L-MT-08-042, Extended Power Uprate: Acceptance Review Supplemental Information Package 5: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 06/05/2008
| issue date = 06/05/2008
| title = Extended Power Uprate: Acceptance Review Supplemental Information Package 5
| title = Extended Power Uprate: Acceptance Review Supplemental Information Package 5
| author name = O'Connor T J
| author name = O'Connor T
| author affiliation = Nuclear Management Co, LLC
| author affiliation = Nuclear Management Co, LLC
| addressee name =  
| addressee name =  
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:Montkelh Nuclear Generatina Plant EwnmltdrdtbWEtrwllones Operated by Nudear Management Company, LLC June 5,2008 L-MT-08-042 10 CFR 50.90 U. S. Nuclear Regulatory Commission ATN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License License No. DPR-22 Monticello Extended Power Uprate (USNRC TAC MD83981: Acceptance Review Supplemental lnforrnation Package 5  
{{#Wiki_filter:Montkelh Nuclear Generatina Plant EwnmltdrdtbWEtrwllones                                 Operated by Nudear Management Company, LLC June 5,2008                                                                     L-MT-08-042 10 CFR 50.90 U. S. Nuclear Regulatory Commission A T N : Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License License No. DPR-22 Monticello Extended Power Uprate (USNRC TAC MD83981:
Acceptance Review Supplemental lnforrnation Package 5


==References:==
==References:==


I) NMC Letter to USNRC, "License Amendment Request: Extended Power Uprate," dated March 31,2008 2) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAG MD8398): Acceptance Review Supplement Regarding Radiological Analysis," dated May 20,2008 3) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information," dated May 28, 2008 4) NMC Letter to USNRC, 'Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 3," dated May 30,2008 5) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 4," dated June 3,2008 Pursuant to 1 0 CFR 50.90, Nuclear Management Company, LLC (NMC), requested in Reference 1 approval of amendments to the Monticello Nuclear Generating Plant (MNGP) Renewed Operating License (OL) and Technical Specfications (TS) to increase the maximum power level authorized from 1775 megawatts thermal (MWt) to 1870 MWt, an approximate five percent increase in the current licensed thermal power (CLTP). The proposed request for Extended Power Uprate (EPU) represents an increase of approximately 12 percent above the Original Licensed Thermal Power (OLTP). The Monticello EPU application was supplemented on May 20, 2008, May 28,2008, May 30,2008, and June 3,2008 by References 2,3,4 and 5. 2807 West County Road 75 Monticello, Minnesota 563624637 Telephone:
I)NMC Letter to USNRC, "License Amendment Request: Extended Power Uprate,"
763.295.51 51 Fax: 783.295.1454 Document Control Desk Page 2 In a teleconference held May 2, 2008, the NRC staff indicated that additional information would be necessary for the Electrical Engineering Branch (EEEB) to complete the acceptance review of the Monticello EPU license amendment request (IAR). The questions were formalized and emailed to NMC on May 1 5,2008. On May 28,2008, NMC submitted responses (Reference
dated March 31,2008 2 ) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAG MD8398): Acceptance Review Supplement Regarding Radiological Analysis,"
: 3) to EEEB Questions 2,3, and 4. Enclosure 1 of this letter contains the response to EEEB Question I. NMC has reviewed the No Significant Hazards Consideration and the Environmental Consideration submitted with Reference 1 relative to the enclosed supplemental information.
dated May 20,2008
NMC has determined that there are no changes required to either of these sections of Reference
: 3) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information," dated May 28, 2008
: 1. Commitment Summan, This letter makes no new commitments and does not change any existing commitments.
: 4) NMC Letter to USNRC, 'Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 3," dated May 30,2008
I declare under penalty of perjury that the foregoing is true and correct. on June 5 A 008. resident, Monticello Nuclear Generating Plant Company, LLC cc: Administrator, Region Ill, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Minnesota Department of Commerce Enclosure 
: 5) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 4," dated June 3,2008 Pursuant to 10 CFR 50.90, Nuclear Management Company, LLC (NMC), requested in Reference 1 approval of amendments to the Monticello Nuclear Generating Plant (MNGP) Renewed Operating License (OL) and Technical Specfications (TS) to increase the maximum power level authorized from 1775 megawatts thermal (MWt) to 1870 MWt, an approximate five percent increase in the current licensed thermal power (CLTP). The proposed request for Extended Power Uprate (EPU) represents an increase of approximately 12 percent above the Original Licensed Thermal Power (OLTP). The Monticello EPU application was supplemented on May 20, 2008, May 28,2008, May 30,2008, and June 3,2008 by References 2 , 3 , 4 and 5.
2807 West County Road 75 Monticello, Minnesota 563624637 Telephone: 763.295.5151 Fax: 783.295.1454


Enclosure 1 to L-MT-08-042 Electrical Engineering Branch Question 1 and Response 1
Document Control Desk Page 2 In a teleconference held May 2, 2008, the NRC staff indicated that additional information would be necessary for the Electrical Engineering Branch (EEEB) to complete the acceptance review of the Monticello EPU license amendment request (IAR). The questions were formalized and emailed to NMC on May 15,2008. On May 28,2008, NMC submitted responses (Reference 3) to EEEB Questions 2,3,and 4. of this letter contains the response to EEEB Question I.
NMC has reviewed the No Significant Hazards Consideration and the Environmental Consideration submitted with Reference 1 relative to the enclosed supplemental information. NMC has determined that there are no changes required to either of these sections of Reference 1.
Commitment Summan, This letter makes no new commitments and does not change any existing commitments.
I declare under penalty of perjury that the foregoing is true and correct.
on June 5 A 008.
resident, Monticello Nuclear Generating Plant Company, LLC cc: Administrator, Region Ill, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Minnesota Department of Commerce Enclosure


Page 1 of 19 4) EEEB - ELECTRICAL ENGINEERING BRANCH NRC Question
Enclosure 1 to L-MT-08-042 Electrical Engineering Branch Question 1 and Response 1
: 1) In Section 2.3 of the LAR under the section titled 'Outside Containment', the licensee stated the following:
"The total integrated doses (normal plus accident) for EPU conditions were evaluated and determined not to adversely affect qualification of most of the EQ equipment located outside of containment. Equipment not qualified to the new environmental conditions at EPU will be reanalyzed, re-qualified, or replaced prior to implementation of EPU." In order for the Electrical Engineering Branch (EEEB) to start its review, the full EQ analysis must be completed. This includes any reanalysis, re-qualification, or replacement of equipment. The licensee must also describe how the equipment was evaluated (e.g., calculations, assessments, etc.) and show how the equipment remains bounded (i.e., provide the original design parameters and the updated values including the supporting calculations).


Enclosure 1
: 4) EEEB - ELECTRICAL ENGINEERING BRANCH NRC Question
: 1) In Section 2.3 of the LAR under the section titled 'Outside Containment', the licensee stated the following:
"The total integrated doses (normal plus accident) for EPU conditions were evaluated and determined not to adversely affect qualification of most of the EQ equipment located outside of containment. Equipment not qualified to the new environmental conditions at EPU will be reanalyzed, re-qualified, or replaced prior to implementation of EPU."
In order for the Electrical Engineering Branch (EEEB) to start its review, the full EQ analysis must be completed. This includes any reanalysis, re-qualification, or replacement of equipment. The licensee must also describe how the equipment was evaluated (e.g., calculations, assessments, etc.) and show how the equipment remains bounded (i.e., provide the original design parameters and the updated values including the supporting calculations).
NMC Response:
NMC Response:
The responses to EEEB Questions 2, 3 and 4 were submitted in Monticello letter L-MT-08-039 on May 28, 2008. The following response is regarding EEEB Question 1.  
The responses to EEEB Questions 2, 3 and 4 were submitted in Monticello letter L-MT-08-039 on May 28, 2008. The following response is regarding EEEB Question 1.
 
Introduction The following information provides more detail regarding the analyses that have been completed relative to the qualification of electrical equipment outside containment. As required, the analyses have addressed the radiation, pressure, temperature and flooding effects from operation at extended power uprate (EPU) conditions. This information describes how the equipment was evaluated and notes where further action, per the applicable regulatory criteria and the Monticello Environmental Qualification (EQ)
Introduction The following information provides more detail regarding the analyses that have been completed relative to the qualification of electrical equipment outside containment. As required, the analyses have addressed the radiation, pressure, temperature and flooding effects from operation at extended power uprate (EPU) conditions. This information describes how the equipment was evaluated and notes where further action, per the applicable regulatory criteria and the Monticello Environmental Qualification (EQ) Program, is necessary prior to implementation of EPU.
Program, is necessary prior to implementation of EPU.
 
Normal Temperature Evaluation An evaluation was completed to assess the impact EPU will have on the normal design temperatures of the Reactor Building. A calculation supports the normal area temperature data for the EQ Program. This calculation uses both survey data and calculated data as inputs. For the Drywell and the Steam Chase, a calculation provides a basis for the normal ambient temperatures. The EPU evaluation indicates no change in normal Drywell temperatures for EPU and a slight increase in normal Steam Chase temperature (less than one degree). This small temperature increase is bounded by the temperature value currently used in the EQ program for the steam chase. Normal plant area ambient temperature will continue to be assessed by the EQ program in lieu of using the maximum design temperature for assessing qualified lifetimes. As such, there is no impact of EPU conditions on normal plant temperature inputs to qualified life assessments.
Normal Temperature Evaluation An evaluation was completed to assess the impact EPU will have on the normal design temperatures of the Reactor Building. A calculation supports the normal area temperature data for the EQ Program. This calculation uses both survey data and calculated data as inputs. For the Drywell and the Steam Chase, a calculation provides a basis for the normal ambient temperatures. The EPU evaluation indicates no change in normal Drywell temperatures for EPU and a slight increase in normal Steam Chase temperature (less than one degree). This small temperature increase is bounded by the temperature value currently used in the EQ program for the steam chase. Normal plant area ambient temperature will continue to be assessed by the EQ program in lieu of using the maximum design temperature for assessing qualified lifetimes. As such, there is no impact of EPU conditions on normal plant temperature inputs to qualified life assessments.  
Page 1 of 19
 
Page 2 of 19 Normal Radiation Dose The EPU evaluation for radiation levels generally indicates an increase of 13 percent for the Reactor Building dose and no change for most Turbine Building normal doses as the result of EPU (some areas of Turbine Building have dose rate increases). This evaluation provides survey data for most plant areas and identifies the applicable increase effect for each plant area outside the Drywell. 


Enclosure 1 Normal Radiation Dose The EPU evaluation for radiation levels generally indicates an increase of 13 percent for the Reactor Building dose and no change for most Turbine Building normal doses as the result of EPU (some areas of Turbine Building have dose rate increases). This evaluation provides survey data for most plant areas and identifies the applicable increase effect for each plant area outside the Drywell.
The current basis for normal radiation doses in the EQ program is provided by calculation. This calculation documents actual survey dose rate data for all of the Reactor Building and the Turbine Building. The tables below relate the normal radiation doses in the calculation for reactor and turbine building.
The current basis for normal radiation doses in the EQ program is provided by calculation. This calculation documents actual survey dose rate data for all of the Reactor Building and the Turbine Building. The tables below relate the normal radiation doses in the calculation for reactor and turbine building.
Reactor Building, Normal 60 Year Doses Current EQ Program Basis Projected 60 year Normal EPU Dose RB Volume (Spec) Dose Rate mR/Hr Survey date Current  60 year Dose (Rad)
Reactor Building, Normal 60 Year Doses Current EQ Program Basis                     Projected 60 year Normal EPU Dose Predicted EPU Dose                        Current        Dose rate    Effect      EPU 60 yr RB Volume       Rate       Survey         60 year       (survey)      (see      Dose (Rad)
Dose rate (survey) mR/Hr Predicted EPU Effect (see note)  EPU 60 yr Dose (Rad)(see note) 1 (B.1.4) 200 01/18/03 1.39E+05 160 180.8 9.51E+04 2 (B.1.4) 200 01/18/03 1.39E+05 Not surv   3 (B.1.4) 100 12/29/02 6.94E+04 50 56.5 2.97E+04 4 (B.1.4) 100 12/29/02 6.94E+04 Not surv   5 (B.1.3) 1 08/18/02 6.94E+02 Not surv   6 (B.1.2) 1000 12/21/02 6.94E+05 100 113 5.94E+04 7 (B.1.10) 1 06/26/00 6.94E+02 Not surv   8 (B.1.2) 46 12/21/03 3.19E+04 3 3.39 1.78E+03 9 (B.1.6) 120 12/15/02 8.33E+04 50 56.5 2.97E+04 10 (B.1.6) 90 12/15/02 6.25E+04 30 33.9 1.78E+04 11 (B.1.6) 140 01/19/03 9.72E+04 60 67.8 3.57E+04 12 (B.1.6) 150 01/19/03 1.04E+05 30 33.9 1.78E+04 13 (B.1.8) 80 01/12/03 5.55E+04 20 22.6 1.19E+04 14 (B.1.9/11) 160 08/03/02 1.11E+05 60 67.8 3.57E+04 15 (B.1.9) 350 03/10/02 2.43E+05 50 56.5 2.97E+04 16 (B.1.7) 4000 07/01/98 2.78E+06 2000 2260 1.19E+06 17 (B.1.9) 4 12/29/02 2.78E+03 4 4.52 2.38E+03 18 (B.1.10) 400 01/21/03 2.78E+05 55 62.15 3.27E+04 19 (B.1.10/12) 42 12/29/02 2.92E+04 4 4.52 2.38E+03 20 (B.1.8) 80 01/18/03 5.55E+04 30 33.9 1.78E+04 21 (B.1.14) 100 02/08/03 6.94E+04 30 33.9 1.78E+04 22 (B.1.14) 80 12/15/02 5.55E+04 1 1.13 5.94E+02 Page 3 of 19 Reactor Building, Normal 60 Year Doses Current EQ Program Basis Projected 60 year Normal EPU Dose RB Volume (Spec) Dose Rate mR/Hr Survey date Current  60 year Dose (Rad)
(Spec)       mR/Hr         date        Dose (Rad)         mR/Hr      note)      (see note) 1 (B.1.4)       200     01/18/03       1.39E+05           160       180.8       9.51E+04 2 (B.1.4)       200     01/18/03       1.39E+05         Not surv 3 (B.1.4)       100     12/29/02       6.94E+04             50       56.5       2.97E+04 4 (B.1.4)       100     12/29/02       6.94E+04         Not surv 5 (B.1.3)       1       08/18/02       6.94E+02         Not surv 6 (B.1.2)     1000     12/21/02       6.94E+05           100         113       5.94E+04 7 (B.1.10)       1       06/26/00       6.94E+02         Not surv 8 (B.1.2)       46     12/21/03       3.19E+04             3       3.39       1.78E+03 9 (B.1.6)       120     12/15/02       8.33E+04             50       56.5       2.97E+04 10 (B.1.6)       90     12/15/02       6.25E+04             30       33.9       1.78E+04 11 (B.1.6)       140     01/19/03       9.72E+04           60         67.8       3.57E+04 12 (B.1.6)       150     01/19/03       1.04E+05           30         33.9       1.78E+04 13 (B.1.8)       80     01/12/03       5.55E+04             20       22.6       1.19E+04 14 (B.1.9/11)       160     08/03/02       1.11E+05             60       67.8       3.57E+04 15 (B.1.9)       350     03/10/02       2.43E+05           50         56.5       2.97E+04 16 (B.1.7)     4000     07/01/98       2.78E+06           2000       2260         1.19E+06 17 (B.1.9)         4     12/29/02       2.78E+03             4       4.52       2.38E+03 18 (B.1.10)     400       01/21/03       2.78E+05           55       62.15       3.27E+04 19 (B.1.10/12)       42       12/29/02       2.92E+04             4         4.52       2.38E+03 20 (B.1.8)       80     01/18/03       5.55E+04             30       33.9       1.78E+04 21 (B.1.14)       100     02/08/03       6.94E+04             30       33.9       1.78E+04 22 (B.1.14)       80     12/15/02       5.55E+04             1       1.13       5.94E+02 Page 2 of 19
Dose rate (survey) mR/Hr Predicted EPU Effect (see note)  EPU 60 yr Dose (Rad)(see note) 23 (B.1.14) 80 02/10/02 5.55E+04 1 1.13 5.94E+02 24 1 01/18/03 6.94E+02 Not surv  25 1 12/15/02 6.94E+02 1 1.13 5.94E+02 26 18 01/18/03 1.25E+04 4 4.52 2.38E+03 27 (B.1.13/15) 260 08/12/02 1.81E+05 30 33.9 1.78E+04 28 (B.1.5) 40 01/04/02 2.78E+04 40 45.2 2.38E+04 29 (B.1.5) 20 01/04/02 1.39E+04 20 22.6 1.19E+04 30 (B.1.5) 800 01/04/02 5.55E+05 80 90.4 4.75E+04 31 (B.1.5) 2200 01/04/02 1.53E+06 2200 2486 1.31E+06 32 (B.1.5) 1600 01/04/02 1.11E+06 1600 1808 9.51E+05 33 (B.1.13) 680 08/12/02 4.72E+05 3 3.39 1.78E+03 34 (B.1.18) 40 12/15/02 2.78E+04 6 6.78 3.57E+03 35 (B.1.17) 5 12/15/02 3.47E+03 4 4.52 2.38E+03 36 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 37 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 38 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 39 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 40 (B.1.16) 2 08/26/02 1.39E+03 1 1.13 5.94E+02 41 (B.1.16) 2 01/18/03 1.39E+03 1 1.13 5.94E+02 42 (B.1.16) 20 12/15/02 1.39E+04 1 1.13 5.94E+02 43 (B.1.19) 700 12/27/02 4.86E+05 500 565 2.97E+05 44 (B.1.20) 200 12/27/02 1.39E+05 5 5.65 2.97E+03 45 (B.1.19) 2 12/27/02 1.39E+03 2 2.26 1.19E+03 46 (B.1.19) 200 12/27/02 1.39E+05 6 6.78 3.57E+03 47 (B.1.19) 1 12/27/02 6.94E+02 Not surv  48 36 02/06/03 2.50E+04 7 7.91 4.16E+03 Note:  EPU 60-year basis dose was determined by increasing the shown dose rate by 13 percent taken over the number of hour s over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values. As illustrated above, the projected 60-year normal dose due to EPU is bounded by the specified doses used in the current EQ Program for the Reactor Building.


