ML18066A703: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML18066A703 | | number = ML18066A703 | ||
| issue date = 03/07/2018 | | issue date = 03/07/2018 | ||
| title = | | title = Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for Information | ||
| author name = Farnholtz T | | author name = Farnholtz T | ||
| author affiliation = NRC/RGN-IV/DRS/EB-1 | | author affiliation = NRC/RGN-IV/DRS/EB-1 | ||
| addressee name = Bement R | | addressee name = Bement R | ||
| addressee affiliation = Arizona Public Service Co | | addressee affiliation = Arizona Public Service Co | ||
| docket = 05000528, 05000529, 05000530 | | docket = 05000528, 05000529, 05000530 | ||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:March 7, 2018 | ||
Mr. Robert S. Bement | |||
Executive Vice President Nuclear/ | |||
Chief Nuclear Officer | |||
Executive Vice President Nuclear/ | Arizona Public Service Company | ||
Chief Nuclear Officer | P.O. Box 52034, MS 7602 | ||
Arizona Public Service Company P.O. Box 52034, MS 7602 Phoenix, AZ | Phoenix, AZ 85072-2034 | ||
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF NRC | |||
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) | DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) | ||
05000528/2018011, 05000529/2018011, AND 05000530/2018011 INITIAL REQUEST FOR INFORMATION | 05000528/2018011, 05000529/2018011, AND 05000530/2018011 INITIAL | ||
Dear Mr. Bement: | REQUEST FOR INFORMATION | ||
On April 24, 2018, the NRC will begin an inspection at the Palo Verde Nuclear Generating Station. | Dear Mr. Bement: | ||
On April 24, 2018, the NRC will begin an inspection at the Palo Verde Nuclear Generating | |||
This inspection will evaluate the implementation of the environmental qualification of electrical equipment program, as required by the Palo Verde Nuclear Generating Station Operating License. | Station. A three-person team will perform this inspection using NRC Inspection | ||
documentation files to verify that electrical equipment important to safety meets the requirements of 10 CFR 50.49. | Procedure 71111.21N, Design Bases Inspection (Programs), Attachment 1, Environmental | ||
environments and required mitigate the consequences of a design basis accident. | Qualification under 10 CFR 50.49 Programs, Processes, and Procedures. | ||
This inspection will evaluate the implementation of the environmental qualification of electrical | |||
equipment program, as required by the Palo Verde Nuclear Generating Station Operating | |||
The purpose of the information gathering visit is to meet with members of your staff to become familiar with the Palo Verde Nuclear Generating Station environmental qualification program. | License. Additionally, the team will perform an inspection of the equipment qualification | ||
which the site is committed. | documentation files to verify that electrical equipment important to safety meets the | ||
inspection will be identified during the inspection, including interviews with engineering | requirements of 10 CFR 50.49. The team will select components that will be subjected to harsh | ||
managers and engineers. | environments and required mitigate the consequences of a design basis accident. | ||
The inspection will include an information gathering site visit by the team leader and risk | |||
analyst, and two weeks of on-site inspection by the team. The inspection will consist of three | |||
NRC inspectors. The current inspection schedule is as follows: | |||
On-site Information Gathering Visit: April 24-26, 2018 | |||
Preparation Weeks: April 30-May 4 and May 14-18, 2018 | |||
On-site Weeks: May 7-11 and May 21-25, 2018 | |||
The purpose of the information gathering visit is to meet with members of your staff to become | |||
familiar with the Palo Verde Nuclear Generating Station environmental qualification program. | |||
The lead inspector will request a meeting with your personnel to discuss the site environmental | |||
qualification program and procedures. Additionally, the lead inspector will request a discussion | |||
with your staff to become familiar with the equipment qualification regulations and standards to | |||
which the site is committed. Additional information and documentation needed to support the | |||
inspection will be identified during the inspection, including interviews with engineering | |||
managers and engineers. | |||
R. Bement 2 | |||
Our experience with these inspections has shown that they are resource intensive, both for the | |||
NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site | |||
and to ensure a productive inspection, we have enclosed a request for information needed for | |||
the inspection. This information should be made available to the lead inspector on or before the | |||
April 24, 2018, visit. Since the inspection will be concentrated on the environmental qualification | |||
of the equipment, the equipment qualification master list should be available to review during | |||
the information gathering visit to assist in our selection of components. | |||
