Line 2: Line 2:
| number = ML13207A246
| number = ML13207A246
| issue date = 09/19/2013
| issue date = 09/19/2013
| title = Zion, Units 1 & 2 Bi-Weekly Notice - Notice of Issuance Amendment Approving the Upgraded Fuel Handling Building Crane
| title = Bi-Weekly Notice - Notice of Issuance Amendment Approving the Upgraded Fuel Handling Building Crane
| author name = Hickman J B
| author name = Hickman J
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| addressee name =  
| addressee name =  
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:September 19, 2013  
{{#Wiki_filter:September 19, 2013 MEMORANDUM TO: Biweekly Notice Coordinator FROM:                   John B. Hickman, Project Manager /RA/
 
Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs
MEMORANDUM TO: Biweekly Notice Coordinator  
 
FROM:   John B. Hickman, Project Manager  
/RA/ Reactor Decommissioning Branch  
 
Decommissioning and Uranium Recovery  
 
Licensing Directorate  
 
Division of Waste Management
 
and Environmental Protection  
 
Office of Federal and State Materials
 
and Environmental Management Programs  


==SUBJECT:==
==SUBJECT:==
REQUEST FOR PUBLICATION IN BIWEEKLY FR NOTICE - NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE (TAC NOS. J00433 AND J00434)  
REQUEST FOR PUBLICATION IN BIWEEKLY FR NOTICE - NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE (TAC NOS. J00433 AND J00434)
 
ZionSolutions, LLC, Docket Nos. 50-295 and 50-304, Zion Nuclear Power Station, Units 1 and 2, Lake County, Illinois Date of application for amendment: May 31, 2012, and October 25, 2012, as supplemented by letters dated December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013.
Zion Solutions , LLC, Docket Nos. 50-295 and 50-304, Zion Nuclear Power Station, Units 1 and 2, Lake County, Illinois Date of application for amendment
Brief description of amendment: The amendments approve the upgraded Fuel Handling Building crane.
: May 31, 2012, and October 25, 2012, as supplemented by letters dated December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May  
Date of issuance: September 19, 2013 Effective date: As of the date of issuance and shall be implemented immediately.
 
Amendment Nos.: 186 and 173 Facility Operating License Nos. DPR-39 and DPR-48: These amendments are effective on the date of issuance and shall be implemented prior to the start of operations to transfer spent fuel to the Zion Independent Spent Fuel Storage Installation Date of initial notice in FEDERAL REGISTER: August 7, 2012 (77 FR 47123)
16, 2013.  
 
Brief description of amendment
: The amendments approve the upgraded Fuel Handling Building crane.  
 
Date of issuance
: September 19, 2013 Effective date
: As of the date of issuance and shall be implemented immediately.
Amendment Nos.
: 186 and 173 Facility Operating License Nos. DPR-39 and DPR-48
: These amendments are effective on the date of issuance and shall be implemented prior to the start of operations to transfer spent fuel  
 
to the Zion Independent Spent Fuel Storage Installation  
 
Date of initial notice in FEDERAL REGISTER
: August 7, 2012 (77 FR 47123)
The Commission's related evaluation of the am endment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information
 
that did not change the scope of the original request.
 
No significant hazards consideration comments received: No
 
The Commission's related evaluation of the am endment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information
 
that did not change the scope of the original request.


No significant hazards consideration comments received: No  
The Commission's related evaluation of the amendment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information that did not change the scope of the original request.
No significant hazards consideration comments received: No


DISTRIBUTION
The Commission's related evaluation of the amendment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information that did not change the scope of the original request.
: DCD R/F OGC ROrlikowski, RIII ML13207A222 OFFICE RDB/PM DURLD/LA RDB/BC OGC RDB/PM NAME JHickman SAchten BWatson HBenowitz JHickman DATE 8 / 1 / 2013 7 / 31 / 2013 8 / 1 / 2013 9 / 17 / 2013 9/19/2013 OFFICIAL RECORD COPY}}
No significant hazards consideration comments received: No DISTRIBUTION:
DCD R/F                 OGC           ROrlikowski, RIII ML13207A222 OFFICE     RDB/PM         DURLD/LA         RDB/BC       OGC               RDB/PM NAME       JHickman       SAchten           BWatson       HBenowitz         JHickman DATE       8 / 1 / 2013   7 / 31 / 2013     8 / 1 / 2013 9 / 17 / 2013     9/19/2013 OFFICIAL RECORD COPY}}

Latest revision as of 16:31, 4 November 2019

Bi-Weekly Notice - Notice of Issuance Amendment Approving the Upgraded Fuel Handling Building Crane
ML13207A246
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 09/19/2013
From: John Hickman
NRC/FSME/DWMEP/DURLD/RDB
To:
NRC/FSME
Shared Package
ML13207A222 List:
References
TAC J00433, TAC J00434
Download: ML13207A246 (3)


Text

September 19, 2013 MEMORANDUM TO: Biweekly Notice Coordinator FROM: John B. Hickman, Project Manager /RA/

Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs

SUBJECT:

REQUEST FOR PUBLICATION IN BIWEEKLY FR NOTICE - NOTICE OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE (TAC NOS. J00433 AND J00434)

ZionSolutions, LLC, Docket Nos. 50-295 and 50-304, Zion Nuclear Power Station, Units 1 and 2, Lake County, Illinois Date of application for amendment: May 31, 2012, and October 25, 2012, as supplemented by letters dated December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013.

Brief description of amendment: The amendments approve the upgraded Fuel Handling Building crane.

Date of issuance: September 19, 2013 Effective date: As of the date of issuance and shall be implemented immediately.

Amendment Nos.: 186 and 173 Facility Operating License Nos. DPR-39 and DPR-48: These amendments are effective on the date of issuance and shall be implemented prior to the start of operations to transfer spent fuel to the Zion Independent Spent Fuel Storage Installation Date of initial notice in FEDERAL REGISTER: August 7, 2012 (77 FR 47123)

The Commission's related evaluation of the amendment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information that did not change the scope of the original request.

No significant hazards consideration comments received: No

The Commission's related evaluation of the amendment is contained in a Safety Evaluation dated September 19, 2013. The October 25, 2012, December 20, 2012, January 17, 2013, February 21, 2013, April 4, 2013, and May 16, 2013, submittals provided clarifying information that did not change the scope of the original request.

No significant hazards consideration comments received: No DISTRIBUTION:

DCD R/F OGC ROrlikowski, RIII ML13207A222 OFFICE RDB/PM DURLD/LA RDB/BC OGC RDB/PM NAME JHickman SAchten BWatson HBenowitz JHickman DATE 8 / 1 / 2013 7 / 31 / 2013 8 / 1 / 2013 9 / 17 / 2013 9/19/2013 OFFICIAL RECORD COPY