Line 84: |
Line 84: |
| e Significant Hazards Considerations | | e Significant Hazards Considerations |
| * A comprehensive review of the Technical Specifications surveillance program for Surry was performed to ensure that a test was being performed for each Technical Specifications surveillance line item in Table 4.1-1, "Minimum Frequencies for Check, Calibration and Test of Instrument Channels." The review included an evaluation of the technical adequacy of each test with respect to the Technical Specifications requirement. The review identified certain instrument and logic circuit tests for which the licensed plant design does not facilitate the complete testing of the circuit or actuation logic without using temporary modifications (e.g., temporary jumpers or lifting leads). Consistent with the approved licensing basis and industry testing standards, these instrument and logic circuits are tested to the extent practicable on a monthly basis and are fully tested on a refueling basis. To ensure the Technical Specifications accurately reflect the actual testing being performed and are consistent with the existing plant design and/or the original licensing basis, Virginia Electric and Power Company is proposing an administrative change to the Technical Specifications to identify the instrument channels and logic actuation circuits that cannot be fully tested in accordance with the definition of channel functional test. | | * A comprehensive review of the Technical Specifications surveillance program for Surry was performed to ensure that a test was being performed for each Technical Specifications surveillance line item in Table 4.1-1, "Minimum Frequencies for Check, Calibration and Test of Instrument Channels." The review included an evaluation of the technical adequacy of each test with respect to the Technical Specifications requirement. The review identified certain instrument and logic circuit tests for which the licensed plant design does not facilitate the complete testing of the circuit or actuation logic without using temporary modifications (e.g., temporary jumpers or lifting leads). Consistent with the approved licensing basis and industry testing standards, these instrument and logic circuits are tested to the extent practicable on a monthly basis and are fully tested on a refueling basis. To ensure the Technical Specifications accurately reflect the actual testing being performed and are consistent with the existing plant design and/or the original licensing basis, Virginia Electric and Power Company is proposing an administrative change to the Technical Specifications to identify the instrument channels and logic actuation circuits that cannot be fully tested in accordance with the definition of channel functional test. |
| Virginia Electric and Power Company has reviewed the proposed change against the criteria of 1O CFR 50.92 and has concluded that the change as proposed does not pose a significant hazards consideration. Specifically, the proposed change is considered to be administrative in nature in that it is a clarification to reconcile actual surveillance test practices and the licensing design basis with the surveillance test requirements. | | Virginia Electric and Power Company has reviewed the proposed change against the criteria of 10 CFR 50.92 and has concluded that the change as proposed does not pose a significant hazards consideration. Specifically, the proposed change is considered to be administrative in nature in that it is a clarification to reconcile actual surveillance test practices and the licensing design basis with the surveillance test requirements. |
