ML14037A365: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(4 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 02/06/2014
| issue date = 02/06/2014
| title = IR 05000134-13-001, on 8/22/13 - 1/16/14, Worcester Polytechnic Institute, Worcester, Ma, Site. Cover Letter
| title = IR 05000134-13-001, on 8/22/13 - 1/16/14, Worcester Polytechnic Institute, Worcester, Ma, Site. Cover Letter
| author name = Ferdas M S
| author name = Ferdas M
| author affiliation = NRC/RGN-I/DNMS/NMSB3
| author affiliation = NRC/RGN-I/DNMS/NMSB3
| addressee name = Curley M J
| addressee name = Curley M
| addressee affiliation = Worcester Polytechnic Institute
| addressee affiliation = Worcester Polytechnic Institute
| docket = 05000134
| docket = 05000134
Line 15: Line 15:
| page count = 3
| page count = 3
}}
}}
See also: [[followed by::IR 05000134/2013001]]
See also: [[see also::IR 05000134/2013001]]


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES
[[Issue date::February 6, 2014]]
                              NUCLEAR REGULATORY COMMISSION
                                              REGION I
                                2100 RENAISSANCE BOULEVARD, SUITE 100
                              KING OF PRUSSIA, PENNSYLVANIA 19406-2713
                                          February 6, 2014
Docket No.    05000134                                        License No.    R-61
Michael J. Curley
University Compliance Officer
Worcester Polytechnic Institute
100 Institute Road
Worcester, MA 01609-2280
SUBJECT:       NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER
                POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE
Dear Mr. Curley:
On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety
inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility
in Worcester, Massachusetts. The inspection was an examination of your licensed activities as
they relate to radiation safety and to compliance with the Commission's regulations and the
license conditions. The inspection consisted of observations by the inspectors, interviews with
WPI and contractor personnel, a review of procedures and records, and acquisition of split
samples. The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform
analysis of samples obtained by the inspectors. ORAU provided the results of the sample
analysis in a report, Letter Report for Analytical Results for Two Concrete and Three Soil
Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,
dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS)
Accession No. ML13309B020). Additional information in documents provided by WPI dated
August 22, August 26, October 29, and December 6, 2013, were also examined as part of the
inspection. On January 16, 2014, the inspectors held a telephone conference call exit with you
and other members of your staff. The enclosed report presents the results of this inspection.
No health and safety concerns were identified.
The enclosed inspection report will be provided to the NRC Division of Waste Management and
Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any
request to terminate the WPI license and release the site for unrestricted use. Please note that
this report does not release the site for unrestricted use nor does it terminate the license.
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov;
select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and
Communications. The current Enforcement Policy is included on the NRC's website at
www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement;
Enforcement documents; then Enforcement Policy (Under 'Related Information'). You
may also obtain these documents by contacting the Government Printing Office (GPO) toll-free
at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday
(except Federal holidays).


Docket No. 05000134License No. R-61 Michael University Compliance Officer Worcester Polytechnic Institute 100 Institute Road Worcester, MA 01609-2280
M. Curley                                     2
 
No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have
SUBJECT: NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE
any questions regarding this matter.
 
                                                  Sincerely,
==Dear Mr. Curley:==
                                                  Original signed by Marc S. Ferdas
On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility in Worcester, Massachusetts. The inspection was an examination of your licensed activities as they relate to radiation safety and to compliance with the Commission's regulations and the license conditions. The inspection consisted of observations by the inspectors, interviews with WPI and contractor personnel, a review of procedures and records, and acquisition of split samples. The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform analysis of samples obtained by the inspectors. ORAU provided the results of the sample analysis in a report, "Letter Report for Analytical Results for Two Concrete and Three Soil Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,"
                                                  Marc S. Ferdas, Chief
dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS) Accession No. ML13309B020). Additional information in documents provided by WPI dated August 22, August 26, October 29, and December 6, 2013, were also examined as part of the inspection. On January 16, 2014, the inspectors held a telephone conference call exit with you and other members of your staff. The enclosed report presents the results of this inspection.
                                                  Decommissioning and Technical
 
                                                  Support Branch
No health and safety concerns were identified. The enclosed inspection report will be provided to the NRC Division of Waste Management and Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any request to terminate the WPI license and release the site for unrestricted use. Please note that this report does not release the site for unrestricted use nor does it terminate the license.
                                                  Division of Nuclear Materials Safety
 
Enclosure:
Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays). No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have any questions regarding this matter.
Inspection Report No. 05000134/2013001
 
cc: Commonwealth of Massachusetts
Sincerely,Original signed by Marc S. Ferdas Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety  
 
