Letter Sequence RAI |
---|
|
|
MONTHYEARL-PI-08-072, Update to Three-Month Response and Request for Extension to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-09-15015 September 2008 Update to Three-Month Response and Request for Extension to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request ML0823208242008-10-0808 October 2008 an 2 - Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action (TAC Nos MD7866 & MD7867) Project stage: Other L-PI-08-088, Nine-Month Response to NRC GL 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2008-10-14014 October 2008 Nine-Month Response to NRC GL 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request L-PI-09-012, Ninety-Day 2R25 Post-Outage Report Pursuant to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2009-01-30030 January 2009 Ninety-Day 2R25 Post-Outage Report Pursuant to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request L-PI-09-102, Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Commitment Changes2009-09-28028 September 2009 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Commitment Changes Project stage: Request ML0926501342009-09-28028 September 2009 Request for Additional Information Related to Response to Generic Letter (GL) 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI L-PI-09-122, Supplement to Responses to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2009-11-24024 November 2009 Supplement to Responses to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Supplement ML1001400732010-01-27027 January 2010 Closeout of Generic Letter 2008-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems. Project stage: Other 2009-01-30
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 ML23356A1232024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24017A0182024-01-19019 January 2024 Confirmation of Initial License Examination ML23356A0032024-01-17017 January 2024 Issuance of Amendments Revise Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report IR 07200010/20234012023-12-20020 December 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200010/2023401 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23215A1672023-12-15015 December 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Surveillance Requirement 3.8.1.2 Note 3 IR 05000282/20234012023-12-13013 December 2023 Security Baseline Inspection Report 05000282/2023401 and 05000306/2023401 L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23304A1632023-11-15015 November 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise SR 3.8.1.2 Note 3 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000282/20230032023-11-0808 November 2023 Integrated Inspection Report 05000282/2023003 and 05000306/2023003 ML23311A3572023-11-0707 November 2023 Core Operating Limits Report (COLR) for Prairie Island Nuclear Generating Plant (PINGP) Unit 2. Cycle 33. Revision 0 ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant ML23270B9022023-09-29029 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23265A2532023-09-26026 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20230102023-08-17017 August 2023 NRC Inspection Report 05000282/2023010 and 05000306/2023010 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence IR 05000282/20230022023-08-0303 August 2023 Integrated Inspection Report 05000282/2023002 and 05000306/2023002 ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT ML23181A0192023-06-30030 June 2023 Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report IR 05000282/20234202023-06-0101 June 2023 Security Baseline Inspection Report 05000282/2023420 and 05000306/2023420 ML23150A1722023-05-30030 May 2023 Preparation and Scheduling of Operator Licensing Examinations 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23096A3082023-04-0707 April 2023 Notification of Inspection an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 ML23053A1432023-02-22022 February 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22145A4152022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22130A5792022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21147A5232021-06-0303 June 2021 Prarie Island Nuclear Generating Plant, Units 1 and 2 - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21131A0752021-05-10010 May 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2021004; 05000306/2021004 ML21099A0972021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000282/2021012 and 05000306/2021012 ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant ML21033A6112021-02-0101 February 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000282/2021010 and 05000306/2021010 ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information ML20192A1442020-07-0707 July 2020 NRR E-mail Capture - Request for Additional Information Prairie Island License Amendment Request to Adopt TSTF-505 ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 ML20133K0692020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20077K6242020-04-13013 April 2020 License Amendment Request - Request for Additional Information ML20052F4102020-02-21021 February 2020 Notification of Nrc Design Bases Assurance Inspection (Programs) (05000282/202010; 05000306/202010) and Initial Request for Information ML20035F1552020-02-0404 February 2020 NRR E-mail Capture - Request for Additional Information Monticello and Prairie Island Alternative Requests to Adopt Code Cases N-786-3 and N-789-3 (Epids: L-2019-LLR-0078 and L-2019-LLR-0079) ML19233A0032019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Prairie