| | docket = 05000416 | | | docket = 05000416 |
| | license number = | | | license number = |
| | contact person = Gavula J A | | | contact person = Gavula J |
| | case reference number = EA-13-058, IR-13-201 | | | case reference number = EA-13-058, IR-13-201 |
| | document type = Slides and Viewgraphs, Meeting Briefing Package/Handouts | | | document type = Slides and Viewgraphs, Meeting Briefing Package/Handouts |
Line 20: |
Line 20: |
| {{#Wiki_filter:Pre-decisional Enforcement Conference in response to NRC Inspection Report 05000416/2013201 | | {{#Wiki_filter:Pre-decisional Enforcement Conference in response to NRC Inspection Report 05000416/2013201 |
|
| |
|
| Agenda Opening Remarks License Renewal Organization Performance Gaps Causes Corrective Actions Perspective on Significance Closing Remarks | | Agenda |
| | * Opening Remarks |
| | * License Renewal Organization |
| | * Performance Gaps |
| | * Causes |
| | * Corrective Actions |
| | * Perspective on Significance |
| | * Closing Remarks |
|
| |
|
| Opening Remarks Acknowledge each example to be valid Implemented interim corrective actions Finalizing causal evaluation Planning additional corrective actions | | Opening Remarks |
| | * Acknowledge each example to be valid |
| | * Implemented interim corrective actions |
| | * Finalizing causal evaluation |
| | * Planning additional corrective actions |
|
| |
|
| License Renewal Organization Corporate team focuses on: | | License Renewal Organization Entergy License Renewal Structure |
| -Standardization of IPA, TLAA, and ER efforts.
| | * Corporate team focuses on: |
| -Standardization of LRA; incorporating latest industry lessons learned and optimized practices.
| | -Standardization of IPA, TLAA, and ER efforts. |
| Site team focuses on: | | -Standardization of LRA; incorporating latest industry lessons learned and optimized practices. |
| -Confirmation of CLB, OE, DB, AMP detail. -Review of all IPA, TLAA, ER, and LRA documents before submittal to NRC. Entergy License Renewal Structure
| | * Site team focuses on: |
| | - Confirmation of CLB, OE, DB, AMP detail. |
| | - Review of all IPA, TLAA, ER, and LRA documents before submittal to NRC. |
|
| |
|
| Performance Gaps Failure to address all attributes of the RAI Failure to adequately describe the use of Moderate Energy Piping Procedure Failure to differentiate FAC and non | | Performance Gaps |
| -FAC wall-thinning mechanisms Ambiguous FAC procedure Failure to initiate CRs for significant wall thinning Causes Insufficient engagement, coordination, and oversight of Grand Gulf license renewal activities Inadequate and ambiguous guidance in FAC procedure Insufficient RAI response guidance in LRA Maintenance procedure | | * Failure to address all attributes of the RAI |
| | * Failure to adequately describe the use of Moderate Energy Piping Procedure |
| | * Failure to differentiate FAC and non-FAC wall-thinning mechanisms |
| | * Ambiguous FAC procedure |
| | * Failure to initiate CRs for significant wall thinning |
|
| |
|
| Corrective Actions Completed Actions Returned to the normal LRA business practice Reinforced NRC communication guidance Revised procedures for FAC and LRA Maintenance Conducted department stand | | Causes |
| -downs Corrective Actions Planned Actions Establish an escalation process Present OE and lessons learned at NEI License Renewal Task Force meeting Present OE to licensees who utilize Entergy License Renewal services Finalize Root Cause Evaluation Complete extent of condition | | * Insufficient engagement, coordination, and oversight of Grand Gulf license renewal activities |
| | * Inadequate and ambiguous guidance in FAC procedure |
| | * Insufficient RAI response guidance in LRA Maintenance procedure |
| | |
| | Corrective Actions Completed Actions |
| | * Returned to the normal LRA business practice |
| | * Reinforced NRC communication guidance |
| | * Revised procedures for FAC and LRA Maintenance |
| | * Conducted department stand-downs |
| | |
| | Corrective Actions Planned Actions |
| | * Establish an escalation process |
| | * Present OE and lessons learned at NEI License Renewal Task Force meeting |
| | * Present OE to licensees who utilize Entergy License Renewal services |
| | * Finalize Root Cause Evaluation |
| | * Complete extent of condition |
|
| |
|
