{{finding
{{finding
| title = Loss Of Onsite Safety Review Committee Independence
| title = Loss of Onsite Safety Review Committee Independence
| docket = 05000458
| docket = 05000458
| inspection report = IR 05000458/2012010
| inspection report = IR 05000458/2012010

Latest revision as of 20:47, 20 February 2018

07
Site: River Bend Entergy icon.png
Report IR 05000458/2012010 Section 4OA5
Date counted Sep 30, 2012 (2012Q3)
Type: NCV: Green
cornerstone Miscellaneous
Identified by: NRC identified
Inspection Procedure: IP 93800
Inspectors (proximate) A Barrett
B Tindell
E Uribe
B Hagar
Violation of: 10 CFR 50 Appendix B

10 CFR 50 Appendix B Criterion V
CCA H.13, Consistent Process
INPO aspect DM.1
'