| Operation of Surry Power Station in accordance with the proposed Technical Specifications change will not: | | Operation of Surry Power Station in accordance with the proposed Technical Specifications change will not: |
| : 1. Involve a significant increase in the probability of occurrence or consequences of an accident previously evaluated. | | : 1. Involve a significant increase in the probability of occurrence or consequences of an accident previously evaluated. |
Revision as of 14:18, 6 November 2019
Similar Documents at Surry |
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML18152B3591999-08-23023 August 1999 Revised Tech Specs Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in UFSAR & Includes Ref to Applicable UFSAR Section ML18152B6591999-04-28028 April 1999 Proposed Tech Specs Re Refueling Water Chemical Addition Tank Min Vol ML18152A2131999-02-16016 February 1999 Proposed Tech Specs,Consolidating AFW cross-connect Requirements by Relocation of Electrical Power Requirements from TS 3.16 to TS 3.6 ML18152B5451999-02-16016 February 1999 Proposed Tech Specs Pages,Revising Augmented Insp Requirements for Reactor Coolant Pump Flywheels ML18152B6151998-11-0404 November 1998 Proposed Tech Specs 4.6.A.1.b,re EDG Start & Load Time Testing Requirements & TS 3.16 Bases Re EDG Ratings ML18153A3311998-09-24024 September 1998 Proposed Tech Specs Modifying Testing Requirements for Reactor Trip Bypass Breaker ML18153A3351998-09-24024 September 1998 Proposed Tech Specs Pages Affected by Suppl to 960912 Resubmittal of Change Request Re Relocation of Fire Protection Requirements from TS to UFSAR ML18152B7551998-06-19019 June 1998 Proposed Tech Specs Establishing Requirements for Use of Temporary Supply Line (Jumper) to Provide Svc Water to Component Cooling Heat Exchangers ML18152A3651998-03-25025 March 1998 Proposed Tech Specs Revising Station Mgt Titles to Reflect New Positions Approved by Vepc Board of Directors on 980220 ML18153A3481997-12-18018 December 1997 Proposed Tech Specs Clarifying Terminology Used for Describing Equipment Surveillances Conducted on Refueling Interval Frequency.Clarification Consistent W/Info Contained in Rev 1 to NUREG-1431 ML18153A1761997-11-0505 November 1997 Proposed Tech Specs Re Temporary Svc Water Supply Line to Component Cooling Heat Exchangers ML18153A3941997-11-0505 November 1997 Proposed Tech Specs Re Change for Increased Enrichment of Reload Fuel ML18153A5231997-04-24024 April 1997 Proposed Corrected Tech Specs Pages 6.1-3 & 6.1-8 Re Relocation of Fire Protection TS to Updated Final Safety Analysis Rept ML18153A5031997-03-18018 March 1997 Proposed Tech Specs Rev to Section 4.15 for Surry Power Station to Include Pp Inadvertently Omitted from 970203 Request for Amend to Licenses DPR-32 & DPR-37 ML18153A4921997-02-0303 February 1997 Proposed Tech Specs Re Deletion of Specific ASME Section XI Code Ref ML18153A6351996-11-26026 November 1996 Proposed Tech Specs Re Removal of Record Retention Requirements,Per GL 95-06 & Administrative Ltr 95-06 ML18153A0671996-09-12012 September 1996 Proposed Tech Specs Re Relocation of Fire Protection Requirements ML18153A6901996-04-15015 April 1996 Proposed Tech Specs,Clarifying Applicability of Quadrant Power Tilt Ration Requirements ML18153A5391996-03-21021 March 1996 Proposed Tech Specs Re Charcoal Filter Testing Clarification ML18153A5271996-03-14014 March 1996 Proposed Tech Specs,Permitting Use of 10CFR50 App J,Option B,performance-based Containment Lrt ML18153A5801996-01-30030 January 1996 Proposed Tech Specs Re Reactor Coolant Sys Liquid Sampling ML18153A6761995-11-20020 November 1995 Proposed Tech Specs Re App J Option B,performance-based Containment Leakage Rate Testing ML18153A7141995-07-20020 July 1995 Proposed Tech Specs Establishing