ML17006A094: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 3: | Line 3: | ||
| issue date = 11/30/2016 | | issue date = 11/30/2016 | ||
| title = DG Completion Time Extension LAR - Follow-up Questions Related to October 13, 2016, RAI Response (MF7147 and MF7148) | | title = DG Completion Time Extension LAR - Follow-up Questions Related to October 13, 2016, RAI Response (MF7147 and MF7148) | ||
| author name = Schaaf R | | author name = Schaaf R | ||
| author affiliation = NRC/NRR/DORL/LPLII-2 | | author affiliation = NRC/NRR/DORL/LPLII-2 | ||
| addressee name = Wells R | | addressee name = Wells R | ||
| addressee affiliation = Tennessee Valley Authority | | addressee affiliation = Tennessee Valley Authority | ||
| docket = 05000390, 05000391 | | docket = 05000390, 05000391 |
Revision as of 19:00, 19 June 2019
ML17006A094 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 11/30/2016 |
From: | Robert Schaaf Plant Licensing Branch II |
To: | Wells R Tennessee Valley Authority |
References | |
MF7147, MF7148 | |
Download: ML17006A094 (5) | |
Text
1 NRR-PMDAPEm Resource From: Schaaf, Robert Sent: Wednesday, November 30, 2016 2:13 PM To:Wells, Russell Douglas Cc:Gordon Arent; Johnston (Dion), Jeanne
Subject:
Watts Bar Units 1 and 2 DG Completion Time Extension LAR - Follow-up Questions
Related to October 13, 2016, RAI response (MF7147 and MF7148)
Attachments:
WBN EDG LAR - Follow-up Questions to October 13 2016 RAI response.pdf Russ, By letter dated March 11, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16071A456), as supplemented by letter dated October 13, 2016 (Accession No.
ML16287A656), the Tennessee Valley Authority (TVA) submitted an application for a proposed amendment for Watts Bar Nuclear Plant (WBN), Units 1 and 2.
The Nuclear Regulatory Commission (NRC) staff has reviewed TVA's responses to staff requests for additional information in TVA's letter dated October 13, 2016, and has identified several supplemental requests for additional information (RAIs) to support completion of its review. The specific information requested is attached to this e-mail. The proposed questions were provided to you on November 25, 2016, for clarification if needed.
You indicated by phone on November 30, 2016, that no clarification was needed and agreed to provide a response to this request by December 30, 2016.
Please confirm receipt of these final RAIs. Please contact me if you have any further questions regarding this request.
Regards, Robert G. Schaaf Robert G. Schaaf Senior Project Manager, Watts Bar/Bellefonte
Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8G9A Washington, DC 20555
301-415-6020 (o) Robert.Schaaf@nrc.gov Robert G. Schaaf Robert G. Schaaf Senior Project Manager, Watts Bar/Bellefonte Plant Licensing Branch II-2 Division of Operating Reactor Licensing 2Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8G9A Washington, DC 20555 301-415-6020 (o) Robert.Schaaf@nrc.gov
Hearing Identifier: NRR_PMDA Email Number: 3246 Mail Envelope Properties (5dfca7bd2c674667b2d84a73696b9049)
Subject:
Watts Bar Units 1 and 2 DG Completion Time Extension LAR - Follow-up Questions Related to October 13, 2016, RAI response (MF7147 and MF7148) Sent Date: 11/30/2016 2:13:17 PM Received Date: 11/30/2016 2:13:00 PM From: Schaaf, Robert Created By: Robert.Schaaf@nrc.gov Recipients: "Gordon Arent" <garent@tva.gov> Tracking Status: None "Johnston (Dion), Jeanne" <jeanne.johnston@nrc.gov> Tracking Status: None "Wells, Russell Douglas" <rdwells0@tva.gov>
Tracking Status: None Post Office: R4PWMSMRS03.nrc.gov
Files Size Date & Time MESSAGE 1885 11/30/2016 2:13:00 PM WBN EDG LAR - Follow-up Questions to October 13 2016 RAI response.pdf 47974 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: ZZZ WATTS BAR NUCLEAR PLANT UNITS 1AND 2SUPPLEMENTAL REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO REVISE TECHNICAL SPECIFICATIONS TO EXTEND INOPERABLE DIESEL GENERATOR COMPLETION TIME TECHNICAL SPECIFICATION 3.8.1,AC SOURCES -OPERATING (TAC NOS. MF7147 ANDMF7148)The Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) for Watts Bar Nuclear Plant (WBN) Units 1 and 2, by letter dated March 11, 2016 (AgencywideDocuments Access and Management System (ADAMS) Accession No. ML16071A456). The LAR proposedrevision to Technical Specification(TS) 3.8.1, "AC Sources -Operating," to extend the Completion Time (CT) for one inoperable Diesel Generator (DG) from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 14 days based upon the availability of a