| Perspective on Significance No impact during the period of extended operation Errors in LRA program descriptions No missing site aging management activities | | Perspective on Significance No impact during the period of extended operation Errors in LRA program descriptions No missing site aging management activities |
|
| |
|
| Perspective on Significance NRC Enforcement Policy guidance for SL III violation -Our errors should not result in the NRC changing a regulatory position | | Perspective on Significance NRC Enforcement Policy guidance for SL III violation |
| -Substantial further inquiry should not be required Conclusion Acknowledge each example to be valid Recognize that providing complete and accurate information is essential GGNS will ensure the fleet and industry learn from our mistakes}}
| | - Our errors should not result in the NRC changing a regulatory position |
| | - Substantial further inquiry should not be required |
| | |
| | Conclusion |
| | * Acknowledge each example to be valid |
| | * Recognize that providing complete and accurate information is essential |
| | * GGNS will ensure the fleet and industry learn from our mistakes}} |
|
---|
Category:Slides and Viewgraphs
MONTHYEARML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML22301A1412022-10-27027 October 2022 Overview of 10 CFR Part 21- Tim Steadham SRI Region IV ML22164A8012022-06-13013 June 2022 Entergy Fleet (GGNS, RBS, and WF-3) - Code Case N-752 RR 6-14-22 Pre-Submittal Public Meeting Presentation Slides ML21319A2452021-11-15015 November 2021 Natrium Energy Island Decoupling Strategy - 11-17-2021 ML21306A3162021-11-0909 November 2021 Digital IC Presentation 11/09/2021 ML21309A0622021-11-0909 November 2021 NRC Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21312A0342021-11-0909 November 2021 Combined Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21280A0282021-10-0404 October 2021 GG - NRC Slides for the October 4, 2021 Regulatory Performance Meeting and 95002 Supplemental Inspection Exit Meeting ML21280A0322021-10-0404 October 2021 GG - Entergy Presentation Slides for the October 4, 2021 Regulatory Performance Meeting and 95002 Supplemental Inspection Exit Meeting ML21200A1792021-07-31031 July 2021 Scale/Melcor Non-LWR Source Term Demonstration Project - High Temperature Gas-Cooled Reactor ML21126A3032021-05-10010 May 2021 Entergy Operations, Inc. Pre-Submittal Meeting - Grand Gulf Nuclear Station, Unit 1 Relief Request to Adopt Performance-based Testing for Pressure Isolation Valves (Pivs) ML21092A1542021-04-0202 April 2021 GG 2020 EOC Public Meeting Summary of Public Meeting with Entergy Operations, Inc ML20357B0612020-12-16016 December 2020 Enc 3 - Entergy Slides for Regulatory Conference December 2020 - Final ML20357B0592020-12-16016 December 2020 Enc 2 - Grand Gulf Nuclear Station Regulatory Conference December 2020 - NRC Presentation ML20344A0572020-12-10010 December 2020 Combined Industry and NRC Slides for the December 10, 2020, Public Meeting on Technology Inclusive Content of Application Project, Advanced Reactor Content of Application Project and Applicability of Regulations to Non-Light Water Reactors ML20269A3452020-09-28028 September 2020 Pre-submittal Meeting for Request for One-Time Exemption from 10 CFR Part 50, Appendix E, Biennial EP Exercise (Offsite) Due to COVID-19- Entergy Presentation Slides ML20176A3452020-06-24024 June 2020 Slides for Public Meeting Confirmatory Success Criteria Using Grand Gulf Nuclear Station ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML18075A1232018-03-20020 March 2018 Entergy Nuclear Operations - March 20, 2018, Presentation Slides for Surveillance Frequency Control Program, UFSAR Change Considerations ML17318A1592017-11-0808 November 2017 Meeting Slides - November 8, 2017 Teleconference with NEI Concerning Feedback on Tornado Missile Risk Evaluator Methodology -Final ML17101A4402017-04-11011 April 2017 Summary of Public Meeting with Entergy Operations, Inc. to Discuss Results of the Annual Assessment of Safety Performance at Grand Gulf Nuclear Station for 2016 ML14142A0412014-05-22022 May 2014 NRC Public Meeting Presentation Grand Gulf Flooding Hazard Reevaluation ML13199A3502013-07-16016 July 2013 Predecisional Enforcement Conference Presentation Slides July 16, 2013 ML12275A5492012-10-0101 October 2012 Summary of Meeting with Entergy Operations, Inc., to Discuss the Performance of the Subject Facilities, Recent Organizational Changes, and Current Regulatory Issues ML12034A0172012-01-31031 