New Setpoint Limit for SG high-high Level & Provides More Restrictive Setting Limits for Certain Rps/Esfas Setpoints ML18153A6991995-07-14014 July 1995 Proposed Tech Specs,Providing Two H Allowed Outage Time for One RHR Pump to Accommodate Plant Safety,Emergency Power Sys Surveillance Testing & Permit Depressurizing SI Accumulators in Lieu of Accumulator Isolation ML18153A8371995-06-0808 June 1995 Proposed Tech Specs,Incorporating Revised Pressure/Temp Limits & Associated Ltops Setpoint That Will Be Valid to end-of-license ML18153B2301995-02-14014 February 1995 Proposed Tech Specs Re App J Testing Requirements ML18153B2131995-01-24024 January 1995 Proposed Tech Specs,Modifying as-found Test Acceptance Criterion for Pressurizer Safety Valves ML18153B1621994-11-29029 November 1994 Proposed Tech Specs Implementing Zirlo Fuel Cladding ML18153B1581994-11-22022 November 1994 Proposed Tech Specs,Deleting Unnecessary Descriptive Phrases Re Number of Cells in Station & EDG Batteries ML18153B1501994-11-10010 November 1994 Proposed Tech Specs Re Changes to TS Will Clarify SR for Reactor Protection & Engineered Safeguard Sys Instrumentation & Actuation Logic ML18153B0941994-10-11011 October 1994 Proposed Tech Specs Surveillance Frequencies for Hydrogen Analyzers ML18152A5061994-09-0606 September 1994 Proposed Tech Specs Re Mgt Safety Review Committee & Station Nuclear Safety & Operating Committee Responsibilities ML18152A1191994-08-30030 August 1994 Proposed Tech Specs to Accomodate Core Uprating ML18153B0061994-07-14014 July 1994 Proposed Tech Specs Changes Will Eliminate Remaining References to cycle-specific Parameters in Surry TS ML18152A1821994-06-0909 June 1994 Proposed TS Re Chemical & Vol Control Sys & Safety Injection Sys ML20065P6111994-04-19019 April 1994 Proposed Tech Specs,Modifying Control Rod Movement Surveillance Frequency ML18153A8821994-02-25025 February 1994 Proposed Tech Specs Modifying Surveillance Frequency of Nozzles in Containment & Recirculation Spray Sys ML18153B4321993-12-27027 December 1993 Proposed Tech Specs Reflecting Revised Review Responsibilities of Station Nuclear Safety & Operating Committee & Mgt Safety Review Committee ML18153B4081993-12-10010 December 1993 Proposed Tech Specs,Establishing Upper Limit on Allowable COLR Mtc Values ML18153B4021993-12-10010 December 1993 Proposed Tech Specs,Modifying Surveillance Frequency of Auxiliary Feedwater Sys Pumps from Monthly to Quarterly Per Generic Ltr 93-05 & NUREG-1431 ML18153B4051993-12-10010 December 1993 Proposed Tech Specs,Updating Augmented Insp Program for Sensitized Stainless Steel by Incorporating Newer Code Requirements,While Maintaining Augmented Insp Philosophy ML18153B3751993-11-15015 November 1993 Proposed Tech Specs Implementing Revised 10CFR20,revising Frequency Radiological Release Repts from Semiannual to Annual & Clarifying Site Maps ML18153B3501993-10-19019 October 1993 Proposed Tech Specs for RSHX Svc Water Outlet Radiation Monitors ML18153B3321993-09-29029 September 1993 Proposed Tech Specs Modifying Required Insp Frequency of Low Pressure Turbine Blades to Permit Blade Insp to Be Performed Concurrent W/Disk & Hub Insp ML18152A0481993-07-20020 July 1993 Proposed Tech Specs Deleting Requirement for Station Nuclear Safety & Operating Committee & Audit Frequencies ML18153D3921993-07-16016 July 1993 Proposed Tech Specs for Operation W/Three Degree Increase in Svc Water Temp Limit for Containment Air Partial Pressures of 9.1,9.2 & 9.35 Psia ML18152A0461993-07-16016 July 1993 Proposed Tech Specs Implementing Revised 10CFR20,revise Frequency of Radiological Effluent Release Repts from semi-annual to Annual,& Clarify Site Maps ML18152A4511993-07-0202 July 1993 Proposed Tech Specs to Include COLR Which Presents reload- Specific Limits for Key Core Operating Parameters ML18153D3811993-07-0202 July 1993 Proposed TS Table 4.2-1 Re Miscellaneous Insps & Sensitized Stainless Steel Exams ML18153D3331993-05-0606 May 1993 Proposed Tech Specs Supporting Operation of Unit 2 w/100 Psi Reduction in RCS Nominal Operating Pressure Through End of Operating Cycle 12 1999-08-23
