|
|
Line 14: |
Line 14: |
| | page count = 8 | | | page count = 8 |
| | project = TAC:MF4864, TAC:MF4865 | | | project = TAC:MF4864, TAC:MF4865 |
| | stage = Acceptance Review | | | stage = Request |
| }} | | }} |
|
| |
|
Line 51: |
Line 51: |
| : 1. The material used in the RN system is bi-modal 4710 resin. The RL system used several types of resin, however, where bi-modal resin was used in the RL system, it was the same resin and pipe manufacturer for both the RN and RL systems. 2. Installation practices were more rigorous for the RN system. With the improved fusing procedure for the RN system, the joints should be of equal or greater quality than the RL system. 3. The RL system used a 10% nominal wall thickness gouge depth allowance, whereas the RN system was limited to 3.5%. RL system piping would be expected to exhibit degradation due to slow crack growth before the RN system piping because of this. Using the installed RL system piping to identify degradation resulting from an installation practice is conservative for the RN system piping. 4. Both systems use the same water source and therefore have the same water chemistry. | | : 1. The material used in the RN system is bi-modal 4710 resin. The RL system used several types of resin, however, where bi-modal resin was used in the RL system, it was the same resin and pipe manufacturer for both the RN and RL systems. 2. Installation practices were more rigorous for the RN system. With the improved fusing procedure for the RN system, the joints should be of equal or greater quality than the RL system. 3. The RL system used a 10% nominal wall thickness gouge depth allowance, whereas the RN system was limited to 3.5%. RL system piping would be expected to exhibit degradation due to slow crack growth before the RN system piping because of this. Using the installed RL system piping to identify degradation resulting from an installation practice is conservative for the RN system piping. 4. Both systems use the same water source and therefore have the same water chemistry. |
| : 5. System design parameters (pressure and temperature) are similar for the two systems. The RL system is subjected to water temperatures above ambient lake temperature whenever the plant is in operation, as many plant non-safety related heat exchangers and motor coolers reject heat loads to the RL system. In contrast, the RN system is only subjected to temperatures above inlet header temperature during diesel gener'ator operation. | | : 5. System design parameters (pressure and temperature) are similar for the two systems. The RL system is subjected to water temperatures above ambient lake temperature whenever the plant is in operation, as many plant non-safety related heat exchangers and motor coolers reject heat loads to the RL system. In contrast, the RN system is only subjected to temperatures above inlet header temperature during diesel gener'ator operation. |
| Using the RL system for monitoring HOPE for degradation is conservative since the RN system has only seen about [[estimated NRC review hours::300 hours]] of operation at elevated temperatures. | | Using the RL system for monitoring HOPE for degradation is conservative since the RN system has only seen about 300 hours of operation at elevated temperatures. |
| : 6. The RL system piping is used inside the plant as well as in buried piping and as such is accessible for inspection and any leakage from this piping would be easily identified. | | : 6. The RL system piping is used inside the plant as well as in buried piping and as such is accessible for inspection and any leakage from this piping would be easily identified. |
| In the supplemental letter, the licensee stated that the RL piping is inspected during operator rounds performed each shift. Any leakage from RL piping is identified and documented in either the Corrective Action Program or the Fluid Leak Management program. In addition, the RL system engineer is required to perform a system walkdown annually and the piping is also inspected during plant maintenance activities. | | In the supplemental letter, the licensee stated that the RL piping is inspected during operator rounds performed each shift. Any leakage from RL piping is identified and documented in either the Corrective Action Program or the Fluid Leak Management program. In addition, the RL system engineer is required to perform a system walkdown annually and the piping is also inspected during plant maintenance activities. |
