBDs) with associated
safety system design confirmations, and as-built confirmation
through drawing review or field walkdown.
These elements will be revised as appropriate
by December 15, 1998 to prevent the recurrence
of conditions
similar to those identified
in the Design Inspection
and cited above. Resolution
of any nonconforming
conditions
identified
will be implemented
through our corrective
action program. 10/1/98 Update: Programs exist at Palisades
that ensure proper station design attributes
are considered, evaluated, changed and documented.
These programs makeup our overall "Design Control" program. In past months, several programs have been reviewed in various inspections
and routine assessments
such as: * NRC INFORMATION
NOTICE 98-22:"DEFICIENCIES
IDENTIFIED
DURING NRC DESIGN INSPECTIONS" was evaluated
by comparing
the adequacy of our program design controls against other station Design Inspection
identified
concerns.
- Self assessments
were performed
in areas such as design document control and modification
programs.
- NRC inspections
and internal NPAD audits in the areas of Engineering
and Technical
Support were performed
in mid 1998 that evaluated
several Palisades
design and configuration
program attributes.
As a result of these and other efforts, "Design Control" Program enhancements
have been identified
and incorporated
into the appropriate
programs.
For example, several changes have been made to design change processes
to better define the applicability
of each distinct process, and to ensure that design change inpuUoutput
requirements
are adequately
addressed.
2
- ATTACHMENT
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE No major programmatic
weaknesses
were identified
in these reviews and program enhancements
are now complete.
To conclude, the Palisades "Design Control" Program is considered
effective.
2. CALCULATION
CONTROL ISSUES: The Design Inspection
issues identified
below reflect weaknesses
in our calculation
control program. Improvements
in our calculation
control program will serve to prevent recurrence
of these conditions.
Inspection
Report Issues: * Required justification
for conclusion
and correct references
to related NRC correspondence
not provided in analysis. (Unresolved
Item 50-255/97-201-04.)
- Not all analyses revised whenever analytical
inputs or major assumptions
change. (Unresolved
Item 50-255/97-201-07.)
- Analyses not reflecting
accurate as-built configuration
and system operation, not all interdependent
analyses have been revised together in response to changes, and analytical
design bases do nofagreewith
test acceptance
criteria. (Unresolved
Item 50-255/97-201-08.)
Palisades
60 Day Response:
Prior to the Design Inspection, calculation
control weaknesses
were recognized
and an improvement
plan was implemented.
Over 19,000 calculations
have .been indexed to provide for improved retrievability.
A cross-index
between selected calculations
of record and the documents
that use the results of the calculations
is being developed.
These and other improvements
to our calculation
program serving to prevent recurrence
of the deficiencies
cited above will be made by December 15, 1998. 10/1/98 Update: The identification
of calculations
referenced
in the major design documents
has been completed.
The Calculation
Control Improvement
Project is on target for 3
- * * ATTACHMENT
8 STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE completion
of the detailed calculation
cross-index
by December 15, 1998. Development
of the computerized
calculation
retrieval
application
and completion
of associated
engineer training will follow in early 1999. 3. SETPOINT CONTROL ISSUES: Station procedures
and guidance to require the use of established
uncertainty
methodology
need to be implemented.
The plan for implementation
should be validated
against weaknesses
identified
in* Unresolved
Item 50-255/97-201-12.
Palisades
60 Day Response:
An instrument
uncertainty
evaluation
methodology
manual has been developed.
Uncertainty
calculations
for Reactor Protection
System and Engineered
Safety Features Actuation
System setpoints
have been performed
Ul?ing .the methodology
manual. Incorporation
of instrument
uncertainty
evaluation
requirements
in procedures, and training select engineers
to perform uncertainty
calculations, will be completed
by December 15, 1998. 10/1/98 Update: As stated in Inspector
Follow-up
Item 50-255/97201-12, station procedures
have been revised to consider use of established
instrument
uncertainty
guidance when developing
test acceptance
criteria and determining
errors for operating
instrument
loops. In addition, a self assessment
of the Setpoint Control Process was performed
with potential
areas for improvement
being evaluated.
4. 10 CFR 50.54(F} RESPONSE:
Evaluate inspection
findings, both specific and programmatic, against the Palisades
response to NRC's October 9, 1996 request for information
pursuant to 1 O CFR 50.54(f) regarding
adequacy and availability
of design bases information.
Palisades
60 Day Response:
After review of the inspection
findings and comparison
to our response to the 1 O CFR 50.54(f) letter regarding
the adequacy and availability
of design basis .4
.. * ATTACHMENT
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE information, we have determined
that our response to the 10 CFR 50.54 (f) letter remains complete and accurate.
Improvements
to our design programs, initiated
through our response, will be directly responsible
for resolution
of issues * identified
within the Design Inspection
report. The programs and projects being improved include our Calculation
Control Program, Setpoint Methodology
and Control Program, FSAR Verification
and. Validation
Project, and our Fuse Control Program. * Beyond programmatic
improvements, design basis knowledge
will be further enhanced by the development
of 1 O additional
DB Os and the performance
of. three safety system design confirmations
similar to the NRC's safety system functional
inspections.
To date, four of the new DBDs have been issued and one design confirmation
has been completed.
No additional
programmatic
improvement
efforts have initiated
as a result of actions being taken
to satisfy our 10 CFR 50.54(f) response.
A final review of the adequacy of our response will be completed
by December 15, 1998. 10/1/98 Update: Some of the initiatives
noted in our 60-day response to the Des_ign Inspection
were not part of Palisades
formal response to the NRC's October 9, 1996 request for information
pursuant to 10 CFR 50.54(f) regarding
adequacy and availability
of design bases information.
Our February 6, 1997, 50.54(f) response coneluded
that the Palisades'
design bases information
was adequate, and reasonabie
assurance
exists that: 1) design bases information
has been translated
into operating, maintenance, and testing procedures, and 2) system, structures, and component
configuration
and performance
are consistent
with the design bases. Our 50.54(f) response also referred to specific initiatives
to further strengthen
plant processes
and design basis documentation.
Specifically
noted as * commitments
in the 50.54(f) response were: 1) performing
an FSAR Verification
Project, 2) completing
ten new Design Basis Documents, 3) conducting
one Safety System Functional
Type inspection
per fuel cycle, and 4) updating and re-instituting
use of a Quality Assurance
Requirements
Matrix database.
Other initiatives
to strengthen
plant processes
and design basis documentation
were also undertaken
that were not specifically
included ln the 50.54(f) response 5
- ATTACHMENT
B STATUS OF PLANS TO RESOLVE RELATED PROGRAMMATIC
ISSUES AND EVALUATE FINDINGS AGAINST THE 10 CFR 50.54(f) RESPONSE such as: 1) implementing
a calculation
control improvement
project, 2) implementing
improvements
in instrument
setpoint uncertainty
methodology, 3) performing
an assessment
of instrument
setpoint control, and 4) performing
an assessment
of the fuse control program. The 50.54(f) response remains complete and accurate.
The response to Attachment
B Item 1 relates to and supports this position.
It should be noted, however, that the 50.54(f) response and its committed
programmatic
initiatives, along with other initiatives
noted above, will not resolve all issues identified
within the Design Inspection
since it is more effective
to resolve certain issues on an individual,
basis. A formal review that evaluates
the Design Inspection
findings against the 50.54(f) response is on target for completion
by December 15, 1998. 6