MONTHYEARW3F1-2011-0018, License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual2011-11-21021 November 2011 License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual Project stage: Request ML1135702672011-12-23023 December 2011 Acceptance Review Email, License Amendment Request, Relocate Technical Specification (TS) 3.4.6, TS 3.7.5, TS 3.7.9, and TS 3.9.5 to the Technical Requirements Manual Project stage: Acceptance Review ML12310A4582012-11-0505 November 2012 Request for Additional Information Email, License Amendment Request to Relocate Technical Specification (TS) 3.4.6, TS 3.7.5, TS 3.7.9, and TS 3.9.5 to the Technical Requirements Manual Project stage: RAI W3F1-2012-0095, Response to a Request for Additional Information Regarding License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual2012-11-26026 November 2012 Response to a Request for Additional Information Regarding License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual Project stage: Response to RAI ML12278A3312012-12-20020 December 2012 Issuance of Amendment No. 238, Relocate Technical Specification (TS) 3.4.6, TS 3.7.5, TS 3.7.9, and TS 3.9.5 to the Technical Requirements Manual Project stage: Approval 2012-11-26
[Table View] |
|
---|
Category:Letter type:W
MONTHYEARW3F1-2023-0056, Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 W3F1-2022-0028, Annual Radiological Environmental Operating Report - 20212022-04-26026 April 2022 Annual Radiological Environmental Operating Report - 2021 W3F1-2022-0029, Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.22062022-04-26026 April 2022 Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.2206 W3F1-2022-0009, Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2022-04-25025 April 2022 Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors W3F1-2022-0031, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-2842022-04-25025 April 2022 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-284 W3F1-2022-0020, Review of Preliminary Accident Sequence Precursor Report2022-04-11011 April 2022 Review of Preliminary Accident Sequence Precursor Report W3F1-2022-0017, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20212022-04-0707 April 2022 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2021 W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis W3F1-2022-0011, Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-02-0808 February 2022 Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0008, SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days2022-02-0101 February 2022 SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days W3F1-2021-0074, Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-022021-12-16016 December 2021 Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02 W3F1-2021-0064, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 2842021-11-30030 November 2021 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 284 W3F1-2021-0061, Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-10-14014 October 2021 Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0063, Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery2021-10-12012 October 2021 Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery W3F1-2021-0050, Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt2021-10-0101 October 2021 Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt W3F1-2021-0060, Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-09-30030 September 2021 Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0039, Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years2021-08-25025 August 2021 Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years W3F1-2021-0055, Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual2021-08-20020 August 2021 Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual W3F1-2021-0057, (Waterford 3) - Emergency Plan Revision 0522021-08-18018 August 2021 (Waterford 3) - Emergency Plan Revision 052 W3F1-2021-0054, License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 20202021-07-29029 July 2021 License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 2020 W3F1-2021-0051, Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator2021-07-19019 July 2021 Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator 2023-09-28
[Table view] |
Text
Entergy Operations, Inc.
17265 River Road Killona, LA 70057-3093 Tel 504 739 6660 Fax 504 739 6678 Djacob2@entergy.com Donna Jacobs Vice President, Operations Waterford 3 W3F1-2012-0095 November 26, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Response to a Request for Additional Information Regarding License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual Waterford Steam Electric Station, Unit 3 (Waterford 3)
Docket No. 50-382 License No. NPF-38
Dear Sir or Madam:
In Email request from N. Kalyanam to M. Mason (ADAMS Accession Number ML12310A458), Waterford 3 received a request for additional information regarding its license amendment request to relocate Technical Specification 3.7.5, Flood Protection, to the Technical Requirements Manual. Please find attached the additional information requested.
There are no commitments associated with this submittal. Should you have any questions or comments concerning this submittal, please contact Michael E. Mason, acting Licensing Manager, at (504) 739-6673.
I declare under penalty of perjury that the foregoing is true and correct. Executed on November 26, 2012.
