| issue date = 09/20/2016
| issue date = 09/20/2016
| title = Request for Additional Information, Request for Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management
| title = Request for Additional Information, Request for Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management
| author name = Lyon C F
| author name = Lyon C
| author affiliation = NRC/NRR/DORL/LPLIV-1
| author affiliation = NRC/NRR/DORL/LPLIV-1
| addressee name = Marik S M
| addressee name = Marik S
| addressee affiliation = Omaha Public Power District
| addressee affiliation = Omaha Public Power District
| docket = 05000285
| docket = 05000285
| license number = DPR-040
| license number = DPR-040
| contact person = LYON C F, DORL/LPLIV-1, 415-2296
| contact person = LYON C, DORL/LPLIV-1, 415-2296
| case reference number = CAC MF8112
| case reference number = CAC MF8112
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008 September 20, 2016
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 20, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008


==SUBJECT:==
==SUBJECT:==
FORT CALHOUN STATION, UNIT NO. 1 -REQUEST FOR ADDITIONAL INFORMATION RE: CERTIFIED FUEL HANDLER TRAINING PROGRAM (CAC NO. MF8112)  
FORT CALHOUN STATION, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION RE: CERTIFIED FUEL HANDLER TRAINING PROGRAM (CAC NO. MF8112)


==Dear Mr. Marik:==
==Dear Mr. Marik:==
By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16190A208), Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1. The U.S. Nuclear Regulatory Commission staff has reviewed the information provided in your submittal and determined that additional information is required in order to complete its formal review of your request. The enclosed questions were provided to E. Matzke of your staff on September 16, 2016. Please provide a response to the enclosed questions within 30 days of the date of this letter. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.
 
Docket No. 50-285  
By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16190A208), Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1.
The U.S. Nuclear Regulatory Commission staff has reviewed the information provided in your submittal and determined that additional information is required in order to complete its formal review of your request. The enclosed questions were provided to E. Matzke of your staff on September 16, 2016. Please provide a response to the enclosed questions within 30 days of the date of this letter.
If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.
Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285


==Enclosure:==
==Enclosure:==


Request for Additional Information cc w/encl: Distribution via Listserv Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION CERTIFIED FUEL HANDLER TRAINING PROGRAM OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION. UNIT NO. 1 DOCKET NO. 50-285 By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16190A208}, Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1 (FCS). The U.S. Nuclear Regulatory Commission (NRG) staff has reviewed the information provided in the submittal and determined that the additional information discussed below is required in order to complete its formal review of the request. RAl-1 The NRG staff has reviewed Certified Fuel Handler Training Program approval requests for several decommissioning licensees, and those requests include a section titled "Evaluating Changes to the Certified Fuel Handler Training and Retraining Program," which generally states that changes may be made to program elements without NRG approval as long as the following are applicable:
Request for Additional Information cc w/encl: Distribution via Listserv
(1) suitable proficiency in the performance of the program's activities is maintained; and (2) changes are documented in an accessible manner that will allow the NRG to verify the adequacy of the program in accordance with Section 50.120 of Title 10 of the Code of Federal Regulations.
The submittal for FCS appears to be missing this section. Please provide a justification for why this section is not included in the submittal, or where the information is located if it is included.
Enclosure Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008 September 20, 2016
 
==SUBJECT:==
FORT CALHOUN STATION, UNIT NO. 1 -REQUEST FOR ADDITIONAL INFORMATION RE: CERTIFIED FUEL HANDLER TRAINING PROGRAM (CAC NO. MF8112)
 
==Dear Mr. Marik:==
By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 16190A208), Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1. The U.S. Nuclear Regulatory Commission staff has reviewed the information provided in your submittal and determined that additional information is required in order to complete its formal review of your request. The enclosed questions were provided to E. Matzke of your staff on September 16, 2016. Please provide a response to the enclosed questions within 30 days of the date of this letter. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.
Docket No. 50-285