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML18152B3591999-08-23023 August 1999 Revised Tech Specs Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in UFSAR & Includes Ref to Applicable UFSAR Section ML18151A6641999-08-0606 August 1999 Rev 0 to Surry Unit 2 Cycle 16 Startup Physics Tests Rept. ML18152B6591999-04-28028 April 1999 Proposed Tech Specs Re Refueling Water Chemical Addition Tank Min Vol ML18152A2131999-02-16016 February 1999 Proposed Tech Specs,Consolidating AFW cross-connect Requirements by Relocation of Electrical Power Requirements from TS 3.16 to TS 3.6 ML18152B5451999-02-16016 February 1999 Proposed Tech Specs Pages,Revising Augmented Insp Requirements for Reactor Coolant Pump Flywheels ML18151A5511999-02-10010 February 1999 to NE-1187, Surry Unit 1,Cycle 16 Startup Physics Tests Rept. ML18152B6151998-11-0404 November 1998 Proposed Tech Specs 4.6.A.1.b,re EDG Start & Load Time Testing Requirements & TS 3.16 Bases Re EDG Ratings ML18153A3351998-09-24024 September 1998 Proposed Tech Specs Pages Affected by Suppl to 960912 Resubmittal of Change Request Re Relocation of Fire Protection Requirements from TS to UFSAR ML18153A3311998-09-24024 September 1998 Proposed Tech Specs Modifying Testing Requirements for Reactor Trip Bypass Breaker ML18152B7551998-06-19019 June 1998 Proposed Tech Specs Establishing Requirements for Use of Temporary Supply Line (Jumper) to Provide Svc Water to Component Cooling Heat Exchangers ML20249B9911998-05-0606 May 1998 Analysis of Capsule X Virginia Power Surry Unit 1 Reactor Vessel Matl Surveillance Program. W/Evaluation of Surry Unit 1 Surveillance Capsule X Results & Response to NRC RAI Re GL 92-01,rev 1,suppl 1 ML18151A1931998-05-0404 May 1998 Rev 1 to Summary of Changes to Surry Units 1 & 2 Third Interval IST Program. ML18152A3651998-03-25025 March 1998 Proposed Tech Specs Revising Station Mgt Titles to Reflect New Positions Approved by Vepc Board of Directors on 980220 ML20199B0711998-01-0505 January 1998 Rev 0 to NE-1148, Surry Unit 2,Cycle 15 Startup Physics Test Rept ML18153A3481997-12-18018 December 1997 Proposed Tech Specs Clarifying Terminology Used for Describing Equipment Surveillances Conducted on Refueling Interval Frequency.Clarification Consistent W/Info Contained in Rev 1 to NUREG-1431 ML18150A4661997-12-16016 December 1997 ISI Plan for Third Insp Interval,Vol 2,Rev 9 for Components & Component Supports,940510-040510, for Surry Power Station,Unit 2 ML18153A3941997-11-0505 November 1997 Proposed Tech Specs Re Change for Increased Enrichment of Reload Fuel ML18153A1761997-11-0505 November 1997 Proposed Tech Specs Re Temporary Svc Water Supply Line to Component Cooling Heat Exchangers ML18150A4641997-10-27027 October 1997 Risk-Informed ISI (RI-ISI) Pilot Program Submittal. ML18151A3911997-10-16016 October 1997 Rev 8 to VPAP-2103, Odcm. ML18151A7231997-08-0707 August 1997 Rev 1 to Nuclear Safety Analysis Manual Part Iv,Chapter a Probabilistic Safety Assessment Products. ML20210J5031997-07-31031 July 1997 Rev 0 to NE-1132, Surry Unit 1,Cycle 15 Startup Physics Tests Rept ML18150A4441997-06-0909 June 1997 Vol 2,Rev 8 to ISI Plan for Third Insp Interval for Components & Component Supports,Oct 14,1993-Oct 13,2003. ML18153A5231997-04-24024 April 1997 Proposed Corrected Tech Specs Pages 6.1-3 & 6.1-8 