===Enclosure:===
Inspection Report No. 05000134/2013001  


M. Curley                                                        2
No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have
any questions regarding this matter.
                                                                      Sincerely,
                                                                      Original signed by Marc S. Ferdas
                                                                      Marc S. Ferdas, Chief
                                                                      Decommissioning and Technical
                                                                      Support Branch
                                                                      Division of Nuclear Materials Safety
Enclosure:
Inspection Report No. 05000134/2013001
cc: Commonwealth of Massachusetts
cc: Commonwealth of Massachusetts
DISTRIBUTION:
T. Smith, FSME, DWMEP
DOCUMENT NAME: G:\WordDocs\Current\Insp Letter\L00-00000-61.2013001.doc
                                                                                                                          ML14037A365
SUNSI Review Complete: MRoberts
After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: AC@ = Copy w/o attach/encl AE@ = Copy w/ attach/encl AN@ = No copy
OFFICE          DNMS/RI                      N    DNMS/RI                        DNMS/RI                  E
NAME            KModes\mcr f\                    MRoberts\mcr                  MFerdas\msf
DATE            1/31/14                          2/6/14                        2/6/14
                                                        OFFICIAL RECORD COPY
}}
}}

Latest revision as of 08:38, 4 November 2019

IR 05000134-13-001, on 8/22/13 - 1/16/14, Worcester Polytechnic Institute, Worcester, Ma, Site. Cover Letter
ML14037A365
Person / Time
Site: 05000134
Issue date: 02/06/2014
From: Marc Ferdas
NRC/RGN-I/DNMS/NMSB3
To: Curley M
Worcester Polytechnic Institute
Shared Package
ML14024A421 List:
References
IR-13-001
Download: ML14037A365 (3)


See also: IR 05000134/2013001

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100

KING OF PRUSSIA, PENNSYLVANIA 19406-2713

February 6, 2014

Docket No. 05000134 License No. R-61

Michael J. Curley

University Compliance Officer

Worcester Polytechnic Institute

100 Institute Road

Worcester, MA 01609-2280

SUBJECT: NRC INSPECTION REPORT NO. 05000134/2013001, WORCESTER

POLYTECHNIC INSTITUTE, WORCESTER, MASSACHUSETTS SITE

Dear Mr. Curley:

On August 22, 2013, the U.S. Nuclear Regulatory Commission (NRC) conducted a safety

inspection at the Worcester Polytechnic Institute (WPI) Leslie C. Wilbur Nuclear Reactor Facility

in Worcester, Massachusetts. The inspection was an examination of your licensed activities as

they relate to radiation safety and to compliance with the Commission's regulations and the

license conditions. The inspection consisted of observations by the inspectors, interviews with

WPI and contractor personnel, a review of procedures and records, and acquisition of split

samples. The NRC contracted with Oak Ridge Associated Universities (ORAU) to perform

analysis of samples obtained by the inspectors. ORAU provided the results of the sample

analysis in a report, Letter Report for Analytical Results for Two Concrete and Three Soil

Samples Associated with the Worcester Polytechnic Institute, in Worcester, Massachusetts,

dated October 7, 2013, (Agencywide Document Access and Management System (ADAMS)

Accession No. ML13309B020). Additional information in documents provided by WPI dated

August 22, August 26, October 29, and December 6, 2013, were also examined as part of the

inspection. On January 16, 2014, the inspectors held a telephone conference call exit with you

and other members of your staff. The enclosed report presents the results of this inspection.

No health and safety concerns were identified.

The enclosed inspection report will be provided to the NRC Division of Waste Management and

Environmental Protection (DWMEP) Project Manager for WPI for consideration for action on any

request to terminate the WPI license and release the site for unrestricted use. Please note that

this report does not release the site for unrestricted use nor does it terminate the license.

Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov;

select Nuclear Materials; Med, Ind, & Academic Uses; then Regulations, Guidance and

Communications. The current Enforcement Policy is included on the NRC's website at

www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement;

Enforcement documents; then Enforcement Policy (Under 'Related Information'). You

may also obtain these documents by contacting the Government Printing Office (GPO) toll-free

at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday

(except Federal holidays).

M. Curley 2

No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have

any questions regarding this matter.

Sincerely,

Original signed by Marc S. Ferdas

Marc S. Ferdas, Chief

Decommissioning and Technical

Support Branch

Division of Nuclear Materials Safety

Enclosure:

Inspection Report No. 05000134/2013001

cc: Commonwealth of Massachusetts

M. Curley 2

No reply to this letter is required. Please contact Mark C. Roberts at (610) 337-5094 if you have

any questions regarding this matter.

Sincerely,

Original signed by Marc S. Ferdas

Marc S. Ferdas, Chief

Decommissioning and Technical

Support Branch

Division of Nuclear Materials Safety

Enclosure:

Inspection Report No. 05000134/2013001

cc: Commonwealth of Massachusetts

DISTRIBUTION:

T. Smith, FSME, DWMEP

DOCUMENT NAME: G:\WordDocs\Current\Insp Letter\L00-00000-61.2013001.doc

ML14037A365

SUNSI Review Complete: MRoberts

After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: AC@ = Copy w/o attach/encl AE@ = Copy w/ attach/encl AN@ = No copy

OFFICE DNMS/RI N DNMS/RI DNMS/RI E

NAME KModes\mcr f\ MRoberts\mcr MFerdas\msf

DATE 1/31/14 2/6/14 2/6/14

OFFICIAL RECORD COPY