==Enclosure:==
REQUEST FOR ADDITIONAL INFORMATION CERTIFIED FUEL HANDLER TRAINING PROGRAM OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION. UNIT NO. 1 DOCKET NO. 50-285 By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16190A208}, Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1 (FCS).
The U.S. Nuclear Regulatory Commission (NRG) staff has reviewed the information provided in the submittal and determined that the additional information discussed below is required in order to complete its formal review of the request.
RAl-1 The NRG staff has reviewed Certified Fuel Handler Training Program approval requests for several decommissioning licensees, and those requests include a section titled "Evaluating Changes to the Certified Fuel Handler Training and Retraining Program," which generally states that changes may be made to program elements without NRG approval as long as the following are applicable: (1) suitable proficiency in the performance of the program's activities is maintained; and (2) changes are documented in an accessible manner that will allow the NRG to verify the adequacy of the program in accordance with Section 50.120 of Title 10 of the Code of Federal Regulations. The submittal for FCS appears to be missing this section. Please provide a justification for why this section is not included in the submittal, or where the information is located if it is included.
Enclosure


Sincerely, IRA/ Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION:
ML16263A049                                                          *via email OFFICE NRR/DORL/LPL4-1/PM NRR/DORL/LPL4-1 /LA NRR/DRA/AHPB/BC NRR/DORL/LPL4-1 /BC NRR/DORL/LPL4-1 /PM NAME   Fl yon             JBurkhardt           SWeerakkody*   RPascarelli          Fl yon DATE   09/19/16           09/16/16             09/14/16       09/19/16             09/20/16}}
PUBLIC LPL4-1 Reading RidsACRS_MailCTR Resource RidsNrrDorllpl4-1 Resource RidsNrrDraAhpb Resource RidsNrrLAJBurkhardt Resource ADAMS Accession No. ML 16263A049 OFFICE NRR/DORL/LPL4-1/PM NRR/DORL/LPL4-1  
/LA NRR/DRA/AHPB/BC NAME Fl yon JBurkhardt SWeerakkody*
DATE 09/19/16 09/16/16 09/14/16 OFFICIAL RECORD COPY RidsNrrPMFortCalhoun Resource RidsRgn4MailCenter Resource MKeefe-Forsyth, NRR/DRNAHPB
*via email NRR/DORL/LPL4-1
/BC NRR/DORL/LPL4-1
/PM RPascarelli Fl yon 09/19/16 09/20/16}}

Latest revision as of 14:01, 30 October 2019

Request for Additional Information, Request for Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management
ML16263A049
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 09/20/2016
From: Lyon C
Plant Licensing Branch IV
To: Marik S
Omaha Public Power District
LYON C, DORL/LPLIV-1, 415-2296
References
CAC MF8112
Download: ML16263A049 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 20, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008

SUBJECT:

FORT CALHOUN STATION, UNIT NO. 1 - REQUEST FOR ADDITIONAL INFORMATION RE: CERTIFIED FUEL HANDLER TRAINING PROGRAM (CAC NO. MF8112)

Dear Mr. Marik:

By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16190A208), Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1.

The U.S. Nuclear Regulatory Commission staff has reviewed the information provided in your submittal and determined that additional information is required in order to complete its formal review of your request. The enclosed questions were provided to E. Matzke of your staff on September 16, 2016. Please provide a response to the enclosed questions within 30 days of the date of this letter.

If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.

Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285

Enclosure:

Request for Additional Information cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION CERTIFIED FUEL HANDLER TRAINING PROGRAM OMAHA PUBLIC POWER DISTRICT FORT CALHOUN STATION. UNIT NO. 1 DOCKET NO. 50-285 By letter dated July 7, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16190A208}, Omaha Public Power District submitted a request for approval of the Certified Fuel Handler Training and Retraining Program at Fort Calhoun Station, Unit No. 1 (FCS).

The U.S. Nuclear Regulatory Commission (NRG) staff has reviewed the information provided in the submittal and determined that the additional information discussed below is required in order to complete its formal review of the request.

RAl-1 The NRG staff has reviewed Certified Fuel Handler Training Program approval requests for several decommissioning licensees, and those requests include a section titled "Evaluating Changes to the Certified Fuel Handler Training and Retraining Program," which generally states that changes may be made to program elements without NRG approval as long as the following are applicable: (1) suitable proficiency in the performance of the program's activities is maintained; and (2) changes are documented in an accessible manner that will allow the NRG to verify the adequacy of the program in accordance with Section 50.120 of Title 10 of the Code of Federal Regulations. The submittal for FCS appears to be missing this section. Please provide a justification for why this section is not included in the submittal, or where the information is located if it is included.