It is requested that this information be provided to the lead inspector as the information is | |||
generated during the inspection. Additional requests by inspectors will be made during the | |||
on-site week for specific documents needed to complete the review of that component/selection. | |||
It is important that all of these documents are up-to-date and complete in order to minimize the | |||
number of additional documents requested during the preparation and/or the on-site portions of | |||
the inspection. In order to facilitate the inspection, we request that a contact individual be | |||
assigned to each inspector to ensure information requests, questions, and concerns are | |||
addressed in a timely manner. | |||
The lead inspector for this inspection is Wayne Sifre. We understand that our licensing | |||
engineer contact for this inspection is Sean Dornseif. If there are any questions about the | |||
inspection or the requested materials, please contact the lead inspector by telephone at | |||
817-200-1193 or by e-mail at Wayne.Sifre@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject | |||
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | |||
collection requirements were approved by the Office of Management and Budget, control | |||
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to | |||
respond to, a request for information or an information collection requirement unless the | |||
requesting document displays a currently valid Office of Management and Budget control | |||
number. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of | |||
this letter will be made available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRCs document system | |||
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Thomas R. Farnholtz, Chief | |||
Engineering Branch 1 | |||
Division of Reactor Safety | |||
Docket Nos. 50-528, 50-529, and 50-530 | |||
License Nos. NPF-41, NPF-51, and NPF-74 | |||
Enclosure: Initial Request for Information | |||
cc: Electronic Distribution | |||
ML18066A703 | |||
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: | |||
By: WSifre Yes No Publicly Available Sensitive NRC-002 | |||
OFFICE RI:EB1 C;PBD C:EB1 | |||
NAME WSifre GMiller TFarnholtz | |||
SIGNATURE /RA/ /RA/ /RA/ | |||
DATE 3/7/18 3/7/18 3/7/18 | |||
Initial Request for Information | |||
Design Bases Inspection (Programs), Environmental Qualification | |||
Palo Verde Nuclear Generating Station | |||
Inspection Report: 05000528/2018011, 05000529/2018011, | |||
050005302018011 | |||
Information Gathering Dates: April 24-26, 2018 | |||
Inspection Dates: May 7-11, 2018, May 21-25, 2018 | |||
Inspection Procedure: IP 71111, Attachment 21N, Design Bases Inspection | |||
(Programs) | |||
Lead Inspector: Wayne C. Sifre, Senior Reactor Inspector | |||
I. Information Requested for Information Gathering Visit (April 24, 2018) | |||
The following information should be provided to the lead inspector in hard copy or | |||
electronic format (Certrec IMS preferred), to the attention of Wayne Sifre by April 23, | |||
2018, to facilitate the reduction in the items to be selected for a final list of components. | |||
The inspection team will finalize the selected list during the prep week using the | |||
documents requested in this enclosure. The specific items selected from the lists shall | |||
be available and ready for review on the day indicated in this request. *Please provide | |||
requested documentation electronically in pdf files, Excel, or other searchable formats, | |||
if possible. The information should contain descriptive names, and be indexed and | |||
hyperlinked to facilitate ease of use. Information in "lists" should contain enough | |||
information to be easily understood by someone who has knowledge of pressurized | |||
water reactor technology. If requested documents are large and only hard copy formats | |||
are available, please inform the inspector(s), and provide subject documentation during | |||
the first day of the on-site inspection. | |||
1. List of components that are in the equipment qualification master list. If plant is | |||
approved to categorize structures, systems, and component in accordance with | |||
10 CFR 50.69, please provide the Risk Informed Safety Category of the component. | |||
2. Listing of the equipment qualification master list components sorted by Birnbaum risk | |||
importance. | |||
3. List of all post-accident monitoring instrumentation components and locations. | |||
4. Documents which show the environmental service conditions expected for areas in | |||
which the equipment qualification components are located. | |||
5. Palo Verde Nuclear Generating Station, word-searchable Updated Final Safety | |||
Analysis Report (UFSAR), License Conditions, and Technical Specifications. | |||
Specifically, identify which UFSAR sections address environmental (including | |||
seismic) qualification, seismic. | |||
Enclosure | |||
6. NRC safety evaluation report(s) associated with Palo Verde Nuclear Generating | |||