Page 4 of 19 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose TB Volume mR/Hr Survey Date Current  60 year Dose (Rad)
Enclosure 1 Reactor Building, Normal 60 Year Doses Current EQ Program Basis                   Projected 60 year Normal EPU Dose Predicted EPU Dose                      Current      Dose rate    Effect      EPU 60 yr RB Volume       Rate        Survey       60 year       (survey)      (see      Dose (Rad)
Dose Rate survey (mRem/hr)
(Spec)      mR/Hr        date      Dose (Rad)       mR/Hr      note)       (see note) 23 (B.1.14)       80      02/10/02     5.55E+04          1         1.13        5.94E+02 24           1        01/18/03      6.94E+02       Not surv 25            1       12/15/02     6.94E+02           1         1.13        5.94E+02 26          18      01/18/03      1.25E+04          4          4.52        2.38E+03 27 (B.1.13/15)     260      08/12/02      1.81E+05         30         33.9        1.78E+04 28 (B.1.5)       40      01/04/02     2.78E+04           40        45.2        2.38E+04 29 (B.1.5)       20      01/04/02     1.39E+04          20        22.6        1.19E+04 30 (B.1.5)     800      01/04/02     5.55E+05          80        90.4        4.75E+04 31 (B.1.5)     2200      01/04/02     1.53E+06        2200        2486        1.31E+06 32 (B.1.5)     1600      01/04/02     1.11E+06        1600        1808        9.51E+05 33 (B.1.13)     680      08/12/02     4.72E+05          3          3.39        1.78E+03 34 (B.1.18)       40      12/15/02     2.78E+04          6          6.78        3.57E+03 35 (B.1.17)       5       12/15/02     3.47E+03           4        4.52        2.38E+03 36 (B.1.21)       1       08/26/02     6.94E+02           1         1.13        5.94E+02 37 (B.1.21)       1       08/26/02     6.94E+02           1        1.13        5.94E+02 38 (B.1.21)       1       08/26/02     6.94E+02           1         1.13        5.94E+02 39 (B.1.21)       1       08/26/02     6.94E+02           1         1.13        5.94E+02 40 (B.1.16)       2      08/26/02     1.39E+03            1         1.13        5.94E+02 41 (B.1.16)       2      01/18/03      1.39E+03            1         1.13        5.94E+02 42 (B.1.16)       20      12/15/02     1.39E+04          1         1.13        5.94E+02 43 (B.1.19)     700      12/27/02     4.86E+05          500          565        2.97E+05 44 (B.1.20)     200      12/27/02     1.39E+05           5          5.65        2.97E+03 45 (B.1.19)       2      12/27/02     1.39E+03            2        2.26        1.19E+03 46 (B.1.19)     200      12/27/02     1.39E+05           6          6.78        3.57E+03 47 (B.1.19)       1       12/27/02     6.94E+02       Not surv 48          36      02/06/03      2.50E+04          7          7.91        4.16E+03 Note: EPU 60-year basis dose was determined by increasing the shown dose rate by 13 percent taken over the number of hours over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values. As illustrated above, the projected 60-year normal dose due to EPU is bounded by the specified doses used in the current EQ Program for the Reactor Building.
EPU Effect  EPU 60 yr Dose (Rad) 1 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 2 (B.1.24) 1 12/18/02 6.94E+02 1 1130%
Page 3 of 19
Increase 5.94E+03 3 (B.1.24) 1 12/18/02 6.94E+02 1 1130%
Increase 5.94E+03 4 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 5 (B.1.24) 8 12/18/02 5.55E+03 1 - 2 No change 1.05E+03 6 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 7 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 8 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 9 (B.1.24) 1 12/18/02 6.94E+02 1 No change 5.26E+02 10 (B.1.24) 2 12/18/02 1.39E+03 1 1 - 5 No change 2.63E+03 11 (B.1.24) 200 01/29/03 1.39E+05 1 - 10 30 No change 1.58E+04 12 (B.1.24) 120 05/01/02 8.33E+04 5 - 30 No change 1.58E+04 13 (B.1.24) 2400 02/07/02 1.67E+06 2 - 1500 25 - 33%
Increase 1.05E+06 14 (B.1.24) 4000 07/01/98 2.78E+06 5 - 1800 Up to 1130% Increase 1.07E+07 15 (B.1.24) 8 12/18/02 5.55E+03 1 No change 5.26E+02 16 (B.1.24) 8 12/18/02 5.55E+03 1 No change 5.26E+02 17 (B.1.24) 8 12/18/02 5.55E+03 1 No change 5.26E+02 18 (B.1.24) 8 12/18/02 5.55E+03 1 No change 5.26E+02 19 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 20 (B.1.23) 46 11/13/02 3.19E+04 Not surveyed No change  21 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 Page 5 of 19 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose TB Volume mR/Hr Survey Date Current  60 year Dose (Rad)
Dose Rate survey (mRem/hr)
EPU Effect  EPU 60 yr Dose (Rad) 22 (B.1.23) 12 11/13/02 8.33E+03 1 No change 5.26E+02 23 (B.1.23) 1 12/18/02 6.94E+02 1-2 No change 1.05E+03 24 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 25 (B.1.23) 2 12/04/02 1.39E+03 1 1130%
Increase 5.94E+03 26 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 27 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 28 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 29 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 30 (B.1.23) 8 02/06/02 5.55E+03 1 No change 5.26E+02 31 (B.1.23) 1 02/06/02 6.94E+02 1 No change 5.26E+02 32 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 33 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 34 (B.1.23) 1 03/28/02 6.94E+02 1 No change 5.26E+02 35 (B.1.23) 1 03/28/02 6.94E+02 1 No change 5.26E+02 36 (B.1.23) 1 03/28/02 6.94E+02 1 No change 5.26E+02 37 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 38 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 39 (B.1.23) 1 12/18/02 6.94E+02 1 No change 5.26E+02 40 (B.1.23) 60 12/18/02 4.17E+04 1 - 2 No change 1.05E+03 41 (B.1.22) 80 05/08/00 5.55E+04 1 - 3 No change 1.58E+03 42 (B.1.22) 3000 05/08/00 2.08E+06 1 - 1000 10 - 3000 2 - 9% Increase 1.72E+06 Page 6 of 19 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose TB Volume mR/Hr Survey Date Current  60 year Dose (Rad)
Dose Rate survey (mRem/hr)
EPU Effect  EPU 60 yr Dose (Rad) 43 (B.1.23) 1 12/18/02 6.94E+02 Not surveyed No change  44 (B.1.22) 3000 05/08/00 2.08E+06 1 - 1000 10 - 3000 2 - 9% Increase 1.72E+06  Note:   EPU 60-year basis dose was determined by increasing the highest shown dose rate by the EPU Effect value and then mu ltiplying by the number of hours over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values.  


Based on the above, it is observed that the projected 60 year normal doses in Turbine Building Volumes 2, 3, 10, 14, 23, and 25 will increase from the current specified EQ Program data. These volumes, with the exception of 14, remain below the radiation harsh classification threshold as defined by the EQ program.
Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose        Projected 60 year Normal EPU Dose Current    Dose Rate Survey        60 year     survey        EPU    EPU 60 yr TB Volume    mR/Hr      Date      Dose (Rad)    (mRem/hr)      Effect Dose (Rad) 1 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 2 (B.1.24)    1    12/18/02      6.94E+02          1        1130%    5.94E+03 Increase 3 (B.1.24)    1    12/18/02      6.94E+02          1        1130%    5.94E+03 Increase 4 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 5 (B.1.24)    8    12/18/02      5.55E+03        1-2          No    1.05E+03 change 6 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 7 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 8 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 9 (B.1.24)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 10 (B.1.24)    2    12/18/02      1.39E+03          1          No    2.63E+03 1-5        change 11 (B.1.24)  200    01/29/03      1.39E+05      1 - 10         No    1.58E+04 30        change 12 (B.1.24)  120    05/01/02      8.33E+04      5 - 30        No    1.58E+04 change 13 (B.1.24)  2400    02/07/02      1.67E+06      2 - 1500  25 - 33%    1.05E+06 Increase 14 (B.1.24)  4000    07/01/98      2.78E+06      5 - 1800      Up to    1.07E+07 1130%
Increase 15 (B.1.24)    8    12/18/02      5.55E+03          1          No    5.26E+02 change 16 (B.1.24)    8    12/18/02      5.55E+03          1          No    5.26E+02 change 17 (B.1.24)    8    12/18/02      5.55E+03          1          No    5.26E+02 change 18 (B.1.24)    8    12/18/02      5.55E+03          1          No    5.26E+02 change 19 (B.1.23)    1    12/18/02      6.94E+02          1          No    5.26E+02 change 20 (B.1.23)    46    11/13/02      3.19E+04        Not          No surveyed      change 21 (B.1.23)    1    12/18/02      6.94E+02          1          No    5.26E+02 change Page 4 of 19


Accident Radiation Doses The EPU evaluation of the impacts of radiation on equipment qualification and the supporting vendor calculation performed by Alion provides the bases for EPU impacts on the EQ program from post-LOCA accident doses. The resulting EPU doses and the indicated increases by location are shown below.
Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose        Projected 60 year Normal EPU Dose Current    Dose Rate Survey        60 year      survey        EPU    EPU 60 yr TB Volume    mR/Hr      Date      Dose (Rad)    (mRem/hr)      Effect Dose (Rad) 22 (B.1.23)    12    11/13/02      8.33E+03        1            No    5.26E+02 change 23 (B.1.23)    1    12/18/02      6.94E+02        1-2          No    1.05E+03 change 24 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 25 (B.1.23)    2    12/04/02      1.39E+03        1        1130%    5.94E+03 Increase 26 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 27 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 28 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 29 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 30 (B.1.23)    8    02/06/02      5.55E+03        1            No    5.26E+02 change 31 (B.1.23)    1    02/06/02      6.94E+02        1            No    5.26E+02 change 32 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 33 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 34 (B.1.23)    1    03/28/02      6.94E+02        1            No    5.26E+02 change 35 (B.1.23)    1    03/28/02      6.94E+02        1            No    5.26E+02 change 36 (B.1.23)    1    03/28/02      6.94E+02        1            No    5.26E+02 change 37 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 38 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 39 (B.1.23)    1    12/18/02      6.94E+02        1            No    5.26E+02 change 40 (B.1.23)    60    12/18/02      4.17E+04      1-2            No    1.05E+03 change 41 (B.1.22)    80    05/08/00      5.55E+04      1-3            No    1.58E+03 change 42 (B.1.22)  3000    05/08/00      2.08E+06    1 - 1000      2 - 9%    1.72E+06 10 - 3000    Increase Page 5 of 19


LOCATION % EPU Dose Increase EPU 180-day TID, (Rads) Drywell 2.5 5.44E+07 HPCI Room - Elevation 896' 7.3 2.73E+06 RCIC Room - Elevation 896' 7.5 1.82E+06 RHR Rooms - Elevation 896' 4.3 2.72E+07 RWCU Pump Room - Elevation 962' 7.8 2.52E+06 Torus Compartment - Elevation 896' 3.5 1.19E+07 Main Steam Chase - Elevation 935' 7.3 2.73E+06 LPCI Valve Injection Room - Elevation 935' 7.8 2.52E+06 Reactor Building - Elevation 935' E 7.8 2.52E+06 Reactor Building - Elevation 935' W 7.8 2.52E+06 Reactor Building - Elevation 935' SE 7.8 2.52E+06 Reactor Building - Elevation 935' SW 7.8 2.52E+06 Reactor Building - Elevation 962' S 7.8 2.52E+06 Reactor Building - Elevation 962' E 7.8 2.52E+06 Reactor Building - Elevation 962' NW 7.8 2.52E+06 Page 7 of 19 Reactor Building - Elevation 985' N 7.9 1.29E+04 Reactor Building - Elevation 985' SW 7.9 1.29E+04 Reactor Building - Elevation 985' SE 7.9 1.29E+04 Reactor Building - Elevation 1001' N 7.9 1.29E+04 Reactor Building - Elevation 1001' S 7.9 1.29E+04 Standby Gas Treatment Room - Elevation 985' 8.3 2.03E+08 Turbine Building Operating Deck -
Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose              Projected 60 year Normal EPU Dose Current      Dose Rate Survey        60 year        survey        EPU      EPU 60 yr TB Volume      mR/Hr        Date      Dose (Rad)      (mRem/hr)      Effect    Dose (Rad) 43 (B.1.23)      1        12/18/02      6.94E+02          Not          No surveyed      change 44 (B.1.22)    3000      05/08/00      2.08E+06        1 - 1000      2 - 9%      1.72E+06 10 - 3000    Increase Note: EPU 60-year basis dose was determined by increasing the highest shown dose rate by the EPU Effect value and then multiplying by the number of hours over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values.
Elevation 951' 0.0 <1.00E+04 Turbine Building Condenser Room -
Based on the above, it is observed that the projected 60 year normal doses in Turbine Building Volumes 2, 3, 10, 14, 23, and 25 will increase from the current specified EQ Program data. These volumes, with the exception of 14, remain below the radiation harsh classification threshold as defined by the EQ program.
Elevations 907', 911' & 931' 0.0 <1.00E+04 Cond Phase Separator Room 3.7 1.19E+07 Waste Collector Tank Room 7.7 3.87E+06 The accident doses developed in the subject EPU evaluation are supported by vendor calculation (ALION). The vendor calculation develops scaling factors on the original plant dose calculations developed in response to the Three Mile Island action plan. For the Reactor Building and Drywell, the EPU effective accident dose increase was shown to range from 2.5 to 8.3 percent with the 180-day integrated accident dose shown above.
Accident Radiation Doses The EPU evaluation of the impacts of radiation on equipment qualification and the supporting vendor calculation performed by Alion provides the bases for EPU impacts on the EQ program from post-LOCA accident doses. The resulting EPU doses and the indicated increases by location are shown below.
For the Turbine Building, the calculation indicates that there were no original plant dose calculations developed for general areas of the Turbine Building. For comparison, the calculation indicates 1-hour dose rates of less than 500 mRem/hour for vital access areas of the Administrative Building that experience shine from the Reactor Building. For conservatism, the accident dose was always listed as being <1.0E+04 Rad. 
                                                    % EPU Dose     EPU 180-day TID, LOCATION Increase            (Rads)
Drywell                         2.5             5.44E+07 HPCI Room - Elevation 896'                 7.3             2.73E+06 RCIC Room - Elevation 896'                 7.5             1.82E+06 RHR Rooms - Elevation 896'                 4.3             2.72E+07 RWCU Pump Room - Elevation 962'                 7.8             2.52E+06 Torus Compartment - Elevation 896'             3.5             1.19E+07 Main Steam Chase - Elevation 935'             7.3             2.73E+06 LPCI Valve Injection Room - Elevation 7.8             2.52E+06 935' Reactor Building - Elevation 935' E           7.8             2.52E+06 Reactor Building - Elevation 935' W           7.8             2.52E+06 Reactor Building - Elevation 935' SE           7.8             2.52E+06 Reactor Building - Elevation 935' SW           7.8             2.52E+06 Reactor Building - Elevation 962' S           7.8             2.52E+06 Reactor Building - Elevation 962' E           7.8             2.52E+06 Reactor Building - Elevation 962' NW           7.8             2.52E+06 Page 6 of 19


