| | number = ML19224A924 | | | number = ML19224A924 |
| | issue date = 08/12/2019 | | | issue date = 08/12/2019 |
| | title = 2019/08/12 Vogtle COL Docs - Discussion on 103g Stretch Goal.Pptx | | | title = COL Docs - Discussion on 103g Stretch Goal.Pptx |
| | author name = | | | author name = |
| | author affiliation = NRC | | | author affiliation = NRC |
Latest revision as of 10:13, 1 December 2019
|
---|
Category:E-Mail
MONTHYEARML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request ML23279A2082023-10-0505 October 2023 Issuance of Formal RAIs - Vogtle, Units 1 and 2 - Proposed LAR and Proposed Alternative Request to Revise TS 3.4.14.1 and IST ALT-VR-02 (EPIDs L-2023-LLA-0061 and L-2023-LLR-0023) ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time ML23270B1912023-09-27027 September 2023 COL Docs - Update Vogtle Units 3&4 Acceptance Letter for LAR-22-002 Technical Specification 3.8.3, Inverters Operating ML23263A1042023-09-20020 September 2023 COL Docs - FW Fyi for Tomorrow'S Psm Meeting ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23257A0632023-09-13013 September 2023 NRR E-mail Capture - Acceptance Review of Southern Nuclear Operating Company'S License Amendment Request to Remove Combined License Appendix C ML23256A2682023-09-13013 September 2023 COL Docs - Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23248A3482023-09-0505 September 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) 6 - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9172023-08-31031 August 2023 NRR E-mail Capture - (External_Sender) Re Question - Legal Contact(S) for Vogtle Electric Generating Plant, Units 3 & 4 ML23241A0452023-08-29029 August 2023 COL Docs - FW Draft LAR and Exemption Request Regarding Tier 1 and Tier 2 Requirements ML23229A2322023-08-17017 August 2023 COL Docs - FW Re LAR 22-002 Second Round RAI Approved ML23188A151 for Vogtle Units 3 & 4 ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23221A3982023-08-0909 August 2023 COL Docs - LAR 22-002 Second Round RAI Approved ML23188A151 ML23216A1592023-08-0404 August 2023 COL Docs - FW Acceptance Review - Requested Licensing Action Regarding TS Revision to Adopt WCAP-17661-P-A, Improved Relaxed Axial Offset Control and Constant Axial Offset Control Fq Surveillance TS (L-2022-LLA-0148 and L-2022-LLA-0149) ML23212A9642023-07-31031 July 2023 COL Docs - Action - Start of Annual Fees - Vogtle Unit 3 Completion of Power Ascension Testing and Declaration of Commercial Operations ML23216A0962023-07-26026 July 2023 Document Request for Vogtle 1 & 2 RP Inspection, Report No. 05000424/2023003 and 05000425/2023003 ML23220A0572023-07-26026 July 2023 Document Request for Vogtle Units 1 and 2 - Radiation Protection Inspection - Inspection Report 2023-03 ML23200A0112023-07-18018 July 2023 Document Request for Vogtle Unit 3 RP Inspection ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23193A7832023-07-12012 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle - TSTF-339 LAR (L-2023-LLA-0053) 2024-01-31
[Table view] |
Text
Vogtle PEmails From: Habib, Donald Sent: Monday, August 12, 2019 10:12 AM To: Vogtle PEmails
Subject:
Discussion on 103g stretch goal.pptx Attachments: Discussion on 103g stretch goal.pptx 1
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 467 Mail Envelope Properties (BL0PR0901MB2514B58AD576853B0077788A97D30)
Subject:
Discussion on 103g stretch goal.pptx Sent Date: 8/12/2019 10:11:35 AM Received Date: 8/12/2019 10:11:41 AM From: Habib, Donald Created By: Donald.Habib@nrc.gov Recipients:
"Vogtle PEmails" <Vogtle.PEmails@nrc.gov>
Tracking Status: None Post Office: BL0PR0901MB2514.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 4 8/12/2019 10:11:41 AM Discussion on 103g stretch goal.pptx 600471 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
52.103(g) Stretch Goal 1
Key Messages Provide Final Commission Memorandum to the Commission within 8 working-hours of receipt of the All ITAAC Complete Notification Issue 52.103(g) Finding within 8 working-hours following the Commissions review This stretch goal assumes that Southern Nuclear Operating Company has met all the necessary prerequisites established to support this stretch goal.
2
Existing 52.103g Office Instruction 3
52.103g Stretch Goal (Reflecting Best Case Scenario) 8 working hours after All ITAAC Complete Notification received - Send Final Memorandum to VOICES Audit (minus Commission-Make 52.103(g) outstanding ICNs)
Basis Document Public, Final VOICES check
-2 Months -6 Weeks -2 Weeks -3 Days -1 Day Day 0 +3 Days 8 working hours Start Final Concurrence following positive NRR Office Director eligible to Begin prep for final for: Finding, Basis communication make the 103(g) finding if no Commission memo package 1)
Document, FRN, Final from Commission, communication from basis doc 2) an order allowing Commission Memo, Office Director Commission after 3 days interim operation (if applicable), 3) FRN, and 4) Letter to Licensee Makes 52.103(g) letter to the licensee Finding. - Send FRN to Federal Convene final memo All ITAAC Construction Register - Send concurrence group for Inspections Complete, Letter to Licensee.
weekly coordination mark complete in meetings VOICES and CIPIMS 4
Prerequisites Ties to the All ITAAC Complete Notification
@ 14 days in advance, specify date and time for submitting the All ITAAC Complete notification
@ 14 days in advance, specific ICNs to be submitted with the All ITAAC Complete notification
@ 4 weeks in advance, SNC to confirm in real time on ICNs submitted to NRC licensing Final ICNs During the last month have daily calls with SNC regarding status updates and progress on ITAAC completion ICNs should match their UINs, otherwise SNC should submit advance draft ICNs Draft Reports SNC to provide advance draft copies of reports that are integral to ITAAC for ICNs submitted within that last 30 days SNC will have 90 day ICNs locked down by Jan 2020 5
Sept 10 Tabletop Exercise The plan for the tabletop exercise will include discussing different scenarios to identify limiting issues and offer mitigating actions.
Proposed scenarios include:
Scenario 1 - ITAAC Maintenance non-reportable example*
Scenario 2 - ITAAC Maintenance reportable example*
Scenario 3 - Green ITAAC finding in last inspections Scenario 4 - Greater than Green ITAAC finding in last inspections
- Post submittal All ITAAC Complete notification 6