Station environmental qualification program. | |||
7. Identify the various environmental qualification standards (including year, edition, or | |||
revision) that Palo Verde Nuclear Generating Station is committed. | |||
8. Identify whether Palo Verde Nuclear Generating Station has entered its period of | |||
extended operation (i.e., operation past the original 40-year license period). | |||
9. Site (and corporate if applicable) procedures associated with the 10 CFR 50.49 | |||
environmental qualification program for electrical components. Additionally, please | |||
provide similar procedures used to verify mechanical components meet their | |||
10 CFR Part 50, Appendix A, Criterion 4, Environmental and Dynamic Effects | |||
Design Bases. Include procedures for procurement of qualified equipment, | |||
maintenance of qualified equipment, and modification to qualified equipment | |||
(including equivalency or commercial grade dedication programs). | |||
10. Site high energy line break analyses, including associated plant area drawings. | |||
11. Procedures for material storage and shelf life controls. | |||
12. List of commercial grade dedication evaluations performed, for which the dedicated | |||
parts have been issued for installation on equipment qualification applications in the | |||
plant, for the previous five years. Include description of the component the part was | |||
issued to repair, work order, and date issued or installed. | |||
13. List of condition reports related to the equipment qualification program or | |||
environmental qualification of components (both electrical and mechanical) for the | |||
previous 5 years. | |||
14. Lists of modifications, repairs, or replacement of equipment qualification master list | |||
components completed for the previous 5 years. | |||
15. List of modifications, repairs, or replacements of containment penetrations for the | |||
previous 5 years. | |||
16. List of components removed from the environmental qualification program since | |||
beginning of operation. | |||
17. Any self-assessments and quality assurance assessments of the environmental | |||
qualification program performed in the previous 5 years. | |||
18. List of systems, system numbers/designators, and corresponding names. | |||
2 | |||
II. Discussions Requested | |||
1. Interview with representative to discuss site environmental qualification service | |||
condition analyses for plant areas, including plant drawings and assumptions. This | |||
includes analysis for areas that are subject to high energy line breaks (HELB). | |||
2. Interview with representative to discuss environmental qualification mandated | |||
maintenance elements are integrated into plant programs and procedures. | |||
3. Interview with representative to discuss maintaining qualification for plant/equipment | |||
that entered its period of extended operation, if applicable. | |||
III. Information Requested for Inspection Preparation (April 30, 2018) | |||
1. Equipment qualification documentation files, including test reports, for the electrical | |||
components selected by the lead inspector listed on the equipment qualification | |||
master list. | |||
2. References associated with the electrical components equipment qualification | |||
document files. | |||
3. Vendor manuals and technical sheets associated with the selected electrical | |||
components. | |||
4. Tours of the rooms in which the selected electrical components are installed. | |||
5. Tour of stored selected electrical components in the warehouse. | |||
Inspector Contact Information: | |||
Wayne C. Sifre Jim Drake Wes Cullum | |||
Senior Reactor Inspector Senior Reactor Inspector Reactor Inspector | |||
817-200-1193 817-200-1558 817-200-1563 | |||
Wayne.Sifre@nrc.gov James.Drake@nrc.gov Wes.Cullum@nrc.gov | |||
Mailing Address: | |||
U.S. NRC, Region IV | |||
Attn: Wayne C. Sifre | |||
1600 East Lamar Blvd. | |||
Arlington, TX 76011-4511 | |||
3 | |||
}} | }} |
Latest revision as of 17:42, 21 October 2019
ML18066A703 | |
Person / Time | |
---|---|
Site: | Palo Verde ![]() |
Issue date: | 03/07/2018 |
From: | Thomas Farnholtz Region 4 Engineering Branch 1 |
To: | Bement R Arizona Public Service Co |
References | |
IR 2018011 | |
Download: ML18066A703 (6) | |
See also: IR 05000528/2018011
Text
March 7, 2018
Mr. Robert S. Bement
Executive Vice President Nuclear/
Chief Nuclear Officer
Arizona Public Service Company
P.O. Box 52034, MS 7602
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF NRC
DESIGN BASES ASSURANCE INSPECTION (PROGRAMS)
05000528/2018011, 05000529/2018011, AND 05000530/2018011 INITIAL
REQUEST FOR INFORMATION
Dear Mr. Bement:
On April 24, 2018, the NRC will begin an inspection at the Palo Verde Nuclear Generating
Station. A three-person team will perform this inspection using NRC Inspection
Procedure 71111.21N, Design Bases Inspection (Programs), Attachment 1, Environmental
Qualification under 10 CFR 50.49 Programs, Processes, and Procedures.