Accordingly, the revised combined 60-year normal doses and the 180-day accident doses under EPU have the potential to impact the qualification of EQ components in the Reactor Building. Using the methods prescribed in the individual EQ calculation files for operating time and distance factors, the revised normal and accident doses were evaluated and compared to the qualified dose as indicated below (for conservatism, the normal dose was increased by +13 percent). For the equipment located in the Drywell, Beta dose was also considered. The Beta dose specified in the Monticello EQ Program is taken from the DOR Guidelines (Division of Operating Reactors - "Guidelines for Evaluating Environmental Qualification of Class 1E Electrical Equipment in Operating Reactors") as an unshielded 200 Mrad dose, which was developed from a 4,100 MWth reactor. Therefore, considerable margin is included in the Beta dose as it applies to  
Enclosure 1 Reactor Building - Elevation 985' N            7.9            1.29E+04 Reactor Building - Elevation 985' SW            7.9            1.29E+04 Reactor Building - Elevation 985' SE            7.9            1.29E+04 Reactor Building - Elevation 1001' N            7.9            1.29E+04 Reactor Building - Elevation 1001' S            7.9            1.29E+04 Standby Gas Treatment Room - Elevation 8.3            2.03E+08 985' Turbine Building Operating Deck -
0.0          <1.00E+04 Elevation 951' Turbine Building Condenser Room -
0.0          <1.00E+04 Elevations 907', 911' & 931' Cond Phase Separator Room                    3.7            1.19E+07 Waste Collector Tank Room                  7.7            3.87E+06 The accident doses developed in the subject EPU evaluation are supported by vendor calculation (ALION). The vendor calculation develops scaling factors on the original plant dose calculations developed in response to the Three Mile Island action plan. For the Reactor Building and Drywell, the EPU effective accident dose increase was shown to range from 2.5 to 8.3 percent with the 180-day integrated accident dose shown above.
For the Turbine Building, the calculation indicates that there were no original plant dose calculations developed for general areas of the Turbine Building. For comparison, the calculation indicates 1-hour dose rates of less than 500 mRem/hour for vital access areas of the Administrative Building that experience shine from the Reactor Building.
For conservatism, the accident dose was always listed as being <1.0E+04 Rad.
Accordingly, the revised combined 60-year normal doses and the 180-day accident doses under EPU have the potential to impact the qualification of EQ components in the Reactor Building. Using the methods prescribed in the individual EQ calculation files for operating time and distance factors, the revised normal and accident doses were evaluated and compared to the qualified dose as indicated below (for conservatism, the normal dose was increased by +13 percent). For the equipment located in the Drywell, Beta dose was also considered. The Beta dose specified in the Monticello EQ Program is taken from the DOR Guidelines (Division of Operating Reactors - Guidelines for Evaluating Environmental Qualification of Class 1E Electrical Equipment in Operating Reactors) as an unshielded 200 Mrad dose, which was developed from a 4,100 MWth reactor. Therefore, considerable margin is included in the Beta dose as it applies to Monticello.
Page 7 of 19


Monticello.
Enclosure 1 EPU      EPU Normal  Accident    Beta Dose    Gamma        Dose    Total EPU Qual.     Note Equipment Title     (rad)   TID (rad)   (rad)   TID (rad) Dose (rad)
Page 8 of 19 Equipment Title EPU Normal Dose (rad) EPU Accident Gamma TID (rad) Beta Dose (rad) Total EPU TID (rad)
Allen Bradley       7.84E+02 4.33E+06             4.33E+06 2.51E+08 Terminal Boards ASCO Solenoid        1.57E+05 2.83E+07              2.84E+07  2.00E+08 Valves (Normally Energized) Group 1 ASCO Solenoid        9.41E+04 1.25E+07              1.25E+07  2.00E+08 Valves (Normally Energized) Group 2 ASCO Solenoid        1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.00E+08 Valves (Normally Energized) Group 3 ASCO Solenoid        3.14E+05 2.53E+06              2.85E+06  2.00E+08 Valves (Normally Energized) Group 4 ASCO Solenoid        1.79E+07 5.44E+07    Shielded 7.23E+07  2.00E+08 Valves (Normally De-energized) Group 1 ASCO Solenoid       1.18E+05 1.25E+07              1.26E+07  2.00E+08 Valves (Normally De-energized) Group 2 ASCO Pressure        1.18E+05 1.25E+07              1.26E+07  1.93E+07 Switches ASCO Temperature    7.84E+02 1.08E+07              1.08E+07  1.50E+07 Switches Automatic Valve      2.79E+06 5.00E+06    Shielded 7.79E+06  7.79E+06  Note Solenoid Valves Barksdale Pressure  1.57E+05 6.50E+06              6.66E+06  1.00E+07 Switch Barton Pressure      1.57E+05 5.42E+05              6.99E+05  3.00E+06 Switches RHR Barton Pressure      1.30E+05 2.53E+06              2.66E+06  3.00E+06 Switches, Non-RHR Barton Pressure      3.14E+05 2.53E+06              2.85E+06  1.00E+07 Switches 580A-0, 580A-1 E.F. Johnson Banana  3.14E+06 HELB only            3.14E+06  4.70E+06 Plug G.E. Cable (Butyl    1.57E+05 2.83E+07              2.84E+07  4.00E+07 type)
Qual. Dose (rad) Note  Allen Bradley Terminal Boards 7.84E+024.33E+06 4.33E+06 2.51E+08 ASCO Solenoid  
G.E. Cable SIS & SI- 1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.00E+08  Note 58109 Control G.E. Cable SI-58081  7.84E+03 2.17E+07              2.17E+07  2.44E+07 Control General Electric    1.57E+05 2.72E+07              2.74E+07  3.00E+07  Note Motors Page 8 of 19


Valves (Normally Energized) Group 1 1.57E+052.83E+07  2.84E+07 2.00E+08 ASCO Solenoid
Enclosure 1 EPU      EPU Normal  Accident    Beta Dose    Gamma        Dose    Total EPU Qual.      Note Equipment Title      (rad)    TID (rad)    (rad)    TID (rad) Dose (rad)
General Electric    1.79E+07 5.44E+07    Shielded 7.23E+07  1.00E+08 Containment Penetrations General Electric    7.84E+02 2.03E+08              2.03E+08  2.20E+08  Note Terminal Blocks General Electric    3.60E+05                      3.60E+05  1.00E+06 MCCs Hevi-Duty Electric  7.84E+02 4.71E+06              2.00E+06  2.00E+06  Note Transformer General Electric Fan 7.84E+02 1.08E+06              1.08E+06  1.00E+06  Note Motors Limitorque Motor    1.79E+07 5.44E+07    2.00E+06 7.43E+07  2.00E+08 Operators (DOR)
(MO-2397)
Limitorque Motor    3.14E+06 2.75E+06              5.89E+06  2.00E+07 Operators (DOR)
(MO-2107)
Limitorque Motor    1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.00E+08 Operators (50.49)
Limitorque Motor    3.14E+06 2.75E+06              5.89E+06  1.00E+07 Operators (50.49)
Limitorque Motor    1.18E+05 1.25E+07              1.26E+07  2.00E+07 Operators (50.49)
Limitorque Motor    1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.27E+08 Operators (50.49)
Limitorque Motor    1.18E+05 1.25E+07              1.26E+07  2.00E+07 Operators (50.49)(MO-4229 &
MO-4230)
Magnetrol Level      1.18E+05 1.25E+07              1.26E+07  2.20E+08 Switches McDonnell & Miller  7.84E+02 5.40E+06              5.40E+06  5.00E+06  Note Flow Switches MicroSwitch Limit    7.84E+02 1.07E+07              1.07E+07  1.00E+07  Note Switches Namco Limit          1.79E+07 5.44E+07    Shielded 7.23E+07  2.04E+08 Switches (50.49)
Namco Quick          1.79E+07 5.44E+07    1.00E+08 1.72E+08  2.04E+08 Disconnects EC210 Raychem NEIS Seals  1.18E+05 1.25E+07              1.26E+07  5.00E+07 Raychem Low          1.79E+07 5.44E+07     1.00E+08 1.72E+08  2.25E+08 Voltage Splices Robertshaw Level    3.14E+05 3.25E+05              6.39E+05  2.00E+06 Switch Rockbestos Coax      1.79E+07 5.44E+07    1.00E+08 1.72E+08  2.00E+08 Cable Page 9 of 19


Valves (Normally Energized) Group 2 9.41E+041.25E+07  1.25E+07 2.00E+08 ASCO Solenoid Valves (Normally Energized) Group 3 1.79E+075.44E+07 2.00E+079.23E+07 2.00E+08 ASCO Solenoid
Enclosure 1 EPU      EPU Normal  Accident    Beta Dose    Gamma      Dose    Total EPU Qual.      Note Equipment Title      (rad)    TID (rad)  (rad)    TID (rad) Dose (rad)
Rosemount Pressure    1.18E+05 1.25E+07            1.26E+07  4.40E+07 Transmitter Rosemount 1153        1.57E+05 2.83E+07            2.84E+07  2.62E+07  Note Series B Rosemount Conduit    1.18E+05 1.25E+07            1.26E+07  1.11E+08 Seals Rotork "A" Range      1.57E+05 1.62E+06            1.78E+06  4.00E+06 Actuators (DOR)
Rotork Valve          1.57E+05 2.83E+07             2.84E+07  1.84E+08 Operators (50.49)
Static O-ring        5.33E+05 5.74E+06            6.27E+06  8.00E+06 Yarway Level          3.14E+05 3.40E+05            6.54E+05  1.00E+06 Samuel Moore          7.84E+02 1.08E+08             1.08E+08  2.00E+08 Instrument Cable Valcor Solenoid       1.10E+05 1.25E+07            1.26E+07  5.90E+07 Valves DG O'Brien Electrical 1.79E+07 5.44E+07    Shielded 7.23E+07  2.20E+08 Penetrations DG O'Brien Electrical 1.79E+07 5.44E+07    1.25E+07 8.48E+07  1.25E+08 Penetrations (Plugs)
Reliance Motors      1.57E+05 2.83E+07            2.84E+07  2.00E+08 Tavis Flow            7.84E+02 1.08E+06            1.08E+06  1.40E+06 Transmitter ITT Grinnel/Conoflow  7.84E+02 5.42E+06            5.42E+06  1.00E+07 Transducer Consolidated Control  3.14E+05 7.58E+04            3.90E+05  5.00E+05 Relays General Atomic        1.79E+07 5.44E+07    2.00E+08 2.72E+08  Not Rad Radiation Detector                                            Sensitive Kerite                1.57E+05 2.83E+07            2.84E+07  2.20E+08 Cable/Termination Westinghouse Starter  1.25E+05 2.53E+06            2.66E+06  5.00E+06 and Transformer GOULD                7.84E+02 4.33E+06            4.33E+06  1.00E+07 CONTACTOR/
DISCONNECT Eaton Thermocouple    1.79E+07 5.44E+07   1.00E+08 1.72E+08  2.00E+08 Extension Cable Brand Rex 600V        1.79E+07 5.44E+07   1.00E+08 1.72E+08  2.00E+08 Instrument Cable (Dywell)
Brand Rex 600V        7.84E+03 1.08E+08            1.08E+08  2.00E+08 Instrument Cable (RB)
Boston Control Cable  7.84E+03 1.08E+08            1.08E+08  2.00E+08 Page 10 of 19


Valves (Normally Energized) Group 4 3.14E+052.53E+06  2.85E+06 2.00E+08 ASCO Solenoid
Enclosure 1 EPU      EPU Normal  Accident    Beta Dose    Gamma      Dose    Total EPU Qual.      Note Equipment Title      (rad)    TID (rad)  (rad)   TID (rad) Dose (rad)
CONAX Electrical      1.79E+07 5.44E+07    2.25E+07 9.48E+07  2.25E+08 Connector Seal CONAX RTDs            1.18E+05 1.25E+07            1.26E+07  2.27E+08 Patel Conduit Seals  1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.00E+08 (Drywell)
Patel Conduit Seals  7.84E+03 1.08E+08            1.08E+08  2.00E+08 (Contact SBGT Filters)
Patel Conformal      1.18E+05 1.25E+07            1.26E+07  2.00E+07 Coating (outside Drywell)
Patel Conformal      1.79E+07 5.44E+07    2.00E+08 2.72E+08  3.06E+08 Coating (Drywell)
EGS Grayboot          1.79E+07 5.44E+07    2.00E+07 9.23E+07  2.08E+08 Electrical Connectors EGS Quick            1.79E+07 5.44E+07    1.00E+08 1.72E+08  2.00E+08 Disconnect Raychem/Swagelok      1.57E+05 2.83E+07            2.84E+07  5.00E+07 Conduit Seals Weed                  1.79E+07 5.44E+07    2.00E+08 2.72E+08  3.06E+08 Thermocouples Rome Cable Type      3.60E+04 3.25E+05            3.61E+05  5.00E+08 SIS Eaton Cutler-        5.33E+05 5.29E+05            1.06E+06  1.43E+06 Hammer Relays PEI/FENWAL            1.18E+05 1.25E+07            1.26E+07  5.00E+07 Temperature Switch ITT-Royal PVC Cable  5.33E+05 2.53E+06            3.07E+06  1.00E+07 Okonite Control      3.14E+05 2.53E+06            2.85E+06  1.00E+07 Cable Triangle Triolene    3.14E+05 7.58E+04            3.90E+05  3.90E+05 Control Cable MNGP-A Cable          1.57E+05 2.83E+07            2.84E+07  5.00E+07 MNGP-B Cable          1.57E+05 2.83E+07            2.84E+07  4.10E+07 Amphenol              5.33E+05 3.79E+06            4.32E+06  6.00E+06 Connectors Pyco Temperature      3.14E+04 2.53E+06            2.57E+06  2.20E+08 Elements SOR Pressure          5.33E+05 2.53E+06            3.07E+06  3.30E+07 Switches General Electric      5.33E+05 2.17E+06            2.70E+06 2.20E+08 Terminal Blocks Patel P-1 Thread      1.79E+07 5.44E+07    2.00E+08 2.72E+08  1.50E+09 Sealant Rockbestos Firewall  1.79E+07 5.44E+07    1.00E+08 1.72E+08  2.00E+08 SR Cable Page 11 of 19