Letter Sequence Acceptance Review |
---|
|
|
|
|
---|
Category:Code Relief or Alternative
MONTHYEARML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22213A2532022-08-31031 August 2022 Authorization and Safety Evaluation for Alternative Request RA-21-0144 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML22007A3452022-01-11011 January 2022 Proposed Alternative to Use the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-885 ML21029A3352021-02-16016 February 2021 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RA-19-0026, Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001)2019-02-11011 February 2019 Response to Request for Additional Information (RAI) Regarding Proposed Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 and 10 (18-GO-001) RA-18-0180, Supplement to Relief Request for an Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 22018-11-12012 November 2018 Supplement to Relief Request for an Alternative to the Depth Sizing Qualification Requirement of Appendix Viii, Supplements 2 ML18016A1782018-01-24024 January 2018 Request for Relief No. 17-CN-001, Regarding Category B-J Pressure Retaining Welds for the Third 10-Year Inservice Testing Interval (CAC Nos. MF9807 and MF9808; EPID L-2017-LLA-0032) ML17331A0862017-12-26026 December 2017 Alternative to Inservice Inspection Regarding Reactor Pressure Vessel Threads ML17104A1102017-04-26026 April 2017 Relief Request CN Grr 01, Alternative to the Testing Frequencies in the American Society of Mechanical Engineers Operation and Maintenance Code, by Adoption of Code Case OMN-20, Inservice Test Frequencies (CAC Nos. MF9595-6) CNS-17-020, Application to Adopt ASME Code Case OMN-20 (CN-GRR-01) for Pump and Valve Inservice Testing2017-04-11011 April 2017 Application to Adopt ASME Code Case OMN-20 (CN-GRR-01) for Pump and Valve Inservice Testing ML15301A5442015-11-10010 November 2015 Proposed Relief Request 15-CN-001, Alternative Repair of a Main Steam System Braided Flex-Hose CNS-15-062, Relief Request Serial Number 15-CN-001, Proposed Alternative Repair for Main Steam System Braided Flex-Hose - Submitted Pursuant to 10 CFR 50.55a(z)(2)2015-07-16016 July 2015 Relief Request Serial Number 15-CN-001, Proposed Alternative Repair for Main Steam System Braided Flex-Hose - Submitted Pursuant to 10 CFR 50.55a(z)(2) ML15161A3762015-06-19019 June 2015 Proposed Relief Request 14-CN-002, Alternative to American Society of Mechanical Engineers (ASME) Section XI Requirements for Class 3 Buried Piping ML15124A6992015-05-0808 May 2015 (Catawba 1 and 2) - Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section X1, for Inservice Inspection Activities ML14295A5322014-10-30030 October 2014 Proposed Relief Request 14-CN-001, American Society of Mechanical Engineers (ASME) Section IX Volumetric Examination Requirements ML14079A5462014-03-26026 March 2014 Proposed Relief Request 13-CN-003, Request for Alternative to the Requirement of IWB-2500, Table IWB-2500-1, Category B-A and Category B-D for Reactor Pressure Vessel Welds ML11187A0012011-07-14014 July 2011 Relief 10-CN-001, Alternative Requirements for Temporary Acceptance of a Through-Wall Flaw in Boric Acid Tank Nozzle Weld ML1012501702010-05-0303 May 2010 Withdrawal of Request for Relief Number 09-CN-001, Limited Weld Examinations During the End-of-Cycle 17 Refueling Outage ML0912401562009-05-27027 May 2009 Relief 06-CN-003 for Use of Polyethylene Material in Buried Service Water Piping ML0902301722009-01-16016 January 2009 Response to NRC Requests for Additional Information and Request for Relief (Alternative) Number 08-CN-002 - Reactor Vessel Hot Leg Nozzle-to-Safe End Weld Full Structural Weld Overlays ML0831506302008-11-0606 November 2008 Transmittal of Request for Relief Number 08-CN-002, Reactor Vessel Hot Leg Nozzle-to-Safe End Weld Full Structural Weld Overlays (Fswols) ML0822403862008-09-12012 September 2008 Relief 06-CN-003, Use of Polyethylene Material in Nuclear Safety-Related Piping Applications ML0815607342008-07-0707 July 2008 Request for Relief 07-CN-001, Limited Weld Examinations During End-Of -Cycle 14 Refueling Outage ML0816000032008-07-0101 July 2008 Request for Relief 07-CN-002, Limited Weld Examinations During End-of-Cycle 14 Refueling Outage ML0731804472007-08-27027 