Line 3: Line 3:
| issue date = 11/19/2012
| issue date = 11/19/2012
| title = E-mail, Request for Additional Information, Review of Revisions 18 and 19 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (D91660)
| title = E-mail, Request for Additional Information, Review of Revisions 18 and 19 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (D91660)
| author name = Wilkins L E
| author name = Wilkins L
| author affiliation = NRC/NRR/DORL/LPLIV
| author affiliation = NRC/NRR/DORL/LPLIV
| addressee name = Hansher B R
| addressee name = Hansher B
| addressee affiliation = Omaha Public Power District
| addressee affiliation = Omaha Public Power District
| docket = 05000285
| docket = 05000285
| license number = DPR-040
| license number = DPR-040
| contact person = Wilkins L E
| contact person = Wilkins L
| case reference number = D91660
| case reference number = D91660
| document type = E-Mail
| document type = E-Mail
| page count = 2
| page count = 2
| project =
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter:Lent, Susan From: Wilkins, Lynnea Sent: Monday, November 19, 2012 5:15 PM To: HANSHER, BILL R Cc: LIPPY, DONNA L; EDWARDS, MICHAEL L  
{{#Wiki_filter:Lent, Susan From:                       Wilkins, Lynnea Sent:                       Monday, November 19, 2012 5:15 PM To:                         HANSHER, BILL R Cc:                         LIPPY, DONNA L; EDWARDS, MICHAEL L


==Subject:==
==Subject:==
DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660) Attachments:
DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660)
50 54 Changes RAls Email.docx Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.
Attachments:                 50 54 Changes RAls Email.docx
The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).
: Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).
The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain related information and should be withheld from public disclosure.
Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain security related information and should be withheld from public disclosure.
Thanks Lynnea Lynnea Wi[ICins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: 301-415-1377 1
Thanks Lynnea Lynnea Wi[ICins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: 301-415-1377 1
Lent, Susan From: Wilkins, Lynnea Sent: Monday, November 19, 2012 5:15 PM To: HANSHER, BILL R Cc: LIPPY, DONNA L; EDWARDS, MICHAEL L  
 
Lent, Susan From:                       Wilkins, Lynnea Sent:                       Monday, November 19, 2012 5:15 PM To:                         HANSHER, BILL R Cc:                         LIPPY, DONNA L; EDWARDS, MICHAEL L


==Subject:==
==Subject:==
DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660) Attachments:
DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660)
50 54 Changes RAls Email.docx Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure.
Attachments:                 50 54 Changes RAls Email.docx
The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).
: Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).
The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain related information and should be withheld from public disclosure.
Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain security related information and should be withheld from public disclosure.
Thanks Lynnea Lynnea Wi(kins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US N udear Regulatory Commission Phone: 301-415-1377 1}}
Thanks Lynnea Lynnea Wi(kins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US N udear Regulatory Commission Phone: 301-415-1377 1}}

Latest revision as of 19:52, 11 November 2019

E-mail, Request for Additional Information, Review of Revisions 18 and 19 of the Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan (D91660)
ML12325A393
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/19/2012
From: Lynnea Wilkins
Plant Licensing Branch IV
To: Hansher B
Omaha Public Power District
Wilkins L
References
D91660
Download: ML12325A393 (2)


Text

Lent, Susan From: Wilkins, Lynnea Sent: Monday, November 19, 2012 5:15 PM To: HANSHER, BILL R Cc: LIPPY, DONNA L; EDWARDS, MICHAEL L

Subject:

DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660)

Attachments: 50 54 Changes RAls Email.docx

Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).

The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.

Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain security related information and should be withheld from public disclosure.

Thanks Lynnea Lynnea Wi[ICins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: 301-415-1377 1

Lent, Susan From: Wilkins, Lynnea Sent: Monday, November 19, 2012 5:15 PM To: HANSHER, BILL R Cc: LIPPY, DONNA L; EDWARDS, MICHAEL L

Subject:

DRAFT: RAI for Fort Calhoun Station Re: 50.54 Changes (D91660)

Attachments: 50 54 Changes RAls Email.docx

Bill, By letter dated August 2,2012, Omaha Public Power District submitted the Fort Calhoun Station's Physical Security Plan (PSP), Training and Qualification Plan, and Safeguards Contingency Plan (SCP), Revisions 18 and 19. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(p)(2).

The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.

Please contact me if a clarifying teleconference is needed for the attached RAls. The RAls contain security related information and should be withheld from public disclosure.