ML072831379: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML072831379
| number = ML072831379
| issue date = 10/23/2007
| issue date = 10/23/2007
| title = St. Lucie, Units 1 and 2; Turkey Point, Units 3 and 4 - (Public Version) - Distribution of Revision 2 of the Nrc'S Significance Determination Process Risk-Informed Inspection Notebooks and Accompanying Phase 2 Pre-Solved Tables (TAC No. MD6
| title = St. Lucie, Units 1 and 2; Turkey Point, Units 3 and 4 - (Public Version) - Distribution of Revision 2 of the Nrc'S Significance Determination Process Risk-Informed Inspection Notebooks and Accompanying Phase 2 Pre-Solved Tables
| author name = Mozafari B L
| author name = Mozafari B L
| author affiliation = NRC/NRR/ADRO/DORL/LPLII-2
| author affiliation = NRC/NRR/ADRO/DORL/LPLII-2

Revision as of 08:07, 10 February 2019

St. Lucie, Units 1 and 2; Turkey Point, Units 3 and 4 - (Public Version) - Distribution of Revision 2 of the Nrc'S Significance Determination Process Risk-Informed Inspection Notebooks and Accompanying Phase 2 Pre-Solved Tables
ML072831379
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 10/23/2007
From: Mozafari B L
NRC/NRR/ADRO/DORL/LPLII-2
To: Stall J A
Florida Power & Light Co
Mozafari B L, NRR/ADRO/DORL, 415-2020
Shared Package
ml072831378 List:
References
TAC MD6415
Download: ML072831379 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION SWASHINGTON, D.C. 20555-0001 October 23, 2007 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

ST. LUCIE, UNITS 1 AND 2; TURKEY POINT, UNITS 3 AND 4 -DISTRIBUTION OF REVISION 2 OF THE NRC'S SIGNIFICANCE DETERMINATION PROCESS RISK-INFORMED INSPECTION NOTEBOOKS AND ACCOMPANYING PHASE 2 PRE-SOLVED TABLES (TAC NO. MD6415)

Dear Mr. Stall:

In 2004, the U.S. Nuclear Regulatory Commission (NRC) requested information from licensees to support the Significance Determination Process [SDP] Risk-Informed Inspection Notebook (notebook) enhancement/standardization effort. The NRC has completed this effort and has issued Revision 2 of the notebook for St. Lucie, Units 1 and 2 (SL1 and SL2), and Turkey Point, Units 3 and 4 (TP3/4). The NRC developed these notebooks to facilitate Phase 2 of the NRC inspection finding SDP detailed in Inspection Manual Chapter 0609, "Significance Determination Process," Appendix A, "Determining the Significance of Reactor Inspection Findings for At-Power Situations." SECY-99-007A, "Recommendations for Reactor Oversight Process Improvements," set forth this process and additional details are included in the NRC, Inspection Manual Chapter 0308, "Reactor Oversight Process Basis Document." NRC inspectors and risk analysts, who have extensive understanding of plant-specific design features and operation, are expected to use these notebooks.

The notebooks will be updated on a case-by-case basis, as needed, to reflect changes to the facilities.

Revision 2 of the notebooks is accompanied by the Site-Specific Pre-Solved Spreadsheet (the Spreadsheet).

The NRC added the Spreadsheet to help reduce the time it takes to process inspection findings.

The NRC benchmarked the notebooks against licensee Probability Risk Assessments and plant configurations.

The enclosed compact disks (CDs) containing the above documents are provided for your use to facilitate your understanding of the significance determination process in Inspection Manual Chapter 0609.The enclosure transmitted herewith contains Security-Related information.

When separated from enclosure, this document is decontrolled.

J. Stall The information on the enclosed compact disk is designated exempt from public disclosure pursuant to Section 2.390(d)(1) of Title 10 of the Code of Federal Regulations since it contains security-related information.

If you have any questions, please contact me at (301) 415-2020.Sincerely, Brenda L. Mozafari, Senior Proj ect ager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335, 50-389, 50-250, and 50-251

Enclosures:

-Official Use Only -Security Related Information

1. CD w/ SL1 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet
2. CD w/ SL2 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet
3. CD w/ TP3/4 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet cc w/o enclosure:

See next page Page 1 of 2 Mr. J. A. Stall Florida Power and Light Company cc w/o enclosure:

William E. Webster Vice President, Nuclear Operations, South Region Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Senior Resident Inspector St. Lucie Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, Florida 34957 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Marjan Mashhadi, Senior Attorney Florida Power & Light Company 801 Pennsylvania Avenue, NW.Suite 220 Washington, DC 20004 William Jefferson, Jr.Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Ft. Pierce, Florida 34982 TURKEY POINT PLANT ST. LUCIE PLANT Christopher R. Costanzo Plant General Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 County Manager Miami-Dade County 111 Northwest 1 Street, 29th Floor Miami, Florida 33128 Senior Resident Inspector Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission 9762 SW. 3 4 4 th Street Florida City, Florida 33035 William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Michael 0. Pearce Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 James Connolly, Licensing Manager Florida Power and Light Company Turkey Point Nuclear Plant 9760 SW. 344th Street Florida City, FL 33035ý7-7' -1 7- 7-7. -------T-1-jr7- -j.. t --,J-..-

Page 2 of 2 Mr. J. A. Stall Florida Power and Light Company ST. LUCIE PLANT TURKEY POINT cc: Don E. Grissette Vice President, Nuclear Training and Performance Improvement Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mark Warner, Vice President Nuclear Operations Support Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Rajiv S. Kundalkar Vice President, Nuclear Technical Services Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Gordon L. Johnston Site Vice President St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Bill Parks Operations Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957-2000 Seth B. Duston Training Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957-2000 Terry L. Patterson Licensing Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 J. Kammel Radiological Emergency Planning Administrator Department of Public Safety 6000 Southeast Tower Drive Stuart, Florida 34997 October 23, 2007 J. Stall The information on the enclosed CDs is designated exempt from public disclosure pursuant to Section 2.390 (d) (1) of Title 10 of the Code of Federal Regulations since it contains security-related information.

If you have any questions, please contact me at (301) 415-2020.Sincerely, Brenda L. Mozafari, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335, 50-389, 50-250, and 50-251

Enclosures:

-Official Use Only -Security Related Information

1. CD w/ SL1 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet
2. CD w/ SL 2 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet
3. CD w/ TP3/4 SDP Rev. 2 and Site Specific Pre-Solved Spreadsheet cc w/o enclosure:

See next page DISTRIBUTION W/O ENCLOSURE:

PUBLIC RidsNrrLABClayton (hardcopy)

LPL2-2 R/F RidsNrrDorILpl2-2 RidsNrrPMBMozafari JWiebe RidsNRRDraApob (MFranovich)

St Lucie 1 Spread: ML071700518 St Lucie 1 Notebook:

ML071700516 St. Lucie 2 Spread: ML071700523 St. Lucie 2 Notebook:

ML071700521 Turkey Pt. Spread: ML071700545 Turkey Pt. Notebook:

ML071700544 ADAMS Accession Number: Non Pub. Ltr.: ML072831371 Pub. Ltr.: ML072831379 Pkg: ML072831378 NRR-106" OFFICE LPL2-2/PM LPL2-2/LA LPL2-2/BC NAME BMozafari BClayton TBoyce ,1 'DFATE wIIA 1ECORD COP IY~~ FICALRECORD COPY U