ML18122A330: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML18122A330
| number = ML18122A330
| issue date = 05/02/2018
| issue date = 05/02/2018
| title = Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 Acceptance of Requested Licensing Action Relief Request SR-1
| title = Unit Nos. 1 and 2 Acceptance of Requested Licensing Action Relief Request SR-1
| author name = Marshall M L
| author name = Marshall M L
| author affiliation = NRC/NRR/DORL/LPLI
| author affiliation = NRC/NRR/DORL/LPLI

Revision as of 07:50, 1 April 2019

Unit Nos. 1 and 2 Acceptance of Requested Licensing Action Relief Request SR-1
ML18122A330
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 05/02/2018
From: Marshall M L
Plant Licensing Branch 1
To: Neff D A
Exelon Nuclear
Marhsall M L, NRR/DORL/LPL, 415-2871
References
EPID L-2018-LLR-0052
Download: ML18122A330 (2)


Text

From: Marshall, Michael To: Neff, David B:(GenCo-Nuc) (david.neff@exeloncorp.com)

Cc:[Licensee] Ron Reynolds (Exelon)

"Kristensen, Kenneth J
(GenCo-Nuc)"

Subject:

Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 - Acceptance of Requested Licensing Action Re: Relief Request SR-1 (EPID L-2018-LLR-0052)

Date: Wednesday, May 02, 2018 1:41:00 PM Hello Dave, By letter dated April 10, 2018, Exelon Generation Company, LLC (Exelon, the licensee) submitted a relief request for Nine Mile Point Nuclear Station, Units 1 and 2 (ADAMS Accession No. ML18100A299).

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review.

If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> to complete.

The NRC staff expects to complete the reviews by the end of December 2018.

If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review.

Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220 and 50-410

From: Marshall, Michael To: Neff, David B:(GenCo-Nuc) (david.neff@exeloncorp.com)

Cc:[Licensee] Ron Reynolds (Exelon)

"Kristensen, Kenneth J
(GenCo-Nuc)"

Subject:

Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 - Acceptance of Requested Licensing Action Re: Relief Request SR-1 (EPID L-2018-LLR-0052)

Date: Wednesday, May 02, 2018 1:41:00 PM Hello Dave, By letter dated April 10, 2018, Exelon Generation Company, LLC (Exelon, the licensee) submitted a relief request for Nine Mile Point Nuclear Station, Units 1 and 2 (ADAMS Accession No. ML18100A299).

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review.

If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> to complete.

The NRC staff expects to complete the reviews by the end of December 2018.

If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review.

Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-220 and 50-410