Valves (Normally De-energized) Group 1 1.79E+075.44E+07 Shielded 7.23E+07 2.00E+08 ASCO Solenoid  
Enclosure 1 EPU        EPU Normal    Accident    Beta Dose      Gamma        Dose      Total EPU    Qual.      Note Equipment Title          (rad)      TID (rad)    (rad)      TID (rad)    Dose (rad)
Rockbestos Firewall      1.79E+07  5.44E+07    1.00E+08  1.72E+08    2.00E+08 III/SIS Cable Rockbestos Firewall      1.57E+05 2.83E+07                  2.84E+07    1.30E+08 EP Cable Valcor MSIV              3.14E+04 8.66E+04                  1.18E+05    5.00E+07 Solenoid Valves Core Spray & RHR          1.57E+05 2.83E+07                  2.84E+07    5.77E+07 High Voltage Termination Dow Corning 3-6548 3.60E+04 HELB only                        3.60E+04    1.36E+06 Silicone RTV Foam Loctite PST 580          1.79E+07 5.44E+07       Shielded 7.23E+07       7.37E+07  Note Thread Sealant Scotch 130C and 69        7.84E+03 1.08E+08                  1.08E+08    1.83E+08 Electrical Tape Fisher E/P                1.57E+05 4.33E+06                  4.49E+06    6.00E+06 Transducer Cutler-Hammer            1.24E+05 2.52E+06                  2.65E+06    2.80E+06  Note Motor Starter/Control Transformer ASCO Scram                7.85E+04 HELB only                7.85E+04    8.55E+04 Solenoid Pilot Valves Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
EPU HELB Evaluation HELB is discussed in PUSAR Section 2.2.1. Under the EPU evaluation for HELB, several high energy break or critical crack scenarios were considered for the Reactor Building. These included feedwater, reactor water cleanup, and control rod drive breaks and cracks in various areas. The EPU evaluation for HELBs, in combination with supporting calculations, provides the bases for temperatures, pressures and flood levels used for evaluation of HELBs in the Reactor and Turbine Buildings. The safe-shutdown equipment located in any Turbine Building locations made harsh (i.e. the peak HELB temperature greater than 140&deg;F) as a result of EPU are being determined and evaluated.
From the evaluation for Reactor Building EPU event cases, the following peak conditions are obtained as compared to the current EQ Program Basis values for the respective Reactor Building Volume:
Page 12 of 19


Valves (Normally De-energized) Group 2 1.18E+051.25E+07 1.26E+07 2.00E+08 ASCO Pressure
Enclosure 1 Current EQ Program Basis Data                        EPU Data RB      Temp    Press    Liquid Temp          Press      Liquid Volume (&deg;F)      (psia)  (ft)      (&deg;F)      (psia)      (ft) Comment 1  142.97  14.86      0.05    114.2    14.81    0.4  Note 2  142.97  14.85      0.01    115.2      14.8    0 3    143.8  14.98      0.05    115.7    14.83    0.4  Note 4    144.4  14.97          0    135.6    14.82      0 5      256  15.15      0.05    121.3    14.81    0.5  Note 6    263.6  15.63      3.95    157.2      14.8    0.6 7    240.4  15.19      4.38    184.5    14.84    0.8 8    <140  14.99          0    140.7      14.8    0.6  Note 9    187.6  15.59      0.01    127.4    14.79    0.5  Note 10    159.9  15.59          0    127.2    14.79    0.5  Note 11    158.7  15.59          0    127.3    14.79    0.5  Note 12      193  15.59      0.01    127.6    14.79    0.5  Note 13    127.3  14.88      0.24    166.2      14.8    0  Note 14    153.3  14.83      0.27    174.7      14.8    0  Note 15    209.6    15.3      0.05    180.2      14.8    0 16    311.3  21.16      6.68    213.1    15.22    8.8  Note 17    222.4  15.14          0    130.6    14.79      0 18    208.1  15.11      0.68    209.7    14.83      0  Note 19    175.9  15.13      0.53    209.3    14.83    0.1  Note 20    112.5  15.14          0    179.4      14.8    0.1  Note 21    112.2   14.87          0      108    14.79      0 22    170.4  14.84          0      184    14.79      0  Note 23    143.7  14.87          0      164    14.79      0  Note 24      104    14.7        0    104.4      14.7    0 25    145.8  14.85          0    183.5    14.79      0  Note 26    109.1   14.89          0    104.4      14.7    0 27    203.6  14.99      0.01    211.7    14.83      0  Note 28    216.7  15.85      0.38    213.3    15.03    1.6 Note 29    214.6  15.85        0.3    213.5      15.4    1.7  Note 30    220.5    17.2     0.27    218.2    16.52    1.4  Note 31    188.3  17.19      0.27      213    16.52    1.4  Note 32    164.1  15.85      0.19    219.8    17.09    1.7  Note 33    128.3  14.99          0    211.7    14.83      0  Note 34    168.3  14.83    0.005      191.4    14.79      0  Note 35    207.8  14.84      0.02    199.2    14.79      0 36    142.4  14.88          0    141.6    14.79      0 37    112.8  14.88          0    143.9      14.8    0  Note Page 13 of 19


Switches 1.18E+051.25E+07  1.26E+07 1.93E+07 ASCO Temperature
Enclosure 1 Current EQ Program Basis Data                                  EPU Data RB        Temp      Press      Liquid Temp            Press      Liquid Volume (&deg;F)          (psia)    (ft)        (&deg;F)      (psia)        (ft)    Comment 38        100        14.7          0      100.3        14.7      0 39    215.3      14.87        0.01      112.2        14.8      0 40    126.2      14.84          0      127.7        14.8      0 41    106.9      14.88          0      104.4        14.7      0 42    204.7      14.85        0.01      198.8      14.79      0 43    128.3      14.83        0.01      122.2      14.78      0 44    160.8      14.82        0.01      138.1     14.78      0 45    169.7      14.85        0.01      198.6      14.78      0    Note 46    219.2      14.86        0.02      106.2      14.77      0 47    101.5      14.84          0      187.8      14.78      0    Note 48    131.1         14.8      0.01      137.3      14.76      0 Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
EPU HELB Temperature Review From the table above, it is observed that the peak EPU liquid break HELB temperatures for Reactor Building Volumes 13, 14, 18, 19, 20, 22, 23, 24, 25, 27, 31, 32, 33, 34, 37, 38, 40, 45, 47, and 48 exceed the currently specified peak HELB temperature provided by the current EQ Program basis data. The peak EPU (or pre-EPU) HELB temperature in Reactor Building Volumes 24, 38, 40, and 48 are less than the harsh/mild threshold temperature of 140&deg;F, so these areas remain mild. Based on EQ end device location and required performance, the impact of EPU HELB conditions focuses on Reactor Building Volumes 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, and 34.
Qualified RB        Temp.      EPU Peak Equipment Title                        Volumes        (&deg;F)      Temp (&deg;F)      Note ASCO Solenoid Valves                    18, 19        346          209.7 (Normally Energized)
ASCO Solenoid Valves                      31          346          213 (Normally De-energized)
ASCO Pressure Switches                14, 19, 31      210          213        Note Barksdale Pressure Switch              14, 18,      212          211.7 22, 33 Barton Pressure Switches                14, 19        212          209.3 Barton Pressure Switches                14, 18        200          209.7        Note 580A-0, 580A-1 G.E. Cable (butyl rubber SI-          13, 14, 18,    340          211.7 58007/58136)                          19, 20, 22, 27, 33, 34 Page 14 of 19


Switches 7.84E+021.08E+07  1.08E+07 1.50E+07 Automatic Valve  
Enclosure 1 Qualified RB        Temp. EPU Peak Equipment Title                Volumes        (&deg;F)  Temp (&deg;F) Note GE Cable (PE type SI-58081)    13, 14, 18,    236      211.7 19, 20, 22, 27, 33, 34 GE Cable (XLPE type, SI-      13, 14, 18,    340      219.8 57275/58109)                  19, 20, 22, 27, 31, 32, 33, 34 General Electric Containment    14, 18        340      209.7 Penetrations General Electric Terminal      13, 14, 18,    340      219.8 Blocks                        19, 20, 22, 27, 31, 32, 33, 34 Limitorque MOVs (50.49, class  13, 19, 20,    340      213 RH, AC motor)                    22, 31 Limitorque MOVs (50.49, class    13, 32        340      219.8 RH, DC motor)
Limitorque Fibrite Switches    13, 19, 20,    420      219.8 22, 31, 32 Namco Limit Switches (EA740        31          352      213 w/o EC210)
Namco Limit Switches (EA180    18, 19, 31      361      213 w/o EC210)
Raychem NEIS Seals            18, 19, 31      366      213 Raychem WCSF-N Splices        13, 14, 18,    350      219.8 19, 20, 22, 27, 31, 32, 33, 34 Robertshaw Level Switch            18          220      209.7 (DOR)
Rockbestos Coax Cable          13, 14, 18,    346      219.8 19, 20, 22, 27, 31, 32, 33, 34 Rosemount 1153 Series A          33, 34        340      211.7 Transmitter (DOR)
Rosemount 1153 Series B        14, 18, 19,    318      211.7 22, 27, 33, 34 Rosemount Conduit Seals        14, 18, 22,    420      211.7 27, 33 Rotork Valve Operators (50.49) 14, 31, 33      385      213 Static O-ring (DOR)              22, 33        212      211.7 Yarway Level (DOR)              14, 18        250      209.7 Page 15 of 19


Solenoid Valves 2.79E+065.00E+06 Shielded 7.79E+06 7.79E+06 Note Barksdale Pressure Switch 1.57E+056.50E+06  6.66E+06 1.00E+07 Barton Pressure
Enclosure 1 Qualified RB        Temp. EPU Peak Equipment Title                  Volumes        (&deg;F)  Temp (&deg;F) Note Samuel Moore Instrument        13, 14, 18,    340      219.8 Cable                          19, 20, 22, 27, 31, 32, 33, 34 Valcor Solenoid Valves           18, 19        365      209.7 DG O'Brien Electrical            14, 19        320      209.3 Penetrations DG O'Brien Electrical            14, 19        345      209.3 Penetrations (Plugs)
Reliance Motors                  14, 19        464      209.3 Consolidated Control Relays        18        223.1    209.7 Westinghouse Starter and          14, 19        260      209.3 Transformer Eaton Thermocouple Extension        14          375      174.7 Cable Brand Rex 600V Instrument      13, 14, 18,    385      219.8 Cable                          19, 20, 22, 27, 31, 32, 33, 34 Boston Control Cable            13, 14, 18,    340      219.8 19, 20, 22, 27, 31, 32, 33, 34 Patel Conduit Seals                18          354      209.7 EGS Grayboot Electrical            31          450      213 Connectors EGS Quick Disconnect            13, 14, 18,    435      219.8 19, 20, 22, 27, 31, 32, 33, 34 Raychem/Swagelok Conduit        14, 18, 19,    340      211.7 Seals                          22, 33, 34 Eaton Cutler-Hammer Relays      22, 33, 34      232      211.7 ITT-Royal PVC Cable (DOR)      14, 18, 19,    211      211.7  Note 22, 33 Okonite Control Cable          14, 18, 19,    211      209.7 22 Triangle Triolene Control Cable  18, 19        211      209.7 (DOR)
MNGP-A Cable (DOR)              13, 14, 18,    230      211.7 19, 20, 22, 27, 33, 34 MNGP-B Cable (DOR)                14, 19        211      209.3 Page 16 of 19


Switches RHR 1.57E+055.42E+05  6.99E+05 3.00E+06 Barton Pressure
Enclosure 1 Qualified RB        Temp.      EPU Peak Equipment Title                      Volumes        (&deg;F)      Temp (&deg;F)      Note Amphenol Connectors (DOR)            14, 18, 19,      266        211.7 22, 33 SOR Pressure Switches               14, 22, 33      350        211.7 (50.49)
General Electric Terminal            22, 33, 34      340        211.7 Blocks (50.49)
Patel P-1 Thread Sealant            13, 14, 18,      400        219.8 19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall SR Cable        13, 14, 18,      351        219.8 19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall III/SIS          13, 14, 18,      342        219.8 Cable                                19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall EP Cable        13, 14, 18,      320        219.8 19, 20, 22, 27, 31, 32, 33, 34 Loctite PST 580 Thread              14, 18, 19,      364        219.8 Sealant                              20, 22, 27, 31, 32, 33, 34 Scotch 130C and 69 Electrical        13, 14, 18,      372        219.8 Tape                                19, 20, 22, 27, 31, 32, 33, 34 Cutler-Hammer Motor                    14, 19        253        209.3 Starter/Control Transformer ASCO Scram Solenoid Pilot              14, 18        277        209.7 Valves Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
Post-LOCA Heat-up in the Reactor Building The Reactor Building post-LOCA heat-up temperatures are provided in the associated EPU evaluation. The EPU data as compared to the current post-LOCA heat-up (PLHU) data is presented below. It is observed that most post-LOCA area temperatures are relatively benign and will not present particular challenges to the EQ components that are generally tested or analyzed to much higher accident temperatures at their location.
However, additional supporting qualification analysis to be performed and documented Page 17 of 19


Switches, Non-RHR 1.30E+052.53E+06  2.66E+06 3.00E+06 Barton Pressure Switches 580A-0, 580A-1 3.14E+052.53E+06  2.85E+06 1.00E+07  E.F. Johnson Banana
Enclosure 1 in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
RB Volume      Current PLHU Temp. (&deg;F)          EPU PLHU Temp. (&deg;F) 1                    110.0                      104.3 2                    110.0                      106.2 3                    129.1                      129.7 4                    129.1                      129.5 5                    109.9                      107.4 6                    140.4                      140.6 7                    116.3                       123.6 8                    106.2                      111.9 9                    160.4                      177.5 10                    159.9                      177.5 11                    158.7                      177.5 12                    157.3                      177.5 13                    112.6                      112.7 14                    107.6                      112.3 15                    106.3                      108.7 16                    135.2                      141.5 17                    106.1                       108.9 18                    109.3                      114.9 19                    106.3                       114.9 20                    112.6                      113.1 21                    112.2                       107.8 22                    106.7                      114.1 23                    106.4                      113.8 24                      104                        104 25                    113.9                      114.1 26                    109.1                      109.7 27                    109.1                      115.4 28                      120                        121.3 29                    120.1                      121.1 30                    120.2                        128 31                    120.2                      129.7 32                    120.2                      120.7 33                    115.6                      115.4 34                    107.9                      114.2 35                    107.8                      114.2 36                    134.4                      120.5 37                    112.8                      120.5 Page 18 of 19


Plug 3.14E+06HELB only  3.14E+06 4.70E+06 G.E. Cable (Butyl
Enclosure 1 RB Volume      Current PLHU Temp. (&deg;F)        EPU PLHU Temp. (&deg;F) 38                  100                            100 39                  126.3                         134.5 40                  105.6                          113.2 41                  106.9                          109.8 42                  104.6                          114.2 43                  109.7                          110.9 44                  108.1                          112.1 45                  104                            114 46                  107.2                          110.3 47                  100                          113.7 48                  103.9                          113.2


type) 1.57E+052.83E+07  2.84E+07 4.00E+07  G.E. Cable SIS & SI-
==SUMMARY==
 
58109 Control 1.79E+075.44E+07 2.00E+079.23E+07 2.00E+08 Note G.E. Cable SI-58081
 
Control 7.84E+032.17E+07  2.17E+07 2.44E+07 General Electric Motors 1.57E+052.72E+07  2.74E+07 3.00E+07 Note Page 9 of 19 Equipment Title EPU Normal Dose (rad) EPU Accident Gamma TID (rad) Beta Dose (rad) Total EPU TID (rad)
Qual. Dose (rad) Note  General Electric Containment
 