August 2007 Request for Relief Number 07-CN-004 Limited Weld Examinations During the End-of-Cycle 16 Refueling Outage ML0706504172007-02-26026 February 2007 Submittal of Request for Relief Number 07-CN-003, Request for Relief to Allow Use of Alternate Requirements for Snubber Inspection & Testing ML0636000142007-01-0909 January 2007 Relief, Request to Use a Portion of a Letter Edition of ASME Code ML0632801882006-11-16016 November 2006 Revision to Relief Request 06-GO-001 ML0623900202006-09-25025 September 2006 Request for Relief 05-CN-004, Limited Weld Examinations During End-of-Cycle 15 Refueling Outage, MC8337, MC9171, MC9172, MC9173, MC9174, MC9175, MC9176, MC9177, MC9178, and MC9179) ML0626202612006-09-11011 September 2006 Relief Request 06-GO-001 Request for Additional Information ML0622304212006-09-0707 September 2006 Relief, Request for Relief for Snubber Visual Examination and Functional Testing Related to the Third 10-year Interval Inservice Inspection Program ML0634903992006-07-27027 July 2006 Relief Request 06-GO-001 ML0616603262006-07-20020 July 2006 Request for Use of Later Edition and Addenda of the ASME Code ML0616800102006-07-19019 July 2006 Regarding Request for Relief 05-CN-001, Limited Weld Examinations During End-of-Cycle 14 Refueling Outage ML0535503702006-04-0303 April 2006 Relief, O5-CN-003 Limited Weld Examination Coverage ML0517801882005-07-25025 July 2005 RR 04-CN-001, Volumetric Weld Inspection Requirements ML0519403672005-07-13013 July 2005 Relief Request MC3057, 04-CN-002, Limited Weld Examinations During End-of-Cycle 12 Refueling Outage ML0518901432005-06-28028 June 2005 Submittal of Third Ten-Year Interval Inservice Inspection Plan for Steam Generator Tubing ML0517801642005-06-23023 June 2005 RR 04-CN-004, Class 1 ISI Pressure Test Boundaries Requirement (Tac No. MC3276, MC3277) ML0510203642005-03-31031 March 2005 Relief, Request to Use a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities at Catawba Nuclear Station, Unit 2 in Accordance with 10 CFR 50.55a(g) (4) (IV) ML0504105322005-03-17017 March 2005 RR, Alternative Code of Prv Nozzle Welds for Volumetic Examination RR-04-GO-001 ML0504904622005-02-17017 February 2005 Relief, RR No. 03-001, 10 CFR Section 50.55a (a)(3)(ii) for Second ISI Intervals ML0428106012004-10-20020 October 2004 Relief Request, Alternate to the American Society of Mechanical Engineers Section XI for Reactor Vessel Examinations RR-04-GO-001 ML0427400272004-09-30030 September 2004 Relief, Amended Relief Request 03-GO-010 Requesting Use of Subsequent Edition and Addenda of the ASME Code for Class Mc and CC Components (MC9674-MC9680) ML0427302912004-09-29029 September 2004 Request for Relief, 04-GO-006, for Use of an Alternate Code Case to Use Ultrasonic Techniques Equipment ML0420403942004-07-20020 July 2004 Request for Relief 03-004, Minimum Percentage Requirements for Second Period of the Second Inservice Inspection Interval 2023-09-25
[Table view] Category:Letter
MONTHYEARML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000413/20243012024-09-16016 September 2024 Operator Licensing Examination Approval 05000413/2024301 and 05000414/2024301 IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) IR 05000413/20230062024-02-28028 February 2024 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - (NRC Inspection Report 05000413/2023006 and 05000414/2023006) IR 05000413/20230042024-02-0202 February 2024 – Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 ML22297A2642022-10-25025 October 2022 Project Manager Assignment ML22276A2492022-10-25025 October 2022 Completion of License Renewal Commitment No. 10, Aging Management of Environmentally Assisted Fatigue 2024-09-05
[Table view] Category:Safety Evaluation