January 2012 License Renewal Process and Environmental Scoping Meeting ML1109600692011-04-0505 April 2011 Licensee Slides from 4/5/11 Pre-Submittal Meeting with Entergy Operations, Inc. Regarding Changes to TSs and QA Program Manual for Unit Staff Qualifications ML1003603572010-02-18018 February 2010 Steam Dryer 2/18/10 NRC Presentation, Redacted Version ML0935201272009-12-18018 December 2009 Nrc/Entergy Operations, Inc., Management Meeting ML0932102002009-11-12012 November 2009 Licensee Slides, Extended Power Uprate - Impact on Steam Dryer ML0921003112009-07-29029 July 2009 Presentation Slides, SFST June 2009 Monthly Seminar - Operational Experience. ML0909100632009-03-31031 March 2009 Entergy Operations, Inc., Project Planning Slides for March 31, 2009, Nrc/Entergy Pre-Application Meeting - Power Uprates ML0634500682006-12-0505 December 2006 12/5/06 Public Meeting Handout from Entergy/Epri Re GGNS Application of N-716 ML0613103512006-05-11011 May 2006 Summary of Meeting with Entergy Operations, Inc., Annual Performance Assessment for Grand Gulf Nuclear Station ML0617802712006-03-0707 March 2006 RIC 2006 Presentation - T2E - Vincent Coulehan - Use of Operating Experience (Regulator/Operator/Licensee) ML0615902322006-03-0707 March 2006 2006/03/07- - RIC 2006 Presentation - T1F - Garry G. Young - License Renewal ML0615901582006-03-0707 March 2006 03/07/2006 - RIC 2006 Presentation - T1E - John F. Mccann - License Renewal ML0607204302006-03-0101 March 2006 March 1, 2006 Public Meeting Slides for Proposed Generic Letter Post-Fire Safe-Shutdown Circuit Analysis Spurious Actuations. ML0532206852005-11-17017 November 2005 Nrc/Entergy Operations, Inc. Management Meeting 11/10/05 ML0514701102005-05-25025 May 2005 Summary of End of Cycle Public Meeting with Entergy Operations, Inc. on Grand Gulf Nuclear Station Performance for Period of 01/01/2004 - 12/31/2004 ML0510203182005-05-0404 May 2005 Licensee'S Slides for 04/11/2005 Summary of Category 1 Meeting with Entergy Corporation, to Discuss an Alternate Compliance Strategy for Meeting Fire Wrap Requirements in Certain Plant Areas ML0422602762004-08-12012 August 2004 Meeting Summary of the August 8, 2004 Public Workshop - Region IV Operator Licensing Feedback ML0323705292003-08-22022 August 2003 Summary of Nrc/Entergy Operations, Inc. Management Meeting ML0316400872003-04-28028 April 2003 Summary of Annual Performance Assessment Meeting for Grand Gulf Nuclear Station ML0210903352002-04-17017 April 2002 Annual Performance Assessment Meeting for Grand Gulf to Discuss Safety Performance at Grand Gulf Between 04/01/2001 & 12/31/2001 2023-12-14
[Table view] Category:Meeting Briefing Package/Handouts
MONTHYEARML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML21309A0622021-11-0909 November 2021 NRC Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21312A0342021-11-0909 November 2021 Combined Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21200A1792021-07-31031 July 2021 Scale/Melcor Non-LWR Source Term Demonstration Project - High Temperature Gas-Cooled Reactor ML21126A3032021-05-10010 May 2021 Entergy Operations, Inc. Pre-Submittal Meeting - Grand Gulf Nuclear Station, Unit 1 Relief Request to Adopt Performance-based Testing for Pressure Isolation Valves (Pivs) ML20357B0592020-12-16016 December 2020 Enc 2 - Grand Gulf Nuclear Station Regulatory Conference December 2020 - NRC Presentation ML20357B0612020-12-16016 December 2020 Enc 3 - Entergy Slides for Regulatory Conference December 2020 - Final ML20344A0572020-12-10010 December 2020 Combined Industry and NRC Slides for the December 10, 2020, Public Meeting on Technology Inclusive Content of Application Project, Advanced Reactor Content of Application Project and Applicability of Regulations to Non-Light Water Reactors ML20269A3452020-09-28028 September 2020 Pre-submittal Meeting for Request for One-Time Exemption from 10 CFR Part 50, Appendix E, Biennial EP Exercise (Offsite) Due to COVID-19- Entergy Presentation Slides ML19122A4202019-05-0202 May 2019 Summary of Public Meeting with Entergy Operations, Inc ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML17283A4122017-10-10010 October 2017 Grand Gulf Nuclear Station, Unit 1 - Meeting Slides - October 10, 2017 Pre-Application Meeting with Grand Gulf Concerning Tornado Missile Risk Evaluator Submittal ML13199A3502013-07-16016 July 2013 Predecisional Enforcement Conference Presentation Slides July 