Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML09273050730 September 20092009/09/30-Prairie Island License Renewal Hearing File and Mandatory Disclosures Updated Hearing File Index -- September 2009, Attachment 1
ML09273050630 September 2009Declaration of Brian E. Holian, Attachment 3
ML09273060630 September 2009Prairie Island Indian Community'S Seventh Supplemental Disclosures
L-PI-09-104, Response to an Apparent Violation in Inspection Report No. 05000282-09-012 (Drs); 05000306-09-012 (Drs); EA-09-19330 September 2009Response to an Apparent Violation in Inspection Report No. 05000282-09-012 (Drs); 05000306-09-012 (Drs); EA-09-193
ML09273052830 September 2009Northern States Power Company - a Minnesota Corporation (NSPM) Discovery Letter
ML09273051130 September 2009in the Matter of Northern States Power Co. (Prairie Island Nuclear Generating Plant, Units 1 and 2)
ML09273050830 September 2009Affidavit of Nathan E. Goodman Concerning Mandatory Disclosure Requirement 10 C.F.R. 2.336(b), Attachment 4
ML09273051030 September 2009Hearing File and Mandatory Disclosures Privilege Log September 2009, Update, Attachment 2
ML09273050930 September 2009Affidavit of Richard A. Plasse, Jr. Concerning Mandatory Disclosure Requirement of 10 C.F.R. 2.336(b), Attachment 5
L-PI-09-094, Independent Spent Fuel Storage Installation, Support for License Amendment Request to Modify TN-40 Cask Design (Designated as TN-40HT)28 September 2009Independent Spent Fuel Storage Installation, Support for License Amendment Request to Modify TN-40 Cask Design (Designated as TN-40HT)
TAC:L2420328 September 2009
ML09265013428 September 2009Request for Additional Information Related to Response to Generic Letter (GL) 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems
L-PI-09-102, Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Commitment Changes28 September 2009Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Commitment Changes
IR 05000282/200900925 September 2009NSP000054-Inspection Report 05000282/2009009; 05000306/2009009Time of Discovery
High Radiation Area
Mission time
Temporary Modification
Condition Adverse to Quality
Aging Management
Significance Determination Process
Operability Determination
ML09268020825 September 2009IR 05000282-09-009, 05000306-09-009, on 07/20/2009 - 08/13/2009, Prairie Island Nuclear Plant, Routine Biennial Problem Identification and Resolution InspectionTime of Discovery
High Radiation Area
Mission time
Temporary Modification
Condition Adverse to Quality
Aging Management
Significance Determination Process
ML10212004225 September 2009Applicant-Northard Exhibit 36 NRC Letter Re CAP Problem Idenitification and Resolution Inspection ReportTime of Discovery
High Radiation Area
Mission time
Temporary Modification
Condition Adverse to Quality
Aging Management
Significance Determination Process
ML10216077125 September 2009Intervenor-Exhibit 20-NRC Biennial Problem Identification and Resolution (Pi&R) Inspection Report (EA 06-178, ML092680208)Time of Discovery
High Radiation Area
Mission time
Temporary Modification
Condition Adverse to Quality
Aging Management
Significance Determination Process
ML10250061524 September 2009NRC000010-NRC Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program-Operations PhaseSignificance Determination Process
Pandemic
L-PI-09-100, Supplement to License Amendment Request (LAR) to Apply Surveillance Requirement (SR) 3.0.2 Interval Extension to SR 3.8.1.823 September 2009Supplement to License Amendment Request (LAR) to Apply Surveillance Requirement (SR) 3.0.2 Interval Extension to SR 3.8.1.8Foreign Material Exclusion
ML09266015723 September 2009Independent Spent Fuel Storage Installation, Notification of Management Change Update
ML10139020017 September 2009Enclosure 5, H4, Offsite Dose Calculation Manual (Odcm), Revision 24Grab sample
Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Process Control Program
ML09257036715 September 2009Correction to Technical Specifications (TAC Nos. MD9142 and MD9143)
IR 05000282/200940614 September 2009IR 05000282-09-406, & IR 05000306-09-406, (Dnms), on 09/11/2009, Prairie Island Nuclear Generating Plant, NRC ISFSI Security Inspection. Cover Letter
ML09257088811 September 2009Minnesota Department of Health/Request to Accompany an NRC Inspector at Prairie Island Nuclear Power Plant/Letter
ML10084064011 September 2009Advisory Brief of Prairie Island Nuclear Generating Plant Study Group to State of Minnesota, Office of Administrative Hearings for the Public Utilities Commission, Sept. 11, 2009. Submitted with Comments on Draft Generic Environmental ImpacEnvironmental Justice