Island Relief Requests 1-RR-10 and 2-RR-10 ML19057A1652019-02-26026 February 2019 NRR E-mail Capture - Request for Additional Information Prairie Island 50.69 Amendment Request ML18313A0832018-11-0707 November 2018 NRR E-mail Capture - Request for Additional Information Prairie Island NFPA-805 License Condition Modification Amendment Request ML18264A1912018-09-19019 September 2018 NRC Information Request (9/19/2018); Part B Items (Onsite) IP 71111.08 - E-Mailed 09/19/18 (DRS-M.Holmberg) ML18235A2982018-08-23023 August 2018 NRR E-mail Capture - Request for Additional Information Prairie Island TSTF-425 License Amendment Request ML18169A4202018-06-25025 June 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18025C0152018-01-24024 January 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000282/2018011; 05000306/2018011 (DRS-A.Dunlop) ML17277B3332017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information Prairie Island Special Heavy Lifting Devices LAR ML17249A9232017-09-0606 September 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2017004; 05000306/2017004 (Exf) ML17235A9982017-08-23023 August 2017 NRR E-mail Capture - Request for Additional Information Prairie Island EAL Scheme Change ML17221A3892017-08-0909 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17219A0762017-08-0707 August 2017 NRR E-mail Capture - Request for Additional Information for Prairie Island Nuclear Generating Plant License Amendment Request Dated February 23, 2017 Emergency Response Organization ML17038A5132017-02-0707 February 2017 NRR E-mail Capture - Prairie Island NFPA 805 LAR, PRA RAI 21.01 ML17018A4272017-01-18018 January 2017 NRR E-mail Capture - Request for Additional Information: Prairie Island License Amendment Request to Revise Technical Specification 3.8.7 to Remove Non-Conservative Required Action ML16326A3532016-11-18018 November 2016 NRR E-mail Capture - Draft Request for Information Related to Prairie Island NFPA-805 License Amendment ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) ML16189A2052016-07-0707 July 2016 Notification of NRC Inspection and Request for Information ML16113A1612016-04-21021 April 2016 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML16075A0802016-03-15015 March 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 Request for Additional Information Related to License Amendment Request to Adopt TSTF-523, GL 2008-01, Managing Gas Accumulation ML16008A1092016-01-0808 January 2016 NRR E-mail Capture - Prairie Island Nuclear Generating Plant, Units 1 and 2 - Requests for Additional Information (Afpb) License Amendment Request to Adopt NFPA 805 ML15195A6562015-07-10010 July 2015 Prairie Island Notification of NRC Inspection and Request for Information ML15149A1662015-05-28028 May 2015 Plan - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15121A6512015-04-29029 April 2015 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection (CDBI) Inspection Report 05000282/2015007; 05000306/2015007 (Jen) 2023-09-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 28, 2009 IVIr. Mark A. Schimmel Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota 1717 Wakonade Drive East Welch, MN 55089-9642 SUB..IECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 REQUEST FOR ADDITIONAL INFORMATION RELATED TO RESPONSE TO GENERIC LETTER (GL) 2008-01, "MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS" (TAC NOS. MD7866 AND MD7867)
Dear Mr. Schimmel:
By letters to the U.S. Nuclear Regulatory Commission (NRC) dated October 14, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082880483), and January 30,2009 (ADAMS Accession No. ML093000705), Northern States Power Company, a Minnesota corporation (the licensee), doing business as Xcel Energy, submitted a response to Generic Letter (GL) 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems" for the Prairie Island Nuclear Generating Plant, Units 1 and 2.
The NRC staff is reviewing your submittals and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on September 3, 2009, it was agreed that you would provide a response within 60 days of the date of this letter.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and
M. Schimmel -2 effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4037.
Sincerely,
~"'~<tt-~G-*-
Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Request for Additional Information cc w/encl: Distribution via ListServ
REQUEST FOR ADDITIONAL INFORMATION (RA!)
PRAIRIE ISLAND NUCLEAR GENERATING PLANT UNITS 1 AND 2 RESPONSE TO GENERIC LETTER (GL) 2008-01, "MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS" DOCKET NOS. 50-282 AND 50-306 The Nuclear Regulatory Commission (NRC) staff is reviewing the subject Prairie Island Nuclear Generating Plant (PINGP) responses dated October 14, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082880483), and January 30,2009 (ADAMS Accession No. ML090300705). The NRC staff has determined that additional information requested below is needed to complete its review. Guidance on the NRC staff's expectations is provided by Reference 1, which is generally consistent with Nuclear Energy Institute (NEI) guidance provided to industry in Reference 2, as clarified in later NEI communications. The NRC staff recommends that the licensee consult Reference 1 when responding to the following RAls:
- 1. Clarify the schedule for submitting a license amendment request (LAR), if it is necessary to submit an LAR as a result of the evaluation of the Technical Specification Task Force traveler.