supplemental alternating current (ac) power source (i.e., a 6.9 kilovolt (kV) FLEX DG). TVA stated that the changes are requested to provide operational and maintenance flexibility. TVA statedthat the proposed CT will allow sufficient time to perform planned maintenance activities that cannot be performed within a 72-hour CT.By letter dated October13, 2016(ADAMS Accession No. ML16287A656),TVA provided responses to staff requests for additional information (RAIs) dated August 3, 2016. The staff has reviewed TVA's responses to the staff's RAIs and has identified supplemental requests for additional information as identified in the follow-upRAIsprovided below.1.TVA response to RAINo. 6states (Reference Page E1-13):"The timeline, based on plant procedures, for connecting the proposed 6.9 kV FLEX DG to the associated safety-related busses is shown on Figure 2, approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />."The staff requests additional information on the timelineto restore power to a6.9 kV shutdown board from the FLEX DG,similar to the level of detail provided verbally to the staff during an October 14, 2016, teleconference to support TVA's request for aNotice of Enforcement Discretion (NOED).The NOED request was subsequently documented in TVA's letter dated October 18, 2016 (ADAMS Accession No. ML16292A827).
2.The following pages ofTVA's October 13, 2016,RAI responsestate that the FLEX DG will be connected within 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />s[Prior to 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />s], thus creating an inconsistency with the 2 hourtimeline discussed in the follow-up Question 1 above. For example:Page E1-8: "Prior to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, the 6.9 kV FLEX DG would be aligned to the Unit 1 6.9 kV SDB..."Page E1-8: "Prior to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, one or more6.9 KV FLEX diesel(s) would be aligned to the Unit 2 6.9 kV SDB..."
2 Page E1-12: "Prior to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, the FLEX DG would be aligned to the unpowered A train SDB."Page E1-12: "Prior to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, the FLEX DG would be aligned to the unpowered 2B-Btrain SDB."Please correct or clarify thisinconsistency and confirm that the FLEX DG will be aligned to the appropriate shutdown bus within the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> period discussedabove and in previous communications.
- 3. Page E1-6of the RAI responses states, "This FSI implements FLEX strategies to place a 480V FLEX DG in operation or to extend DC battery lifetime to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Extending battery lifetime is accomplished by performing a DC load shed within the first 90 minutes of the event if neither 480V FLEX DGs can be initially placed in operation. If no 480V FLEX DG is available when the 6.9 kV FLEX DG(s) are available, guidance is provided to power the 6.9 kV SDB(s) with the available 6.9 kV FLEX DG which would allow the 480V SDB(s) to be energized from the 6.9 kV SDB."The proposed TS 3.8.1 mark-up pagesdo not identify the 480 V FLEX DG as a required source for the proposed LAR.Please confirm that the 480V FLEX DGs are procedurally required to be connected to the station busses but are not credited for the purposes ofthis LAR,as alternate plans to load shed the DC system or connect the 6.9 kV DGs in a timely manner may be implementedin case of failure of the 480V FLEX DGs.
4.The staff also reviewed the information provided on page E1-9of and Table3-1, "6.9kV FLEX Diesel Generator Loads"of the RAI responses.Please provide the timeline ofFLEX DGloads separately for each of the following scenarios, up to the time both units will bein cold shutdown. (Note: In thefollowing scenarios, the staff assumes that aFLEX DG is connected to a 6.9 kV shutdown board/bussothat at least one train has a safety-related DG and a FLEX DGto provide cold shutdown of both units).i.LOOP (both Units), when Unit 1 DG 1A-A (or 1B-B) is under maintenance, the redundant DG 1B-B (or 1A-A) fails to start (SBO Unit 1),and a Unit 2 DG 2A-Ahas a single failure.ii.LOOP (both Units), SBO Unit 1,and a Unit 2 DG 2B-B has a single failure. iii.LOOP (both Units),SBOUnit 2,and a Unit 1 DG 1A-Ahas a single failure.iv.LOOP (both Units), SBO Unit 2,and a Unit 1 DG 1B-B has a single failure. v.In addition to the major loads, provide details of any miscellaneous loads which are likely to be fed from the FLEX DG.