Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. | Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later. | ||
ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later. | |||
The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants. | The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants. | ||
The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment. | The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment. | ||
Line 38: | Line 37: | ||
==Subject:== | ==Subject:== | ||
Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. | Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later. | ||
ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later. | |||
The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants. | The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants. | ||
The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment. | The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment. |
Latest revision as of 03:45, 5 February 2020
ML16102A005 | |
Person / Time | |
---|---|
Site: | McGuire, Mcguire |
Issue date: | 04/08/2016 |
From: | Geoffrey Miller Plant Licensing Branch II |
To: | Vu P Duke Energy Corp |
References | |
Download: ML16102A005 (2) | |
Text
NRR-PMDAPEm Resource From: Miller, Ed Sent: Friday, April 08, 2016 2:48 PM To: 'Vu, Phong T (Phong.Vu@duke-energy.com)'
Subject:
Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later.
The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants.
The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment.
If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence. If you have any questions, please contact me at (301) 415-2481.
G. Edward Miller Project Manager Plant Licensing Branch 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 1
Hearing Identifier: NRR_PMDA Email Number: 2767 Mail Envelope Properties (d1e9ee656a064c96a2f2b8eecc1c1575)
Subject:
Acceptance review for Type A ILRT Extension Sent Date: 4/8/2016 2:47:48 PM Received Date: 4/8/2016 2:47:00 PM From: Miller, Ed Created By: Ed.Miller@nrc.gov Recipients:
"'Vu, Phong T (Phong.Vu@duke-energy.com)'" <Phong.Vu@duke-energy.com>
Tracking Status: None Post Office: HQPWMSMRS02.nrc.gov Files Size Date & Time MESSAGE 1706 4/8/2016 2:47:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
NRR-PMDAPEm Resource From: Miller, Ed Sent: Friday, April 08, 2016 2:48 PM To: 'Vu, Phong T (Phong.Vu@duke-energy.com)'
Subject:
Acceptance review for Type A ILRT Extension PT, By letter dated February 18, 2016 (Agencywide Documents Access and Management System Accession No. ML16076A413, Duke Energy Carolinas, LLC (Duke Energy) requested approval of a one-time extension of the Appendix J Type-A Integrated Leakage Rate Test Interval for McGuire. Specifically, the proposed amendment would add an additional 6 months to allow the test to be performed one refueling outage later.
The purpose of this e-mail is to provide you with the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this submittal. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants.
The NRC staff has reviewed your submittal and concluded that it does provide technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and protection of public health and safety and the environment.
If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence. If you have any questions, please contact me at (301) 415-2481.
G. Edward Miller Project Manager Plant Licensing Branch 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 1
Hearing Identifier: NRR_PMDA Email Number: 2767 Mail Envelope Properties (d1e9ee656a064c96a2f2b8eecc1c1575)
Subject:
Acceptance review for Type A ILRT Extension Sent Date: 4/8/2016 2:47:48 PM Received Date: 4/8/2016 2:47:00 PM From: Miller, Ed Created By: Ed.Miller@nrc.gov Recipients:
"'Vu, Phong T (Phong.Vu@duke-energy.com)'" <Phong.Vu@duke-energy.com>