Penetrations 1.79E+075.44E+07 Shielded 7.23E+07 1.00E+08 General Electric Terminal Blocks 7.84E+022.03E+08  2.03E+08 2.20E+08 Note General Electric
 
MCCs 3.60E+05  3.60E+05 1.00E+06  Hevi-Duty Electric
 
Transformer 7.84E+024.71E+06  2.00E+06 2.00E+06 Note General Electric Fan Motors 7.84E+021.08E+06  1.08E+06 1.00E+06 Note Limitorque Motor
 
Operators (DOR)
(MO-2397) 1.79E+075.44E+07 2.00E+067.43E+07 2.00E+08 Limitorque Motor
 
Operators (DOR) (MO-2107) 3.14E+062.75E+06  5.89E+06 2.00E+07 Limitorque Motor
 
Operators (50.49) 1.79E+075.44E+07 2.00E+079.23E+07 2.00E+08 Limitorque Motor Operators (50.49) 3.14E+062.75E+06  5.89E+06 1.00E+07 Limitorque Motor
 
Operators (50.49) 1.18E+051.25E+07  1.26E+07 2.00E+07 Limitorque Motor
 
Operators (50.49) 1.79E+075.44E+07 2.00E+079.23E+07 2.27E+08 Limitorque Motor
 
Operators
 
(50.49)(MO-4229 &
 
MO-4230) 1.18E+051.25E+07  1.26E+07 2.00E+07 Magnetrol Level
 
Switches 1.18E+051.25E+07  1.26E+07 2.20E+08 McDonnell & Miller
 
Flow Switches 7.84E+025.40E+06  5.40E+06 5.00E+06 Note MicroSwitch Limit
 
Switches 7.84E+021.07E+07  1.07E+07 1.00E+07 Note  Namco Limit
 
Switches (50.49) 1.79E+075.44E+07 Shielded 7.23E+07 2.04E+08  Namco Quick
 
Disconnects EC210 1.79E+075.44E+07 1.00E+081.72E+08 2.04E+08  Raychem NEIS Seals 1.18E+051.25E+07  1.26E+07 5.00E+07  Raychem Low Voltage Splices 1.79E+075.44E+07 1.00E+081.72E+08 2.25E+08 Robertshaw Level
 
Switch 3.14E+053.25E+05  6.39E+05 2.00E+06 Rockbestos Coax
 
Cable 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08 Page 10 of 19 Equipment Title EPU Normal Dose (rad) EPU Accident Gamma TID (rad) Beta Dose (rad) Total EPU TID (rad)
Qual. Dose (rad) Note  Rosemount Pressure Transmitter 1.18E+051.25E+07  1.26E+07 4.40E+07 Rosemount 1153
 
Series B 1.57E+052.83E+07  2.84E+07 2.62E+07 Note Rosemount Conduit
 
Seals 1.18E+051.25E+07  1.26E+07 1.11E+08 Rotork "A" Range
 
Actuators (DOR) 1.57E+051.62E+06  1.78E+06 4.00E+06 Rotork Valve
 
Operators (50.49) 1.57E+052.83E+07  2.84E+07 1.84E+08 Static O-ring 5.33E+055.74E+06  6.27E+06 8.00E+06  Yarway Level 3.14E+053.40E+05  6.54E+05 1.00E+06  Samuel Moore
 
Instrument Cable 7.84E+021.08E+08  1.08E+08 2.00E+08  Valcor Solenoid
 
Valves 1.10E+051.25E+07  1.26E+07 5.90E+07  DG O'Brien Electrical
 
Penetrations 1.79E+075.44E+07 Shielded 7.23E+07 2.20E+08  DG O'Brien Electrical
 
Penetrations (Plugs) 1.79E+075.44E+07 1.25E+078.48E+07 1.25E+08 Reliance Motors 1.57E+052.83E+07  2.84E+07 2.00E+08 Tavis Flow Transmitter 7.84E+021.08E+06  1.08E+06 1.40E+06 ITT Grinnel/Conoflow Transducer 7.84E+025.42E+06  5.42E+06 1.00E+07  Consolidated Control
 
Relays 3.14E+057.58E+04  3.90E+05 5.00E+05 General Atomic
 
Radiation Detector 1.79E+075.44E+07 2.00E+082.72E+08 Not Rad Sensitive Kerite Cable/Termination 1.57E+052.83E+07  2.84E+07 2.20E+08  Westinghouse Starter and Transformer 1.25E+052.53E+06  2.66E+06 5.00E+06 GOULD CONTACTOR/
DISCONNECT 7.84E+024.33E+06  4.33E+06 1.00E+07 Eaton Thermocouple
 
Extension Cable 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08  Brand Rex 600V
 
Instrument Cable (Dywell) 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08  Brand Rex 600V
 
Instrument Cable (RB) 7.84E+031.08E+08  1.08E+08 2.00E+08 Boston Control Cable 7.84E+031.08E+08  1.08E+08 2.00E+08 Page 11 of 19 Equipment Title EPU Normal Dose (rad) EPU Accident Gamma TID (rad) Beta Dose (rad) Total EPU TID (rad)
Qual. Dose (rad) Note  CONAX Electrical Connector Seal 1.79E+075.44E+07 2.25E+079.48E+07 2.25E+08  CONAX RTDs 1.18E+051.25E+07  1.26E+07 2.27E+08 Patel Conduit Seals (Drywell) 1.79E+075.44E+07 2.00E+079.23E+07 2.00E+08 Patel Conduit Seals (Contact SBGT
 
Filters) 7.84E+031.08E+08  1.08E+08 2.00E+08 Patel Conformal
 
Coating (outside
 
Drywell) 1.18E+051.25E+07  1.26E+07 2.00E+07 Patel Conformal Coating (Drywell) 1.79E+075.44E+07 2.00E+082.72E+08 3.06E+08  EGS Grayboot Electrical Connectors 1.79E+075.44E+07 2.00E+079.23E+07 2.08E+08 EGS Quick
 
Disconnect 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08  Raychem/Swagelok
 
Conduit Seals 1.57E+052.83E+07  2.84E+07 5.00E+07 Weed Thermocouples 1.79E+075.44E+07 2.00E+082.72E+08 3.06E+08  Rome Cable Type SIS 3.60E+043.25E+05  3.61E+05 5.00E+08 Eaton Cutler-Hammer Relays 5.33E+055.29E+05  1.06E+06 1.43E+06  PEI/FENWAL


Temperature Switch 1.18E+051.25E+07  1.26E+07 5.00E+07 ITT-Royal PVC Cable 5.33E+052.53E+06  3.07E+06 1.00E+07 Okonite Control
Calculations were prepared to evaluate the impact of EPU conditions on equipment for radiation, temperature, pressure and flood level for safety related equipment. These calculations and related results are described above. The majority of issues will be addressed by revisions to the EQ files that support continued qualification of existing equipment with the new EPU conditions. EQ file updates will be completed as required by 10 CFR 50.49 prior to EPU implementation. Any required modifications or replacement of equipment will also be completed prior to EPU implementation.
 
Page 19 of 19}}
Cable 3.14E+052.53E+06  2.85E+06 1.00E+07 Triangle Triolene
 
Control Cable 3.14E+057.58E+04  3.90E+05 3.90E+05  MNGP-A Cable 1.57E+052.83E+07  2.84E+07 5.00E+07  MNGP-B Cable 1.57E+052.83E+07  2.84E+07 4.10E+07 Amphenol Connectors 5.33E+053.79E+06  4.32E+06 6.00E+06  Pyco Temperature
 
Elements 3.14E+042.53E+06  2.57E+06 2.20E+08 SOR Pressure
 
Switches 5.33E+052.53E+06  3.07E+06 3.30E+07 General Electric Terminal Blocks 5.33E+052.17E+06  2.70E+06 2.20E+08 Patel P-1 Thread Sealant 1.79E+075.44E+07 2.00E+082.72E+08 1.50E+09 Rockbestos Firewall
 
SR Cable 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08 Page 12 of 19 Equipment Title EPU Normal Dose (rad) EPU Accident Gamma TID (rad) Beta Dose (rad) Total EPU TID (rad)
Qual. Dose (rad) Note  Rockbestos Firewall III/SIS Cable 1.79E+075.44E+07 1.00E+081.72E+08 2.00E+08 Rockbestos Firewall
 
EP Cable 1.57E+052.83E+07  2.84E+07 1.30E+08 Valcor MSIV
 
Solenoid Valves 3.14E+048.66E+04  1.18E+05 5.00E+07  Core Spray & RHR
 
High Voltage
 
Termination 1.57E+052.83E+07  2.84E+07 5.77E+07  Dow Corning 3-6548 Silicone RTV Foam 3.60E+04HELB only  3.60E+04 1.36E+06 Loctite PST 580
 
Thread Sealant 1.79E+075.44E+07 Shielded 7.23E+07 7.37E+07 Note Scotch 130C and 69 Electrical Tape 7.84E+031.08E+08  1.08E+08 1.83E+08 Fisher E/P Transducer 1.57E+054.33E+06  4.49E+06 6.00E+06 Cutler-Hammer Motor Starter/Control Transformer 1.24E+052.52E+06  2.65E+06 2.80E+06 Note ASCO Scram
 
Solenoid Pilot Valves 7.85E+04HELB only  7.85E+04 8.55E+04  Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
 
EPU HELB Evaluation HELB is discussed in PUSAR Section 2.2.1. Under the EPU evaluation for HELB, several high energy break or critical crack scenarios were considered for the Reactor Building. These included feedwater, reactor water cleanup, and control rod drive breaks and cracks in various areas. The EPU evaluation for HELBs, in combination with supporting calculations, provides the bases for temperatures, pressures and flood levels used for evaluation of HELBs in the Reactor and Turbine Buildings. The safe-shutdown equipment located in any Turbine Building locations made harsh (i.e. the peak HELB temperature greater than 140&deg;F) as a result of EPU are being determined and evaluated. 
 
From the evaluation for Reactor Building EPU event cases, the following peak conditions are obtained as compared to the current EQ Program Basis values for the respective
 
Reactor Building Volume:
Page 13 of 19 Current EQ Program Basis Data EPU Data RB Volume Temp
(&deg;F) Press (psia) Liquid (ft) Temp
(&deg;F) Press (psia) Liquid (ft) Comment 1 142.97 14.86 0.05114.214.810.4 Note  2 142.97 14.85 0.01115.214.80  3 143.8 14.98 0.05115.714.830.4 Note  4 144.4 14.97 0135.614.820  5 256 15.15 0.05121.314.810.5 Note  6 263.6 15.63 3.95157.214.80.6  7 240.4 15.19 4.38184.514.840.8  8 <140 14.99 0140.714.80.6 Note 9 187.6 15.59 0.01127.414.790.5 Note  10 159.9 15.59 0127.214.790.5 Note  11 158.7 15.59 0127.314.790.5 Note  12 193 15.59 0.01127.614.790.5 Note  13 127.3 14.88 0.24166.214.80 Note 14 153.3 14.83 0.27174.714.80 Note 15 209.6 15.3 0.05180.214.80  16 311.3 21.16 6.68213.115.228.8 Note  17 222.4 15.14 0130.614.790  18 208.1 15.11 0.68209.714.830 Note 19 175.9 15.13 0.53209.314.830.1 Note  20 112.5 15.14 0179.414.80.1 Note 21 112.2 14.87 010814.790  22 170.4 14.84 018414.790 Note 23 143.7 14.87 016414.790 Note 24 104 14.7 0104.414.70  25 145.8 14.85 0183.514.790 Note 26 109.1 14.89 0104.414.70  27 203.6 14.99 0.01211.714.830 Note 28 216.7 15.85 0.38213.315.031.6 Note  29 214.6 15.85 0.3213.515.41.7 Note  30 220.5 17.2 0.27218.216.521.4 Note 31 188.3 17.19 0.2721316.521.4 Note  32 164.1 15.85 0.19219.817.091.7 Note  33 128.3 14.99 0211.714.830 Note 34 168.3 14.83 0.005191.414.790 Note 35 207.8 14.84 0.02199.214.790  36 142.4 14.88 0141.614.790  37 112.8 14.88 0143.914.80 Note Page 14 of 19 Current EQ Program Basis Data EPU Data RB Volume Temp
(&deg;F) Press (psia) Liquid (ft) Temp
(&deg;F) Press (psia) Liquid (ft) Comment 38 100 14.7 0100.314.70  39 215.3 14.87 0.01112.214.80  40 126.2 14.84 0127.714.80  41 106.9 14.88 0104.414.70  42 204.7 14.85 0.01198.814.790  43 128.3 14.83 0.01122.214.780  44 160.8 14.82 0.01138.114.780  45 169.7 14.85 0.01198.614.780 Note 46 219.2 14.86 0.02106.214.770  47 101.5 14.84 0187.814.780 Note 48 131.1 14.8 0.01137.314.760 Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
EPU HELB Temperature Review From the table above, it is observed that the peak EPU liquid break HELB temperatures for Reactor Building Volumes 13, 14, 18, 19, 20, 22, 23, 24, 25, 27, 31, 32, 33, 34, 37, 38, 40, 45, 47, and 48 exceed the currently specified peak HELB temperature provided by the current EQ Program basis data. The peak EPU (or pre-EPU) HELB temperature in Reactor Building Volumes 24, 38, 40, and 48 are less than the harsh/mild threshold temperature of 140&deg;F, so these areas remain "mild". Based on EQ end device location and required performance, the impact of EPU HELB conditions focuses on Reactor Building Volumes 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, and 34. 
 
