Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20080B09230 September 1994Evaluation of Util Response to Suppl 1 to NRC Bulletin 90-01, for Plant
ML20073S64810 June 1994Technical Evaluation:Core Thermal Limit Protection Function Setpoint Methodology for Seabrook Station YAEC-1854P for Yankee Atomic Electric CoAnticipated operational occurrence
ML20091H87517 December 1991Final Technical Evaluation Rept,Seabrook Station Unit 1 Station Blackout EvaluationSafe Shutdown
Battery sizing
ML20006F03530 November 1989Technical Evaluation Rept on First 10-yr Interval Inservice Insp Program Plan:Public Svc of New Hampshire,Seabrook Station,Unit 1.Incorporated by reference
Dissimilar Metal Weld
ML19332B61431 October 1989Conformance to Generic Ltr 83-28,Item 2.2.1--Equipment Classification for All Other Safety-Related Components:Quad Cities 1 & 2, Final Technical Evaluation ReptSafe Shutdown
ML20248E21916 August 1989Mod 16,reflecting Return of Equipment to Tva,To Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators
ML20248E21216 August 1989Notification of Contract Execution,Mod 16,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva
ML20244A47031 May 1989Rev 1 to Technical Evaluation Rept,Tmi Action--NUREG-0737 (II.D.1),Relief & Safety Valve Testing,Seabrook Nuclear Station - Units 1 & 2
ML20247R39416 May 1989Mod 15,extending Period of Performance,Providing Addl Work Re Training for NRC Inspectors & Supervisors,Changing NRC Project Officer & Adding TVA Project Manager & Increasing Contract Ceiling & Funding to Use of TVA Reactor..
ML20247R38516 May 1989Notification of Contract Execution,Mod 15,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn,For Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva
ML20246B81530 April 1989Rev 1 to Conformance to Item 4.5.2 of Generic Ltr 83-28, Duane Arnold,Enrico Fermi-2,Hope Creek,Lasalle County 1 & 2, Limerick 1 & 2,Millstone 1,Monticello,Nine Mile Point 1 & 2 & Oyster Creek, Technical Evaluation Rept
ML20246B97331 March 1989Conformance to Reg Guide 1.97:Byron 1/2 & Braidwood 1/2, Technical Evaluation ReptBoric Acid
ML20236B80513 March 1989Monthly Progress Rept for Contract NRC-02-87-004 for Period 890204-890303.Financial Data Available in Central Files
ML20205N94331 October 1988Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Millstone-1
ML20155B7531 June 1988Corrected Mod 1,restoring Funds That Was Deobligated & Providing Final Increment of Funding to Contract,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee, Pilgrim & Seabrook Resident Sites
ML20155B7391 June 1988Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Telephone Co
ML20150D90917 March 1988Mod 1,deobligating Funds from Total Obligated Amount of Contract & to Correct FIN Number,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites
ML20150D90017 March 1988Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Telephone Co
ML20196C1644 February 1988Independent Assessment & Analysis, Monthly Progress Rept for Period Ending 880131
ML20205N95331 January 1988Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Millstone-3Safe Shutdown
ML20205N94831 January 1988Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components - Millstone-2Safe Shutdown
ML20149F16911 January 1988Contract: Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee,Pilgrim & Seabrook Resident Sites, Awarded to New England Bell Telephone Co
ML20149F13111 January 1988Notification of Contract Execution: Local Telephone Svc for Yankee Rowe,Vermont Yankee,Maine Yankee & Pilgrim & Seabrook Resident Sites, Awarded to New England Bell Telephone Co
ML20236T73724 November 1987Notification of Contract Execution,Mod 7,to Dresden & Perry Simulator. Contractor:Ge
ML20236T74624 November 1987Mod 7,extending Period of Performance Through 880930,adding Addl GE Simulator to Contract & Scheduling Four Simulator Courses Through FY88,to Dresden & Perry Simulator
ML18040B18931 August 1987Selected Operating Reactors Issues:Stability Calculations for Grand Gulf 1 & Susquehanna 2 Bwrs.
