| Q | CCA | Title |
---|
05000458/FIN-2011004-01 | 2011Q3 | H.14 | Inadequate Standby Gas Treatment Electric Heater Power Output Calculation |
05000458/FIN-2011004-02 | 2011Q3 | H.13 | Ineffective Corrective Actions on the Main Steam Equalizing Header Drain Bypass Valve Results in an Unplanned Down Power |
05000458/FIN-2011008-04 | 2011Q4 | | Station Blackout-Containment Venting |
05000458/FIN-2011008-06 | 2011Q4 | | Failure to Obtain NRC Approval for Change to Ultimate Heat Sink Inventory Requirements |
05000458/FIN-2011402-01 | 2011Q4 | H.14 | Security |
05000458/FIN-2011008-09 | 2011Q4 | H.9 | Inadequate Simulator Fidelity for Emergency Diesel Generator Loading |
05000458/FIN-2011008-08 | 2011Q4 | P.5 | Inadequate Emergency and Abnormal Procedures for Standby Diesel Generator Fail to Load Sequences |
05000458/FIN-2011008-07 | 2011Q4 | H.9 | Inadequate Abnormal Procedure for Reducing Loads on Standby Diesel Generators |
05000458/FIN-2011008-03 | 2011Q4 | | Failure to Establish Residual Heat Removal Heat Exchanger Testing Frequency |
05000458/FIN-2011005-01 | 2011Q4 | H.12 | Standby Service Water Pump Motor Lubrication Deficiencies |
05000458/FIN-2011005-02 | 2011Q4 | H.2 | Failure to Adequately Monitor the Performance of the Control Building Chiller System |
05000458/FIN-2011008-02 | 2011Q4 | P.2 | Failure to Use Conservative Design Assumptions in the Ultimate Heat Sink Inventory Calculation |
05000458/FIN-2011008-05 | 2011Q4 | | Inadequate Procedures for Monitoring Standby Service Water System Leakage |
05000458/FIN-2011008-01 | 2011Q4 | P.2 | Inadequate Testing of Division I and Division III Standby Diesel Generators |
05000458/FIN-2012002-01 | 2012Q1 | H.9 | Failure to Adequately Monitor the Performance of the Digital Radiation Monitoring System |
05000458/FIN-2012002-02 | 2012Q1 | H.8 | Failure to Appropriately Assess and Manage Risk for Internal Flooding Events |
05000458/FIN-2012002-03 | 2012Q1 | H.14 | Failure to Verify Assumptions used in Standby Equipment Room Temperature Analysis |
05000458/FIN-2012002-04 | 2012Q1 | H.7 | Failure to Appropriately Set Reactor Core Isolation Cooling Flow Controller High Output Limit |
05000458/FIN-2012002-05 | 2012Q1 | H.8 | Inadequate Relief Valve Configuration Control Results in a Reactor Downpower |
05000458/FIN-2012002-06 | 2012Q1 | H.7 | Inadequate Maintenance Instructions for the Suppression Pool Cooling Isolation Valves |
05000458/FIN-2012002-07 | 2012Q1 | H.8 | Failure to Perform a Radiation Survey |
05000458/FIN-2012002-08 | 2012Q1 | H.2 | Failure to Control Access to a High Radiation Area |
05000458/FIN-2012002-09 | 2012Q1 | | Failure to Properly Fabricate and Install the mid-Standard Turbine Shaft Brush |
05000458/FIN-2012003-01 | 2012Q2 | H.2 | Failure to Follow Procedure to Protect Sensitive Plant Areas |
05000458/FIN-2012003-02 | 2012Q2 | H.13 | Failure to Follow Severe Weather Operations Procedure |
05000458/FIN-2012003-03 | 2012Q2 | P.1 | High Pressure Core Spray Diesel Generator Bearing Lubrication Deficiencies |
05000458/FIN-2012003-04 | 2012Q2 | | Failure to Properly Assemble Turbine Control Valve Push ROD-SPRING Housing Coupling |
05000458/FIN-2012003-05 | 2012Q2 | | Failure to Specify Manual Actions for Safety Relief Valve Operations During a Station Blackout Event |