Sincerely, DJ/WH
Attachment:
Response to NRC Request for Additional Information
W3F1-2012-0095 Page 2 cc: Mr. Elmo E. Collins, Jr., Regional Administrator U.S. NRC, Region IV RidsRgn4MailCenter@nrc.gov U.S. NRC Program Manager for Waterford 3 Kaly.Kalyanam@nrc.gov U.S. NRC Senior Resident Inspector for Waterford 3 Marlone.Davis@nrc.gov Louisiana Department of Environmental Quality Office of Environmental Compliance, Surveillance Division Ji.Wiley@LA.gov
Attachment to W3F1-2012-0095 Response to NRC Request for Additional Information
Attachment to W3F1-2012-0095 Page 1 of 3 Response to NRC Request for Additional Information (RAI)
RAI 1
By letter dated [November] 21, 2011 (ADAMS Accession No. ML11326A283), Entergy Operations Inc. submitted a License Amendment Request (LAR) to Relocate the following Technical Specifications (TSs) to the Technical Requirements Manual:
TS 3.4.6 (Chemistry)
TS 3.7.5 (Flood Protection)
TS 3.7.9 (Sealed Source Contamination)
TS 3.9.5 (Communications)
On reviewing the Technical Analysis for the relocation of TS 3.7.5, the NRC staff requests additional information as stated below, on or before November 16, 2012.
The application mentions a non-conservatism related to flooding but has not identified what it is. It has also not provided the language to be put into the TRM concerning flooding. The staff has 2 comments as explained below:
The statements below are from the amendment application:
- 1. Criterion 2. Criterion 2 refers to a process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of, or presents a challenge to, the integrity of a fission product barrier. The "Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors" (58FR39132) defines the design basis accident or transients as that contained in the UFSAR Chapter 6 and 15. The flood related events are contained in UFSAR Chapter 2 and 3. Thus flood protection is not an initial condition for any design basis accident that would present a challenge to the integrity of any fission product barrier. Therefore, TS 3.7.5 does not meet Criterion 2 for inclusion in the TSs.
Comment - The flood events discussed in Chapter 2 and 3 are based on older analysis and apparently did not threaten the plants flood protection. However, due to the licensees discovery of a non-conservatism, this may no longer be true.
The licensee should be more specific. If the flood protection is no longer adequate, then flooding could be an initiating event for an accident. Please explain the non-conservatism that currently exists and explain your position with regard to Criterion 2.
RAI 1 Response Entergy Operations Inc. letter dated November 21, 2011, (Reference 1) is a License Amendment Request (LAR) to relocate several Technical Specifications (TSs), including TS 3.7.5, Flood Protection, to the Technical Requirements Manual (TRM). The relocation of TS 3.7.5 to the TRM was justified in Reference 1 based on a determination that the TS 3.7.5 Limiting Condition for Operation (LCO) does not meet the four criteria in 10 CFR 50.36 for inclusion in the TSs. Additionally, relocation of TS 3.7.5 LCO was
Attachment to W3F1-2012-0095 Page 2 of 3 evaluated in accordance with 10 CFR 50.91(a)(1) using the criteria in 10 CFR 50.92(c),
and it was determined that the changes involve no significant hazards consideration.
This RAI requests an explanation of the TS 3.7.5 non-conservatism that currently exists and explanation of the position with regard to Criterion 2. As indicated in this RAI, the statement that TS 3.7.5 is non-conservative created a concern among the NRC staff that the flooding analysis described in the Waterford 3 Update Final Safety Analysis Report (UFSAR) and the resulting conclusions about the effect of flooding on Core Damage Frequency (CDF) described in the Waterford 3 Individual Plant Examination for External Events (IPEEE) (Reference 2) may no longer be valid.