MONTHYEARML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22213A2532022-08-31031 August 2022 Authorization and Safety Evaluation for Alternative Request RA-21-0144 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 ML22007A3452022-01-11011 January 2022 Proposed Alternative to Use the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-885 ML21266A0112021-10-0505 October 2021 Staff Evaluation Related to Aging Management Program and Inspection Plan of Reactor Vessel Internals Per MRP-227, Revision 1-A ML21253A0822021-09-20020 September 2021 Proposed Alternative Request RA-21-0145 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML21155A2132021-08-26026 August 2021 Plant ML21131A0262021-06-23023 June 2021 Issuance of Amendments to Change Technical Specification 3.8.1, to Reduce Emergency Diesel Generator Maximum Voltage ML21113A0132021-05-0606 May 2021 Request for Use of a Later Edition of ASME Boiler and Pressure Vessel Code, Section XI for Repair and Replacement Activities ML21029A3352021-02-16016 February 2021 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20300A2062020-11-0909 November 2020 Duke Fleet - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20258A2712020-09-21021 September 2020 Correction Letter to Amendment Nos. 301, 329, 307, 303, 178, 317, 296, 416, 418, 417, and 268 ML20083F9272020-08-12012 August 2020 Issuance of Amendments to Relocate the Unit/Facility/Plant Staff Qualification Requirements to the Duke Energy Quality Assurance Program Description ML20174A0452020-08-0404 August 2020 Issuance of Amendment No. 306 to Revise Technical Specification 3.4.3, RCS (Reactor Coolant System) Pressure and Temperature (P/T) Limits ML19296D1192020-01-31031 January 2020 Issuance of Amendment Nos. 305 and 301 to Revise Technical Specification 3.0, Surveillance Requirement (SR) Applicability ML19254A6202019-09-17017 September 2019 Duke Energy Fleet (Brunswick, Catawba, Robinson, McGuire, Oconee, and Shearon Harris) - Alternative to Use Encoded Phased Array Ultrasonic Examination in Lieu of Radiography ML19212A6552019-08-27027 August 2019 Issuance of Amendment Nos. 304 and 300 to Technical Specification 3.8.1, AC Sources - Operating ML19191A0612019-07-15015 July 2019 Review of the Steam Generator Tube Inservice Inspection Report for the Fall 2018 Refueling Outage 24 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs ML19128A3262019-06-20020 June 2019 Alternative to Depth Sizing Qualification Examination of Welds ML19121A5512019-06-17017 June 2019 Issuance of Amendments Related to the Removal of Containment Valve Injection Water System Supply from Specified Containment Isolation Valves ML19050A2972019-04-18018 April 2019 McGuire Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, H B. Robinson Steam Electric Plant, Unit 2 - Issuance of Amendments Regarding Removal ML18275A2782018-11-28028 November 2018 Issuance of Amendments Related to the Nuclear Service Water System New Condition for Single Pond Return Header Configuration ML18172A1722018-08-15015 August 2018 Issuance of Amendments to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application ML18016A1782018-01-24024 January 2018 Request for Relief No. 17-CN-001, Regarding Category B-J Pressure Retaining Welds for the Third 10-Year Inservice Testing Interval (CAC Nos. MF9807 and MF9808; EPID L-2017-LLA-0032) ML17296A2082018-01-0404 January 2018 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-197-A, Revision 2 (CAC Nos. MF8971 & MF8972, EPID L-2016-LLA-0026) ML17331A0862017-12-26026 December 2017 Alternative to Inservice Inspection Regarding Reactor Pressure Vessel Threads ML17254A1442017-10-23023 October 2017 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-352-A, Revision 1 (CAC Nos. MF8969 and MF8970; EPID L-2017-LLA-0031) ML17261B2902017-10-23023 October 2017 Issuance of Amendment Nos. 296 and 292, Adopt TSTF-142-A, Revision 0, Increase the Completion Time When the Core Reactivity Balance Is Not within Limit (CAC Nos. MF8962 and MF8963); EPID L-2017-LLA-0024 ML17257A2972017-10-23023 October 2017 Issuance of Amendment Nos. 295 and 291, Adoption of TSTF-340-A, Revision 3, Allow 7-Day Completion Time for a Turbine-Driven AFW Pump Inoperable (CAC Nos. MF8979 and MF8980; EPID L-2017-LLA-0043) ML17249A1352017-09-29029 September 2017 Issuance of Amendments Adopting Technical Specifications Task Force Travelers TSTF-349-A, Revision 1, TSTF-361-A, Revision 2, and TSTF-438-A, Revision 0 ML17188A3872017-08-21021 August 2017 Issuance of Amendments Regarding Application to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes (CAC Nos. MF7650 Through MF7660) ML17172A4282017-07-26026 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-315-A, Revision 0 ML17165A4412017-07-21021 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-269-A, Revision 2 (CAC Nos. MF8983 and MF8984). 