ML12125A013: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(6 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML12125A013
| number = ML12125A013
| issue date = 05/15/2012
| issue date = 05/15/2012
| title = Point Beach Nuclear Plant, Units 1 and 2 - Acknowledgment Letter Withdrawal of License Amendment Request (ME8488 & ME8489)
| title = Acknowledgment Letter Withdrawal of License Amendment Request (ME8488 & ME8489)
| author name = Beltz T A
| author name = Beltz T
| author affiliation = NRC/NRR/DORL/LPLIII-1
| author affiliation = NRC/NRR/DORL/LPLIII-1
| addressee name = Meyer L
| addressee name = Meyer L
Line 9: Line 9:
| docket = 05000266, 05000301
| docket = 05000266, 05000301
| license number = DPR-024, DPR-027
| license number = DPR-024, DPR-027
| contact person = Beltz T A
| contact person = Beltz T
| case reference number = TAC ME8488, TAC ME8489
| case reference number = TAC ME8488, TAC ME8489
| document type = Letter
| document type = Letter
| page count = 2
| page count = 2
| project = TAC:ME8488, TAC:ME8489
| project = TAC:ME8488, TAC:ME8489
| stage = Other
| stage = Withdrawal
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 Ma.y 15, 2012 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 -WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489) Dear Mr. Meyer: By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuantto 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request. The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register. If you have any questions regarding this matter, please contact me at (301) 415-3049. Sincerely, --'-"-,"....' . Terry A.'/ Beltz, Senior Project Manager Plant licensing Branch 111-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via listServ Mr. Larry Meyer May 15,2012 Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 -WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489) Dear Mr. Meyer: By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating Licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuant to 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request. The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register. If you have any questions regarding this matter, please contact me at (301) 415-3049. Sincerely, IRAJ Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via ListServ DISTRIBUTION: Public RidsAcrsAcnw MailCTR Resource RidsNrrDeEeeb Resource LPL3-1 rlt RidsNrrDorlDpr Resource RidsNrrDeEptb Resource RidsNrrLABTully RidsRgn3MailCenter Resource RidsNrrDssSbpb Resource RidsNrrPMPointBeach Resource RidsOgcMailCenter Resource RidsNrrDssStsb Resource RidsNrrDorlLpl3-1 Resource RidsNrrDe Resource RidsNrrDss Resource ADAMS Accession No' ML12125A013 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC LPL3-1/PM NAME TBeitz BTuily IFrankl IPTam for TBeitz DATE 05/10112 05114/12 05/15/12 OFFICIAL RECORD COpy
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Ma.y 15, 2012 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241
}}
 
==SUBJECT:==
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489)
 
==Dear Mr. Meyer:==
 
By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuantto 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request.
The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register.
If you have any questions regarding this matter, please contact me at (301) 415-3049.
Sincerely,
_/-;;~&1-
                                              ....:.:-:Z.~ ~t~.* ' . "~
                                                        '/
Terry A. Beltz, Senior Project Manager Plant licensing Branch 111-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via listServ
 
Mr. Larry Meyer                                 May 15,2012 Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241
 
==SUBJECT:==
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489)
 
==Dear Mr. Meyer:==
 
By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating Licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuant to 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request.
The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register.
If you have any questions regarding this matter, please contact me at (301) 415-3049.
Sincerely, IRAJ Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via ListServ DISTRIBUTION:
Public                         RidsAcrsAcnw MailCTR Resource             RidsNrrDeEeeb Resource LPL3-1 rlt                     RidsNrrDorlDpr Resource                   RidsNrrDeEptb Resource RidsNrrLABTully                 RidsRgn3MailCenter Resource               RidsNrrDssSbpb Resource RidsNrrPMPointBeach Resource   RidsOgcMailCenter Resource               RidsNrrDssStsb Resource RidsNrrDorlLpl3-1 Resource     RidsNrrDe Resource                       RidsNrrDss Resource ADAMS Accession No' ML12125A013 OFFICE     LPL3-1/PM           LPL3-1/LA             LPL3-1/BC               LPL3-1/PM NAME     TBeitz               BTuily                 IFrankl IPTam for       TBeitz DATE     ~11/12                05/10112               05114/12               05/15/12 OFFICIAL RECORD COpy}}

Latest revision as of 16:40, 6 February 2020

Acknowledgment Letter Withdrawal of License Amendment Request (ME8488 & ME8489)
ML12125A013
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/15/2012
From: Beltz T
Plant Licensing Branch III
To: Meyer L
Point Beach
Beltz T
References
TAC ME8488, TAC ME8489
Download: ML12125A013 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Ma.y 15, 2012 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489)

Dear Mr. Meyer:

By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuantto 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request.

The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register.

If you have any questions regarding this matter, please contact me at (301) 415-3049.

Sincerely,

_/-;;~&1-

....:.:-:Z.~ ~t~.* ' . "~

'/

Terry A. Beltz, Senior Project Manager Plant licensing Branch 111-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via listServ

Mr. Larry Meyer May 15,2012 Site Vice President NextEra Energy Point Beach, LLC Point Beach Nuclear Plant 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NOS. ME8488 AND ME8489)

Dear Mr. Meyer:

By letter dated April 26, 2012, as supplemented by letter dated April 30, 2012, NextEra Energy Point Beach, LLC (NextEra) applied for a license amendment to Renewed Facility Operating Licenses DPR-24 and DPR-27 for the Point Beach Nuclear Plant (PBNP), Units 1 and 2, respectively. The proposed amendment was submitted under emergency circumstances pursuant to 10 CFR 50.90 and 10 CFR 50.91 (a)(5), and would have changed the facility Technical Specifications on a one-time only basis. Subsequently, by letter dated May 2,2012, NextEra withdrew the amendment request.

The purpose of this letter is to advise you that the above application is being treated as withdrawn. A notice of consideration of issuance of the proposed amendment had not been published in the Federal Register.

If you have any questions regarding this matter, please contact me at (301) 415-3049.

Sincerely, IRAJ Terry A. Beltz, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: Distribution via ListServ DISTRIBUTION:

Public RidsAcrsAcnw MailCTR Resource RidsNrrDeEeeb Resource LPL3-1 rlt RidsNrrDorlDpr Resource RidsNrrDeEptb Resource RidsNrrLABTully RidsRgn3MailCenter Resource RidsNrrDssSbpb Resource RidsNrrPMPointBeach Resource RidsOgcMailCenter Resource RidsNrrDssStsb Resource RidsNrrDorlLpl3-1 Resource RidsNrrDe Resource RidsNrrDss Resource ADAMS Accession No' ML12125A013 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC LPL3-1/PM NAME TBeitz BTuily IFrankl IPTam for TBeitz DATE ~11/12 05/10112 05114/12 05/15/12 OFFICIAL RECORD COpy