| title = Robinson RAI Regarding NTTF 2.1 - Flooding
| title = RAI Regarding NTTF 2.1 - Flooding
| author name = Uribe J F
| author name = Uribe J
| author affiliation = NRC/NRR/JLD
| author affiliation = NRC/NRR/JLD
| addressee name = Guill P F, Maysam A
| addressee name = Guill P, Maysam A
| addressee affiliation = Duke Energy Corp
| addressee affiliation = Duke Energy Corp
| docket = 05000261
| docket = 05000261
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:From:Uribe, JuanTo:"Maysam, Al"; Paul.Guill@duke-energy.com
{{#Wiki_filter:From:               Uribe, Juan To:                 "Maysam, Al"; Paul.Guill@duke-energy.com


==Subject:==
==Subject:==
Robinson RAI regarding NTTF 2.1-FloodingDate:Monday, December 14, 2015 9:52:00 AMAl, Paul: As previously discussed, here is the info need that will be docketed as an RAI as part of the review.Please reference this email as the source in the response letter.
Robinson RAI regarding NTTF 2.1-Flooding Date:               Monday, December 14, 2015 9:52:00 AM Al, Paul:
Thanks Robinson Info Needs-12/14/2015 1.       Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staff's review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, "Using HEC-RAS for Dam Break Studies," August 2014, p.9) states that "the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam.Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation. JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809   l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission Please consider the environment before printing this e-mail From:Uribe, JuanTo:"Maysam, Al"; Paul.Guill@duke-energy.com
As previously discussed, here is the info need that will be docketed as an RAI as part of the review.
Please reference this email as the source in the response letter.
Thanks Robinson Info Needs-12/14/2015
: 1. Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staffs review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, Using HEC-RAS for Dam Break Studies, August 2014, p.9) states that the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam. Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation.
JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809 l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission P Please consider the environment before printing this e-mail
 
From:               Uribe, Juan To:                 "Maysam, Al"; Paul.Guill@duke-energy.com


==Subject:==
==Subject:==
Robinson RAI regarding NTTF 2.1-FloodingDate:Monday, December 14, 2015 9:52:00 AMAl, Paul: As previously discussed, here is the info need that will be docketed as an RAI as part of the review.Please reference this email as the source in the response letter.
Robinson RAI regarding NTTF 2.1-Flooding Date:               Monday, December 14, 2015 9:52:00 AM Al, Paul:
Thanks Robinson Info Needs-12/14/2015 1.       Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staff's review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, "Using HEC-RAS for Dam Break Studies," August 2014, p.9) states that "the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam.Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation. JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809   l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission Please consider the environment before printing this e-mail}}
As previously discussed, here is the info need that will be docketed as an RAI as part of the review.
Please reference this email as the source in the response letter.
Thanks Robinson Info Needs-12/14/2015
: 1. Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staffs review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, Using HEC-RAS for Dam Break Studies, August 2014, p.9) states that the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam. Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation.
JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809 l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission P Please consider the environment before printing this e-mail}}

Latest revision as of 03:21, 31 October 2019

RAI Regarding NTTF 2.1 - Flooding
ML15348A340
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/14/2015
From: Juan Uribe
Japan Lessons-Learned Division
To: Guill P, Maysam A
Duke Energy Corp
Uribe, Juan NRR/JLD 415-3809
References
Download: ML15348A340 (1)


Text

From: Uribe, Juan To: "Maysam, Al"; Paul.Guill@duke-energy.com

Subject:

Robinson RAI regarding NTTF 2.1-Flooding Date: Monday, December 14, 2015 9:52:00 AM Al, Paul:

As previously discussed, here is the info need that will be docketed as an RAI as part of the review.

Please reference this email as the source in the response letter.

Thanks Robinson Info Needs-12/14/2015

1. Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staffs review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, Using HEC-RAS for Dam Break Studies, August 2014, p.9) states that the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam. Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation.

JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809 l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission P Please consider the environment before printing this e-mail

From: Uribe, Juan To: "Maysam, Al"; Paul.Guill@duke-energy.com

Subject:

Robinson RAI regarding NTTF 2.1-Flooding Date: Monday, December 14, 2015 9:52:00 AM Al, Paul:

As previously discussed, here is the info need that will be docketed as an RAI as part of the review.

Please reference this email as the source in the response letter.

Thanks Robinson Info Needs-12/14/2015

1. Starting Water Level for the Robinson Dam Overtopping Failure in HEC-RAS: NRC staffs review of the HEC-RAS dam failure file revealed that the breach starting elevation is set to the top of the embankment elevation of 229.075 ft NAVD88. However, this assumption does not consider the time needed to erode the downstream face of the dam and is also not supported by the NWS BREACH model output data. USACE Guide (TD-39, Using HEC-RAS for Dam Break Studies, August 2014, p.9) states that the HEC-RAS breach start time is considered to be when the erosion process has mitigated to the upstream face of the dam. Provide additional information that justifies selecting a breach starting elevation set to the top of the embankment elevation.

JUAN F. URIBE PROJECT MANAGER NRR/JLD/JHMB 301-415-3809 l O-13F10 l Juan.Uribe@nrc.gov U.S. Nuclear Regulatory Commission P Please consider the environment before printing this e-mail