Equipment Title RB Volumes Qualified Temp.  (&deg;F) EPU Peak Temp (&deg;F) Note ASCO Solenoid Valves (Normally Energized) 18, 19 346 209.7 ASCO Solenoid Valves (Normally De-energized) 31 346 213  ASCO Pressure Switches 14, 19,  31210 213 Note  Barksdale Pressure Switch 14, 18, 22, 33 212 211.7  Barton Pressure Switches 14, 19 212 209.3 Barton Pressure Switches 580A-0, 580A-1 14, 18 200 209.7 Note G.E. Cable (butyl rubber SI-
 
58007/58136) 13, 14, 18, 19, 20, 22, 27, 33, 34 340 211.7 Page 15 of 19 Equipment Title RB Volumes Qualified Temp.  (&deg;F) EPU Peak Temp (&deg;F) Note GE Cable (PE type SI-58081) 13, 14, 18, 19, 20, 22, 27, 33, 34 236 211.7  GE Cable (XLPE type, SI-57275/58109) 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 340 219.8  General Electric Containment
 
Penetrations 14, 18 340 209.7  General Electric Terminal
 
Blocks 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 340 219.8 Limitorque MOVs (50.49, class RH, AC motor) 13, 19, 20, 22, 31 340 213  Limitorque MOVs (50.49, class RH, DC motor) 13, 32 340 219.8  Limitorque Fibrite Switches 13, 19, 20, 22,  31, 32420 219.8  Namco Limit Switches (EA740 w/o EC210) 31 352 213  Namco Limit Switches (EA180 w/o EC210) 18, 19, 31 361 213  Raychem NEIS Seals 18, 19, 31 366 213  Raychem WCSF-N Splices 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 350 219.8 Robertshaw Level Switch (DOR) 18 220 209.7  Rockbestos Coax Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 346 219.8 Rosemount 1153 Series A Transmitter (DOR) 33, 34 340 211.7  Rosemount 1153 Series B 14, 18, 19, 22, 27, 33, 34 318 211.7  Rosemount Conduit Seals 14, 18, 22, 27, 33 420 211.7  Rotork Valve Operators (50.49) 14, 31, 33 385 213  Static O-ring (DOR) 22, 33 212 211.7  Yarway Level (DOR) 14, 18 250 209.7 Page 16 of 19 Equipment Title RB Volumes Qualified Temp.  (&deg;F) EPU Peak Temp (&deg;F) Note Samuel Moore Instrument Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 340 219.8  Valcor Solenoid Valves 18, 19 365 209.7  DG O'Brien Electrical
 
Penetrations 14, 19 320 209.3  DG O'Brien Electrical
 
Penetrations (Plugs) 14, 19 345 209.3  Reliance Motors 14, 19 464 209.3  Consolidated Control Relays 18 223.1 209.7  Westinghouse Starter and Transformer 14, 19 260 209.3 Eaton Thermocouple Extension
 
Cable 14 375 174.7  Brand Rex 600V Instrument
 
Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 385 219.8  Boston Control Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 340 219.8  Patel Conduit Seals 18 354 209.7  EGS Grayboot Electrical
 
Connectors 31 450 213  EGS Quick Disconnect 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 435 219.8  Raychem/Swagelok Conduit Seals 14, 18, 19, 22, 33, 34 340 211.7  Eaton Cutler-Hammer Relays 22, 33, 34 232 211.7  ITT-Royal PVC Cable (DOR) 14, 18, 19, 22, 33 211 211.7 Note  Okonite Control Cable 14, 18, 19, 22 211 209.7 Triangle Triolene Control Cable (DOR) 18, 19 211 209.7  MNGP-A Cable (DOR) 13, 14, 18, 19, 20, 22, 27, 33, 34 230 211.7  MNGP-B Cable (DOR) 14, 19 211 209.3 Page 17 of 19 Equipment Title RB Volumes Qualified Temp.  (&deg;F) EPU Peak Temp (&deg;F) Note Amphenol Connectors (DOR) 14, 18, 19, 22, 33 266 211.7  SOR Pressure Switches (50.49) 14, 22, 33 350 211.7  General Electric Terminal Blocks (50.49) 22, 33, 34 340 211.7  Patel P-1 Thread Sealant 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 400 219.8  Rockbestos Firewall SR Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 351 219.8  Rockbestos Firewall III/SIS
 
Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 342 219.8  Rockbestos Firewall EP Cable 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 320 219.8 Loctite PST 580 Thread
 
Sealant 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 364 219.8  Scotch 130C and 69 Electrical
 
Tape 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, 34 372 219.8 Cutler-Hammer Motor Starter/Control Transformer 14, 19 253 209.3 ASCO Scram Solenoid Pilot
 
Valves 14, 18 277 209.7  Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
Post-LOCA Heat-up in the Reactor Building The Reactor Building post-LOCA heat-up temperatures are provided in the associated EPU evaluation. The EPU data as compared to the current post-LOCA heat-up (PLHU) data is presented below. It is observed that most post-LOCA area temperatures are relatively benign and will not present particular challenges to the EQ components that are generally tested or analyzed to much higher accident temperatures at their location.
However, additional supporting qualification analysis to be performed and documented Page 18 of 19 in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.
 
RB Volume Current PLHU Temp. (&deg;F) EPU PLHU Temp. (&deg;F) 1 110.0 104.3 2 110.0 106.2 3 129.1 129.7 4 129.1 129.5 5 109.9 107.4 6 140.4 140.6 7 116.3 123.6 8 106.2 111.9 9 160.4 177.5 10 159.9 177.5 11 158.7 177.5 12 157.3 177.5 13 112.6 112.7 14 107.6 112.3 15 106.3 108.7 16 135.2 141.5 17 106.1 108.9 18 109.3 114.9 19 106.3 114.9 20 112.6 113.1 21 112.2 107.8 22 106.7 114.1 23 106.4 113.8 24 104 104 25 113.9 114.1 26 109.1 109.7 27 109.1 115.4 28 120 121.3 29 120.1 121.1 30 120.2 128 31 120.2 129.7 32 120.2 120.7 33 115.6 115.4 34 107.9 114.2 35 107.8 114.2 36 134.4 120.5 37 112.8 120.5 Page 19 of 19 RB Volume Current PLHU Temp. (&deg;F) EPU PLHU Temp. (&deg;F) 38 100 100 39 126.3 134.5 40 105.6 113.2 41 106.9 109.8 42 104.6 114.2 43 109.7 110.9 44 108.1 112.1 45 104 114 46 107.2 110.3 47 100 113.7 48 103.9 113.2
 
==SUMMARY==
Calculations were prepared to evaluate the impact of EPU conditions on equipment for radiation, temperature, pressure and flood level for safety related equipment. These calculations and related results are described above. The majority of issues will be addressed by revisions to the EQ files that support continued qualification of existing equipment with the new EPU conditions. EQ file updates will be completed as required by 10 CFR 50.49 prior to EPU implementation. Any required modifications or replacement of equipment will also be completed prior to EPU implementation.}}

Latest revision as of 17:00, 14 November 2019

Extended Power Uprate: Acceptance Review Supplemental Information Package 5
ML081570467
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 06/05/2008
From: O'Connor T
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-08-042, TAC MD8398
Download: ML081570467 (22)


Text

Montkelh Nuclear Generatina Plant EwnmltdrdtbWEtrwllones Operated by Nudear Management Company, LLC June 5,2008 L-MT-08-042 10 CFR 50.90 U. S. Nuclear Regulatory Commission A T N : Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed Facility Operating License License No. DPR-22 Monticello Extended Power Uprate (USNRC TAC MD83981:

Acceptance Review Supplemental lnforrnation Package 5

References:

I)NMC Letter to USNRC, "License Amendment Request: Extended Power Uprate,"

dated March 31,2008 2 ) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAG MD8398): Acceptance Review Supplement Regarding Radiological Analysis,"

dated May 20,2008

3) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information," dated May 28, 2008
4) NMC Letter to USNRC, 'Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 3," dated May 30,2008
5) NMC Letter to USNRC, "Monticello Extended Power Uprate (USNRC TAC MD8398): Acceptance Review Supplemental Information Package 4," dated June 3,2008 Pursuant to 10 CFR 50.90, Nuclear Management Company, LLC (NMC), requested in Reference 1 approval of amendments to the Monticello Nuclear Generating Plant (MNGP) Renewed Operating License (OL) and Technical Specfications (TS) to increase the maximum power level authorized from 1775 megawatts thermal (MWt) to 1870 MWt, an approximate five percent increase in the current licensed thermal power (CLTP). The proposed request for Extended Power Uprate (EPU) represents an increase of approximately 12 percent above the Original Licensed Thermal Power (OLTP). The Monticello EPU application was supplemented on May 20, 2008, May 28,2008, May 30,2008, and June 3,2008 by References 2 , 3 , 4 and 5.

2807 West County Road 75 Monticello, Minnesota 563624637 Telephone: 763.295.5151 Fax: 783.295.1454

Document Control Desk Page 2 In a teleconference held May 2, 2008, the NRC staff indicated that additional information would be necessary for the Electrical Engineering Branch (EEEB) to complete the acceptance review of the Monticello EPU license amendment request (IAR). The questions were formalized and emailed to NMC on May 15,2008. On May 28,2008, NMC submitted responses (Reference 3) to EEEB Questions 2,3,and 4. of this letter contains the response to EEEB Question I.

NMC has reviewed the No Significant Hazards Consideration and the Environmental Consideration submitted with Reference 1 relative to the enclosed supplemental information. NMC has determined that there are no changes required to either of these sections of Reference 1.

Commitment Summan, This letter makes no new commitments and does not change any existing commitments.

I declare under penalty of perjury that the foregoing is true and correct.

on June 5 A 008.

resident, Monticello Nuclear Generating Plant Company, LLC cc: Administrator, Region Ill, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Minnesota Department of Commerce Enclosure

Enclosure 1 to L-MT-08-042 Electrical Engineering Branch Question 1 and Response 1

Enclosure 1

4) EEEB - ELECTRICAL ENGINEERING BRANCH NRC Question
1) In Section 2.3 of the LAR under the section titled 'Outside Containment', the licensee stated the following:

"The total integrated doses (normal plus accident) for EPU conditions were evaluated and determined not to adversely affect qualification of most of the EQ equipment located outside of containment. Equipment not qualified to the new environmental conditions at EPU will be reanalyzed, re-qualified, or replaced prior to implementation of EPU."

In order for the Electrical Engineering Branch (EEEB) to start its review, the full EQ analysis must be completed. This includes any reanalysis, re-qualification, or replacement of equipment. The licensee must also describe how the equipment was evaluated (e.g., calculations, assessments, etc.) and show how the equipment remains bounded (i.e., provide the original design parameters and the updated values including the supporting calculations).

NMC Response:

The responses to EEEB Questions 2, 3 and 4 were submitted in Monticello letter L-MT-08-039 on May 28, 2008. The following response is regarding EEEB Question 1.

Introduction The following information provides more detail regarding the analyses that have been completed relative to the qualification of electrical equipment outside containment. As required, the analyses have addressed the radiation, pressure, temperature and flooding effects from operation at extended power uprate (EPU) conditions. This information describes how the equipment was evaluated and notes where further action, per the applicable regulatory criteria and the Monticello Environmental Qualification (EQ)

Program, is necessary prior to implementation of EPU.

Normal Temperature Evaluation An evaluation was completed to assess the impact EPU will have on the normal design temperatures of the Reactor Building. A calculation supports the normal area temperature data for the EQ Program. This calculation uses both survey data and calculated data as inputs. For the Drywell and the Steam Chase, a calculation provides a basis for the normal ambient temperatures. The EPU evaluation indicates no change in normal Drywell temperatures for EPU and a slight increase in normal Steam Chase temperature (less than one degree). This small temperature increase is bounded by the temperature value currently used in the EQ program for the steam chase. Normal plant area ambient temperature will continue to be assessed by the EQ program in lieu of using the maximum design temperature for assessing qualified lifetimes. As such, there is no impact of EPU conditions on normal plant temperature inputs to qualified life assessments.

Page 1 of 19

Enclosure 1 Normal Radiation Dose The EPU evaluation for radiation levels generally indicates an increase of 13 percent for the Reactor Building dose and no change for most Turbine Building normal doses as the result of EPU (some areas of Turbine Building have dose rate increases). This evaluation provides survey data for most plant areas and identifies the applicable increase effect for each plant area outside the Drywell.

The current basis for normal radiation doses in the EQ program is provided by calculation. This calculation documents actual survey dose rate data for all of the Reactor Building and the Turbine Building. The tables below relate the normal radiation doses in the calculation for reactor and turbine building.

Reactor Building, Normal 60 Year Doses Current EQ Program Basis Projected 60 year Normal EPU Dose Predicted EPU Dose Current Dose rate Effect EPU 60 yr RB Volume Rate Survey 60 year (survey) (see Dose (Rad)

(Spec) mR/Hr date Dose (Rad) mR/Hr note) (see note) 1 (B.1.4) 200 01/18/03 1.39E+05 160 180.8 9.51E+04 2 (B.1.4) 200 01/18/03 1.39E+05 Not surv 3 (B.1.4) 100 12/29/02 6.94E+04 50 56.5 2.97E+04 4 (B.1.4) 100 12/29/02 6.94E+04 Not surv 5 (B.1.3) 1 08/18/02 6.94E+02 Not surv 6 (B.1.2) 1000 12/21/02 6.94E+05 100 113 5.94E+04 7 (B.1.10) 1 06/26/00 6.94E+02 Not surv 8 (B.1.2) 46 12/21/03 3.19E+04 3 3.39 1.78E+03 9 (B.1.6) 120 12/15/02 8.33E+04 50 56.5 2.97E+04 10 (B.1.6) 90 12/15/02 6.25E+04 30 33.9 1.78E+04 11 (B.1.6) 140 01/19/03 9.72E+04 60 67.8 3.57E+04 12 (B.1.6) 150 01/19/03 1.04E+05 30 33.9 1.78E+04 13 (B.1.8) 80 01/12/03 5.55E+04 20 22.6 1.19E+04 14 (B.1.9/11) 160 08/03/02 1.11E+05 60 67.8 3.57E+04 15 (B.1.9) 350 03/10/02 2.43E+05 50 56.5 2.97E+04 16 (B.1.7) 4000 07/01/98 2.78E+06 2000 2260 1.19E+06 17 (B.1.9) 4 12/29/02 2.78E+03 4 4.52 2.38E+03 18 (B.1.10) 400 01/21/03 2.78E+05 55 62.15 3.27E+04 19 (B.1.10/12) 42 12/29/02 2.92E+04 4 4.52 2.38E+03 20 (B.1.8) 80 01/18/03 5.55E+04 30 33.9 1.78E+04 21 (B.1.14) 100 02/08/03 6.94E+04 30 33.9 1.78E+04 22 (B.1.14) 80 12/15/02 5.55E+04 1 1.13 5.94E+02 Page 2 of 19

Enclosure 1 Reactor Building, Normal 60 Year Doses Current EQ Program Basis Projected 60 year Normal EPU Dose Predicted EPU Dose Current Dose rate Effect EPU 60 yr RB Volume Rate Survey 60 year (survey) (see Dose (Rad)

(Spec) mR/Hr date Dose (Rad) mR/Hr note) (see note) 23 (B.1.14) 80 02/10/02 5.55E+04 1 1.13 5.94E+02 24 1 01/18/03 6.94E+02 Not surv 25 1 12/15/02 6.94E+02 1 1.13 5.94E+02 26 18 01/18/03 1.25E+04 4 4.52 2.38E+03 27 (B.1.13/15) 260 08/12/02 1.81E+05 30 33.9 1.78E+04 28 (B.1.5) 40 01/04/02 2.78E+04 40 45.2 2.38E+04 29 (B.1.5) 20 01/04/02 1.39E+04 20 22.6 1.19E+04 30 (B.1.5) 800 01/04/02 5.55E+05 80 90.4 4.75E+04 31 (B.1.5) 2200 01/04/02 1.53E+06 2200 2486 1.31E+06 32 (B.1.5) 1600 01/04/02 1.11E+06 1600 1808 9.51E+05 33 (B.1.13) 680 08/12/02 4.72E+05 3 3.39 1.78E+03 34 (B.1.18) 40 12/15/02 2.78E+04 6 6.78 3.57E+03 35 (B.1.17) 5 12/15/02 3.47E+03 4 4.52 2.38E+03 36 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 37 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 38 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 39 (B.1.21) 1 08/26/02 6.94E+02 1 1.13 5.94E+02 40 (B.1.16) 2 08/26/02 1.39E+03 1 1.13 5.94E+02 41 (B.1.16) 2 01/18/03 1.39E+03 1 1.13 5.94E+02 42 (B.1.16) 20 12/15/02 1.39E+04 1 1.13 5.94E+02 43 (B.1.19) 700 12/27/02 4.86E+05 500 565 2.97E+05 44 (B.1.20) 200 12/27/02 1.39E+05 5 5.65 2.97E+03 45 (B.1.19) 2 12/27/02 1.39E+03 2 2.26 1.19E+03 46 (B.1.19) 200 12/27/02 1.39E+05 6 6.78 3.57E+03 47 (B.1.19) 1 12/27/02 6.94E+02 Not surv 48 36 02/06/03 2.50E+04 7 7.91 4.16E+03 Note: EPU 60-year basis dose was determined by increasing the shown dose rate by 13 percent taken over the number of hours over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values. As illustrated above, the projected 60-year normal dose due to EPU is bounded by the specified doses used in the current EQ Program for the Reactor Building.