- 2. In Reference 5, it was reported that several voids were found that resulted in systems conditions being evaluated as "operable but nonconforming." Clarify how operability is determined, including a description of criteria used, analyses performed, and consideration of the size of the void and how it affects the system in all modes of operation.
- 3. In Reference 4, it is stated that the licensee's "CAP process requires that a potentially nonconforming condition be documented in the CAP. This would be the case should an as-found measured void size fail[s] to meet its acceptance criterion. The Shift Manager would review the CAP to evaluate for potential impact on operability and reportability."
Clarify the meaning of "potentially nonconforming" and "potential impact", including any criteria used in the determination. Describe follow-up actions to be taken when a void is identified as nonconforming and documented in the CAP.
- 4. Training was not identified in the Generic Letter (GL), but is considered to be a necessary part of applying procedures and other activities when addressing the issues identified in the GL, as the licensee has recognized. Provide a brief description of training.
ENCLOSURE
-2
- 5. In Reference 4, it is stated that "Design features and water level set points are controlled by design and operating procedures to prevent vortex effects that can potentially introduce gas into the system during design basis events". Since flow rates under realistic accident conditions (non-degraded pumps, two trains running) may significantly exceed the design basis accident flow rates, clarify how the stated conclusions are applicable to actual expected accident conditions and for all modes of operation.
- 6. In Reference 4, it is stated that "PINGP does not have specific leakage acceptance criteria for leakage between high pressure and low pressure systems pertaining to gas intrusion." Reference 3 states "Gas in discharge piping can be an indicator of potential backleakage from high-pressure sources such as accumulators or the RCS ..." Clarify whether a gas leakage acceptance criterion will be developed or justify that existing procedures and criteria are able to control gas intrusion. Include consideration of the effects of leakage on the pressures of the systems involved; the accumulator, reactor cooling system, emergency core cooling system piping.
REFERENCES
- 1. Ruland, William H., "Preliminary Assessment of Responses to Generic Letter 2008-01,
'Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems,' and Future NRC Staff Review Plans," NRC letter to James H. Riley, NEI, ADAMS Accession No. ML091390637, May 28,2009.
- 2. Riley, James H., "Generic Letter (GL) 2008-01, 'Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Contain Spray Systems' Evaluation and 3 Month Response Template," Letter to Administrative Points of Contact from Director, Engineering, Nuclear Generation Division, NEI, Enclosure 2, "Generic Letter 2008-01 Response Guidance," March 20, 2008.
- 3. Case, Michael J., "NRC Generic Letter 2008-01: Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems,"
Letter from Director, Division of Policy and Rulemaking, Office of Nuclear Reactor Regulation, NRC, ADAMS Accession No. ML072910759, January 11, 2008.
- 4. Wadley, Michael D., "Prairie Island Nuclear Generating Plant Units 1 and 2, Dockets 50 282 and 50-306, License Nos. DPR-42 and DPR-60, Nine-Month Response to NRC Generic Letter 2008-01, 'Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems'," Letter to Document Control Desk (DCD), NRC, from Site Vice President, Northern States Power Co. - Minnesota, ADAMS Accession No. ML082880483, October 14, 2008.
- 5. Sorensen, Joel P., "Prairie Island Nuclear Generating Plant Units 1 and 2, Dockets 50 282 and 50-306, License Nos. DPR-42 and DPR-60, Ninety-Day 2R25 Post-Outage Report Pursuant to Generic Letter 2008-01, 'Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems'," Letter to DCD, NRC, from Director Site Operations, Northern States Power Co. - Minnesota, ADAMS Accession No. ML090300705, January 30, 2009.
' ML092650134 *via memo dated 8/24/09 OFFICE LPL3-1/PM LPL3-1/LA NRR/DSS/SRXB/BC LPL3-1/(A) BC NAME TWengert BTully GCranston* PTam (THarris for)
DATE 09/25/09 09/25/09 08/24/09 09/28/09