08/10/2017 ML17055A6472017-05-0808 May 2017 Brunswick, Catawba, McGuire, Shearon Harris, and H. B. Robinson - Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-522, Revision 0 (CAC Nos. MF8422, MF8423, MF8424, MF8425, MF8426, MF8427, MF8428, and MF8429) ML17066A3742017-04-26026 April 2017 Issuance of Amendments Re. Application to Revise TSs to Adopt TSTF-427, Rev. 2, Using the Consolidated Line Item Improvement Process (CAC Nos. MF8039 Through MF8049) ML16137A3082017-02-0808 February 2017 Issuance of Amendments Regarding National Fire Protection Association Standard NFPA 805 ML16277A4042016-10-20020 October 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16208A2832016-08-0808 August 2016 Correction to Issuance of Amendments Regarding Use of Optimized Zirlo ML16159A3362016-07-19019 July 2016 Issuance of Amendments Regarding Request to Use an Alternate Fission Gas Gap Release Fraction (CAC Nos. MF6480 Through MF6486) 2024-07-12
[Table view] |
Text
Mr. Kelvin Henderson Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 297 45 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 19, 2015
SUBJECT:
CATAWBA NUCLEAR STATION UNITS 1AND2: PROPOSED RELIEF REQUEST 14-CN-002, ALTERNATIVE TO AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME) SECTION XI REQUIREMENTS FOR CLASS 3 BURIED PIPING (TAC NOS. MF4864 AND MF4865)
Dear Mr. Henderson:
By letter dated September 15, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 14265A043), as supplemented by letters dated December 2, 2014 (ADAMS Accession No. ML 14338A620), and May 18, 2015 (ADAMS Accession No. ML 15142A412), Duke Energy Carolinas, LLC requested approval of an alternative to the requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI, for Class 3 piping, for the fourth 10-year inservice inspection (ISi) interval for Catawba Nuclear Station (Catawba), Units 1 and 2. Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(a)(z)(1
), the licensee requested continued use of installed high density polyethylene piping on the basis that the alternative examination provides an acceptable level of quality and safety. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the subject request and concludes, as set forth in the enclosed safety evaluation, the examinations exams were performed to the extent practical and provide reasonable assurance of structural.
integrity of the subject areas. Therefore, the NRC staff authorizes the alternative as requested in 14-CN-002.
All other ASME Code,Section XI, requirements, for which relief was not specifically requested and authorized herein by the NRC staff, remain applicable, including the third-party review by the Authorized Nuclear In-service Inspector.
K. Henderson If you have any questions, please contact the Project Manager, Ed Miller at 301-415-2481 or via e-mail at Ed.Miller@nrc.gov.
Docket Nos. 50-413 and 50-414
Enclosure:
Safety Evaluation cc w/encl: Distribution via ListServ Sincerely, Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUEST 14-CN-002 FOURTH 10-YEAR INSERVICE INSPECTION INTERVAL DUKE ENERGY CAROLINAS, LLC . CATAWBA NUCLEAR STATION. UNITS 1AND2 DOCKET NOS. 50-413 AND 50-414
1.0 INTRODUCTION
By letter dated September 15, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 14265A043), as supplemented by letters dated December 2, 2014 (ADAMS Accession No. ML 14338A620), and-May 18, 2015 (ADAMS Accession No. ML 15142A412), the licensee, requested relief from the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code),Section XI, associated with requirements for class 3 buried piping systems at Catawba Nuclear Station, Units 1 and 2. The applicable code requirement is IWA-4221 (b), which requires that "An item to be used for repair/replacement activities shall meet the Construction Code specified in accordance with (1 ), (2), or (3)," and ASME Section XI, IWA-4221(b)(1), which requires that "when replacing an existing item, the new item shall meet the Construction Code to which the original item was constructed."
- Specifically, pursuant to Title 1 O of the Code of Federal Regulations (10 CFR) Section 50.55a(a)(z)(1
), the licensee requested continued use of installed high density polyethylene (HOPE) piping on the basis that the alternative examination provides an acceptable level of quality and safety.
2.0 REGULATORY EVALUATION
Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the pre-service examination requirements set forth in the ASME Code,Section XI, to the extent practical within the limitations of design, geometry, and materials of construction of the components.