Page 3 of 19

Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose Current Dose Rate Survey 60 year survey EPU EPU 60 yr TB Volume mR/Hr Date Dose (Rad) (mRem/hr) Effect Dose (Rad) 1 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 2 (B.1.24) 1 12/18/02 6.94E+02 1 1130% 5.94E+03 Increase 3 (B.1.24) 1 12/18/02 6.94E+02 1 1130% 5.94E+03 Increase 4 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 5 (B.1.24) 8 12/18/02 5.55E+03 1-2 No 1.05E+03 change 6 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 7 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 8 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 9 (B.1.24) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 10 (B.1.24) 2 12/18/02 1.39E+03 1 No 2.63E+03 1-5 change 11 (B.1.24) 200 01/29/03 1.39E+05 1 - 10 No 1.58E+04 30 change 12 (B.1.24) 120 05/01/02 8.33E+04 5 - 30 No 1.58E+04 change 13 (B.1.24) 2400 02/07/02 1.67E+06 2 - 1500 25 - 33% 1.05E+06 Increase 14 (B.1.24) 4000 07/01/98 2.78E+06 5 - 1800 Up to 1.07E+07 1130%

Increase 15 (B.1.24) 8 12/18/02 5.55E+03 1 No 5.26E+02 change 16 (B.1.24) 8 12/18/02 5.55E+03 1 No 5.26E+02 change 17 (B.1.24) 8 12/18/02 5.55E+03 1 No 5.26E+02 change 18 (B.1.24) 8 12/18/02 5.55E+03 1 No 5.26E+02 change 19 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 20 (B.1.23) 46 11/13/02 3.19E+04 Not No surveyed change 21 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change Page 4 of 19

Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose Current Dose Rate Survey 60 year survey EPU EPU 60 yr TB Volume mR/Hr Date Dose (Rad) (mRem/hr) Effect Dose (Rad) 22 (B.1.23) 12 11/13/02 8.33E+03 1 No 5.26E+02 change 23 (B.1.23) 1 12/18/02 6.94E+02 1-2 No 1.05E+03 change 24 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 25 (B.1.23) 2 12/04/02 1.39E+03 1 1130% 5.94E+03 Increase 26 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 27 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 28 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 29 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 30 (B.1.23) 8 02/06/02 5.55E+03 1 No 5.26E+02 change 31 (B.1.23) 1 02/06/02 6.94E+02 1 No 5.26E+02 change 32 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 33 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 34 (B.1.23) 1 03/28/02 6.94E+02 1 No 5.26E+02 change 35 (B.1.23) 1 03/28/02 6.94E+02 1 No 5.26E+02 change 36 (B.1.23) 1 03/28/02 6.94E+02 1 No 5.26E+02 change 37 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 38 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 39 (B.1.23) 1 12/18/02 6.94E+02 1 No 5.26E+02 change 40 (B.1.23) 60 12/18/02 4.17E+04 1-2 No 1.05E+03 change 41 (B.1.22) 80 05/08/00 5.55E+04 1-3 No 1.58E+03 change 42 (B.1.22) 3000 05/08/00 2.08E+06 1 - 1000 2 - 9% 1.72E+06 10 - 3000 Increase Page 5 of 19

Enclosure 1 Turbine Building, Normal 60 Year Doses Current EQ Program Basis Normal Dose Projected 60 year Normal EPU Dose Current Dose Rate Survey 60 year survey EPU EPU 60 yr TB Volume mR/Hr Date Dose (Rad) (mRem/hr) Effect Dose (Rad) 43 (B.1.23) 1 12/18/02 6.94E+02 Not No surveyed change 44 (B.1.22) 3000 05/08/00 2.08E+06 1 - 1000 2 - 9% 1.72E+06 10 - 3000 Increase Note: EPU 60-year basis dose was determined by increasing the highest shown dose rate by the EPU Effect value and then multiplying by the number of hours over 60 years (365.25 days/year used to account for leap years). No equivalent 60 year dose was determined for areas where the EPU evaluation did not provide dose rate values.

Based on the above, it is observed that the projected 60 year normal doses in Turbine Building Volumes 2, 3, 10, 14, 23, and 25 will increase from the current specified EQ Program data. These volumes, with the exception of 14, remain below the radiation harsh classification threshold as defined by the EQ program.

Accident Radiation Doses The EPU evaluation of the impacts of radiation on equipment qualification and the supporting vendor calculation performed by Alion provides the bases for EPU impacts on the EQ program from post-LOCA accident doses. The resulting EPU doses and the indicated increases by location are shown below.

% EPU Dose EPU 180-day TID, LOCATION Increase (Rads)

Drywell 2.5 5.44E+07 HPCI Room - Elevation 896' 7.3 2.73E+06 RCIC Room - Elevation 896' 7.5 1.82E+06 RHR Rooms - Elevation 896' 4.3 2.72E+07 RWCU Pump Room - Elevation 962' 7.8 2.52E+06 Torus Compartment - Elevation 896' 3.5 1.19E+07 Main Steam Chase - Elevation 935' 7.3 2.73E+06 LPCI Valve Injection Room - Elevation 7.8 2.52E+06 935' Reactor Building - Elevation 935' E 7.8 2.52E+06 Reactor Building - Elevation 935' W 7.8 2.52E+06 Reactor Building - Elevation 935' SE 7.8 2.52E+06 Reactor Building - Elevation 935' SW 7.8 2.52E+06 Reactor Building - Elevation 962' S 7.8 2.52E+06 Reactor Building - Elevation 962' E 7.8 2.52E+06 Reactor Building - Elevation 962' NW 7.8 2.52E+06 Page 6 of 19

Enclosure 1 Reactor Building - Elevation 985' N 7.9 1.29E+04 Reactor Building - Elevation 985' SW 7.9 1.29E+04 Reactor Building - Elevation 985' SE 7.9 1.29E+04 Reactor Building - Elevation 1001' N 7.9 1.29E+04 Reactor Building - Elevation 1001' S 7.9 1.29E+04 Standby Gas Treatment Room - Elevation 8.3 2.03E+08 985' Turbine Building Operating Deck -

0.0 <1.00E+04 Elevation 951' Turbine Building Condenser Room -

0.0 <1.00E+04 Elevations 907', 911' & 931' Cond Phase Separator Room 3.7 1.19E+07 Waste Collector Tank Room 7.7 3.87E+06 The accident doses developed in the subject EPU evaluation are supported by vendor calculation (ALION). The vendor calculation develops scaling factors on the original plant dose calculations developed in response to the Three Mile Island action plan. For the Reactor Building and Drywell, the EPU effective accident dose increase was shown to range from 2.5 to 8.3 percent with the 180-day integrated accident dose shown above.

For the Turbine Building, the calculation indicates that there were no original plant dose calculations developed for general areas of the Turbine Building. For comparison, the calculation indicates 1-hour dose rates of less than 500 mRem/hour for vital access areas of the Administrative Building that experience shine from the Reactor Building.

For conservatism, the accident dose was always listed as being <1.0E+04 Rad.

Accordingly, the revised combined 60-year normal doses and the 180-day accident doses under EPU have the potential to impact the qualification of EQ components in the Reactor Building. Using the methods prescribed in the individual EQ calculation files for operating time and distance factors, the revised normal and accident doses were evaluated and compared to the qualified dose as indicated below (for conservatism, the normal dose was increased by +13 percent). For the equipment located in the Drywell, Beta dose was also considered. The Beta dose specified in the Monticello EQ Program is taken from the DOR Guidelines (Division of Operating Reactors - Guidelines for Evaluating Environmental Qualification of Class 1E Electrical Equipment in Operating Reactors) as an unshielded 200 Mrad dose, which was developed from a 4,100 MWth reactor. Therefore, considerable margin is included in the Beta dose as it applies to Monticello.

Page 7 of 19

Enclosure 1 EPU EPU Normal Accident Beta Dose Gamma Dose Total EPU Qual. Note Equipment Title (rad) TID (rad) (rad) TID (rad) Dose (rad)

Allen Bradley 7.84E+02 4.33E+06 4.33E+06 2.51E+08 Terminal Boards ASCO Solenoid 1.57E+05 2.83E+07 2.84E+07 2.00E+08 Valves (Normally Energized) Group 1 ASCO Solenoid 9.41E+04 1.25E+07 1.25E+07 2.00E+08 Valves (Normally Energized) Group 2 ASCO Solenoid 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.00E+08 Valves (Normally Energized) Group 3 ASCO Solenoid 3.14E+05 2.53E+06 2.85E+06 2.00E+08 Valves (Normally Energized) Group 4 ASCO Solenoid 1.79E+07 5.44E+07 Shielded 7.23E+07 2.00E+08 Valves (Normally De-energized) Group 1 ASCO Solenoid 1.18E+05 1.25E+07 1.26E+07 2.00E+08 Valves (Normally De-energized) Group 2 ASCO Pressure 1.18E+05 1.25E+07 1.26E+07 1.93E+07 Switches ASCO Temperature 7.84E+02 1.08E+07 1.08E+07 1.50E+07 Switches Automatic Valve 2.79E+06 5.00E+06 Shielded 7.79E+06 7.79E+06 Note Solenoid Valves Barksdale Pressure 1.57E+05 6.50E+06 6.66E+06 1.00E+07 Switch Barton Pressure 1.57E+05 5.42E+05 6.99E+05 3.00E+06 Switches RHR Barton Pressure 1.30E+05 2.53E+06 2.66E+06 3.00E+06 Switches, Non-RHR Barton Pressure 3.14E+05 2.53E+06 2.85E+06 1.00E+07 Switches 580A-0, 580A-1 E.F. Johnson Banana 3.14E+06 HELB only 3.14E+06 4.70E+06 Plug G.E. Cable (Butyl 1.57E+05 2.83E+07 2.84E+07 4.00E+07 type)

G.E. Cable SIS & SI- 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.00E+08 Note 58109 Control G.E. Cable SI-58081 7.84E+03 2.17E+07 2.17E+07 2.44E+07 Control General Electric 1.57E+05 2.72E+07 2.74E+07 3.00E+07 Note Motors Page 8 of 19

Enclosure 1 EPU EPU Normal Accident Beta Dose Gamma Dose Total EPU Qual. Note Equipment Title (rad) TID (rad) (rad) TID (rad) Dose (rad)

General Electric 1.79E+07 5.44E+07 Shielded 7.23E+07 1.00E+08 Containment Penetrations General Electric 7.84E+02 2.03E+08 2.03E+08 2.20E+08 Note Terminal Blocks General Electric 3.60E+05 3.60E+05 1.00E+06 MCCs Hevi-Duty Electric 7.84E+02 4.71E+06 2.00E+06 2.00E+06 Note Transformer General Electric Fan 7.84E+02 1.08E+06 1.08E+06 1.00E+06 Note Motors Limitorque Motor 1.79E+07 5.44E+07 2.00E+06 7.43E+07 2.00E+08 Operators (DOR)

(MO-2397)

Limitorque Motor 3.14E+06 2.75E+06 5.89E+06 2.00E+07 Operators (DOR)

(MO-2107)

Limitorque Motor 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.00E+08 Operators (50.49)

Limitorque Motor 3.14E+06 2.75E+06 5.89E+06 1.00E+07 Operators (50.49)

Limitorque Motor 1.18E+05 1.25E+07 1.26E+07 2.00E+07 Operators (50.49)

Limitorque Motor 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.27E+08 Operators (50.49)

Limitorque Motor 1.18E+05 1.25E+07 1.26E+07 2.00E+07 Operators (50.49)(MO-4229 &

MO-4230)

Magnetrol Level 1.18E+05 1.25E+07 1.26E+07 2.20E+08 Switches McDonnell & Miller 7.84E+02 5.40E+06 5.40E+06 5.00E+06 Note Flow Switches MicroSwitch Limit 7.84E+02 1.07E+07 1.07E+07 1.00E+07 Note Switches Namco Limit 1.79E+07 5.44E+07 Shielded 7.23E+07 2.04E+08 Switches (50.49)

Namco Quick 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.04E+08 Disconnects EC210 Raychem NEIS Seals 1.18E+05 1.25E+07 1.26E+07 5.00E+07 Raychem Low 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.25E+08 Voltage Splices Robertshaw Level 3.14E+05 3.25E+05 6.39E+05 2.00E+06 Switch Rockbestos Coax 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 Cable Page 9 of 19

Enclosure 1 EPU EPU Normal Accident Beta Dose Gamma Dose Total EPU Qual. Note Equipment Title (rad) TID (rad) (rad) TID (rad) Dose (rad)

Rosemount Pressure 1.18E+05 1.25E+07 1.26E+07 4.40E+07 Transmitter Rosemount 1153 1.57E+05 2.83E+07 2.84E+07 2.62E+07 Note Series B Rosemount Conduit 1.18E+05 1.25E+07 1.26E+07 1.11E+08 Seals Rotork "A" Range 1.57E+05 1.62E+06 1.78E+06 4.00E+06 Actuators (DOR)

Rotork Valve 1.57E+05 2.83E+07 2.84E+07 1.84E+08 Operators (50.49)

Static O-ring 5.33E+05 5.74E+06 6.27E+06 8.00E+06 Yarway Level 3.14E+05 3.40E+05 6.54E+05 1.00E+06 Samuel Moore 7.84E+02 1.08E+08 1.08E+08 2.00E+08 Instrument Cable Valcor Solenoid 1.10E+05 1.25E+07 1.26E+07 5.90E+07 Valves DG O'Brien Electrical 1.79E+07 5.44E+07 Shielded 7.23E+07 2.20E+08 Penetrations DG O'Brien Electrical 1.79E+07 5.44E+07 1.25E+07 8.48E+07 1.25E+08 Penetrations (Plugs)

Reliance Motors 1.57E+05 2.83E+07 2.84E+07 2.00E+08 Tavis Flow 7.84E+02 1.08E+06 1.08E+06 1.40E+06 Transmitter ITT Grinnel/Conoflow 7.84E+02 5.42E+06 5.42E+06 1.00E+07 Transducer Consolidated Control 3.14E+05 7.58E+04 3.90E+05 5.00E+05 Relays General Atomic 1.79E+07 5.44E+07 2.00E+08 2.72E+08 Not Rad Radiation Detector Sensitive Kerite 1.57E+05 2.83E+07 2.84E+07 2.20E+08 Cable/Termination Westinghouse Starter 1.25E+05 2.53E+06 2.66E+06 5.00E+06 and Transformer GOULD 7.84E+02 4.33E+06 4.33E+06 1.00E+07 CONTACTOR/

DISCONNECT Eaton Thermocouple 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 Extension Cable Brand Rex 600V 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 Instrument Cable (Dywell)

Brand Rex 600V 7.84E+03 1.08E+08 1.08E+08 2.00E+08 Instrument Cable (RB)

Boston Control Cable 7.84E+03 1.08E+08 1.08E+08 2.00E+08 Page 10 of 19

Enclosure 1 EPU EPU Normal Accident Beta Dose Gamma Dose Total EPU Qual. Note Equipment Title (rad) TID (rad) (rad) TID (rad) Dose (rad)

CONAX Electrical 1.79E+07 5.44E+07 2.25E+07 9.48E+07 2.25E+08 Connector Seal CONAX RTDs 1.18E+05 1.25E+07 1.26E+07 2.27E+08 Patel Conduit Seals 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.00E+08 (Drywell)

Patel Conduit Seals 7.84E+03 1.08E+08 1.08E+08 2.00E+08 (Contact SBGT Filters)

Patel Conformal 1.18E+05 1.25E+07 1.26E+07 2.00E+07 Coating (outside Drywell)

Patel Conformal 1.79E+07 5.44E+07 2.00E+08 2.72E+08 3.06E+08 Coating (Drywell)