Re Relocation of Fire Protection TS to Updated Final Safety Analysis Rept ML18153A5031997-03-18018 March 1997 Proposed Tech Specs Rev to Section 4.15 for Surry Power Station to Include Pp Inadvertently Omitted from 970203 Request for Amend to Licenses DPR-32 & DPR-37 ML18153A4921997-02-0303 February 1997 Proposed Tech Specs Re Deletion of Specific ASME Section XI Code Ref ML18153A6351996-11-26026 November 1996 Proposed Tech Specs Re Removal of Record Retention Requirements,Per GL 95-06 & Administrative Ltr 95-06 ML18153A0671996-09-12012 September 1996 Proposed Tech Specs Re Relocation of Fire Protection Requirements ML18151A9761996-08-13013 August 1996 Cycle 14 Startup Physics Test Rept. W/960830 Ltr ML20134J9861996-07-30030 July 1996 /Unit 2 Fuel Assembly Insp Program ML18152A4701996-06-13013 June 1996 Cycle 13 Control Rod Performance Test Results. ML18153A6901996-04-15015 April 1996 Proposed Tech Specs,Clarifying Applicability of Quadrant Power Tilt Ration Requirements ML18153A5391996-03-21021 March 1996 Proposed Tech Specs Re Charcoal Filter Testing Clarification ML18153A5271996-03-14014 March 1996 Proposed Tech Specs,Permitting Use of 10CFR50 App J,Option B,performance-based Containment Lrt ML18153A5801996-01-30030 January 1996 Proposed Tech Specs Re Reactor Coolant Sys Liquid Sampling ML18152A0571995-12-20020 December 1995 Startup Physics Test Rept,Surry Unit 1,Cycle 14. W/960111 Ltr ML18153A6761995-11-20020 November 1995 Proposed Tech Specs Re App J Option B,performance-based Containment Leakage Rate Testing ML18151A6421995-08-0101 August 1995 Change 3 to Rev 0 to Third Interval IST Program ML18153A7141995-07-20020 July 1995 Proposed Tech Specs Establishing New Setpoint Limit for SG high-high Level & Provides More Restrictive Setting Limits for Certain Rps/Esfas Setpoints ML18153A6991995-07-14014 July 1995 Proposed Tech Specs,Providing Two H Allowed Outage Time for One RHR Pump to Accommodate Plant Safety,Emergency Power Sys Surveillance Testing & Permit Depressurizing SI Accumulators in Lieu of Accumulator Isolation ML18153A8371995-06-0808 June 1995 Proposed Tech Specs,Incorporating Revised Pressure/Temp Limits & Associated Ltops Setpoint That Will Be Valid to end-of-license ML20083C9951995-05-0808 May 1995 Rev 0 to Surry Unit 2,Cycle 13 Startup Physics Tests Rept ML18153B2301995-02-14014 February 1995 Proposed Tech Specs Re App J Testing Requirements ML18153B2131995-01-24024 January 1995 Proposed Tech Specs,Modifying as-found Test Acceptance Criterion for Pressurizer Safety Valves ML18153B1621994-11-29029 November 1994 Proposed Tech Specs Implementing Zirlo Fuel Cladding ML18153B1581994-11-22022 November 1994 Proposed Tech Specs,Deleting Unnecessary Descriptive Phrases Re Number of Cells in Station & EDG Batteries ML18153B1501994-11-10010 November 1994 Proposed Tech Specs Re Changes to TS Will Clarify SR for Reactor Protection & Engineered Safeguard Sys Instrumentation & Actuation Logic ML18153B0941994-10-11011 October 1994 Proposed Tech Specs Surveillance Frequencies for Hydrogen Analyzers ML18152A5061994-09-0606 September 1994 Proposed Tech Specs Re Mgt Safety Review Committee & Station Nuclear Safety & Operating Committee Responsibilities ML18152A1191994-08-30030 August 1994 Proposed Tech Specs to Accomodate Core Uprating 1999-08-06
[Table view] |
Text
TABLE 4.1-1 (Continued)
""(1""(1...0 O.f:>
- o .... MINIMUM FREQUENCIES FOR CHECK, CALIBRATIONS, AND TEST OF INSTRUMENT CHANNELS
....
t-J J>t-J 00 0 .... Channel Description Check Calibrate Test Remarks n...a 7':.f:>
- 10. Rod Position Bank Counters S(1,2) N.A. N.A. 1) Each six inches of rod motion 0-0 UJ.f:,, Q(3) when data logger is out of service 0 .... 2) With analog rod position 0 ....