16, 2013 ML12275A5492012-10-0101 October 2012 Summary of Meeting with Entergy Operations, Inc., to Discuss the Performance of the Subject Facilities, Recent Organizational Changes, and Current Regulatory Issues ML1203401902012-01-30030 January 2012 (Non- Proprietary) Licensee Slides from 1/30/12 Meeting with Entergy Operations, Inc ML1117906392011-06-28028 June 2011 Summary of Meeting with Entergy Operations Inc ML1109600692011-04-0505 April 2011 Licensee Slides from 4/5/11 Pre-Submittal Meeting with Entergy Operations, Inc. Regarding Changes to TSs and QA Program Manual for Unit Staff Qualifications ML1003603572010-02-18018 February 2010 Steam Dryer 2/18/10 NRC Presentation, Redacted Version ML0935201272009-12-18018 December 2009 Nrc/Entergy Operations, Inc., Management Meeting ML0932102002009-11-12012 November 2009 Licensee Slides, Extended Power Uprate - Impact on Steam Dryer ML0921003112009-07-29029 July 2009 Presentation Slides, SFST June 2009 Monthly Seminar - Operational Experience. ML0909100632009-03-31031 March 2009 Entergy Operations, Inc., Project Planning Slides for March 31, 2009, Nrc/Entergy Pre-Application Meeting - Power Uprates ML0712005272007-04-30030 April 2007 Nrc/Entergy Operations, Inc. Management Meeting to Discuss the Performance of Arkansas Nuclear One, Cooper, Grand Gulf, River Bend and Waterford, Unit 3 ML0634500682006-12-0505 December 2006 12/5/06 Public Meeting Handout from Entergy/Epri Re GGNS Application of N-716 ML0613103512006-05-11011 May 2006 Summary of Meeting with Entergy Operations, Inc., Annual Performance Assessment for Grand Gulf Nuclear Station ML0510203182005-05-0404 May 2005 Licensee'S Slides for 04/11/2005 Summary of Category 1 Meeting with Entergy Corporation, to Discuss an Alternate Compliance Strategy for Meeting Fire Wrap Requirements in Certain Plant Areas ML0418202762004-06-30030 June 2004 Summary of Meeting with Entergy Operations, Inc Re Initial Examination and Requalification Program Improvements ML0324717142003-09-0202 September 2003 Meeting with Entergy Nuclear Potomac Plans for NRC to Conduct Inspections of Quality Assurance Measures in Support of Prospective ESP Application for Grand Gulf Site ML0323705292003-08-22022 August 2003 Summary of Nrc/Entergy Operations, Inc. Management Meeting ML0208107562002-03-19019 March 2002 Operator Licensing Workshop Meeting Summary 2023-12-14
[Table view] |
Text
Pre-decisional Enforcement Conference in response to NRC Inspection Report 05000416/2013201
Agenda
- Perspective on Significance
Opening Remarks
- Acknowledge each example to be valid
- Implemented interim corrective actions
- Finalizing causal evaluation
- Planning additional corrective actions
License Renewal Organization Entergy License Renewal Structure
- Corporate team focuses on:
-Standardization of IPA, TLAA, and ER efforts.
-Standardization of LRA; incorporating latest industry lessons learned and optimized practices.
- Confirmation of CLB, OE, DB, AMP detail.
- Review of all IPA, TLAA, ER, and LRA documents before submittal to NRC.
Performance Gaps
- Failure to address all attributes of the RAI
- Failure to adequately describe the use of Moderate Energy Piping Procedure
- Failure to differentiate FAC and non-FAC wall-thinning mechanisms
- Failure to initiate CRs for significant wall thinning
Causes
- Insufficient engagement, coordination, and oversight of Grand Gulf license renewal activities
- Inadequate and ambiguous guidance in FAC procedure
- Insufficient RAI response guidance in LRA Maintenance procedure
Corrective Actions Completed Actions
- Returned to the normal LRA business practice
- Reinforced NRC communication guidance
- Revised procedures for FAC and LRA Maintenance
- Conducted department stand-downs
Corrective Actions Planned Actions
- Establish an escalation process
- Finalize Root Cause Evaluation
- Complete extent of condition
Perspective on Significance No impact during the period of extended operation Errors in LRA program descriptions No missing site aging management activities
Perspective on Significance NRC Enforcement Policy guidance for SL III violation
- Our errors should not result in the NRC changing a regulatory position
- Substantial further inquiry should not be required
Conclusion
- Acknowledge each example to be valid
- Recognize that providing complete and accurate information is essential
- GGNS will ensure the fleet and industry learn from our mistakes