Entergy Operations, Inc., Project Planning Slides for March 31, 2009, Nrc/Entergy Pre-Application Meeting - Power Uprates
ML090910063
Person / Time
Site: Palisades, Grand Gulf, FitzPatrick  Entergy icon.png
Issue date: 03/31/2009
From:
Entergy Operations
To:
Office of Nuclear Reactor Regulation
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
TAC ME0922, TAC ME0923, TAC ME0924
Download: ML090910063 (12)


Text

Entergy Power Uprate Project Planning March 31, 2009 1

Entergy Power Uprate Projects O Introductions O Project Overview / Organization O Licensing Goals O Projected Submittal Schedules O Topics of Interest O Summary 2

Project Overview O Grand Gulf1 15% EPU OLTP Spring 2012 O James A. FitzPatrick2 20% EPU OLTP Fall 2012 O Palisades 3.3% SPU OLTP Under study 1Grand Gulf EPU project has not received final internal approvals and is presented here based on current projections and proposed timing.

2JAF EPU project has not received final internal approvals and is presented here based on current projections and proposed timing.

3

Organization VP - PM VP - ENGINEERING GM Project GM Major Projects Engineering Site Director Director Eng. Director VP Power Uprate Power Uprate Site Eng.

(Typ.)

Director Director Manager, Supv Project Sr Mgr, GG EPU Fitz. EPU Licensing Controls Proj Mgmt Engineering Engineering Engineering Manager Manager Manager JAF GGNS Palisades Mgr, Mgr, Contracts/

Mgr, Regulatory Mgr, Licensing Standards Oversight 4

Licensing Principles O NRR Office Instruction LIC-109 O NRC Review Standard RS-001 O Industry operating experience and lessons from recent submittals O Approved Licensing Topical Reports

- NEDC 33004 (CLTR)

- NEDC 33410 (PRNM LTR)

- NEDC 32410 (Stability LTR)

- NEDC 33006 (MELLLA+ LTR) 5

LAR Summary GGNS JAF 15% 20%

MWe Online 2012 2012 24-Month Cycle X current PRNMS X X Extended Power X X Uprate MELLLA+ X X License Renewal X current 6

Proposed GGNS Timeline Projected Submittal Submittal Date NRC Review 24 Month Dec. 2011 12 Months PRNMS Oct. 2009 9 Months EPU July 2010 16 Months MELLLA+ Dec. 2011 12 Months NRC Reviews 2009 2010 2011 2012 2013 24 Month PRNMS EPU MELLLA+

Lic. Renewal 7

Proposed JAF Timeline Projected Submittal Submittal Date NRC Review PRNMS Nov. 2009 11 Months EPU Oct. 2010 18 Months MELLLA+ April 2012 12 Months NRC Reviews 2009 2010 2011 2012 2013 PRNMS EPU MELLLA+

8

Proposed Palisades Timeline Projected Submittal Submittal Date NRC Review Stretch Uprate Feb. 2012 14 Months NRC Reviews 2009 2010 2011 2012 2013 SPU 9

Topics of Interest O Containment Overpressure Credit - JAF

- Credited in current licensing basis

- EPU analysis consistent with recent BWR EPUs O Large Transient Testing O Steam Dryers

- Steam line instrumented / acoustic analysis

- Vermont Yankee experience 10

LAR Summary 2009 2010 2011 2012 2013 GGNS GGNS 24 Month PRNMS EPU MELLLA+

Lic. Renewal JAF JAF PRNMS EPU MELLLA+

11

Questions 12