Entergy Operations, Inc., Project Planning Slides for March 31, 2009, Nrc/Entergy Pre-Application Meeting - Power Uprates
ML090910063
Person / Time
Site: Palisades, Grand Gulf, FitzPatrick  Entergy icon.png
Issue date: 03/31/2009
From:
Entergy Operations
To:
Office of Nuclear Reactor Regulation
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
TAC ME0922, TAC ME0923, TAC ME0924
Download: ML090910063 (12)


Text

1 Entergy Power Uprate Project Planning March 31, 2009

2 Entergy Power Uprate Projects O Introductions O Project Overview / Organization O Licensing Goals O Projected Submittal Schedules O Topics of Interest O Summary

3 Project Overview O Grand Gulf1 15% EPU OLTP Spring 2012 O James A. FitzPatrick2 20% EPU OLTP Fall 2012 O Palisades 3.3% SPU OLTP Under study 1Grand Gulf EPU project has not received final internal approvals and is presented here based on current projections and proposed timing.

2JAF EPU project has not received final internal approvals and is presented here based on current projections and proposed timing.

4 Organization Director GG EPU GM Major Projects Director Power Uprate Sr Mgr, Proj Mgmt

Mgr, Standards Director Fitz. EPU GM Project Engineering Mgr, Regulatory Engineering Manager GGNS Mgr, Licensing Director Eng.

Power Uprate VP - PM VP - ENGINEERING Supv Project Controls Engineering Manager Palisades Engineering Manager JAF Director Site Eng.

Site VP

Manager, Licensing Mgr, Contracts/

Oversight (Typ.)

5 Licensing Principles O NRR Office Instruction LIC-109 O NRC Review Standard RS-001 O Industry operating experience and lessons from recent submittals O Approved Licensing Topical Reports

- NEDC 33004 (CLTR)

- NEDC 33410 (PRNM LTR)

- NEDC 32410 (Stability LTR)

- NEDC 33006 (MELLLA+ LTR)

6 LAR Summary current X

License Renewal X

X MELLLA+

X X

Extended Power Uprate X

X PRNMS current X

24-Month Cycle 2012 JAF 20%

2012 GGNS 15%

MWe Online

7 Proposed GGNS Timeline 24 Month PRNMS EPU MELLLA+

Lic. Renewal 2009 2010 2011 2012 2013 Projected Submittal Submittal Date NRC Review 24 Month Dec. 2011 12 Months PRNMS Oct. 2009 9 Months EPU July 2010 16 Months MELLLA+

Dec. 2011 12 Months NRC Reviews

8 Proposed JAF Timeline PRNMS EPU MELLLA+

2009 2010 2011 2012 2013 Projected Submittal Submittal Date NRC Review PRNMS Nov. 2009 11 Months EPU Oct. 2010 18 Months MELLLA+

April 2012 12 Months NRC Reviews

9 Proposed Palisades Timeline Projected Submittal Submittal Date NRC Review Stretch Uprate Feb. 2012 14 Months SPU 2009 2010 2011 2012 2013 NRC Reviews

10 Topics of Interest O Containment Overpressure Credit - JAF

- Credited in current licensing basis

- EPU analysis consistent with recent BWR EPUs O Large Transient Testing O Steam Dryers

- Steam line instrumented / acoustic analysis

- Vermont Yankee experience

11 LAR Summary GGNS 24 Month PRNMS EPU MELLLA+

Lic. Renewal JAF PRNMS EPU MELLLA+

2009 2010 2011 2012 2013 GGNS JAF

12 Questions