ML13226A260: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 5: Line 5:
| author name = Boska J
| author name = Boska J
| author affiliation = NRC/NRR/DORL
| author affiliation = NRC/NRR/DORL
| addressee name = Spink T E
| addressee name = Spink T
| addressee affiliation = Tennessee Valley Authority
| addressee affiliation = Tennessee Valley Authority
| docket = 05000269, 05000270, 05000287
| docket = 05000269, 05000270, 05000287
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Boska, John From: Boska, John Sent: Monday, March 25, 2013 8:10 AM To: Spink, Thomas E  
{{#Wiki_filter:Boska, John From:                           Boska, John Sent:                           Monday, March 25, 2013 8:10 AM To:                             Spink, Thomas E


==Subject:==
==Subject:==
RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROUNAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 Attachments:
RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROUNAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 Attachments:                     2013-03-25 Oconee slides on flood hazard report.pdf Attached are the slides, John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: john.boska(,nrc.qov From: Boska, John Sent: Thursday, March 21, 2013 7:37 AM To: 'Spink, Thomas E'
2013-03-25 Oconee slides on flood hazard report.pdf Attached are the slides, John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: john.boska(,nrc.qov From: Boska, John Sent: Thursday, March 21, 2013 7:37 AM To: 'Spink, Thomas E'


==Subject:==
==Subject:==
RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 At 2 pm on 3/25/13, call 888-469-5869, enter code (D)(6) nd press the # button. During the meeting we ask that you don't allow your background noise on to the line, which is shared by everyone who is calling in.If your phone has a mute button you can use that. Otherwise, use the built in mute feature of our phone system. Press *6 to mute your phone, and *6 again to unmute if you decide to ask a question during the public question period. If your phone system plays music when you put a call on hold, please do not put this call on hold.John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: iohn.boska(,nrc.gov From: Spink, Thomas E [maitto:tesoink)tva.aov1 Sent: Thursday, March 21, 2013 7:32 AM To: Boska, John  
RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 At 2 pm on 3/25/13, call 888-469-5869, enter code (D)(6)     nd press the # button. During the meeting we ask that you don't allow your background noise on to the po*n--e line, which is shared by everyone who is calling in.
If your phone has a mute button you can use that. Otherwise, use the built in mute feature of our phone system. Press *6 to mute your phone, and *6 again to unmute ifyou decide to ask a question during the public question period. If your phone system plays music when you put a call on hold, please do not put this call on hold.
John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: iohn.boska(,nrc.gov From: Spink, Thomas E [maitto:tesoink)tva.aov1 Sent: Thursday, March 21, 2013 7:32 AM To: Boska, John


==Subject:==
==Subject:==
FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 John, Can you please provide me with the call in # and pass code?Thank you C---'
FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3
Senior Program Manager, WBN2 Licensing Nuclear Construction Cell: (b)(6)2}}
: John, Can you please provide me with the call in # and pass code?
Thank you C---'
 
Senior Program Manager, WBN2 Licensing Nuclear Construction Cell: (b)(6) 2}}

Latest revision as of 15:45, 4 November 2019

E-mail from J. Boska, NRR to T. Spink, TVA on Forthcoming Meeting with Duke Energy Carolinas, LLC, to Discuss Response to NRC Request for Information for a Flooding Hazard Reevaluation for the Oconee Nuclear Station, Units 1, 2, and 3
ML13226A260
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 03/25/2013
From: Boska J
Division of Operating Reactor Licensing
To: Spink T
Tennessee Valley Authority
References
FOIA/PA-2013-0264
Download: ML13226A260 (2)


Text

Boska, John From: Boska, John Sent: Monday, March 25, 2013 8:10 AM To: Spink, Thomas E

Subject:

RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROUNAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 Attachments: 2013-03-25 Oconee slides on flood hazard report.pdf Attached are the slides, John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: john.boska(,nrc.qov From: Boska, John Sent: Thursday, March 21, 2013 7:37 AM To: 'Spink, Thomas E'

Subject:

RE: FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 At 2 pm on 3/25/13, call 888-469-5869, enter code (D)(6) nd press the # button. During the meeting we ask that you don't allow your background noise on to the po*n--e line, which is shared by everyone who is calling in.

If your phone has a mute button you can use that. Otherwise, use the built in mute feature of our phone system. Press *6 to mute your phone, and *6 again to unmute ifyou decide to ask a question during the public question period. If your phone system plays music when you put a call on hold, please do not put this call on hold.

John Boska Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 301-415-2901 email: iohn.boska(,nrc.gov From: Spink, Thomas E [maitto:tesoink)tva.aov1 Sent: Thursday, March 21, 2013 7:32 AM To: Boska, John

Subject:

FORTHCOMING MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS RESPONSE TO NRC REQUEST FOR INFORMATION FOR A FLOODING HAZARD REEVALUATION FOR THE OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3

John, Can you please provide me with the call in # and pass code?

Thank you C---'

Senior Program Manager, WBN2 Licensing Nuclear Construction Cell: (b)(6) 2