This inspection will evaluate the implementation of the environmental qualification of electrical
equipment program, as required by the Palo Verde Nuclear Generating Station Operating
License. Additionally, the team will perform an inspection of the equipment qualification
documentation files to verify that electrical equipment important to safety meets the
requirements of 10 CFR 50.49. The team will select components that will be subjected to harsh
environments and required mitigate the consequences of a design basis accident.
The inspection will include an information gathering site visit by the team leader and risk
analyst, and two weeks of on-site inspection by the team. The inspection will consist of three
NRC inspectors. The current inspection schedule is as follows:
On-site Information Gathering Visit: April 24-26, 2018
Preparation Weeks: April 30-May 4 and May 14-18, 2018
On-site Weeks: May 7-11 and May 21-25, 2018
The purpose of the information gathering visit is to meet with members of your staff to become
familiar with the Palo Verde Nuclear Generating Station environmental qualification program.
The lead inspector will request a meeting with your personnel to discuss the site environmental
qualification program and procedures. Additionally, the lead inspector will request a discussion
with your staff to become familiar with the equipment qualification regulations and standards to
which the site is committed. Additional information and documentation needed to support the
inspection will be identified during the inspection, including interviews with engineering
managers and engineers.
R. Bement 2
Our experience with these inspections has shown that they are resource intensive, both for the
NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site
and to ensure a productive inspection, we have enclosed a request for information needed for
the inspection. This information should be made available to the lead inspector on or before the
April 24, 2018, visit. Since the inspection will be concentrated on the environmental qualification
of the equipment, the equipment qualification master list should be available to review during
the information gathering visit to assist in our selection of components.
It is requested that this information be provided to the lead inspector as the information is
generated during the inspection. Additional requests by inspectors will be made during the
on-site week for specific documents needed to complete the review of that component/selection.
It is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the on-site portions of
the inspection. In order to facilitate the inspection, we request that a contact individual be
assigned to each inspector to ensure information requests, questions, and concerns are
addressed in a timely manner.
The lead inspector for this inspection is Wayne Sifre. We understand that our licensing
engineer contact for this inspection is Sean Dornseif. If there are any questions about the
inspection or the requested materials, please contact the lead inspector by telephone at
817-200-1193 or by e-mail at Wayne.Sifre@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of
this letter will be made available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-528, 50-529, and 50-530
License Nos. NPF-41, NPF-51, and NPF-74
Enclosure: Initial Request for Information
cc: Electronic Distribution
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: WSifre Yes No Publicly Available Sensitive NRC-002
OFFICE RI:EB1 C;PBD C:EB1
NAME WSifre GMiller TFarnholtz
SIGNATURE /RA/ /RA/ /RA/
DATE 3/7/18 3/7/18 3/7/18
Initial Request for Information
Design Bases Inspection (Programs), Environmental Qualification
Palo Verde Nuclear Generating Station
Inspection Report: 05000528/2018011, 05000529/2018011,
050005302018011
Information Gathering Dates: April 24-26, 2018
Inspection Dates: May 7-11, 2018, May 21-25, 2018
Inspection Procedure: IP 71111, Attachment 21N, Design Bases Inspection
(Programs)
Lead Inspector: Wayne C. Sifre, Senior Reactor Inspector
I. Information Requested for Information Gathering Visit (April 24, 2018)
The following information should be provided to the lead inspector in hard copy or
electronic format (Certrec IMS preferred), to the attention of Wayne Sifre by April 23,
2018, to facilitate the reduction in the items to be selected for a final list of components.