ML09316058610 September 2009Attachment 8 to Enclosure, Calculation GEN-PI-087, Rev. 0, Hld Analysis Titled, Heavy Load Drop Event Dose Analysis - Ast.Deep Dose Equivalent
ML0931605879 September 2009Attachment 9 to Enclosure, Calculation GEN-PI-078, Rev. 0, MSLB Analysis Titled, Main Steam Line Break (MSLB) Accident Analysis Using Ast.Deep Dose Equivalent
ML0931605889 September 2009Attachment 10 to Enclosure, Calculation GEN-PI-081, Rev. 0, SGTR Analysis Titled, Eab, LPZ, and CR Doses Due to Steam Generator Tube Rupture Accident - Ast.Deep Dose Equivalent
ML0931605909 September 2009Attachment 12 to Enclosure, Calculation GEN-PI-083, Rev. 0, LRA Analysis Titled, Locked Rotor Accident (LRA) Analysis Using Ast.Deep Dose Equivalent
ML0931605898 September 2009Attachment 11 to Enclosure, Calculation GEN-PI-082, Rev. 0, Crea Analysis Titled, Control Rod Ejection Accident - Ast.Deep Dose Equivalent
ML0931605847 September 2009Attachment 6 to Enclosure, Calculation GEN-PI-079, Rev. 0, LOCA Analysis Titled, Post-LOCA Eab, LPZ and CR-Doses - Ast.Boric Acid
Coatings
Deep Dose Equivalent
Power Uprate
IR 05000282/20090123 September 2009IR 05000282-09-012(DRS); 05000306-09-012(DRS); 05/1/2009 - 08/10/2009 (in-office Review); Prairie Island Nuclear Generating Plant, Units 1 and 2; Licensed Operator RequalificationSignificance Determination Process
License Renewal
ML1021607673 September 2009Intervenor-Exhibit 13-Letter from Mark A. Satorius, Regional Administrator, U.S. NRC to Mark A. Schimmel, Acting Site Vice President, Prairie Island Nuclear Plant in Regard to EA-09-167Significance Determination Process
Preliminary White Finding
ML0924506243 September 2009EA-09-167, Prairie Island Nuclear Generating Plant, Unit 2, Final Significance Determination for a White Finding and Notice of Violation, NRC Inspection Report No. 05000306-09-013Significance Determination Process
Preliminary White Finding
IR 05000306/20090133 September 2009NRC000023-Final Significance Determination for a White Finding and Notice of Violation; NRC Inspection Report No. 05000306/2009013; Prairie Island Nuclear Generating Plant, Unit 2Significance Determination Process
Preliminary White Finding
ML0921204292 September 2009Summary of Meeting with Northern States Power Company to Discuss License Amendment Request Concerning Unit 2 Emergency Diesel Generator Surveillance Test Loads
ML1001206031 September 2009Email from Vincent Dale to Thomas Wengert Dated 9/1/09
ML1001206271 September 2009Inspection Report Regarding Steam Generator Tube 2008 Responses
ML1021200561 September 2009Applicant-Northard Exhibit 21-090109-NRC Mid-Year Assessment Letter - Prairie Island Nuclear Generating Plant, Unit 1 and 2Significance Determination Process
Preliminary White Finding
ML1021607801 September 2009Intervenor-Exhbit 15-Letter from K. Stephen West, Director of Reactor Projects, U.S. NRC to Mark A. Schimmel, Site Vice President (Acting), Prairie Island Nuclear Generating Plant in Regard to Mid-Cycle Performance Review and Inspection PlaSignificance Determination Process
Preliminary White Finding
ML1024606151 September 2009NSP000039-Revised Testimony of Northard/Petersen/Peterson-NRC Mid-2009 Performance Review ReportSignificance Determination Process
Preliminary White Finding
ML0924403671 September 2009Prairie Island - Mid-Cycle Performance Review and Inspection PlanSignificance Determination Process
Preliminary White Finding
ML09243044531 August 2009NRC Staff Notifying the Licensing Board and the Parties That Hearing File Has Been Updated for Prairie Island, Units 1 and 2
ML09243044631 August 2009NRC Staff Transmittal Letter Dated August 31, 2009 - Attachment 3, Affidavit of Nathan E. Goodman
ML09243064031 August 2009Prairie Island Indian Community'S Sixth Supplemental Disclosures
ML09224033231 August 2009Correction to Safety Evaluation Supporting Amendment Nos. 192 and 181 Technical Specification Changes to Allow Use of Westinghouse 0.422-Inch OD 14 X 14 Vantage+ Fuel (TAC Nos. MD9142/MD9143)Boric Acid
Loop seal
TAC:MD814331 August 2009
ML09243044431 August 2009NRC Staff Transmittal Letter Dated August 31, 2009 - Attachment 2, Declaration of Brian E. Holian
ML09243039131 August 2009EN-09-044, Northern States Power CompanySignificance Determination Process
ML09243044731 August 2009NRC Staff Transmittal Letter Dated August 31, 2009 - Attachment 1- Hearing File and Mandatory Disclosures Privilege Log, August 2009, Update