10 CFR 50.55a(a)(z) states that alternatives to the requirements of paragraph (g) of 10 CFR 50.55a may be used, when authorized by the NRC, if the licensee demonstrates (1) the proposed alternatives would provide an acceptable level of quality and safety or (2) compliance Enclosure with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. 3.0 PROPOSED ALTERNATIVE AND JUSTIFICATION The ASME Code components affected by the licensee's request are as follows:
- ASME Class 3 buried piping in the Catawba Nuclear Service Water System serving the diesel generator jacket water coolers. The ASME Section XI Code of Record for the 4th ISi interval is the ASME Section XI, 2007 Edition through the 2008 Addenda. Relief is requested for the fourth ISi interval, which is scheduled to begin on August 19, 2015, and is currently scheduled to end on November 19, 2025. The applicable code requirement is IWA-4221 (b), which requires that "An item to be used for repair/replacement activities shall meet the Construction Code specified in accordance with (1 ), (2), or (3)," and ASME Section XI, IWA-4221(b)(1), which requires that "when replacing an existing item, the new item shall meet the Construction Code to which the original item was constructed." The Construction Code of record for buried ASME Class 3 piping is ASME Boiler and Pressure Vessel Code, Section Ill, Subsection ND, 1974 Edition, through Summer 1974 Addenda. This Construction Code and later editions and addenda of this Construction Code do not provide rules for the design, fabrication, installation, examination and testing of piping constructed using HOPE material.
On May 27, 2009, the NRC approved HOPE for use for the buried section of the SWS system (RN system) in lieu of the carbon steel piping for Catawba's third 10-year* ISi interval (ML090970160).
The licensee has stated that in-service testing of the subject piping is not feasible and as such, the licensee is basing support of continued structural integrity of the piping on reliability of the piping material, adequate installation requirements and flow testing of the system. Catawba has installed approximately 20,000 linear feet of HOPE material in non-safety related Low Pressure Service Water System (RL system), which has been in service since 1998. The licensee stated the .continued operability of this system provides evidence of long-term reliability of HOPE material, and in particular continued operability of the safety-related RN system because of the following considerations:
- 1. The material used in the RN system is bi-modal 4710 resin. The RL system used several types of resin, however, where bi-modal resin was used in the RL system, it was the same resin and pipe manufacturer for both the RN and RL systems. 2. Installation practices were more rigorous for the RN system. With the improved fusing procedure for the RN system, the joints should be of equal or greater quality than the RL system. 3. The RL system used a 10% nominal wall thickness gouge depth allowance, whereas the RN system was limited to 3.5%. RL system piping would be expected to exhibit degradation due to slow crack growth before the RN system piping because of this. Using the installed RL system piping to identify degradation resulting from an installation practice is conservative for the RN system piping. 4. Both systems use the same water source and therefore have the same water chemistry.
- 5. System design parameters (pressure and temperature) are similar for the two systems. The RL system is subjected to water temperatures above ambient lake temperature whenever the plant is in operation, as many plant non-safety related heat exchangers and motor coolers reject heat loads to the RL system. In contrast, the RN system is only subjected to temperatures above inlet header temperature during diesel gener'ator operation.
Using the RL system for monitoring HOPE for degradation is conservative since the RN system has only seen about 300 hours0.00347 days <br />0.0833 hours <br />4.960317e-4 weeks <br />1.1415e-4 months <br /> of operation at elevated temperatures.
- 6. The RL system piping is used inside the plant as well as in buried piping and as such is accessible for inspection and any leakage from this piping would be easily identified.
In the supplemental letter, the licensee stated that the RL piping is inspected during operator rounds performed each shift. Any leakage from RL piping is identified and documented in either the Corrective Action Program or the Fluid Leak Management program. In addition, the RL system engineer is required to perform a system walkdown annually and the piping is also inspected during plant maintenance activities.
Any leakage found during either inspection would be evaluated using the Corrective Action Program. The licensee also provides a table of known leakage in the RL system and the action taken in regards to the RN system. As a result of recent operating experience with the HOPE flange joint leakage in the RL system, Catawba will perform vt-2 inspections of accessible RN system HOPE flanges. These inspections will encompass eleven underground vaults containing sixteen HOPE flanged joints and will occur during the fourth ISi interval.