ML20235V15231 August 1987Technical Evaluation Rept,Reactor Trip Sys Reliability Conformance to Item 4.5.2 of Generic Ltr 83-28,Peach Bottom 2 & 3,Perry 1 & 2,Pilgrim 1,Quad Cities 1 & 2,River Bend 1, Shoreham,Susquehanna 1 & 2,Vermont Yankee & WNP-2
ML20235M35931 August 1987Preliminary Conformance to Reg Guide 1.97:Byron Units 1 & 2 & Braidwood Units 1 & 2, Technical Evaluation ReptBoric Acid
ML20237J06219 August 1987Technical Evaluation Rept on Duke Power Co McGuire & Catawba Nuclear Stations SpdsBackfit
ML20237J14117 August 1987Facility Sys Analysis Support, Progress Rept 23 for 870713 -0807
ML20236P21810 August 1987Mod 1,increasing Total Amount of Contract,To Local Telephone Svc for Yankee Rowe,Vermont Yankee,Main Yankee, Pilgrim & Seabrook Resident Sites
ML20236P20510 August 1987Notification of Contract Execution,Mod 1,to Local Telephone Svc for Yankee Rowe,Vermont Yankee,Main Yankee,Pilgrim & Seabrook Resident Sites. Contractor:New England Bell Telephone Co
ML20236P64031 July 1987Review of Recirculation Pump Trip Design for Brunswick Steam Electric Plants, Informal Rept
ML20236D91831 July 1987Methodology and Application of Surrogate Plant PRA Analysis to the Rancho Seco Power Plant.Task 1 - Analysis of ANO-1 and Oconee PRAsProbabilistic Risk Assessment
Earthquake
ML17347A59331 July 1987Retran Code:Transient Analysis Model Qualification, Technical Evaluation Rept
ML20235L98130 June 1987Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Seabrook 1 & 2, Informal Rept
ML18052B19330 June 1987Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Calvert Cliffs-1 & -2, Millstone-2 & Palisades, Final Informal Rept
ML20235L83930 June 1987Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components: Seabrook Units 1 & 2, Final Informal Rept
ML20214R14829 May 1987Notification of Contract Execution,Mod 12,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva
ML20214R15629 May 1987Mod 12,providing Incremental Funds & Increasing Ceiling,To Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators
ML18150A18830 April 1987Conformance to Generic Ltr 83-28,Item 2.2.2 - Vendor Interface Programs for All Other Safety-Related Components, North Anna Units 1 & 2 & Surry Units 1 & 2, Informal Rept
ML18150A11930 April 1987Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,North Anna 1 & 2 & Surry 1 & 2, Final Informal Rept
ML20214Q89830 April 1987Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Hatch-1 & 2,Millstone-1, Final Rept
ML20214R06830 April 1987Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,Arnold,Brunswick-1 & 2, Informal Rept
ML18152A58330 April 1987Conformance to Item 2.1 (Part 2) of Generic Ltr 83-28, Reactor Trip Sys Vendor Interface,North Anna 1 & 2 & Surry 1 & 2.
ML20206G2688 April 1987Mod 6,changing Project Officer Address Due to NRC Reorganization,To Dresden & Perry Simulator
ML20206G0818 April 1987Notification of Contract Execution,Mod 6,to Dresden & Perry Simulator. Contractor:Ge
ML20206G6388 April 1987Mod 11,recognizing Administrative Changes Due to NRC Reorganization,To Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Browns Ferry,Sequoyah & Bellefonte Simulators
ML20206G5868 April 1987Notification of Contract Execution,Mod 11,to Use of TVA Reactor Simulator Facilities at Chattanooga,Tn for Training on Brown Ferry,Sequoyah & Bellefonte Simulators. Contractor:Tva
ML20206F0718 April 1987Flow-Pattern Results for Tmlb' Accident Sequence in Surry Plant Using Melprog