The inspection team will finalize the selected list during the prep week using the
documents requested in this enclosure. The specific items selected from the lists shall
be available and ready for review on the day indicated in this request. *Please provide
requested documentation electronically in pdf files, Excel, or other searchable formats,
if possible. The information should contain descriptive names, and be indexed and
hyperlinked to facilitate ease of use. Information in "lists" should contain enough
information to be easily understood by someone who has knowledge of pressurized
water reactor technology. If requested documents are large and only hard copy formats
are available, please inform the inspector(s), and provide subject documentation during
the first day of the on-site inspection.
1. List of components that are in the equipment qualification master list. If plant is
approved to categorize structures, systems, and component in accordance with
10 CFR 50.69, please provide the Risk Informed Safety Category of the component.
2. Listing of the equipment qualification master list components sorted by Birnbaum risk
importance.
3. List of all post-accident monitoring instrumentation components and locations.
4. Documents which show the environmental service conditions expected for areas in
which the equipment qualification components are located.
5. Palo Verde Nuclear Generating Station, word-searchable Updated Final Safety
Analysis Report (UFSAR), License Conditions, and Technical Specifications.
Specifically, identify which UFSAR sections address environmental (including
seismic) qualification, seismic.
Enclosure
6. NRC safety evaluation report(s) associated with Palo Verde Nuclear Generating
Station environmental qualification program.
7. Identify the various environmental qualification standards (including year, edition, or
revision) that Palo Verde Nuclear Generating Station is committed.
8. Identify whether Palo Verde Nuclear Generating Station has entered its period of
extended operation (i.e., operation past the original 40-year license period).
9. Site (and corporate if applicable) procedures associated with the 10 CFR 50.49
environmental qualification program for electrical components. Additionally, please
provide similar procedures used to verify mechanical components meet their
10 CFR Part 50, Appendix A, Criterion 4, Environmental and Dynamic Effects
Design Bases. Include procedures for procurement of qualified equipment,
maintenance of qualified equipment, and modification to qualified equipment
(including equivalency or commercial grade dedication programs).
10. Site high energy line break analyses, including associated plant area drawings.
11. Procedures for material storage and shelf life controls.
12. List of commercial grade dedication evaluations performed, for which the dedicated
parts have been issued for installation on equipment qualification applications in the
plant, for the previous five years. Include description of the component the part was
issued to repair, work order, and date issued or installed.
13. List of condition reports related to the equipment qualification program or
environmental qualification of components (both electrical and mechanical) for the
previous 5 years.
14. Lists of modifications, repairs, or replacement of equipment qualification master list
components completed for the previous 5 years.
15. List of modifications, repairs, or replacements of containment penetrations for the
previous 5 years.
16. List of components removed from the environmental qualification program since
beginning of operation.
17. Any self-assessments and quality assurance assessments of the environmental
qualification program performed in the previous 5 years.
18. List of systems, system numbers/designators, and corresponding names.
2
II. Discussions Requested
1. Interview with representative to discuss site environmental qualification service
condition analyses for plant areas, including plant drawings and assumptions. This
includes analysis for areas that are subject to high energy line breaks (HELB).
2. Interview with representative to discuss environmental qualification mandated
maintenance elements are integrated into plant programs and procedures.
3. Interview with representative to discuss maintaining qualification for plant/equipment
that entered its period of extended operation, if applicable.
III. Information Requested for Inspection Preparation (April 30, 2018)
1. Equipment qualification documentation files, including test reports, for the electrical
components selected by the lead inspector listed on the equipment qualification
master list.
2. References associated with the electrical components equipment qualification
document files.
3. Vendor manuals and technical sheets associated with the selected electrical
components.
4. Tours of the rooms in which the selected electrical components are installed.
5. Tour of stored selected electrical components in the warehouse.
Inspector Contact Information:
Wayne C. Sifre Jim Drake Wes Cullum
Senior Reactor Inspector Senior Reactor Inspector Reactor Inspector
817-200-1193 817-200-1558 817-200-1563
Wayne.Sifre@nrc.gov James.Drake@nrc.gov Wes.Cullum@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Wayne C. Sifre
1600 East Lamar Blvd.
Arlington, TX 76011-4511
3