|
|
(4 intermediate revisions by the same user not shown) |
Line 2: |
Line 2: |
| | number = ML120060041 | | | number = ML120060041 |
| | issue date = 01/06/2012 | | | issue date = 01/06/2012 |
| | title = Grand Gulf, Unit 1 - Acceptance Review Email, License Amendment Request to Revise Minimum Critical Power Ratio Safety Limit in Technical Specification 2.1.1.2 for Two-Loop and Single Recirculation Loop (TAC No. ME7531) | | | title = Acceptance Review Email, License Amendment Request to Revise Minimum Critical Power Ratio Safety Limit in Technical Specification 2.1.1.2 for Two-Loop and Single Recirculation Loop |
| | author name = Wang A B | | | author name = Wang A |
| | author affiliation = NRC/NRR/DORL/LPLIV | | | author affiliation = NRC/NRR/DORL/LPLIV |
| | addressee name = Jackson R R, Perino C L, Seiter J A | | | addressee name = Jackson R, Perino C, Seiter J |
| | addressee affiliation = Entergy Operations, Inc | | | addressee affiliation = Entergy Operations, Inc |
| | docket = 05000416 | | | docket = 05000416 |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:From: Wang, Alan Sent: Friday, January 06, 2012 8:51 AM To: JACKSON, RITA R; Perino, Christina; 'SEITER, JEFFERY ALAN' Cc: Burkhardt, Janet; Lent, Susan | | {{#Wiki_filter:From: Wang, Alan Sent: Friday, January 06, 2012 8:51 AM To: JACKSON, RITA R; Perino, Christina; 'SEITER, JEFFERY ALAN' Cc: Burkhardt, Janet; Lent, Susan |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Acceptance of Grand Gulf Nuclear Station License Amendment Reqest Regarding Minimun Critical Power Ration Safety Limit TS Change (ME7531) Rita, Jeff and Christina, By letter dated October 28, 2011 (Agencywide Documents Access and Management System, Accession No. ML113060150), Entergy Operations, Inc. (Entergy, the licensee), submitted a request to amend the Facility Operating License No. NPF-29 for Grand Gulf Nuclear Station, Unit 1 (GGNS). The licensee proposed a license amendment request (LAR) to revise Minimum Critical Power Ratio Safety Limit (MCPR) values for both two loop and single loop operation in accordance with the requirements set forth in GE Nuclear Energy Topical Report NEDC-33173P, "Applicability fo GE Methods to Expanded Operating Domains, Rev. 0." | | Acceptance of Grand Gulf Nuclear Station License Amendment Reqest Regarding Minimun Critical Power Ration Safety Limit TS Change (ME7531) |
| | | Rita, Jeff and Christina, By letter dated October 28, 2011 (Agencywide Documents Access and Management System, Accession No. ML113060150), Entergy Operations, Inc. (Entergy, the licensee), submitted a request to amend the Facility Operating License No. NPF-29 for Grand Gulf Nuclear Station, Unit 1 (GGNS). The licensee proposed a license amendment request (LAR) to revise Minimum Critical Power Ratio Safety Limit (MCPR) values for both two loop and single loop operation in accordance with the requirements set forth in GE Nuclear Energy Topical Report NEDC-33173P, Applicability fo GE Methods to Expanded Operating Domains, Rev. 0. |
| The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | | The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. |
| | |
| Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), | | Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), |
| an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations. | | an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations. |
| | | The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. |
| The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence. | | If you have any questions, please contact me at (301) 415-1445. |
| | | Alan Wang Project Manager (Grand Gulf Nuclear Station) |
| If you have any questions, please contact me at (301) 415-1445. | | Nuclear Regulatory Commission Division of Operating Reactor Licensing |
|
| |
|
| Alan Wang Project Manager (Grand Gulf Nuclear Station) Nuclear Regulatory Commission Division of Operating Reactor Licensing Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222
| | Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222}} |
| | |
| }} | |
Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML11306A0642011-08-31031 August 2011 Gnf S-0000-0136-7814 R0-NP, Rev. 0, Gnf Additional Information Regarding Requested Changes to the Technical Specification SLMCPR, Grand Gulf Cycle 19, Extended Power Uprate. Project stage: Other ML1200405012012-01-0404 January 2012 Email, Request for Additional Information, License Amendment Request to Revise Minimum Critical Power Ratio Safety Limit in Technical Specification 2.1.1.2 for Two-Loop and Single Recirculation Loop Project stage: RAI ML1200600412012-01-0606 January 2012 Acceptance Review Email, License Amendment Request to Revise Minimum Critical Power Ratio Safety Limit in Technical Specification 2.1.1.2 for Two-Loop and Single Recirculation Loop Project stage: Acceptance Review GNRO-2012/00005, Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 2.1.1.22012-01-26026 January 2012 Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 2.1.1.2 Project stage: Request ML1207206412012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 8/1/2011 Affidavit Executed by Andrew A. Lingenfelter, Gnf, for Attachment 3 to GNRO-2011/00064 Project stage: Withholding Request Acceptance ML1207206272012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 1/12/2012 Affidavit Executed by Lukas Trosman, Gnf, for Attachment 1 to GNRO-2012/00005 Project stage: Withholding Request Acceptance ML1207202832012-04-20020 April 2012 Issuance of Amendment No. 189, Revise Minimum Critical Power Ratio Safety Limit in Technical Specification 2.1.1.2 for Two-Loop and Single Recirculation Loop Project stage: Approval 2012-01-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24289A1442024-10-15015 October 2024 NRR E-mail Capture - Acceptance Review - Entergy (Grand Gulf Nuclear Station and River Bend Station) - CNRO2024-00017 - Adopt TSTF-592 - CLIIP (L-2024-LLA-0133) ML24137A2702024-05-16016 May 2024 NRR E-mail Capture - Entergy Fleet - Acceptance Review of License Amendment Request to Remove Obsolete License Conditions from Operating Licenses for GGNS, RBS, and WF3 (L-2024-LLA-0062) ML24108A1142024-04-17017 April 2024 June 2024 Emergency Preparedness Program Inspection - Request for Information ML24088A0092024-03-27027 March 2024 NRR E-mail Capture - Entergy Fleet - Final Request for Confirmation of Information (RCI) Re Alternative Request EN-RR-22-001 Concerning ASME Code Case N-752 (L-2022-LLR-0054) ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23335A0652023-12-0101 December 2023 NRR E-mail Capture - GGNS - Audit Questions for LARs Associated with TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Init. 4b and 50.69, Risk-Informed Cat. and Treatment of SSCs for Nuclear Pwr Rx (L-2023-LLA-0081/0080) ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23191A8662023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review of LAR Adopting 10 CFR 50.69, Risk-Informed Categorization and Treatment of SSCs for Nuclear Power Reactors ML23191A2802023-07-10010 July 2023 NRR E-mail Capture - Grand Gulf - Acceptance Review for LAR Adopting TSTF-505, Rev. 2, Provide Risk-Informed Completion Times - RITSTF Initiative 4b ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23009B6912023-01-0909 January 2023 NRR E-mail Capture - Grand Gulf, Unit 1 and River, Unit 1 - Acceptance of Requested Licensing Action Request to Update ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines ML22353A6122022-12-19019 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22173A0372022-06-21021 June 2022 NRR E-mail Capture - Entergy (Grand Gulf and River Bend) - Acceptance Review of the License Amendment Request to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 ML22075A3692022-03-0303 March 2022 Email Grand Gulf 2022 PI&R Request for Information ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21165A1352021-06-14014 June 2021 NRR E-mail Capture - Grand Gulf - Acceptance Review for Inserice Testing Program Relief Request VRR-GGNS-2021-1, Pressure Isolation Valve Testing Frequency ML21119A2152021-04-28028 April 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSE Unit 1 - Acceptance of Relief Request Proposed Alternative to Use ASME OM Code Case OMN-27 ML21109A2142021-04-19019 April 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Rev. Est Hours for Review of Relief Request (RR) - ASME Code RR Safety Eval with NRC-Approved Rev of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21109A2132021-03-23023 March 2021 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Relief Request (RR) Associated with ASME Code RR Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML21068A4092021-03-0909 March 2021 NRR E-mail Capture - Entergy Fleet (GGNS and RBS) -Approval of TSTF-501 LAR, Relocate Sored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21015A3452021-01-14014 January 2021 NRR E-mail