The licensee performs an unimpaired flow test IWA-5244(b)(2) in conjunction with visual examinations of the ground surface areas. For each segment of buried pipe, periodic flow testing is performed in accordance with the flow balance test procedure for each train. These surveillance procedures require flow to be measured, recorded, and compared to established acceptance criteria to provide assurance that flow is not impaired during operation.
The
- licensee stated that the visual examinations and unimpaired flow tests provide reasonable assurance of the structural and leak-tight integrity of the buried components.
The licensee proposed to continue use of the HOPE piping that was installed in the ESW system during the third ISi interval for the fourth ISi interval that is scheduled to begin on August 19, 2015 and end on November 19, 2025. 4.0 NRC STAFF EVALUATION The use of HOPE was approved at Catawba for the third 10-year ISi interval in May 2009. The NRC staff has been involved in implementation of HOPE for use in nuclear power plants for several years and understands that the primary advantage is using HOPE in lieu of carbon steel is its resistance to corrosion, which ensures long-term reliability of structural integrity.
With nearly 20 years of inservice history, there is compelling evidence that the continued use of HOPE will provide an acceptable level of quality and safety. However, since the licensee is unable to perform periodic inservice pressure testing, continued use of HOPE in the RN system is limited to the fourth 1 O year ISi interval.
The NRC staff reviewed the information provided in support of this request. NRC staff evaluated the licensee's assertion that the RL system constitutes a leading indicator for the safety-related RN system. The NRC staff finds the licensee's assertion that leakage is more likely to occur in the non-safety RL system piping and monitoring of this system in addition to the RN system provides additional assurance of the continued operability of HOPE to be valid. The RL system has a greater potential for slow crack growth for several reasons. The RL system uses both uni-modal and bi-modal resins, whereas the RN system only uses the modal resin. The uni-modal resin has a lower resistance to slow crack growth. The RL system . also allowed a 10% nominal wall thickness gouge depth as compared to the 3.5% for the RN system. A greater percent gouge depth would be expected to degrade quicker. In addition, the RL system has consistently operated at higher temperatures than the RN system, which also would contribute to a faster growth rate. Because of these three reasons, the RL system piping would be expected to exhibit degradation before the RN system. The licensee monitors the RL piping through daily walk downs and yearly system inspections.
Any leakage is evaluated through the Corrective Action Program and results are incorporated into inspection of the RN piping. These inspections and evaluation of any leakage provides reasonable assurance that the RL piping is in good working order. The licensee currently monitors the RN system with an unimpaired flow test in with visual examinations of the ground surface areas. In addition, based on operating experience in the RL piping, the licensee will perform VT-2 inspections of accessible RN system HOPE flanges. The NRC finds that the visual examinations, unimpaired flow tests and using the RL piping as a leading indicator of operability provide reasonable assurance of the structural and leak-tight integrity of the buried components.
5.0 CONCLUSION
As set forth above, the NRC staff determines that the proposed alternative provides an acceptable level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(1
). Therefore, the NRC staff authorizes the continued use of HOPE for the fourth ISi interval at Catawba Units 1 and 2, which is scheduled to begin on August 19, 2015, and end on November 19, 2025. All other requirements of the ASME Code for which relief has not been specifically requested and authorized remain applicable, including a third party review by the Authorized Nuclear In-service Jnspector.
Principal Contributors:
M. Audrain, NRR Date of issuance:
June 19, 2015 K. Henderson If you have any questions, please contact the Project Manager, Ed Miller at 301-415-2481 or via e-mail at Ed.Miller@nrc.gov.
Docket Nos. 50-413 and 50-414
Enclosure:
Safety Evaluation cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC LPL2-1 R/F RidsNrrDorlDpr Resource RidsNrrDorllpl2-1 Resource RidsNrrDeEvib Resource RidsAcrsAcnw_MailCTR Resource RidsNrrLASFigueroa Resource RidsNrrPMCatawba Resource (hard copy) RidsRgn2MailCenter Resource ADAMS Accession No. ML 15161A376 Sincerely, /RA/ Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
- via memorandum OFFICE DORL/LPL2-1
/PM DORL/LPL2-1
/LA DE/EPNB/BC DORL/LPL2-1
/BC NAME GEMiller SFigueroa DAiiey* RPascarelli DATE 06/16/15 06/16/15 10/15/14 06/19/15 OFFICIAL RECORD COPY