""(10 .... 3) For the control banks, the bench-Ot,.JO
- OOJ board indicators shall be checked 0 against the output of the bank overlap unit.
- 11. Steam Generator Level s R M
- 12. Charging Flow N.A. R N.A.
- 13. Residual Heat Removal Pump Flow N.A. R N.A.
- 14. Boric Acid Tank Level *D R N.A.
- 15. Recirculation Mode Transfer
- a. Refueling Water Storage Tank Level-Low s R M
- b. Automatic Actuation Logic and N.A. N.A. M Actuation Relays
- 16. Volume Control Tank Level N.A. R N.A.
- 17. Reactor Containment Pressure-CLS *D R M(1) 1) Isolation valve signal and spray signal
- 18. Boric Acid Control N.A. R N.A.
- 19. Item Deleted
-I V,
- 20. Accumulator Level and Pressure s R N.A.
.....
.i:=,.
- 21. Containment Pressure-Vacuum s R N.A. I
"'-I Pump System
- 22. Steam Line Pressure s R M
TABLE 4.1-1 (Continued)
MINIMUM FREQUENCIES FOR CHECK, CAUBRATIONS, AND TEST OF INSTRUMENT CHANNELS Channel Description ~ Calibrate Tust Remarks
- 23. Turbine First Stage Pressure s R M
- 24. Emergency Plan Radiation Instr. *M R M
- 25. Environmental Radiation Monitors *M N.A. N.A. TLD Dosimeters
- 26. Logic Channel Testing N.A. N.A. M(1)(2) 1) Reactor protection, safety injection and the consequence limiting safeguards
- 27. Turbine Overspeed Protection Trip N.A. R R system logic channels are tested monthly Channel (Electrical) per this line item.
- 2) The master and slave relays are not included in the monthly logic channel test of the safety injection system.
- 28. Turbine Trip Setpoint verification is not applicable A. Stop valve closure N.A. N.A. p B. Low fluid oil pressure N.A. N.A. p
- 29. Seismic Instrumentation M R M
- 30. Reactor Trip Breaker N.A. N.A. M The test shall independently verify operability of the undervoltage and shunt trip attachments
- 31. Reactor Coolant Pressure (Low) N.A. R N.A.
-I V,
......
~
I 00
TABLE 4.1-1 (Continued)
MINIMUM FREQUENCIES FOR CHECK, CALIBRATIONS, AND TEST OF INSTRUMENT CHANNELS Channel Pescrjptjon .Qbe.ck canbrate ks1 Remarks
- 32. Auxiliary Feedwater
- a. Steam Generator Water Level Low-Low s R M(1) 1) The auto start of the turbine driven pump is not included in the monthly test, but is tested within 30 days prior to each startup.
- b. RCP Undervoltage s R N.A.(1) 1) The actuation logic and relays are tested within 30 days prior to each startup.
- c. S.I. (All Safety Injection surveillance requirements)
- d. Station Blackout N.A. R N.A.
- e. Main Feedwater Pump Trip N.A. N.A. .R
- 33. Loss of Power
- a. 4.16 KV Emergency Bus Under- N.A. R M voltage (Loss of Voltage)
- b. 4.16 KV Emergency Bus Under- N.A. R M voltage (Degraded Voltage)
- 34. Deleted
- 35. Manual Reactor Trip N.A. N.A. R The test shall independently verify the operability of the undervoltage and shunt
-e trip attachments for the manual reactor trip function. The test shall also verify the operability of the bypass breaker trip circuit.