EGS Grayboot 1.79E+07 5.44E+07 2.00E+07 9.23E+07 2.08E+08 Electrical Connectors EGS Quick 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 Disconnect Raychem/Swagelok 1.57E+05 2.83E+07 2.84E+07 5.00E+07 Conduit Seals Weed 1.79E+07 5.44E+07 2.00E+08 2.72E+08 3.06E+08 Thermocouples Rome Cable Type 3.60E+04 3.25E+05 3.61E+05 5.00E+08 SIS Eaton Cutler- 5.33E+05 5.29E+05 1.06E+06 1.43E+06 Hammer Relays PEI/FENWAL 1.18E+05 1.25E+07 1.26E+07 5.00E+07 Temperature Switch ITT-Royal PVC Cable 5.33E+05 2.53E+06 3.07E+06 1.00E+07 Okonite Control 3.14E+05 2.53E+06 2.85E+06 1.00E+07 Cable Triangle Triolene 3.14E+05 7.58E+04 3.90E+05 3.90E+05 Control Cable MNGP-A Cable 1.57E+05 2.83E+07 2.84E+07 5.00E+07 MNGP-B Cable 1.57E+05 2.83E+07 2.84E+07 4.10E+07 Amphenol 5.33E+05 3.79E+06 4.32E+06 6.00E+06 Connectors Pyco Temperature 3.14E+04 2.53E+06 2.57E+06 2.20E+08 Elements SOR Pressure 5.33E+05 2.53E+06 3.07E+06 3.30E+07 Switches General Electric 5.33E+05 2.17E+06 2.70E+06 2.20E+08 Terminal Blocks Patel P-1 Thread 1.79E+07 5.44E+07 2.00E+08 2.72E+08 1.50E+09 Sealant Rockbestos Firewall 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 SR Cable Page 11 of 19

Enclosure 1 EPU EPU Normal Accident Beta Dose Gamma Dose Total EPU Qual. Note Equipment Title (rad) TID (rad) (rad) TID (rad) Dose (rad)

Rockbestos Firewall 1.79E+07 5.44E+07 1.00E+08 1.72E+08 2.00E+08 III/SIS Cable Rockbestos Firewall 1.57E+05 2.83E+07 2.84E+07 1.30E+08 EP Cable Valcor MSIV 3.14E+04 8.66E+04 1.18E+05 5.00E+07 Solenoid Valves Core Spray & RHR 1.57E+05 2.83E+07 2.84E+07 5.77E+07 High Voltage Termination Dow Corning 3-6548 3.60E+04 HELB only 3.60E+04 1.36E+06 Silicone RTV Foam Loctite PST 580 1.79E+07 5.44E+07 Shielded 7.23E+07 7.37E+07 Note Thread Sealant Scotch 130C and 69 7.84E+03 1.08E+08 1.08E+08 1.83E+08 Electrical Tape Fisher E/P 1.57E+05 4.33E+06 4.49E+06 6.00E+06 Transducer Cutler-Hammer 1.24E+05 2.52E+06 2.65E+06 2.80E+06 Note Motor Starter/Control Transformer ASCO Scram 7.85E+04 HELB only 7.85E+04 8.55E+04 Solenoid Pilot Valves Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.

EPU HELB Evaluation HELB is discussed in PUSAR Section 2.2.1. Under the EPU evaluation for HELB, several high energy break or critical crack scenarios were considered for the Reactor Building. These included feedwater, reactor water cleanup, and control rod drive breaks and cracks in various areas. The EPU evaluation for HELBs, in combination with supporting calculations, provides the bases for temperatures, pressures and flood levels used for evaluation of HELBs in the Reactor and Turbine Buildings. The safe-shutdown equipment located in any Turbine Building locations made harsh (i.e. the peak HELB temperature greater than 140°F) as a result of EPU are being determined and evaluated.

From the evaluation for Reactor Building EPU event cases, the following peak conditions are obtained as compared to the current EQ Program Basis values for the respective Reactor Building Volume:

Page 12 of 19

Enclosure 1 Current EQ Program Basis Data EPU Data RB Temp Press Liquid Temp Press Liquid Volume (°F) (psia) (ft) (°F) (psia) (ft) Comment 1 142.97 14.86 0.05 114.2 14.81 0.4 Note 2 142.97 14.85 0.01 115.2 14.8 0 3 143.8 14.98 0.05 115.7 14.83 0.4 Note 4 144.4 14.97 0 135.6 14.82 0 5 256 15.15 0.05 121.3 14.81 0.5 Note 6 263.6 15.63 3.95 157.2 14.8 0.6 7 240.4 15.19 4.38 184.5 14.84 0.8 8 <140 14.99 0 140.7 14.8 0.6 Note 9 187.6 15.59 0.01 127.4 14.79 0.5 Note 10 159.9 15.59 0 127.2 14.79 0.5 Note 11 158.7 15.59 0 127.3 14.79 0.5 Note 12 193 15.59 0.01 127.6 14.79 0.5 Note 13 127.3 14.88 0.24 166.2 14.8 0 Note 14 153.3 14.83 0.27 174.7 14.8 0 Note 15 209.6 15.3 0.05 180.2 14.8 0 16 311.3 21.16 6.68 213.1 15.22 8.8 Note 17 222.4 15.14 0 130.6 14.79 0 18 208.1 15.11 0.68 209.7 14.83 0 Note 19 175.9 15.13 0.53 209.3 14.83 0.1 Note 20 112.5 15.14 0 179.4 14.8 0.1 Note 21 112.2 14.87 0 108 14.79 0 22 170.4 14.84 0 184 14.79 0 Note 23 143.7 14.87 0 164 14.79 0 Note 24 104 14.7 0 104.4 14.7 0 25 145.8 14.85 0 183.5 14.79 0 Note 26 109.1 14.89 0 104.4 14.7 0 27 203.6 14.99 0.01 211.7 14.83 0 Note 28 216.7 15.85 0.38 213.3 15.03 1.6 Note 29 214.6 15.85 0.3 213.5 15.4 1.7 Note 30 220.5 17.2 0.27 218.2 16.52 1.4 Note 31 188.3 17.19 0.27 213 16.52 1.4 Note 32 164.1 15.85 0.19 219.8 17.09 1.7 Note 33 128.3 14.99 0 211.7 14.83 0 Note 34 168.3 14.83 0.005 191.4 14.79 0 Note 35 207.8 14.84 0.02 199.2 14.79 0 36 142.4 14.88 0 141.6 14.79 0 37 112.8 14.88 0 143.9 14.8 0 Note Page 13 of 19

Enclosure 1 Current EQ Program Basis Data EPU Data RB Temp Press Liquid Temp Press Liquid Volume (°F) (psia) (ft) (°F) (psia) (ft) Comment 38 100 14.7 0 100.3 14.7 0 39 215.3 14.87 0.01 112.2 14.8 0 40 126.2 14.84 0 127.7 14.8 0 41 106.9 14.88 0 104.4 14.7 0 42 204.7 14.85 0.01 198.8 14.79 0 43 128.3 14.83 0.01 122.2 14.78 0 44 160.8 14.82 0.01 138.1 14.78 0 45 169.7 14.85 0.01 198.6 14.78 0 Note 46 219.2 14.86 0.02 106.2 14.77 0 47 101.5 14.84 0 187.8 14.78 0 Note 48 131.1 14.8 0.01 137.3 14.76 0 Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.

EPU HELB Temperature Review From the table above, it is observed that the peak EPU liquid break HELB temperatures for Reactor Building Volumes 13, 14, 18, 19, 20, 22, 23, 24, 25, 27, 31, 32, 33, 34, 37, 38, 40, 45, 47, and 48 exceed the currently specified peak HELB temperature provided by the current EQ Program basis data. The peak EPU (or pre-EPU) HELB temperature in Reactor Building Volumes 24, 38, 40, and 48 are less than the harsh/mild threshold temperature of 140°F, so these areas remain mild. Based on EQ end device location and required performance, the impact of EPU HELB conditions focuses on Reactor Building Volumes 13, 14, 18, 19, 20, 22, 27, 31, 32, 33, and 34.

Qualified RB Temp. EPU Peak Equipment Title Volumes (°F) Temp (°F) Note ASCO Solenoid Valves 18, 19 346 209.7 (Normally Energized)

ASCO Solenoid Valves 31 346 213 (Normally De-energized)

ASCO Pressure Switches 14, 19, 31 210 213 Note Barksdale Pressure Switch 14, 18, 212 211.7 22, 33 Barton Pressure Switches 14, 19 212 209.3 Barton Pressure Switches 14, 18 200 209.7 Note 580A-0, 580A-1 G.E. Cable (butyl rubber SI- 13, 14, 18, 340 211.7 58007/58136) 19, 20, 22, 27, 33, 34 Page 14 of 19

Enclosure 1 Qualified RB Temp. EPU Peak Equipment Title Volumes (°F) Temp (°F) Note GE Cable (PE type SI-58081) 13, 14, 18, 236 211.7 19, 20, 22, 27, 33, 34 GE Cable (XLPE type, SI- 13, 14, 18, 340 219.8 57275/58109) 19, 20, 22, 27, 31, 32, 33, 34 General Electric Containment 14, 18 340 209.7 Penetrations General Electric Terminal 13, 14, 18, 340 219.8 Blocks 19, 20, 22, 27, 31, 32, 33, 34 Limitorque MOVs (50.49, class 13, 19, 20, 340 213 RH, AC motor) 22, 31 Limitorque MOVs (50.49, class 13, 32 340 219.8 RH, DC motor)

Limitorque Fibrite Switches 13, 19, 20, 420 219.8 22, 31, 32 Namco Limit Switches (EA740 31 352 213 w/o EC210)

Namco Limit Switches (EA180 18, 19, 31 361 213 w/o EC210)

Raychem NEIS Seals 18, 19, 31 366 213 Raychem WCSF-N Splices 13, 14, 18, 350 219.8 19, 20, 22, 27, 31, 32, 33, 34 Robertshaw Level Switch 18 220 209.7 (DOR)

Rockbestos Coax Cable 13, 14, 18, 346 219.8 19, 20, 22, 27, 31, 32, 33, 34 Rosemount 1153 Series A 33, 34 340 211.7 Transmitter (DOR)

Rosemount 1153 Series B 14, 18, 19, 318 211.7 22, 27, 33, 34 Rosemount Conduit Seals 14, 18, 22, 420 211.7 27, 33 Rotork Valve Operators (50.49) 14, 31, 33 385 213 Static O-ring (DOR) 22, 33 212 211.7 Yarway Level (DOR) 14, 18 250 209.7 Page 15 of 19

Enclosure 1 Qualified RB Temp. EPU Peak Equipment Title Volumes (°F) Temp (°F) Note Samuel Moore Instrument 13, 14, 18, 340 219.8 Cable 19, 20, 22, 27, 31, 32, 33, 34 Valcor Solenoid Valves 18, 19 365 209.7 DG O'Brien Electrical 14, 19 320 209.3 Penetrations DG O'Brien Electrical 14, 19 345 209.3 Penetrations (Plugs)

Reliance Motors 14, 19 464 209.3 Consolidated Control Relays 18 223.1 209.7 Westinghouse Starter and 14, 19 260 209.3 Transformer Eaton Thermocouple Extension 14 375 174.7 Cable Brand Rex 600V Instrument 13, 14, 18, 385 219.8 Cable 19, 20, 22, 27, 31, 32, 33, 34 Boston Control Cable 13, 14, 18, 340 219.8 19, 20, 22, 27, 31, 32, 33, 34 Patel Conduit Seals 18 354 209.7 EGS Grayboot Electrical 31 450 213 Connectors EGS Quick Disconnect 13, 14, 18, 435 219.8 19, 20, 22, 27, 31, 32, 33, 34 Raychem/Swagelok Conduit 14, 18, 19, 340 211.7 Seals 22, 33, 34 Eaton Cutler-Hammer Relays 22, 33, 34 232 211.7 ITT-Royal PVC Cable (DOR) 14, 18, 19, 211 211.7 Note 22, 33 Okonite Control Cable 14, 18, 19, 211 209.7 22 Triangle Triolene Control Cable 18, 19 211 209.7 (DOR)

MNGP-A Cable (DOR) 13, 14, 18, 230 211.7 19, 20, 22, 27, 33, 34 MNGP-B Cable (DOR) 14, 19 211 209.3 Page 16 of 19

Enclosure 1 Qualified RB Temp. EPU Peak Equipment Title Volumes (°F) Temp (°F) Note Amphenol Connectors (DOR) 14, 18, 19, 266 211.7 22, 33 SOR Pressure Switches 14, 22, 33 350 211.7 (50.49)

General Electric Terminal 22, 33, 34 340 211.7 Blocks (50.49)

Patel P-1 Thread Sealant 13, 14, 18, 400 219.8 19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall SR Cable 13, 14, 18, 351 219.8 19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall III/SIS 13, 14, 18, 342 219.8 Cable 19, 20, 22, 27, 31, 32, 33, 34 Rockbestos Firewall EP Cable 13, 14, 18, 320 219.8 19, 20, 22, 27, 31, 32, 33, 34 Loctite PST 580 Thread 14, 18, 19, 364 219.8 Sealant 20, 22, 27, 31, 32, 33, 34 Scotch 130C and 69 Electrical 13, 14, 18, 372 219.8 Tape 19, 20, 22, 27, 31, 32, 33, 34 Cutler-Hammer Motor 14, 19 253 209.3 Starter/Control Transformer ASCO Scram Solenoid Pilot 14, 18 277 209.7 Valves Note: Additional supporting qualification analysis to be performed and documented in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.

Post-LOCA Heat-up in the Reactor Building The Reactor Building post-LOCA heat-up temperatures are provided in the associated EPU evaluation. The EPU data as compared to the current post-LOCA heat-up (PLHU) data is presented below. It is observed that most post-LOCA area temperatures are relatively benign and will not present particular challenges to the EQ components that are generally tested or analyzed to much higher accident temperatures at their location.

However, additional supporting qualification analysis to be performed and documented Page 17 of 19

Enclosure 1 in EQ qualification file and/or equipment to be replaced/modified prior to EPU implementation.

RB Volume Current PLHU Temp. (°F) EPU PLHU Temp. (°F) 1 110.0 104.3 2 110.0 106.2 3 129.1 129.7 4 129.1 129.5 5 109.9 107.4 6 140.4 140.6 7 116.3 123.6 8 106.2 111.9 9 160.4 177.5 10 159.9 177.5 11 158.7 177.5 12 157.3 177.5 13 112.6 112.7 14 107.6 112.3 15 106.3 108.7 16 135.2 141.5 17 106.1 108.9 18 109.3 114.9 19 106.3 114.9 20 112.6 113.1 21 112.2 107.8 22 106.7 114.1 23 106.4 113.8 24 104 104 25 113.9 114.1 26 109.1 109.7 27 109.1 115.4 28 120 121.3 29 120.1 121.1 30 120.2 128 31 120.2 129.7 32 120.2 120.7 33 115.6 115.4 34 107.9 114.2 35 107.8 114.2 36 134.4 120.5 37 112.8 120.5 Page 18 of 19

Enclosure 1 RB Volume Current PLHU Temp. (°F) EPU PLHU Temp. (°F) 38 100 100 39 126.3 134.5 40 105.6 113.2 41 106.9 109.8 42 104.6 114.2 43 109.7 110.9 44 108.1 112.1 45 104 114 46 107.2 110.3 47 100 113.7 48 103.9 113.2

SUMMARY

Calculations were prepared to evaluate the impact of EPU conditions on equipment for radiation, temperature, pressure and flood level for safety related equipment. These calculations and related results are described above. The majority of issues will be addressed by revisions to the EQ files that support continued qualification of existing equipment with the new EPU conditions. EQ file updates will be completed as required by 10 CFR 50.49 prior to EPU implementation. Any required modifications or replacement of equipment will also be completed prior to EPU implementation.

Page 19 of 19