The Entergy Operations Inc. letter dated November 21, 2011, (Reference 1) communicated that the TS 3.7.5 was identified to be non-conservative with respect to the implementation of flood protection actions. This non-conservative TS action statement was identified in the NRC Problem Identification and Resolution Inspection Report (PI&R), dated July 12, 2010, (Reference 3). The inspection report specifically states the following:
The team identified a noncited violation of 10 CFR 50.36 (b), "Technical Specifications," for failure to derive technical specifications from the analyses and evaluation included in the safety analysis report. Specifically, the licensee failed to derive an action statement for Technical Specification 3.7.5 that meets the assumptions included in the Waterford Unit 3 Updated Safety Analysis Report.
The Updated Safety Analysis Report evaluation assumes an instantaneous levee failure occurs at a Mississippi River level of +27 feet mean sea level. The inspectors determined that the action statement for Technical Specification 3.7.5, to complete procedures to secure doors and penetrations in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, was not derived from the evaluation included in the safety analysis report because the actions would take place after the assumed instantaneous levee failure. The licensee entered this condition into the corrective action program as CR-WF3-2010-03232. As a short term compensatory measure, the licensee established criteria for taking appropriate action before the Mississippi River level would reach the +27 feet mean sea level safety limit.
The PI&R inspection report identifies that the TS 3.7.5 non-conservatism is in the TS action statement and that compensatory measures were taken. Because the non-conservative aspect of TS 3.7.5 is the TS action statement completion time and does not involve the LCO, the evaluation of TS 3.7.5 against the criteria in 10 CFR 50.36 for inclusion in TSs and the validity of the flooding analysis described in UFSAR are unaffected. Compensatory actions have been implemented which initiate procedures to secure doors and penetrations if Mississippi River level is projected to rise to +27 feet mean sea level within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. These actions will be completed well before reaching the river level assumed in the Updated Final Safety Analysis Report evaluation.
Waterford 3 has implemented administrative controls, in accordance with NRC Administrative Letter 98-10 (Reference 4), to apply revised TS action statement timing while the NRC completes its review and approval. The final resolution is being tracked in accordance with the Entergy Corrective Action Program due to being cited in NRC Problem Identification and Resolution Inspection Report (PI&R), dated July 12, 2010, (Reference 3).
Attachment to W3F1-2012-0095 Page 3 of 3
RAI 2
The statements below are from the amendment application:
- 2. Criterion 4. Criterion 4 refers to a structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety. The Waterford 3 Individual Plant Examination for External Events (IPEEE) response [Reference 7.12] found no high winds, floods, or off site industrial facility accidents that significantly alters the Waterford 3 estimate of either the core damage frequency, or the distribution of containment release categories. The NRC IPEEE safety evaluation [Reference 7.13]
reiterated this information as the licensee stated that Waterford 3 complies with the 1975 Standard Review Plan (SRP) criteria. Based on this compliance, all of the high winds, floods, transportation, and other (HFO) external events were dropped from further consideration and judged to not be a significant contributor to the total Core Damage Frequency (CDF). Based upon these risk insights, TS 3.7.5 does not meet Criterion 4 for inclusion in the TSs.
Comment - Conclusions based on IPEEE studies may not be valid for this LAR.
Please provide some alternate reasoning for not having to meet Criterion 4.
RAI 2 Response The response to RAI 1 provides the basis that the non-conservatism identified in the TS 3.7.5 action statement does not impact the TS 3.7.5 LCO or UFSAR analysis, nor does it impact the validity of the IPEEE analysis.
References:
- 1. Entergy Operations Inc. letter, License Amendment Request to Relocate Technical Specifications to the Technical Requirements Manual -- Waterford Steam Electric Station Unit 3, dated November 21, 2011 (ADAMS Accession No. ML11326A283).
- 2. Waterford 3 Individual Plant Examination for External Events (IPEEE), dated July 28, 1995.
- 3. Waterford Steam Electric Station, Unit 3 - NRC Problem Identification and Resolution Inspection Report (PI&R) 05000382/2010006, dated July 12, 2010, (ADAMS Accession No. ML101930439).
- 4. NRC Administrative Letter 98-10, Dispositioning of Technical Specifications That Are Insufficient to Assure Plant Safety, dated December 29, 1998.