- 36. Reactor Trip Bypass Breaker N.A. N.A. M(1), 1) Remote manual undervoltage trip prior R(2) to placing breaker in service.
- 2) Automatic undervoltage trip. -I V,
- 37. Safety Injection Input to RPS N.A. N.A. R ..::.....
I
- 38. Reactor Coolant Pump Breaker N.A. N.A. R 00 Cl Position Trip
- Attachment 3 Significant Hazards Consideration Determination Surry Power Station
e Significant Hazards Considerations
- A comprehensive review of the Technical Specifications surveillance program for Surry was performed to ensure that a test was being performed for each Technical Specifications surveillance line item in Table 4.1-1, "Minimum Frequencies for Check, Calibration and Test of Instrument Channels." The review included an evaluation of the technical adequacy of each test with respect to the Technical Specifications requirement. The review identified certain instrument and logic circuit tests for which the licensed plant design does not facilitate the complete testing of the circuit or actuation logic without using temporary modifications (e.g., temporary jumpers or lifting leads). Consistent with the approved licensing basis and industry testing standards, these instrument and logic circuits are tested to the extent practicable on a monthly basis and are fully tested on a refueling basis. To ensure the Technical Specifications accurately reflect the actual testing being performed and are consistent with the existing plant design and/or the original licensing basis, Virginia Electric and Power Company is proposing an administrative change to the Technical Specifications to identify the instrument channels and logic actuation circuits that cannot be fully tested in accordance with the definition of channel functional test.
Virginia Electric and Power Company has reviewed the proposed change against the criteria of 10 CFR 50.92 and has concluded that the change as proposed does not pose a significant hazards consideration. Specifically, the proposed change is considered to be administrative in nature in that it is a clarification to reconcile actual surveillance test practices and the licensing design basis with the surveillance test requirements.
Operation of Surry Power Station in accordance with the proposed Technical Specifications change will not:
- 1. Involve a significant increase in the probability of occurrence or consequences of an accident previously evaluated.
The proposed change to clarify the surveillance requirements for the Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic has no impact on the probability of an accident occurrence. The instrumentation and actuation logic will continue to be operated in the same manner. The actual test frequency is not changing. Rather, surveillance requirements are being clarified to represent the actual testing and the licensing and design bases. Testing of these instruments and actuation logic are presently design limited and would otherwise require using temporary modifications to complete the testing. Since the testing is not changing, the clarification of the Page 1 of 2
e
- actual testing does not contribute to the probability of any previously analyzed accident. The Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic will be operated in the same manner and the system operability requirements are not being altered. Therefore, the consequences of any design basis accident are not being increased by the proposed change to clarify the surveillance test requirements for the Reactor Protection and Engineered Safeguards System instrumentation and actuation logic.
- 2. Create the possibility of a new or different kind of accident from any accident previously evaluated.
There are no plant modifications or changes in methods of plant operation introduced by this change in the clarification of the testing for the Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic. The plant is not being operated or tested in a different manner due to the proposed change. Therefore, no new accidents or accident precursors are generated by the proposed change to clarify the surveillance test requirements.
Clarifying the surveillance test requirements to represent the original licensing design basis and test conditions does not create the possibility of a new or different accident than previously analyzed.
- 3. Involve a significant reduction in a margin of safety.
Clarification of the testing for the Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic surveillance requirements does not affect the margin of safety in that the operability requirements for these safety systems remain unchanged. The existing testing is performed in accordance with plant design and licensing basis and provides adequate indication of the operability of the affected instrumentation or actuation logic. The Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic are fully tested on a refueling cycle basis which includes complete operation of each relay and end device. Therefore, the margin of safety is not altered by the proposed clarification of the testing for the Reactor Protection and Engineered Safeguards Systems instrumentation and actuation logic.
Page 2 of 2