Capture - Grand Gulf and River Bend - Revised Estimated Hours for Relief Request Associated with ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20363A1462020-12-22022 December 2020 Request for Information: Grand Gulf EP Exercise Inspection - March 2021 ML20352A1192020-12-10010 December 2020 Email from Thomas Saporito 12-10-20 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20323A4162020-11-18018 November 2020 Response to Choice Letter (EA-20-094) ML20337A2712020-11-0909 November 2020 Email - Grand Gulf Nuclear Station 050-00416, Requested Regulatory Conference ML20289A3542020-10-14014 October 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of TSTF-563 LAR, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20258A0202020-09-0909 September 2020 EP Program Inspection RFI, Request for Information to Support and Prepare for Emergency Preparedness (EP) Program Inspection Scheduled to Occur the Week of November 16, 2020 ML20260H4422020-09-0808 September 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Official RAIs for RR Associated with Updating ASME Code RR SEs with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20176A4832020-06-22022 June 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of Relief Request Associated with ASME Code RR SE with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020 and RBS-ISI-019) ML20150A6012020-05-29029 May 2020 NRR E-mail Capture - Grand Gulf - Official RAI for LAR Associated with Containment ILRT Interval Change from 10 Years to 15 Years ML20097B8032020-04-0303 April 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the Exigent LAR Associated with One-Time Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) ML20079D9302020-03-19019 March 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with Adopting TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control ML20076B6322020-03-16016 March 2020 NRR E-mail Capture - Grand Gulf - Acceptance Review for the LAR Associated with Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies ML20057G1592020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML20057G1752020-02-24024 February 2020 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Acceptance Review of LAR Associated with TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems ML19242C0122019-08-29029 August 2019 2.206 Petitioner (No Public Meeting Required) ML19339H4362019-08-26026 August 2019 Request for Information IR 05000416/2019-004 ML19115A3512019-04-25025 April 2019 LTR-19-0177 Tom Gurdziel, E-mail a Matter of Fairness Entergy Grand Gulf Seems to Be Running Rather Steadily at 100 Percent ML19151A3312019-04-0303 April 2019 (OEDO-19-00053)10 CFR 2.206 Petition Involving Grand Gulf Nuclear Station ML19095B7622019-04-0303 April 2019 Acceptance Review Results for License Amendment Request to Adopt TSTF-564, Revision 2, Safety Limit MCPR (Minimum Critical Power Ratio), for Grand Gulf Nuclear Station, Unit 1 and River Bend Station, Unit 1 (EPID L-22019-LLA-0051) ML19078A3772019-03-19019 March 2019 NRR E-mail Capture - Grand Gulf - Official Rais for Relief Request GG-ISI-023, Inservice Inspection Impracticality, Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet 2024-05-16
[Table view] |
Text
From: Wang, Alan Sent: Friday, January 06, 2012 8:51 AM To: JACKSON, RITA R; Perino, Christina; 'SEITER, JEFFERY ALAN' Cc: Burkhardt, Janet; Lent, Susan
Subject:
Acceptance of Grand Gulf Nuclear Station License Amendment Reqest Regarding Minimun Critical Power Ration Safety Limit TS Change (ME7531)
Rita, Jeff and Christina, By letter dated October 28, 2011 (Agencywide Documents Access and Management System, Accession No. ML113060150), Entergy Operations, Inc. (Entergy, the licensee), submitted a request to amend the Facility Operating License No. NPF-29 for Grand Gulf Nuclear Station, Unit 1 (GGNS). The licensee proposed a license amendment request (LAR) to revise Minimum Critical Power Ratio Safety Limit (MCPR) values for both two loop and single loop operation in accordance with the requirements set forth in GE Nuclear Energy Topical Report NEDC-33173P, Applicability fo GE Methods to Expanded Operating Domains, Rev. 0.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR),
an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1445.
Alan Wang Project Manager (Grand Gulf Nuclear Station)
Nuclear Regulatory Commission Division of Operating Reactor Licensing
Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222